RFP - Wellness Center Basin LS Project No 2018-21
PROJECT NO 2018-21
WELLNESS CENTER BASIN LS
Dianne Hansen
DHANSEN@LAQUINTACA.GOV
City of La Quinta
Project No. 2018-21 WELLNESS CENTER BASIN LS
Contractor will provide labor, fertilizer, irrigation materials, and
equipment for installation of plant and hardscape materials.
Contractor is responsible for mobilization, site protection, traffic and dust
control within the parking lot. Means and methods required to perform the
work are to be determined by Contractor.
Decomposed granite (DG), rock and plant material to be provided by the City.
Item
No.
Description Qty Unit
Unit
Price
(Dollars)
Item
Total
(Dollars)
1
Remove two tree stumps,
existing plants in three parking
lot islands, street frontage,
three plants in the turf. Turf
removal near La Fonda, marked
with a red X. Clear and grub
the bottom of the retention
basin.
1 LS
2
Furnish and Install Irrigation to
new plant material in parking
lot and the side by the retention
basin.
Re-align or add irrigation in the
turf at two existing palm trees
locations where turf is not
getting watered.
1 LS
3
Install Plants at the side of the
parking lot, three parking lot
islands and the area between
the street and the parking lot.
1 LS
4 Install Cobble; ¾ Stone; DG;
and Boulders (Est. 15 - 20) 1 SF
Total:
Existng:
Basic Concept: (Adjustments will be made on site)
Parking Lot:
Mobilization includes expenditures for all preparatory work and operations,
including but not limited to, those costs necessary for the movement of
personnel, equipment, supplies, and incidentals to the project site; for the
establishment of all facilities necessary for work on the project; and for all
other work and operations which must be performed or costs incurred prior
to beginning work on the various contract items on the project site as well
as the related demobilization costs anticipated at the completion of the
project.
Irrigation: All pipe 3” and smaller shall be Schedule 40 PVC Type 1, Grade
1 pipe. All plastic pipes will bear the following markings: the manufacturer’s
name, nominal pipe size or schedules. Note: Irrigation sleeves have been
previously installed at the landscape islands. Contactor is responsible to
connect irrigation to the existing system.
Main Line Fittings will be solvent welded using pipe primer ASTM F656 and
pipe solvent ASTM D-2564. All other fittings will be solvent welded with pipe
solvent ASTM D-2564, NSF or approved equal.
Fertilizer is to be applied at planting of palm trees and shrubs. Industry
standard generic fertilizer on installation.
Boulders: Bury boulders 1/3 of boulder dimension so that they appear in
natural state. Orientation of boulder shall expose most surface area possible
set as approved by Project Manager.
Crushed rock is to be spread over the planting area to a 2” depth. Apply
moisture after spreading and raking to compact and remove dust.