04-6326 (6).s
City of La Quinta
BUILDING & SAFETY DEPARTMENT
SPECIAL INSPECTOR'S REPORT
PROJECT INFORMATION CONTACT INFORMATION
PROJECT NAME: INSPECTOR'S NAME: Steve W. Bodnar
Bed Bath & Beyond CERTIFIED BY (AGENCY): ICBO
INSPECTION ADDRESS: CERTIFICATION NUMBER: 0849264-85
79-110 Highway 111
La Quinta, CA "TESTING LABORATORY/COMPANY: - --
Permit No, 04-6326 MTGL
SUPERINTENDENT: 29992 East La Palma Avenue Suite A
Larry Moodv / (760) 771-5333 714 632-2999 714 632-2974 Fax
WEEK OF: 12/15 & 16/2005
INSPECTION'S PERFORMED
IN PROGRESS:
Erection of the canopy framing from line 13.2 to F.3 between lines 6 and 7.
COMPLETED WELDING:
(1) Tube steel to top cord of roof joists on lines 3,4,& 5 from line A to C.
(2) Splice plates on the top cord of roof joists on lines 3 & 4 from line A to I.
(3) Sauare Dlates to block wall embeds at the bottom cord of roof foists on lines A3, A4 & A5.
Steve W. Bodnar
80-400 Camino Santa Elise
Indio, CA 92203-7489 DATE: 12/16/2005
City of Ga Quinta
BUILDING & SAFETY DEPARTMENT
SPECIAL INSPECTOR'S REPORT
PROJECT INFORMATION CONTACT INFORMATION
PROJECT NAME: INSPECTOR'S NAME: Steve W. Bodnar
Bed Bath & Beyond CERTIFIED BY (AGENCY): ICBO
INSPECTION ADDRESS: CERTIFICATION NUMBER: 0849264-85
79-110 Highway 111
`!! La Quinta; CA - --TESTING LABORATORY/COMPANY: --
Permit No, 04-6326 MTGL
SUPERINTENDENT: 29992 East La Palma Avenue Suite A
Larry Mood / 760 771-5333 714 632-2999 714 632-2974 Fax
WEEK OF: 12/20, 21, 22, 23/2005
INSPECTION'S PERFORMED
IN PROGRESS:
(1) Welding of the roof joists bridging angles.
(2) Welding of the support framing for the HVAC units along lines 3 & 5.
(3) Placement and puddle welding of the metal roof decking.
COMPLETED WELDING:
W8x10 beams and beam tie angles on the top cord of roof joists on line 5.9 from line C.9 to F.5.
Steve W. Bodnar
80-400 Camino Santa,Elise
Indio, CA 92203-7489 DATE: 12/23/2005
r
Corporate: 2992 E. La Palma Avenue, Suite A, Anaheim, CA 92806
Tel: (714) 632-2999 Fax: (714) 632-2974
Branch: 7313 Carroll Road, Suite G, San Diego, CA 92121
Tel: (858) 537-3999 Fax: (858) 537-3990
Branch: 14320 Elsworth Street, Suite C101, Moreno Valley, CA 92553
Tel: (909) 653-4999 Fax: (909) 653-4666
Branch: 13010 San Fernando Road, Unit 1, Sylmar, CA 91342
Tel: (818) 833-8100 Fax: (818) 833-0085
Report of: COMPRESSIVE STRENGTH -GROUT ASTM C1019
CITY OF LA QUINTA-BLDG & SAFETY
78495 CALLE TAMPICO
LA QUINTA, CA 92253
Client:: THOMAS ENTERPRISES
A
— - — -Set No.: 5-7459 —
File No.:
Date
Tested
Permit No.:
046-326
Project No.:
31151303
Project Name:
BED, BATH & BEYOND MARKET PLACE @ LA Q
12/5/2005
HWY 111 @ ADAMS
10.52
LA QUINTA, CA
Age
(Days)
Date
Tested
Nominal
Size
Actual Area
(Sq. Inch)
Load
(lbs.)
Strength
(psi)
Type of
Fracture
7
12/5/2005
3 X 3 X 6
10.52
29,470
2,800
N/A
28
12/26/2005
3 X 3 X 6
10.53
35,630
3,380
N/A
28
12/26/2005
3 X 3 X 6
10.66
1 38,330
1 3,600
N/A
28H
12/26/2005
3 X 3 X 6
9.00
Specified Strength: 2,500 PSI Sampled By
Location: 4TH LIFT LINE I
Concrete Supplier: ASSOCIATED READY MIX
Mix No.: 46511
Ticket No.: 117201
Water added at Site: 0.00 gal. By
Cement Type: Mix Time: 30 min.
Remarks: TRUCK # 265
Distribution: THOMAS ENTERPRISES
VCC .
CITY OF LA QUINTA-BLDG & SAFETY
**LAB COPY**
ASTM C172 Date Sampled: 11/28/2005 Date Received: 11/30/2005
Concrete Temp: 71 °F ASTM C1064
Ambient Temp: 81 °F ASTM C1064
Slump: 9.00 in. ASTM C143
Tested at: Anaheim
Respectfully Submitted,
MTGL, Inc.
1
M.B.(Ben) Lo
Chief Engineer
3490 PSI
28 -day compression test complies with the specified strength.
t
.�z
MTGL
Corporate:
2992 E. La Palma Ave., Ste. A
Anaheim, CA 92806
Tel: 714.632.2999
Fax: 714.632.2974
San Diego/Imperial County:
7313 Carroll Road, Suite G
San Diego, CA 92121
Tel: 858.537.3999
Fax: 858.537.3990
Inland Emp
14320 Elsworth Street, Ste. C101
Moreno Valley, CA 92553
Te I: 951.653.4999
Fax: 951.653.4666
FIELD REPORT
TYPE OF WORK NSPECTOR ❑ TECHNICIAN
AVAILABLE: SOIL REPORT (Y) (N) SPECS (Y) (N)
APPROVED PLANS j APPROVED SHOP DRAWING (Y) (N)
ARCHITECT
m;
FOR WEEK ENDING
a � 1 —
PROJECT. NO.
,T
G
ENGINEER
s -s1
REPORT NO. f PG / OF
/
CONTRACTOR
PLAN FILE NO.
PERMIT NO.
SUB•CONTRACTO
L-
PROJECT N
eJ/
INSPECTION ADDRESS
ADDRESS OF PROJECT
5
REPORTING REQUIREMEN S: ICBO FIELD INSPECTION MANUAUMTGL SOIL MANUAL - REVIEW PREVIOUS REPORTS AND LISTS
IF THERE IS NON -CONFORMING WORK AT THE END OF THE WORK DAY, OR MISSING MTRS, AND RFIS, ETC., FILL OUT AND ATTACH A DEFICIENCY REPORT
WHEN A DEFICIENCY, YOURS OR A PREVIOUS INSPECTOR'S, IS CORRECTED, SO NOTE ON THE ORIGINAL DEFICIENCY REPORT AND
SUBMIT A COPY WITH YOUR WEEK'S REPORTS.
MATERIALS USED BY CONTRACTOR (INCLUDE RESEARCH REPORT NO. OR MATERIAL TEST REPORTS):
CONTRACTORS EQUIPMENT/ MANPOWER USED:
irP�/�G/�
S 1(7 /�C ,IJ
el 2-11 /1Cw icy /CAGB lc, ✓1 /
((ti�l�c�ln
lG /G ZC / Ganz, �Lj
AREA, Gnru LINES, PIECES OBSERVED:
STRU TURAL NOTES, DETAIL, OR RFIS USED:
REMARKS, INCLUDING MEERNGS: A
/�� <rrye�✓ �r-.� c ; �, � �� .� / ,t" h+- � .• � 5?cC
/ �/'��l'r• .�. ���, �-cJ'c r /` , r .� ri-,
/�
& ZC
d_ I e*c . , ✓s /I Zi- L. Z7,- ,-r
V
Oc /� � ,1 7', r c .., I „-► �4.�v
_4 h7
/fro
—4 le' t,e-19r�/c
V—�--_
REWORK AS PERCENT 0,KALL WORK'TODAYo
PER NT P JECT COMPLETIM
WEATHER:�• ��� /./�
TEMPERATURE: vPvge,- �
SAMPLES TAKEN:
TESTS REQUIRED:
SITE TIME START: !J ! , r^ SITE TIME FINISH: �. D
LUNCH PERIOD: c1 G TRAVEL TIME: VERIFIED BY:
I DO CERTIFY THAT I HAVE PERSONALLY OBSERVED ALL OF THE WORK LISTED ABOVE AND THAT THIS WORK COMPLIES WITH THE SOIL INVESTIGATION RECOMMENDATIONS,
AND / OR THE APPROVED PLANS, SPECIFICATIONS AND APPLICABLE SECTION OF THE BUILDING CODE, UNLESS OTHERWISE NOTED IN THE DEFICIENCY REPORT
s
l
Signature
Sinat
9 Date of eport ICBG Certification Number
Print Name
City / County Certification Number
CORPORATE
2992 E. La Palma Ave., Suite A
Anaheim, CA 92806
Tel: 714.632.2999
Fax: 714.632.2974
San Diego / Imperial County
7313 Carroll Road, Suite G
San Diego, CA 92121
Tel: 858.537.3999
Fax: 858.537.3990
FIELD REPORT
Inland Empire
14320 Ellsworth Street, Suite C101
Moreno Valley, CA 92553
Tel: 95.1.653.4999
Fax: 951.653.4666 11��
Type Of Work X INSPECTOR TECHNICIAN
SSW
AVAILABLE: SOIL REPORT (Y) (N) SPECS. (Y)
APPROVED PLANS (Y) APPROVED SHOP DRAWINGS (Y)
ARCHITECT: Smith Consulting Architects
12220 EI Camino Real Suite 200 San Diego, CA 92130
FOR WEEK ENDING 12117/2005
PROJECT NO.—T118303
ENGINEER: CSSI
2445 Fifth Street Suite 300 San Diego, CA 92102
REPORT NO. 1 PG 1 OF 1
CONTRACTOR: Vratsinas Construction Co.
P.O. Box 2558 Little Rock, AR 72203
PLAN FILE NO.
PERMIT NO. 04 6326
SUB -CONTRACTOR: Portola Constructios, Inc.
10722 Edison Court Rancho Cucamonga, CA 91730
PROJECT NAME: Bed bath & Beyond
INSPECTION ADDRESS: 79-110 Highway 111
La Quinta, CA
ADDRESS OF PROJECT: 79-110 Highway 111
La Quinta, CA
REPORTING REQUIREMENTS: ICSO FIELD INSPECTION MANUAL / MTGL SOIL MANUAL -REVIEW PREVIOUS REPORTS AND LISTS
IF THERE IS NON -CONFORMING WORK AT THE END OF THE WORK DAY, OR MISSING MTRS, AND RFIS, ETC., FILL OUT AND ATTACH A DEFICIENCY REPORT
WHEN A DEFICIENCY, YOURS OR A PREVIOUS INSPECTORS, IS CORRECTED, SO NOTE ON THE ORIGINAL DEFICIENCY REPORT AND
SUBMIT A COPY WITH YOUR WEEKS REPORTS.
MATERIALS USED BY CONTRACTOR: (INCLUDE RESEARCH REPORT NO. OR MATERIAL TEST REPORTS):
WELDING ELECTRODES SMAW E-7018
CONTRACTORS EQUIPMENT / MANPOWER USED:
WELDING MACHINE: MQ Whisperweld BLW-400SSW2, Lincoln Shield -Arc SA -250, Miller trailblazer 301G
AREA, GRIDLINES, PIECES OBSERVED:
(1) In Progress: Erection of Canopy framing from line B.2 to F.3 between lines6 & T.
(2) Completed Welding:
a) Tube steel to top of roof joists on line 4 from A to C.
b) Tube steel to top of roof joists on line 5 from A to C.
c) Square plates to wall embeds at bottom cord of roof joists at lines A3, A4 and A5.
STRUCTURAL NOTES, DETAIL, OR RFIS USED: (PER APPROVED PLANS)
REMARKS: INCLUDING MEETINGS:
REWORK AS PERCENT OF ALL WORK TODAY: PERCENT PROJECT COMPLETION:
WEATHER: cool SAMPLES TAKEN: n/a
TEMPERATURE: 73 deg. F TESTS REQUIRED: n/a
SITE TIME START: 7:00 AM SITE TIME FINISH: 4:30 PM
LUNCH PERIOD: 1/2 Hr. TRAVEL TIME: ERIFIED BY
i uv DT �cn t it T i ntAI i nrwt: MKOUNALLT UtsstKVtU ALL Ut I Ht WUHK LISTED ABOVE AND THAT THIS WORK COMPLIES WITH
THE SOIL INVESTIGATION RECOMMENDATIONS, AND / OR THE APPROVED PLANS, SPECIFICATIONS AND APPLICABLE SECTION OF THE
BUILDING CODE, UNLESS OTHERWISE NOTED
IN THE DEFICIENCY REPORT.
7
z,l 0849264-85
Signature ICBO Certification Number
Steve W. Bodnar 12/15/2005 City Of La Quinta
Print Name Date Of Report City / County Certification Number
CORPORATE
2992 E. La Palma Ave., Suite A
Anaheim, CA 92806
Tel: 714.632.2999
Fax: 714.632.2974
San Diego / Imperial County
7313 Carroll Road, Suite G
San Diego, CA 92121
Tel: 858.537.3999
Fax: 858.537.3990
FIELD REPORT
Inland Empire
14320 Elsworth Street, Suite C101
Moreno Valley, CA 92553
Tel: 951.653.4999
Fax: 951.653.4666
Type Of Work X INSPECTOR TECHNICIAN
SSW
AVAILABLE: SOIL REPORT (Y) (N) SPECS. (Y)
APPROVED PLANS (Y) APPROVED SHOP DRAWINGS (Y)
ARCHITECT: Smith Consulting Architects
12220 EI Camino Real Suite 200 San Diego, CA 92130
FOR WEEK ENDING 12117/2005
PROJECT N0<, -,?1'1B303
ENGINEER: CSSI
2445 Fifth Street Suite 300 San Diego, CA 92102
REPORT NO. 2 PG 1 OF 1
CONTRACTOR: Vratsinas Construction Co.
P.O. Box 2558 Little Rock, AR 72203
PLAN FILE NO.
PERMIT NO. 04-6326
SUB -CONTRACTOR: Portola Constructios, Inc.
10722 Edison Court Rancho Cucamonga, CA 91730
PROJECT NAME: Bed bath & Beyond
INSPECTION ADDRESS: 79-110 Highway 111
La Quints, CA
ADDRESS OF PROJECT: 79-110 Highway 111
La Quinta, CA
REPORTING REQUIREMENTS: ICBO FIELD INSPECTION MANUAL ! MTGL SOIL MANUAL -REVIEW PREVIOUS REPORTS AND LISTS
IF THERE IS NON -CONFORMING WORK AT THE END OF THE WORK DAY, OR MISSING MTRS, AND RFIS, ETC., FILL OUT AND ATTACH A DEFICIENCY REPORT
WHEN A DEFICIENCY, YOURS OR A PREVIOUS INSPECTORS, IS CORRECTED, SO NOTE ON THE ORIGINAL DEFICIENCY REPORT AND
SUBMIT A COPY WITH YOUR WEEKS REPORTS.
MATERIALS USED BY CONTRACTOR: (INCLUDE RESEARCH REPORT NO. OR MATERIAL TEST REPORTS):
WELDING ELECTRODES SMAW E-7018
CONTRACTORS EQUIPMENT / MANPOWER USED:
WELDING MACHINE: MQ Whisperweld BLW-400SSW2, Lincoln Shield -Arc SA -250, Miller trailblazer 301 G
AREA, GRIDLINES, PIECES OBSERVED:
(1) In Progress:
Erection of canopy framing from line B.2 to F.3 between lines 6 & 7.
(2) Completed Welding:
a) Tube steel to top of roof joists on line 3 from line A to C.
b) Splice plates to top cord of roof joists on lines 3 and 4 from line A to 1.
STRUCTURAL NOTES, DETAIL, OR RFIS USED: (PER APPROVED PLANS)
REMARKS: INCLUDING MEETINGS:
REWORK AS PERCENT OF ALL WORK TODAY: PERCENT PROJECT COMPLETION:
WEATHER: cool SAMPLES TAKEN: n/a
TEMPERATURE: TESTS REQUIRED: Na
SITE TIME START: 7:00 AM SITE TIME FINISH: 4:30 PM
LUNCH PERIOD: 1/2 HR TRAVEL TIME: VERIFIED BY
f 111.,1 , -Q rCKJUIVMLLT UDJCKVtU ALL Ur I HE VVUHK LISTED ABOVE AND THAT THIS WORK COMPLIES WITH
THE SOIL INVESTIGATION RECOMMENDATIONS, AND / OR THE APPROVED PLANS, SPECIFICATIONS AND APPLICABLE SECTION OF THE
BUILDING ODE, UNLESS OTHERWISE NOTED IN THE DEFICIENCY REPORT.
Signature
Steve W. Bodnar 12/16/2005
Print Name Date Of Report
0849264-85
ICBO Certification Number
City Of La Quinta
City / County Certification Number