11-0773 (RC) Ste. 110P.O. BOX 1504
78-495 CALLE TAMPICO
LA QUINTA, CALIFORNIA 92253
Application Number: �_ _11-00000773—
Property
11-00000773—Property Address: 78134 - CALLE TAMPICO STE 110
APN: 770-020-012- - -
Application description: REMODEL - COMMERCIAL
Property Zoning: VILLAGE COMMERCIAL
Application valuation: . .12000
Tay/ 4�
VOICE (760) 777-7012
FAX (760) 777-7011 .
BUILDING & SAFETY DEPARTMENT INSPECTIONS (760) 777-7153
BUILDING PERMIT
Date: 8/09/11
Owner:
HIGHLAND LA QUINTA II LLC
80 S LAKE AVE STE 660
PASADENA, CA 91101 i 72
IF /1
c (� �t
I:
Contractor:
Applicant: Architect or Engineer: CONSTRUCTION ZONE, THE
77799 JACKEL DRIVE, SUIPE B (+,F5,A.0`U11NTA
PALM DESERT, CA 92211 r ra1C,`;S?:_:K�
(760)772-3585
I /Qr LiC. No.: 740276
---------------------------------------------------------------------------------------------------
LICENSED CONTRACTOR'S DECLARATION
I hereby affirm under penalty of perjury that I am licensed under provisions of Chapter 9 (commencing with
Section 7000) of Division 3 of the Business and Professionals Code, and my License is in full force and effect.
Liceose Class: B C cense No.: 740276
Date: �ontractor. L
OWNER -BUILDER DECLARATION
I hereby affirm under penalty of perjury that I am exempt from the Contractor's State License Law for the
following reason (Sec. 7031.5, Business and Professions Code: Any city or county that requires a permit to
construct, alter, improve, demolish, or repair any structure, prior to its issuance, also requires the applicant for the
permit to file a signed statement that he or she is licensed pursuant to the provisions of the Contractor's State
License Law (Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code) or
that he or she is exempt therefrom and the basis for the alleged exemption. Any violation of Section 7031.5 by
any applicant for a permit subjects the applicant to a civil penalty of not more than five hundred dollars ($500).:
(_ 1 I, as owner of the property, or my employees with wages as their sole compensation, will do the work, and
the structure is not intended or offered for sale (Sec. 7044, Business and Professions Code: The
Contractors' State License Law does not apply to an owner of property who builds or improves thereon,
and who does the work himself or herself through his or her own employees, provided that the
improvements are not intended or offered for sale. If, however, the building or improvement is sold within
one year of completion, the owner -builder will have the burden of proving that he or she did not build or
improve for the purpose of sale.).
(_ 1 I, as owner of the property, am exclusively contracting with licensed contractors to construct the project (Sec.
7044, Business and Professions Code: The Contractors' State License Law does not apply to an owner of
property who builds or improves thereon, and who contracts for the projects with a contractor(s) licensed
pursuant to the Contractors' State License Law.).
( 1 I am exempt under Sec. , B.&P.C. for this reason
Date:
Owner:
CONSTRUCTION LENDING AGENCY
I hereby affirm under penalty of perjury that there is a construction lending agency for the performance of the
work for which this permit is issued (Sec. 3097, Civ. C.).
Lender's Name:
Lender's Address: W1 JA
.0
LQPERMIT
WORKER'S COMPENSATION DECLARATION
I hereby affirm under penalty of perjury one of the following declarations:
_ 'I have and will maintain a certificate of consent to self -insure for workers' compensation, as provided
for by Section 3700 of the Labor Code, for the performance of the work for which this permit is.
issued.
y I have and will maintain workers' compensation insurance, as required by Section 3700 of the Labor
Code, for the performance of the work for which this permit is issued. My workers' compensation
insurance carrier and policy number are: '
Carrier ULLICO CASUALTY Policy Number UWHA48600009210
I certify that, in the performance of the work for which this permit is issued, I shall not employ any
person inany manner so as to become subject to the workers' compensation laws of California,
and agree that, if I should become subject to the workers' compensation provisions of Section
C 3700 of the L boorr�Code, I shall forthwith comply with those provisions. .
11 -ate: 7 �� pplican, x
WARNING: FAILURE TO SECURE WORKERS' COMPENSATION COVERAGE IS UNLAWFUL, AND SHALL
SUBJECT AN EMPLOYER TO CRIMINAL PENALTIES AND CIVIL FINES UP TO ONE HUNDRED THOUSAND
DOLLARS ($100,000). IN ADDITION TO THE COST OF COMPENSATION, DAMAGES AS PROVIDED FOR IN
SECTION 3706 OF THE LABOR CODE, INTEREST, AND ATTORNEY'S FEES.
APPLICANT ACKNOWLEDGEMENT
IMPORTANT Application is hereby made to the Director of Building and Safety for a permit subject to the
conditions and restrictions set forth on this application.
1 . Each person upon whose behalf this application is made, each person at whose request and for
whose benefit work is performed under or pursuant to any permit issued as a result of this application, .
the owner, and the applicant, each agrees to, and shall defend, indemnify and hold harmless the City
of La Quinta, its officers, agents and employees for any act or omission related to the work being
performed under or following issuance of this permit.
2. Any permit issued as a result of this application becomes null and void if work is not commenced
within 180 days from date of issuance of such permit, or cessation of work for 180 days will subject
permit to cancellation.
I certify that I have read this application and state that the above information is correct. I agree to comply with all
city and county ordinances and state laws relating to building construction, and hereby authorize representatives
of t county to enter upon the above-mentioned property for inspection purposes.
a15 te:-��Si ture (Applicant or Agent): D
Application Number
. . . . . 1 11-00000713
Structure Information
Construction Type
. . . . . TYPE V, UNPROTECTED
Occupancy Type .
. . . . . BUSINESS <50
Other struct info
. . . . . CODE EDITION
2010
FIRE SPRINKLERS
YES
OCCUPANT LOAD
41.00
-----------------------------------------------------------------------------
1ST FLOOR SQUARE FOOTAGE
1718.00
Permit .. . . . .
. BUILDING PERMIT'
Additional desc .
.
Permit Fee . . .
135.00 Plan Check Fee
87.75
Issue Date . . .
. valuation . .
. . 12000
Expiration Date
2/05/12
Qty Unit Charge
Per
Extension
BASE FEE
45.00
10.00 9.0000
THOU BLDG 2,001-25,000
90.00
---------------
--------------------------------------------------------
Special NotesandComments
1718 SF INT. T.I.
FOR DANCE STUDIO. 2010
CODES
-------------------------------------------------------------------------
Other Fees . . .
. . . . . . ACCESSIBILITY PLAN REVIEW 8.77.
BLDG STDS ADMIN (SB1473)
1,00
ENERUY REVIEW FEE
8.77
Fee summary
Charged Paid Credited
-------
---7--Permit
Due
-----------------
PermitFee Total
135.00 .00 ..00
135.00
Plan Check Total
87.75 .00 .00
87.75
Other Fee Total
18.54 .00 .00
18.54
Grand Total
241.29 .00 .00
241.29
LQPERAIIT
Bin #
City of La Quin'ta
Building &r Safety, Division
-Box 1504, 78-495 Calle Tampico
La Quinta, CA 92253 - (7.60) 777-7012
99� Building Permit Application and Tracking Sheet
Permit #P.O.
Project Address:
Owner's Name:. All, hC4 ZA 0kj)1TA- Z LCC
A. P. Number: O
Address: SO 44 kq- A Lk-
. Legal Description:
City, ST, Zip: PA.J,wQA-
Contractor: V 6-Telephone:
ZIC3�_JV(30
Address: 7 7-7 J-A JQ f)e 13
Project Description:
City, ST, Zip:
Telephone._o- 3 (-7 2 7 1
I-j1A_C--1A C—(19-cj(L14 I
State Lic. 9 : 7((0 Z 7( :,
City Lic. #:
Arch., Engr., Designer:
Address:
City, ST, Zip:
Telephone:
......
. . . . . . . . . .
Construction Type: Occupancy:
State Lic. #:
Project type (circle one): New Add'n Alter Repair Demo
Name of Contact Person: (f c- 1c-- A f f AA
Sq. Ft.: 1718
# Stories:
#Units:
Telephone # of Contact Person: 71.0 - _SG7, 2 21
Estimated Value of Project:
APPLICANT: DO NOT WRITE BELOW THIS LINE
N
Submittal
Reqld
Recld
TRACKING
PERMIT FEES
Plan Sets
3
Plan Check submitto'71Item
Amount'
Structural CaIcs.
Reviewed, ready for corrections 9/79.�
Plan Check Deposit
Truss Calts.
Called Contact Person
Plan Check Balance.
Title 24 Calcs.
pi
Plans picked up
Construction
Flood plain plan
Plans resubmitted
Mechanical
Grading plan
21" Review, ready for correction CH
Electrical
Subcontactor List
Called Contact Person
Plumbing
Grant Deed
Plans picked up
S.M.I.
H.O.A. Approval
Plans resubmitted
Grading
IN HOUSE:-
Review, ready for corrections/issue
Developer Impact Fee
Planning Approval
,
I Called Contact Person
A.I.P.P
Pub. Wks. Appr
Date of permit issue
School Fees
10
4dPFr
Total Permit Fees
!Z7.2
7 1.16 . � fRedp" d-44 7/25/// 7118 UW-
P.O. Box 1504
78-495 CALLE TAMPICO
LA QUINTA, CALIFORNIA- ?2253
�r CV
R
BUILDING' & SAFETY DEPARTMENT
(760) 777-7012
FAX (760) 77 7-70 11
To: Greg Butler, Building & Safety Manager To CDD: 7 " 16 -4
From: Les Johnson, Director -Planning Due•Date: 7
oU-) J
Permit #: Status: %�T ale-
Building
lBuilding Plans Approval
(This is an approval to issue a Building Permit)'
The. Planning Department has . rev,sewed the Building Plans .for the following
project:
Description:��
Address or General Location: 7- /38
Applicant Contact: 6tZ&3e 7 - 567 - 2 Z!
The Planning Department finds that:
❑ . ...these Building Plans do not require Planning Department approval.
...these Building Plans are approved by the Planning Department.-
0
epartment:❑ ...these Buildig Plans requi:-e corrections. Please forward'a copy of the
attached corr. ctions to the applicant:. When the corrections are made
Upleaseetur them to the Planning Department for review.
, Director -Planning
recon d
JUL 18 2011
city of La Quinta
Planning Depcs4rcnt
Date
a
18 CALLE TAMPICO - SUITE ADDRE SSING
THE PLAZA @ CALLE TAMPICO -SHOP BUILDING 1
grouna tio.orplan: B.HOP BUILDING '1 1
scale.: 118' = -1,4,
<11
-TITLE 24 REPORT
Title 24 Report for:
The Plaza @ Calle Tampico' Shop Bldg 2
NW Crnr of Calle Tampico & Desert Club Dr -
La Quinta , Ca 92253
Project Designer:
Olshan & Associates
811 7th Street #B
Santa Monica, Ca 90405-1407
310-394-3132 ,
Report Prepared By:
Yam Chapagain a
Fruchtman & Associates, Inc.
12655 Washington Blvd., Ste. 204
Los Angeles, CA 90.066- -
(310)
66-
(310) 915-6110
CITY OF LA QUINTA. _4
L 18 2011
BUILDING & SAFETY DEPT. i -
� Job Number:.
----�.
ROVETamp1495
FOR CONSTRUCTION
DATE B "1 &166' s Date •
�77t-.. 2/12/2008
The EnergyPro computer program has been used to perform the calculations summarized in this compliance report. This program has approval and is
authorized by the California Energy Commission for use with both the Residential and Nonresidential 2005 Building Energy Efficiency Standards.
This program developed by EnergySoft, LLC - www.energysoft.com.
EnergyPro 4.2 by EnergySoft Job Number: Tamp1495 User Number: 4469
t
EnergyPro 4.2 by EnergySoft Job Number: Tampl495 User Number: 4469
(PERFORMANCE CERTIFICATE OF COMPLIANCE Part 1 of 3 PERF -11
PROJECT NAME
This Certificate of Compliance lists the building features and performance specifications needed to comply with Title 24, Parts 1 and 6 of the
DATE
The Plaza @ Calle Tampico Shop Bldg 2
DOCUMENTATION AUTHOR
2/12/2008
PROJECT ADDRESS
BUILDING CONDITIONED FLOOR AREA
12,024 Sq.Ft.
NW Crnr of Calle Tampico & Desert Club Dr
La Quinta
BUILDING TYPE
PRINCIPAL DESIGNER - ENVELOPE
NONRESIDENTIAL HIGH RISE RESIDENTIAL
TELEPHONE
Building Permit #
Olshan & Associates
NEW CONSTRUCTION ADDITION
310-394-3132
EXISTING + ADDITION/ALTERATION
DOCUMENTATION AUTHOR
❑ F-1 F� 3. 1 affirm that I am eligible under Division 3 of the Business and Professions Code to sign this document
TELEPHONE
Checked by/Date
Fruchtman & Associates, Inc.
ENVELOPE COMPLIANCE
(310) 915-6110
EnforcememAgency Use
GENERAL INFORMATION
This Certificate of Compliance lists the building features and performance specifications needed to comply with Title 24, Parts 1 and 6 of the
California Code of Regulations. This certificate applies only to a Building using the performance compliance approach.
The documentation preparer hereby certifies that the documentation is accurate and complete.
DOCUMENTATION AUTHOR
DATE OF PLANS
10-12-07
BUILDING CONDITIONED FLOOR AREA
12,024 Sq.Ft.
CLIMATE ZONE
15
BUILDING TYPE
®
NONRESIDENTIAL HIGH RISE RESIDENTIAL
HOTEL/MOTEL GUEST ROOM
PHASE OF CONSTRUCTION
®
NEW CONSTRUCTION ADDITION
❑ ❑ R 2. 1 affirm that I am eligible under the provisions of Division 3 of the Business and Professions Code Section
EXISTING + ADDITION/ALTERATION
STATEMENT OF COMPLIANCE
This Certificate of Compliance lists the building features and performance specifications needed to comply with Title 24, Parts 1 and 6 of the
California Code of Regulations. This certificate applies only to a Building using the performance compliance approach.
The documentation preparer hereby certifies that the documentation is accurate and complete.
DOCUMENTATION AUTHOR
SIGNATURE
DATE
Yam Cha a ain
The Principal Designer hereby certifys that the proposed building design represented in this set of construction documents is
consistent with the other compliance forms and worksheets, with the specifications, and with.any other calculations submitted with this
permit application. The proposed building as designed meets the energy efficiency requirements contained in sections 110, 116,
through 118, and 140, 142, 143 or 149 of Title 24, Part 6.
ENV. LTG. MECH.
❑ ❑ ❑ 1. 1 hereby affirm that I am eligible under the provisions of Division 3 of the Business and Professions Code to
sign this document as the person responsible for its preparation; and that I am licensed in the State of
California as a civil engineer, mechanical engineer, or I am a licensed architect.
❑ ❑ R 2. 1 affirm that I am eligible under the provisions of Division 3 of the Business and Professions Code Section
5537.2 or 6737.3 to sign this document as the person responsible for its preparation; and that I am a licensed
contractor performing this work.
❑ F-1 F� 3. 1 affirm that I am eligible under Division 3 of the Business and Professions Code to sign this document
because it pertains to a structure or type of work described as exempt pursuant to Business and Professions
Code Sections 5537, 5538, and 6737.1. (These sections of the Business and Professions Code are printed in
full in the Nonresidential Manual.)
ENVELOPE COMPLIANCE
Indicate location on plans of Note Block for Mandatory Measures
Envelo a Compliance Not In The Scope Of
Required Forms
IS U mittai
PRINCIPAL ENVELOPE DESIGNER - NAME
SIGNATURE
LIC. NO.
DATE
LIGHTING COMPLIANCE
Indicate location on plans of Note Block for Mandatory Measures
Lighting Compliance Not In The Scope Of
Required Forms
1111 s Submittal
PRINCIPAL LIGHTING DESIGNER - NAME
SIGNATURE
LIC. NO.
DATE
MECHANICAL COMPLIANCE
Indicate location on plans of Note Block for Mandatory Measures
MECH-1 MECH-2 MECH-3 MECH-5
Required Forms
PRINCIPAL MECHANICAL DESIGNER - NAME
SIGNATURE
LIC. NO.
DATE
Fruchtman & Associates Inc
I EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamp1495 Page:3 of 28 1
PERFORMANCE CERTIFICATE OF COMPLIANCE 'Part 2 of 3 J PERF -1
PROJECT NAMEDATE
The Plaza C@ Calle Tampico Shop Bld 2 r' 2/12/2008
ANNUAL TDV ENERGY USE SUMMARY kBtu/s ft- r
Standard Proposed
ENERGY COMPONENT Design Design
Space Heating 0.01 0.01
Space Cooling 437.47 396.19
Indoor Fans 141.02 151.71
Heat Rejection 6.00 0.00
Pumps & Misc. 0.00 0.00
Domestic Hot Water ` 16.36 16.39-
Lighting 187.32 187.32
Receptacle
Process
TOTALS: 869.65 839.05
Percent better than Standard: 3.5%
.
Compliance,
Margin
'
[❑spa°aam Popo:ed
0.00°"
°0�°•B;a ��
Hmf p8lt ., �._ .
'At
,
`� `.•"
0 30 80 I.90 120 150 1-80 210 240 270 300 330 380 390 420
k61u/-41-y1
- 9
41.28
-10.69
� 0.00
0.00BR
0.00
0.00
910
30.59
process)
(: 3.5% excluding
• BUILDING COMPLIES
GENERAL INFORMATION
Building Orientation
Number of Stories
Number of Systems
Number of Zones
s 180 deq
Conditioned Floor Area.
Unconditioned Floor Area •
Conditioned Footprint Area •
Fuel -Type
12,024
sgft.
sgft. r
sgft.
'
1
0
- 9
12,024
7
Natural Gas
Left Elevation
Orientation Gross Area Glazing Area Glazing Ratio
Front Elevation
S
2,456
sgft.
1,123
sgft:
45.7%.
Left Elevation
(w)
910
sgft.
157
sgft.
17.3%
Rear Elevation
N
2,456
sgft. ,
o
sgft.
0.0%
'Right Elevation
Total
Roof
(E)
1 910
x,732
.12,023
sgft.
sgft.
Y
sgft.
157 sgft.
1,437 sgft.
o sgft.
17.3%
-
Standard Proposed
Lighting Power Density 1.700 wisgft. 1.700 wisgft.
.Prescriptive Env. Heat Loss 1,809 eium 2616 Btu/h
Prescriptive Env. Heat Gain 208,638 Btwh-F 356,507 Btuih-F
Remarks:
` Run Initiation Time: 02/12/08 09:46:53 Run Code: 1202838413
EnergyPro 4.2 by Energysoft 7 . User Number: 4469 Job Number: Tamp1495 � Page:4 of 28
PERFORMANCE CERTIFICATE OF COMPLIANCE Part 3 of 3 PERF -1
PROJECT NAME
The Plaza @ Calle Tampico
Shop Bldg 2
DATE
2/12/2008
ZONE INFORMATION
-
System Name Zone Name
Occupancy Type
Floor
Area
(sgft.)
Inst.
LPD
(W/sf)1
Ctrl.
.Credits
(W/sf)2
Allowed LPD Proc.
Area - Tailored Loads
(W/S3 (W/S4 (W/sf)
PGE -2G SPACE -G
'Retail Sales, Wholesale
2,272
-1.70
PGE -2F SPACE -F
Retail Sales, Wholesale
1,622
'1.70
'
PGE -2E SPACE -E
Retail Sales, Wholesale
1,622
.- '1.70
`
PGE -2D SPA CE -D
Retail Sales, Wholesale
1,622
'1.70
•.
PGE -2C SPACE -C
Retail Sales, Wholesale
1,622
'1.70
PGE -2B SPACE -B
Retail Sales, Wholesale
1,621
' -1.70C
f
PGE -2A SPACE -A ..
Retail Sales, Wholesale '
1,644
'1.70
c,
y
.
Notes: 1. See LTG -2-C
(items marked with asterisk, see LTG -2 -C by others)
2. See LTG -4-C 3. See LTG -5-C
(by others)
4. See LTG -6-C
Items above require special documentation
EXCEPTIONAL CONDITIONS COMPLIANCE CHECKLIST
The local enforcement agency should pay special attention to the items specified in this checklist. These items require special written justification
and documentation, and special verification to be used with the performance approach. The local enforcement agency determines the adequacy of
the justification, and may reject a building or design that otherwise complies based on the adequacy of the special justification and documentation
submitted. r ` • •
The HVAC System "PGE -6T Carrier48HJ " includes an Economizer. This s stem has a cooling output < 75,000 Btuh or a supply cfm < 2500. '
The HVAC System "PGE -6T Carrier48HJ " is designated as 3 Phase, or is Exempted from the NAECA 13 SEER requirement.
The HVAC System "PGE -6T Carrier481-!J " includes Demand Control Ventilation per Standards Section 121.
The HVAC System "PGE -5T (Carrier48hj) " is designated as 3 Phase, or is Exempted from the NAECA 13 SEER requirement.
The exceptional features listed in this performance approach application have specifically been reviewed. Adequate written justification and r
documentation for their use have been provided by the applicant. '
Authorized Signature or Stam `
Run Initiation Time: 02/12/08 09:46:53 - Run Code: 1202838413
EnergyPro 4.2 by EnergySott User Number: 4469 Job Number: Tamp1495 Page:5 of 28
CERTIFICATE OF COMPLIANCE MECH-I-C I
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldci 2 1
2/12/2008
Designer:
This form is to be used by the designer and attached to the plans. Listed below are all the acceptance tests for mechanical systems. The designer is required to
check the boxes by all acceptance tests that apply and list all equipment that requires an acceptance test. If all equipment of a certain type requires a test, list the
equipment description and the number of systems to be tested in parentheses. The NJ number designates the Section in the Appendix of the Nonresidential
ACM Manual that describes the test. Also indicate the person responsible for performing the tests (i.e. the installing contractor, design professional or an agent
selected by the owner). Since this form will be part of the plans, completion of this section will allow the responsible party to budget for the scope of work
appropriately.
Building Departments:
SYSTEM ACCEPTANCE. Before an occupancy permit is granted for a newly constructed building or space, or a new space -conditioning system serving a
building or space is operated for normal use, all control devices serving the building or space shall be certified as meeting the Acceptance Requirements for
Code Compliance.
In addition a Certificate of Acceptance, MECH-I-A Form shall be submitted to the building department that certifies plans, specifications, installation
certificates, and operatinq and maintenance information meet the requirements of Section 10-103(b) and Title 24 Part 6.
STATEMENT OF COMPLIANCE
❑ MECH-2-A: Ventilation System Acceptance Document
-Variable Air Volume Systems Outdoor Air Acceptance
-Constant Air Volume Systems Outdoor Air Acceptance
Equipment requiring acceptance testing
Test required on all New systems both New Construction and Retrofit.
❑ MECH-3-A: Packaged HVAC Systems Acceptance Document
Equipment requiring acceptance testing
Test required on all New systems both New Construction and Retrofit.
❑ MECH-4-A: Air -Side Economizer Acceptance Document
Equipment requiring acceptance testing
'
Test required on all New systems both New Construction and Retrofit. Units with economizers that are installed at the factory and certified with the
commission do not require equipment testing but do require construction inspection.
❑ MECH-5-A: Air Distribution Acceptance Document
Equipment requiring acceptance testing
This test required If the unit serves 5,000 V of space or less and 25% or more of the ducts are in nonconditioned or semiconditioned space like an
attic. New systems that meet the above requirements. Retrofit systems that meet the above requirements and either extend ducts, replace ducts or
replace the packaged unit.
❑ MECH-6-A: Demand Control Ventilation Acceptance Document
Equipment requiring acceptance testing
Agnew DCV controls installed on new or existing packaged systems must be tested.
❑ MECH-7-A: Supply Fan Variable Flow Control Acceptance Document
Equipment requiring acceptance testing
All new VA fan volume controls installed on new or existing systems must be tested
❑ MECH-8-A: -Hydronic System Control Acceptance Document
-Variable Flow Controls Applies to chilled and hot water systems.
-Automatic Isolation Controls Applies to new boilers and chillers and the primary pumps are connected to a common header.
-Supply Water Temperature Reset Controls
Applies to new constant flow chilled and hot water systems that have a design capacity greater than or equal to 500,000 Btu/hr.
-Water-loop Heat Pump Controls
Applies to all new waterfoop heat pump systems where the combined loop pumps are greater than 5 hp.
-Variable Frequency Controls Applies to all new distribution pumps on new variable flow chilled, hydronic heat pump
or condenser water systems where the pumps motors are greater than 5 hp.
.
Equipment re uirin acceptance testing
EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamp1495 Page:6 of 28
IAIR SYSTEM REQUIREMENTS Part 1 of 2 MECH-2-CI
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM FEATURES
ITEM OR SYSTEM TAG(S)
Number of Systems
T-24
MANDATORY MEASURES Section
Heating Equipment Efficiency
Cooling Equipment Efficiency
Heat Pump Thermostat
Furnace Controls
Natural Ventilation
Minimum Ventilation
VAV Minimum Position Control
Demand Control Ventilation
Time Control
Setback and Setup Control
Outdoor Damper Control
Isolation Zones
Pipe Insulation
Duct Insulation
PRESCRIPTIVE MEASURES
Calculated Heating Capacity x 1.43 2
Proposed Heating Capacity 2
Calculated Sensible Cooling Capacity x 1.212
Proposed Sensible Cooling Capacity 2.
Fan Control
DP Sensor Location
Supply Pressure Reset (DDC only)
Simultaneous Heat/Coal
Economizer
Heating Air Supply Reset
Cooling Air Supply Reset
Duct Sealing for Prescriptive Compliance
AIR SYSTEMS Central or Single Zone
PGE -2G,
PGE -2F
PGE -2E
2
1
1
Reference on Plans or Specification
112(a)
82%AFUE
82%AFUE
82%AFUE
112(a)
13.0 SEER / 11.0 EER
9.0 EER
9.0 EER
112(b)
n/a
n/a
n/a
112(c), 115(a)
n/a
n/a
n/a
121(b) -
Yes
Yes.
Yes
121 b
568 cfm
405 cfm
405 cfm
121 c
No
No
No
121 c
No
Yes
Yes
121(c), i22(e)
Pro rammable Switch
Programmable Switch
Programmable Switch
122(e)
Heating & Cooling Required Heating & Cooling Required Heating & Cooling Required
122(f)
Auto
Auto
Auto
122
n/a
n/a
n/a
123
No
124
R-8.0
R-8.0 -
R-8.0
144 a & b
n/a
n/a
n/a
144 a & b
118,080 btuh.
59,040 btuh
59,040 btuh
144 a & b
n/a
n/a
n/a
144 a & b
93,968 btuh
59,565 btuh
59,565 btuh
144 c
Constant Volume
Constant Volume
Constant Volume
144 c
144 c
Yes
Yes
Yes
144 d
No
No
No
144 a
No Economizer
Diff. Enth Inte rated
Diff. Enth (Integrated)
144 f
Constant Temp
Constant Temp
Constant Tem
144 (f)
Constant Temp
Constant Temp
Constant Temp
144 k
. No '
No
No
1: For each central and single zone air systems (or group of similar units) fill in the reference to sheet number and/or specification section and paragraph number where the
required features are documented. If a requirement is not applicable, put "N/A" in the column.
2: Not required for hydronic heating and cooling. Either enter a value here or put in reference of plans and specificatons per footnote 1.
3: Enter Yes if System is: Constant Volume, Single Zone; Serves < 5,000 sgft; Has > 25% duct in unconditioned space. 'Duct sealing is required for Prescriptive Compliance,
see PERF -1 for performance method duct sealing requirements.
EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamp1495 Page:7 of 28 1
JAIR SYSTEM REQUIREMENTS . Part 1 of 2 MECH-2-Cl
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM FEATURES
ITEM OR SYSTEM TAG(S)
Number of Systems
AIR SYSTEMS Central or Single Zone
PGE -2D
PGE -2C
PGE -26
1
1
1
T-24
MANDATORY MEASURES Section Reference on Plans or Specification
Heating Equipment Efficiency
Cooling Equipment Efficiency
Heat Pump Thermostat
Furnace Controls
Natural Ventilation
Minimum Ventilation
VAV Minimum Position Control
Demand Control Ventilation
Time Control
Setback and Setup Control
Outdoor Damper Control
Isolation Zones
Pipe Insulation
Duct Insulation
PRESCRIPTIVE MEASURES
Calculated Heating Capacity x 1.43 2
Proposed Heating Capacity 2
Calculated Sensible Cooling Capacity x 1.212
Proposed Sensible Cooling Capacity 2
Fan Control
DP Sensor Location
Supply Pressure Reset (DDC only)
Simultaneous Heat/Cool
Economizer
Heating Air Supply Reset
Cooling Air Supply Reset
Duct Sealing for Prescriptive Compliance
112(a)
82% AFUE
82% AFUE
82% AFUE
112(a)
9.0 EER
9.0 EER
9.0 EER
112(b)
n/a
n/a
n/a
112(c), 115(a)
n/a
n/a
n/a
121(b)
Yes
Yes
Yes
121 b
405 cfm
405 cfm
405 cfm
121 c
No
No
No
121 c
Yes
Yes
Yes
121 c 122(e)
Pro rammable Switch
Programmable Switch
Programmable Switch
122(e)
Heating & Cooling Required Heating & Cooling Required Heating & Cooling Required
122(f)
Auto
Auto
Auto
122
n/a I
n/a
n/a
123
No
124
R-8.0
R-8.0 -
R-8.0
144 a & b
n/a
n/a
n/a
144 a & b
59,040 btuh
59,040 btuh
59,040 btuh
144 a & b
n/a
n/a
n/a
144 a & b
56,151 btuh
56,144 btuh
56,144 btuh
144 c
Constant Volume
Constant Volume
Constant Volume
144 c
144 c
Yes
Yes
Yes
144 d
No
No
No
144 a
Diff. Enth (Integrated)
Diff. Enth (Integrated)
Diff. Enth (integrated)
144 f
Constant Temp
Constant Temp
Constant Tem
144 (f)
Constant Temp
r
Constant Temp
Constant Temp
144 k
No
No
No
1: For each central and single zone air systems (or group of similar units) fill in the reference to sheet number and/or specification section and paragraph number where the
required features are documented. If a requirement is not applicable, put "N/A" in the column.
2: Not required for hydronic heating and cooling. Either enter a value here or put in reference of plans and specificatons per footnote 1.
3: Enter Yes if System is: Constant Volume, Single Zone; Serves < 5,000 sqft; Has > 25% duct in unconditioned space. Duct sealing is required for Prescriptive Compliance,
see PERF -1 for performance method duct sealing requirements.
EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tampl495 Paae:8 of 28 1
JAIR SYSTEM REQUIREMENTS Part 1 of 2, MECH-2-Cl
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
ITEM OR SYSTEM TAG(S)
Number of Systems
T-24
MANDATORY MEASURES Section Reference on Plans or Specification '
Heating Equipment Efficiency
Cooling Equipment Efficiency
Heat Pump Thermostat
Furnace Controls
Natural Ventilation
Minimum Ventilation
VAV Minimum Position Control
Demand Control Ventilation
Time Control
Setback and Setup Control
Outdoor Damper Control
Isolation Zones
Pipe Insulation
Duct Insulation
PRESCRIPTIVE MEASURES
Calculated Heating Capacity x 1.43 2
Proposed Heating Capacity 2
Calculated Sensible Cooling Capacity x 1.212
Proposed Sensible Cooling Capacity 2
Fan Control
DP Sensor Location
Supply Pressure Reset (DDC only)
Simultaneous Heat/Coal
Economizer
Heating Air Supply Reset
Cooling Air Supply Reset
Duct Sealing for Prescriptive Compliance
1: For each central and single zone air systems (or group of similar units) fill in the reference to sheet number and/or specification section and paragraph number where the
required features are documented. If a requirement is not applicable, put "N/A" in the column.
2: Not required for hydronic heating and cooling. Either enter a value here or put in reference of plans and specificatons per footnote 1.
3: Enter Yes if System is: Constant Volume, Single Zone; Serves < 5,000 sgft; Has > 25% duct in unconditioned space. Duct sealing is required for Prescriptive Compliance,
see PERF -1 for performance method duct sealing requirements.
112(a)
82% AFUE
112(a)
13.0 SEER / 11.0 EER
112(b)
n/a
112(c), 115(a)
n/a
121(b)
Yes
121 b
411 cfm t
121 c
No
121 c
No
121(c), 122(e)
Programmable Switch
122(e)
Heating & Cooling Required
122(f)
Auto
122
n/a
123
124
1 R-8.0
144 a & b
n/a
144 a & b
118,080 btuh
144 a & b
n/a
144 a & b
96,350 btuh
144 c
Constant Volume
144 c
144 c
Yes
144 d
No
144 a
No Economizer
144 f
Constant Tem
144 (f)
Constant Temp
144 k
No
MECHANICAL VENTILATION MECH-3-C
PROJECT NAME DATE
The Plaza P Calle Tampico Shop Bldg 2 2/12/2008
PRESCRIPTIVE REHEAT
LIMITATION Section 144(d))
MECHANICAL VENTILATION Section 121(b)2)
AREA BASIS
OCCUPANCY
BASIS
VAV MINIMUM
A
B
C
D
E
F
G
H
I
J
K
L
M
N
ZONE/SYSTEM
a0
Ned
�fYO
�
N
m
���
T��
°0
W'P
XD3
�im�
3
2Cr
��
CQ
��
0
InM A
?��
m0�
X1077
TjT
`�» 3
vim
�XD
si �.G
D
v
�1 A.
3n3
0 oo
Tye'
C�00
T`
0
'lao
�X
aA
p 0
C 3
p3X
-y0
m.
'pO
03
a F
-11
y
A
D
SPACE -G
2,271
0.25
568
568
568
PGE -2G
Total
568
568
SPACE -F
1,622
0.25
405
405
405
PGE -2F
Total
405
405
SPACE -E
1,621
0.25
405
405
405
'
PGE -2E
Total
405
405
SPACE -D
1,622
0.25
405
405
405
PGE -2D
Total
405
405
SPACE -C
1,622
0.25
405
405
405
PGE -2C
Total
405
405
SPACE -B
1,621
0.25
405
1
405
405
PGE -26
I
Total
405
405
SPACE -A
1,644
0.25
411
411
411
PGE -2A
Total
411
411
E Based on fixed seat or the greater of the expected number of occupants and 50% of the CBC occupant load foregress purposes for spaces without fixed seatin .
H Required Ventilation Air REO'D V.A. is the larger of the ventilation rates calculated on and AREA or OCCUPANCY BASIS column D or G).
I Must be greater than or equal to H or use Transfer Air column N to make up the difference.
J Design Ian supply cfm Fan CFM x 30%; or
K Condition area fl. s x 04 cfm/ft. .: or
L I Maximum of Columns H, J, K, or 300 cfm
M IThis must be less than or equal to Column L and greater that orequal to the sum of Columns H + N.
N Transfer air must be provided where the Required Ventilation Air (column H) is greater than the Design Minimum Air (column M). Where required, transfer air must be greater than or
equal to the difference between the Required Ventilation Air (column H) and the Design Minimum Air (column M), column H - M.
Ener Pro 4.2 by Ener oft User Number: 4469 Job Number: Tam 1495 Page: 10 of 28
MECHANICAL EQUIPMENT DETAILS
Part 1 of 2 MECH-5-C
PROJECT NAME
The Plaza Calle Tampico Shop Bldg 2
DATE 2/12/20
CHILLER AND TOWER M Y
System Type
Distribution Type
Efficiency
Tons
PUMPS
Condition
Status
Equipment Name
Equipment Type
Qty.
Tot.
Qty
GPM
BHP
Motor
Eff.
Drive
Eff.
Pump
Control
MULTI -FAMILY CENTRAL WATER HEATING DETAILS
Hot Water P mp Hot Water Pipina Len th ft
Control
#
HP
Type In Plenum
Outside
Buried
Add 1/2"
Insulation
1QHW BOILER SUMMA Y
Energy
Factor
or RE I
Standby
Loss or
Pilot
TANK INSUL.
System Name
System Type
Distribution Type
Qty
Rated
Input
Vol.
(Gals.)
Condition
Status
Ext.
R -Val.
MULTI -FAMILY CENTRAL WATER HEATING DETAILS
Hot Water P mp Hot Water Pipina Len th ft
Control
#
HP
Type In Plenum
Outside
Buried
Add 1/2"
Insulation
CENTRAL SYSTEM RATINGS
HEATING
COOLING
System Name
System Type
Oty
Output
Aux.
kW
Eff.
Outout
Efficiency
Condition
Status
Economizer Type
PGE -5T (Carrier48hj)
packaged DX
4
59,040
5.0
82%AFUE
62,500
13.0 SEER / 11.0 EER
New
No Economizer
PGE -6T (Carrier48HJ)
Packaged DX
5
59,040
5.0
82%AFUE
73,000
9.0 EER
New
Diff. Enth (Integrated)
CENTRAL SYSTEM FAN SUMMARY
SUPPLY FAN
RETURN
FAN
System Name
Fan Type
Motor Location
CFM
BHP
Motor
Eff.
Drive
Eff.
CFM
BHP
Motor
Eff.
Drive
Eff.
PGE -5T (Carrier48hj)
Constant Volume
Blow -Through
1,750
1.20
82.5%
100.0%
none
PGE -6T (Carrier48HJ)
Constant Volume
Blow -Through
2,400
2.40
84.0%
100.0%
none
Run Initiation Time: 02/12/08 09:46:53 Run Code: 1202838413
EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamp1495 Page: 11 of 28
ENVELOPE MANDATORY MEASURES 7
PROJECT NAME
The Plaza 0 Calle Tampico Shop Blda 2
ENV -MM
DATE •
2/12/2008
DESCRIPTION'- - •
Designer
Enforcement
§ 118(a) Installed Insulating Material shall have been certified by the manufacturer to comply
r
with the California Quality Standards for insulating material, Title 20, Chapter 4, Article
- •.3 ,
X❑ § 118(c) All Insulating Materials shall be installed in compliance with the flame spread rating
}
and smoke density requirements of Sections 2602 and 707 of Title 24, Part 2.
§117(a) All Exterior Joints and openings in the building that are observable sources of air,
`
leakage shall be:caulked, gasketed, weatherstripped or otherwise sealed..
X] § 116(b) Site Constructed Doors, Windows and Skylights shall be caulked between the unit
and the building, and shall be weatherstripped (except for unframed glass doors and
• fire doors).
❑ § 116(a)1 Manufactured Doors and Windows installed shall have air infiltration rates not,
exceeding those shown in Table Number 1-E. of the Standards. Manufactured
fenestration products must be labeled for U -value according to NFRC procedures.
§ 118(e) Demising Walls in Nonresidential Buildings:
The opaque portions of framed demising walls in nonresidential buildings shall have
- insulation with an installed R -value of no less than R-13 between framing members.
s s
M • t
EnergyPro By EnergySoft User Number: User Job Number. • Tamp1495 Page: 12 of 28
MECHANICAL MANDATORY MEASURES Part 1 of 2 MECH-MM
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldq 2 2/12/2008
7
DESCRIPTION
Designer
Enforcement
Equipment and Systems Efficiencies
§111 Any appliance for which there is a California standard established in the Appliance
Efficiency Regulations will comply with the applicable standard.
§ 115(a) Fan type central furnaces shall not have a pilot light.
§ 123 Piping, except that conveying fluids at temperatures between 60 and 105 degrees
Fahrenheit, or within HVAC equipment, shall be insulated in accordance with
Standards Section 123.
§ 124 Air handling duct systems shall be installed and insulated in compliance with
Sections 601, 602, 603, 604, and 605 of the 2001 CMC Standards.
Controls
§ 122(e) Each space conditioning system shall be installed with one of the following:
FXJ § 122(e)1A Each space conditioning system serving building types such as offices and
manufacturing facilities (and all•others not explicitly exempt from the requirements
of Section 112 (d)) shall be installed with an automatic time switch with an
accessible manual override that allows operation of the system during off -hours for
up to 4 hours. The time switch shall be capable of programming different .
schedules for weekdays and weekends and have program backup capabilities that
prevent the loss of the device's program and time setting for at least 10 hours if
power is interrupted; or
F] § 122(e)1 B An occupancy sensor to control the operating period of the system; or
§ 122(e)1 C A 4 -hour timer that can be manually operated to control the operating period of the
system. �-
F_]
§ 122(e)2 Each space conditioning system shall be installed with controls that temporarily
restart and temporarily operate the system as required to maintain a setback
heating and/or a setup cooling thermostat setpoint.
r.
§ 122(g) Each space conditioning system serving multiple zones with a combined
conditioned floor area more than 25,000 square feet shall be provided with isolation
zones. Each zone: shall not exceed 25,000 square feet; shall be provided with
isolation devices, such as valves or dampers, that allow the supply of heating or
cooling to be setback or shut off independently of other isolation areas; and shall
be controlled by a time control device as described above.
® § 122(a&b) Each space conditioning system shall be controlled by an individual thermostat
that responds to temperature within the zone. Where used to control heating, the
control shall be adjustable down to 55 degrees F or lower. For cooling, the control
shall be adjustable up to 85 degrees F or higher. Where used for both heating and
cooling, the control shall be capable of providing a deadband of at least 5 degrees
F within which the supply of heating and cooling is shut off or reduced to a
minimum.
§ 122(c) Thermostats shall have numeric setpoints in degrees Fahrenheit (F) and adjustable
setpoint stops accessible only to authorized personnel.
§ 112(b) Heat pumps shall be installed with controls to prevent electric resistance .
supplementary heater operation when the heating load can be met by the heat
pump alone.
EnergyPro By EnergySoft User Number: User Job Number: Tampl495 Page: 13 of 28
• f
MECHANICAL MANDATORY MEASURES _ Part 2 of 2 MECH-MM ,
PROJECT NAMEThDATE '
e Plaza @ Calle Tam ico Shop Bld 2 2/12/2008
Description
Designer
Enforcement
Ventilation
'
i.
❑X § 121(e) Controls shall be provided to allow outside air dampers or devices to be operated at
the ventilation rates as specified on these plans:-
lans.-❑
F—]§ 122(f) Gravity or automatic dampers interlocked and closed on fan shutdown shall be
provided on the outside air intakes and discharges of all space conditioning and
exhaust systems.
❑ § 122(f) All gravity ventilating systems shall be provided with automatic or, readily accessible
manually operated dampers in all openings to the outside, except for combustion air -
openings. t
§ 121(f)1 Air Balancing: The system shall be balanced in accordance with the National ,
Environmental Balancing Bureau (NEBB) Procedural Standards (1983), or
,
Associated Air Balance Council (AABC) National Standards (1989); or
§ 121(f)2 .. Outside Air Certification: The system shall provide the minimum outside air as
shown on the mechanical drawings, and shall be measured and certified by the
installing licensed C-20 mechanical contractor and certified by (1) the design
mechanical engineer, (2) the installing licenced C-20 mechanical contractor, or (3) the
3 '
person with overall responsibility for the design of the'ventilation system; or
❑ § 121(f)3 Outside Air Measurement: The system shall be equipped with a calibrated local or
;
remote device capable of measuring the quantity of outside air on a continuous
basis and displaying that quantity on a readily accessible display divice; or
`
§ 121(f)4 Another method approved by the Commission.
Service Water Heating Systems
❑ § 113(b)2 If a circulating hot water system is installed, it shall have a control capable of
automatically turning off the circulating pump(s) when hot water is not required. `
§ 113(c) Lavatories in restrooms of public facilities shall be equipped with controls to limit the
outlet temperature to 110 degrees F.
r
i
EnergyPro By EnergySoft User Number: User Job Number: Tamp1495 Page: 14 of 28
HVAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME FLOOR AREA
PGE -2G 2,272
ENGINEERING CHECKS 11SYSTEM LOAD
Number of Systems
2
Heating System
Output per System
59,040
Total Output (Btuh)
118,080
Output (Btuh/sqft)
52.0
Cooling System
Output per System 62,500
Total Output (Btuh) 125,000
Total Output (Tons) 10.4
Total Output (Btuh/sqft) 55.0
Total Output (sgft/Ton) 218.1
Air System
CFM per System
1,750
Airflow (cfm)
3,500
Airflow (cfm/sgft)
1.54
Airflow (cfm/Ton)
336.0
Outside Air (%)
16.2
Outside Air (cfm/sgft)
0.25
Note: values above given at ARI conditions
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM
ISensiblel
Latent
1, CFM
I Sensible
4,170
85,315
14,995 1,354
35,024
0
1,280
525
0
0
568
19,721
6,422 568
26,512
0
0
1,280
525
107,681L:3;:;17 62 586
PGE -5T (Carrier48hj) 93,968 22,625 118,080
5.0 kW Supplemental Electric 0
Total Adjusted System Output 83,968 22,625 118,080
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK177 Aug 2 pm Jan 12 am
EATING SYSTEM PSYCHROMETRICS Airstream Temperatures at Time of Heating Peak
26.0 OF 62.7 OF 62.7 OF 94.4 OF 94.4 OF
O Supply Air Ducts
Outside Air
568 cfm 94.3 of
Supply Fan Heating Coil Aux. Heat Coil
3500 cfm ROOMS
69.9 of 70.0 of
TOOLING SYSTEM
11.0 / 77.6 of
Outside Air
568 cfm
78.4/65.4 of
4.2
Return Air Ducts
83.6 / 67.6 of 83.6 / 67.6 of 58.4 / 57.1 of
--&— .", I
Supply Fan Cooling Coil
3500 cfm
User Number: 4469
Return Air Ducts `5
Job Number: Tampl495
Supply Air Ducts
58.8/57.3OF
51.2% R.H. ROOMS
78.0/65.3OF
15 of 28
1HVAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME FLOOR AREA
PGE -2F 1.622
ENGINEERING CHECKS IFSYSTEM LOAD
Number of Systems
1
Heating System
Output per System
59,040
Total Output (Btuh)
59,040
Output (Btuh/sgft)
36.4
Cooling System
Output per System 73,000
Total Output (Btuh) 73,000
Total Output (Tons) 6.1
Total Output (Btuh/sgft) 45.0
Total Output (sgft/Ton) 266.6
Air System
CFM per System
2,400
Airflow (cfm)
2,400
Airflow (cfm/sgft)
1.48
Airflow (cfm/Ton)
394.5
Outside Air (%)
16.9
Outside Air (cfm/sgft)
0.25
Note: values above given at ARI conditions
26.0 OF 62.5 OF
Outside Air
405 cfm
Supply Fan
2400 cfm
69.9 of
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM
I Sensiblel Latent
CFM I Sensible
61,3 9 32 32 905
PGE -6T (Carrier48HJ) 59,565 10,019 59,040
5.0 kW Supplemental Electric 0
Total Adjusted System Output 59,565 10,019 59,040
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK Sep 2 m Jan 12 am
62.5 of. 85.6 of 85.6 of
Heating Coil Aux. Heat Coil
o .... n:. n.. .
Supply Air Ducts
85.5 of
ROOMS
70.0 of
106.0 / 73.4 of
83.0 167.4 of 83.0 / 67.4 of
59.6 / 58.4 of
Supply Air Ducts
JJWO
Outside Air
405 cfm
Supply Fan Cooling Coil
59.9 / 58.5 of
2400 cfm
ROOMS
53.6% R.H.
` of
78.0 ! 66.0 of
78.3 66.1
Return Air Ducts
EnergyPro 4.2 by EnergySoft
User Number: 4469
Job Number: Tamp1495
Page: 16 of 28
HVAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME FLOOR AREA
PGE -2E 1,622
ENGINEERING CHECKS SYSTEM LOAD
Number of Systems
1
Heating System
Output per System
59,040
Total Output (Btuh)
59,040
Output (Btuh/sgft)
36.4
Cooling System
Output per System
73,000
Total Output (Btuh)
73,000
Total Output (Tons)
6.1
Total Output (Btuh/sgft)
45.0
Total Output (sgft/Ton)
266.6
Air System
CFM per System
2,400
Airflow (cfm)
2,400
Airflow (cfm/sgft)
1.48
Airflow (cfm/Ton)
394.5
Outside Air (%)
16.9
Outside Air (cfm/sgft)
0.25
Note: values above
(EATING SYSTE
26.0 OF
Outside Air
405 cfm
69.9 OF
at ARI conditions
62.5 OF
Supply Fan
2400 cfm
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM ISensiblel
Latent
CFMI
Sensible
61,307F 9321 32 905
PGE -6T (Carrier48HJ) 59,565 10,019 59,040
5.0 kW Supplemental Electric 0
Total Adjusted System OutputSs,565 10,019 59,040
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK Sep 2 pm Jan 12 am
tream Temperatures at Time of Heatina Peak)
62.50E ®1 85.60F ® 85.6 OF
Heating Coil Aux. Heat Coil
K Return Air Ducts 4
Supply Air Ducts
85.5 OF
ROOMS
70.0 OF
I
106.0 / 73.4 OF 83.0 / 67.4 OF 83.0 / 67.4 OF 59.6 / 58.4 OF
O F Supply Air Ducts
Outside Air
405 cfm Supply Fan Cooling Coil 59.9 / 58.5 OF
2400 cfm 53.6% R.H. ROOMS
78.3/66.1 0 F 78.0 ! 66.0 OF
Return Air Ducts
EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamol495 Paae:17 of 28
WAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME FLOOR AREA
PGE -2D 1.622
Number of Systems
1
Heating System
Output per System
59,040
Total Output (Btuh)
59,040
Output (Btuh/sqft)
36.4
Cooling System
Output per System 73,000
Total Output (Btuh) 73,000
Total Output (Tons) 6.1
Total Output (Btuh/sgft) 45.0
Total Output (sgft/Ton) 266.6
Air System
CFM per System
2,400
Airflow (cfm)
2,400
Airflow (cfm/sgft)
1.48
Airflow (cfm/Ton)
394.5
Outside Air (%)
16.9
Outside Air (cfm/sgft)
0.25
Note: values above given at ARI conditions
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM
I Sensiblel
Latent
CFM
I Sensible
58,0061 12,3651
PGE -6T (Carrier48HJ) 56,151 13,619 59,040
5.0 kW Supplemental Electric 0
Total Adjusted System Output 56,151 13,619 59,040
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK Jul 3 pm Jan 12 am
EATING SYSTEM PSYCHROMETRICS Airstream Temperatures at Time of Heating Peak
26.0 of 62.5 of 62.5 of 85.6 °F 85.6 of
O Supply Air Ducts
Outside Air
405 cfm 85.5 of
Supply Fan Heating Coil Aux. Heat Coil
2400 cfm ROOMS
69.9 of 70.0 of
Return Air Ducts I
DOLING SYSTEM PSYCHROMETRICS (Airstream Temoeratures at Time of Coolina Peak)
12.0 / 77.9 of 84.0169A of 84.0 / 69.4 of 62.0 / 60.8 of
Outside Air O
405 cfm
Supply Fan
2400 cfm
78.3/67.5 of
Cooling Coil
h Return Air Ducts `i
Supply Air Ducts
62.3/60.9OF
58.3% R.H. ROOMS
78.0 / 67.4 of
EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamp1495 Page: 18 of 28
HVAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME FLOOR AREA
PGE -2C 1,622
ENGINEERING CHECKS IFSYSTEM LOAD
Number of Systems
1
Heating System
Output per System
59,040
Total Output (Btuh)
59,040
Output (Btuh/sgft)
36.4
Cooling System
Output per System
73,000
Total Output (Btuh)
73,000
Total Output (Tons)
6.1
Total Output (Btuh/sgft)
45.0
Total Output (sgftlron)
266.6
Air System
CFM per System
2,400
Airflow (cfm)
2,400
Airflow (cfm/sgft)
1.48
Airflow (cfm/Ton)
394.5
Outside Air (%)
16.9
Outside Air (cfm/sgft)
0.25
Note: values above given at ARI conditions
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM
I Sensiblel
Latent
I CFM
I Sensible
2,504 41,985
10,703 885
14,628
0
630
0
219
0
405 14,557
1,665
405
18,947
0
630
0
219
57,88 12 369 34 014
PGE -6T (Carrier48HJ) 56,144 13,621 59,040
5.0 kW Supplemental Electric 0
Total Adjusted System Output5s,1aa 13,621 5s,oao
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK Jul 3 pml Jan 12 am
EATING SYSTEM PSYCHROMETRICS Airstream Temperatures at Time of Heating Peak
26.0 OF 62.5 OF 62.5 OF 85.6°F 85.6 OF
O Supply Air Ducts
Outside Air
405 cfm 85.5 of
Supply Fan Heating Coil Aux. Heat Coil
2400 cfm ROOMS
69.9 OF 70.0 of
12.0 / 77.9 of
Outside
��
405 cfm
78.3/67.5 ° F
4.2
Return Air Ducts
84.0 / 69.4 of 84.0 / 69.4 of 62.0 / 60.8 of
Supply Fan , Cooling Coil
2400 cfm
User Number: 4469
Return Air Ducts
Job Number: Tamp1495
Supply Air Ducts
62.2 / 60.9 of
58.3% R.H. ROOMS
78.0 / 67.4 of
19 of 28
HVAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME J FLOOR AREA
PGE -2B 1 621
ENGINEERING CHECKS IFSYSTEM LDAD
Number of Systems
1
Heating System
Output per System
59,040
Total Output (Btuh)
59,040
Output (Btuh/sgft)
1 36.4
Cooling System
Output per System 73,000
Total Output (Btuh) 73,000
Total Output (Tons) 6.1
Total Output (Btuh/sgft) 45.0
Total Output (sgftrron) 266.5
Air System
CFM per System
2,400
Airflow (cfm)
2,400
Airflow (cfm/sgft)
1.48
Airflow (cfm/Ton)
394.5
Outside Air (%)
16.9
Outside Air (cfm/sgft)
0.25
Note: values above given at ARI conditions
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM
I Sensiblel
CFM
I Sensible
2,502
41,973
10,699 885
14,628
0
630
219
0
0
405
14,550
1,668 405
18,939
0
0
6301
219
57,862=T2 366 34 005
PGE -6T (Carrier48HJ) 56,144 13,618 59,040
5.0 kW Supplemental Electric 0
Total Adjusted System Output56,144 13,618 59,040
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK Jul 3 m Jan 12 am
EATING SYSTEM PSYCHROMETRICS Airstream Temperatures at Time of Heating Peak
26.0 OF 62.5 OF 62.50F 85.60F 85.6 OF
O Supply Air Ducts
Outside Air
405 cfm o
Supply Fan Heating Coil Aux. Heat Coil 85.5 F
2400 cfm ROOMS
69.9 of 70.0 of
OE 0� 1E{ Return Air Ducts I
12.0 / 77.9 of
Outside Air
405 cfm
78.3/67.5 of
4.2
84.0 / 69.4 of 84.0 / 69.4 of 62.0 / 60.8 of
--&— .01 1
Supply Fan Cooling Coil
2400 cfm
User Number: 4469
Return Air Ducts
Job Number: Tampl
Supply Air Ducts
62.2/60.9OF
58.3% R.H. ROOMS
78.0 / 67.4 of
of 28
HVAC SYSTEM HEATING AND COOLING LOADS SUMMARY
PROJECT NAME DATE
The Plaza @ Calle Tampico Shop Bldg 2 2/12/2008
SYSTEM NAME FLOOR AREA
PGE -2A 1,644
ENGINEERING CHECKS lrqVqTFM t OAF
Number of Systems
2
Heating System
Output per System
59,040
Total Output (Btuh)
118,080
Output (Btuh/sqft)
71.8
Cooling System
Output per System
62,500
Total Output (Btuh)
125,000
Total Output (Tons)
10.4
Total Output (Btuh/sqft)
76.0
Total Output (sgft/Ton)
157.8
Air System
CFM per System 1,750
Airflow (cfm) 3,500
Airflow (cfm/sgft) 2.13
Airflow (cfm/Ton) 336.0
Outside Air (%) 11.7
Outside Air (cfm/sqft) 0.25
Note: values above given at ARI conditions
26.0 of 64.7 of
Outside Air
411 cfm
Supply Fan
3500 cfm
69.9 of
64.7 of
Total Room Loads
Return Vented Lighting
Return Air Ducts
Return Fan
Ventilation
Supply Fan
Supply Air Ducts
TOTAL SYSTEM LOAD
COIL COOLING PEAK
COIL HTG. PEAK
CFM
Sensible
Latent
CFM
I Sensible
1 2,6941 61,7191 10,8501
0
411 14,316 6,710
0
926
77,8951 17 560
PGE -5T (Carrier48hj) 96,350 16,645 118,080
5.0 kW Supplemental Electric 0
Total Adjusted System Output gs,35o 16,645 118,080
(Adjusted for Peak Design Conditions)
TIME OF SYSTEM PEAK Jul 4 pm Jan 12 am
-earn Temperatures at Time of Heatina Peak)
QR d OF — QR d OP
Heating Coil Aux. Heat Coil
11.0 / 77.6 of 82.1 / 65.7 of
Outside Air O
411 cfm
Supply Fai
3500 cfm
78.2/63.9 of
h Return Air Ducts '�
lirstream Temperatures at Time
82.1 / 65.7 of M 56.2 / 54.9 of
Cooling Coil
h Return Air Ducts 11
Supply Air Ducts
96.3 of
ROOMS
70.0 of
Supply Air Ducts
56.5 / 55.0 of
46.3% R.H. ROOMS
78.0 ( 63.8 of
1 EnergyPro 4.2 by EnergySoft User Number: 4469 Job Number: Tamp1495 Page:21 of 28 1
ROOM LOAD SUMMARY
PROJECT NAME
The Plaza @ Calle Tampico Shop Bldg 2
DATE
2/12/2008
SYSTEM NAME
PGE -2G
FLOOR AREA
2,272
ROOM LOAD SUMMARY
ROOM COOLING PEAK
COIL COOLING PEAK
COIL HTG. PEAK
ZONE NAME
ROOM NAME
Mult.
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
SPACE -G
RETAIL FLOOR -G
1
4,309
88,152
14,995
4,170
85,315
14,995
1,354
35,024
PAGE TOTAL 1 4,170 85,315 14,995 1,354 35,024
TOTAL 4,170 85,315 14,995 1,354 35,024
EnergyPro By EnergySoff User Number: User Job Number: Tamp1495 Page:22 of 28
ROOM LOAD SUMMARY
PROJECT NAME
DATE
The Plaza @ Calle Tampico Shop Bldg 2
2/12/2008
SYSTEM NAME
FLOOR AREA
PGE -2F
1,622
ZONE NAME I ROOM NAME IMult. I CFM I SENSIBLE1 LATENT I CFM ISENSIBLE1 LATENT CFM SENSIBLE
RETAIL FLOOR -F
SPACE -F 1 2,499 48,080 10,703 2,491 47,914 10,703 819 13,549
�I
PAGE TOTAL 1 2,491 47,914 10,703 819 13,549
TOTAL 2,491 47,914 10,703 819 13,549
EnergyPro By EnergySoft User Number: User Job Number: Tamp1495 Page:23 of 28
ROOM LOAD SUMMARY
PROJECT NAME
The Plaza @ Calle Tampico Shop Bldg 2
DATE
2/12/2008
SYSTEM NAME
PGE -2E
FLOOR AREA
1,622
ROOM LOAD SUMMARY
ROOM COOLING PEAK
COIL COOLING PEAK
COIL HTG. PEAK
ZONE NAME
ROOM NAME
Mult.
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
SPACE -E
RETAIL FLOOR -E
1
2,499
48,080
10,703
2,491
47,914
10,703
819
13,549
r
PAGE TOTAL 1 2,491 47,914 10,703 819 13,549
TOTAL 1 2,491 47,914 10,703 819 13,549
EnergyPro By EnergySoft User Number: User Job Number: Tamp1495 Page:24 of 28
ROOM LOAD SUMMARY
PROJECT NAME
The Plaza @ Calle Tampico Shop Bldg 2
DATE
2/12/2008
SYSTEM NAME
PGE-2D
FLOOR AREA
1,622
ROOM LOAD SUMMARY
ROOM COOLING PEAK
COIL COOLING PEAK
COIL HTG. PEAK
ZONE NAME
ROOM NAME
Mult.
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
SPACE-D
RETAIL FLOOR-D
1
2,750
46,078
10,703
2,511
42,071
10,703
890
14,708
PAGE TOTAL 1 2,511 42,071 10,703 890 14,708
TOTAL 1 2,511 42,071F 10,703 F 890 14,708
EnergyPro By EnergySoft User Number: User Job Number: Tamp1495 _ , Page:25 of 28
ROOM LOAD SUMMARY
PROJECT NAME
The Plaza ,@ Calle Tampico Shop Bldg 2
DATE
2/12/2008
SYSTEM NAME
PGE -2C
FLOOR AREA
1,622
ROOM LOAD SUMMARY
ROOM COOLING PEAK
COIL COOLING PEAK
COIL HTG. PEAK
ZONE NAME
ROOM NAME
Mult.
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
SPACE -C
RETAIL FLOOR -C
1
2,661
44,632
10,703
2,504
41,985
10,703
885
14,628
PAGE TOTAL 1 2,504 41,985F 10,703 885 14,628
TOTAL 2,504 41,985 10,703 885 14,628
EnergyPro By EnergySoft User Number: User Job Number: Tamp1495 Page:26 of 28
ROOM LOAD SUMMARY
PROJECT NAME
The Plaza @ Calle Tampico Shop Bldg 2
DATE
2/12/2008
SYSTEM NAME
PGE -2B
FLOOR AREA
1,621
ROOM LOAD SUMMARY
ROOM COOLING PEAK
COIL COOLING PEAK
COIL HTG. PEAK
ZONE NAME
ROOM NAME
Mult.
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
SPACE -B
RETAIL FLOOR -B
1
2,660
44,619
10,699
2,502
41,973
10,699
885
14,628
PAGE TOTAL 2,502 41,973 10,699 885 14,628
TOTAL 1 2,502 41,973 10,699 885 14,628
EnergyPro By EnergySoft User Number: User Job Number: Tamp1495 Page:27 of 28
r
ROOM LOAD SUMMARY I
PROJECT NAME
The Plaza @ Calle Tampico Shop Bldg 2
DATE
2/12/2008
SYSTEM NAME
PGE -2A
FLOOR AREA
1,644
ROOM LOAD SUMMARY
ROOM COOLING PEAK
COIL COOLING PEAK
COIL HTG. PEAK
ZONE NAME
ROOM NAME
Mult.
v
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
LATENT
CFM
SENSIBLE
SPACE -A
RETAIL FLOOR -A
1
2,707
62,006
10,850
2,694
61,719
10,850
1,045
29,268
PAGE TOTAL 1 2,694 61,716 10,850 1,045 29,268
TOTAL 1 2,694 61,716 10,850 1,045 29,268
EnergyPro . By EnergySoff User Number: User Job Number: Tamp1495 Page:28 of 28