5026For the co
works imp
Finance Revenue Code E-1
ENCROACHMENT PERMIT
PUBLIC WORKS CONSTRUCTION
eways, pavements, sidewalks, parking lots, sewers, water mains and other like public
PROVEMENTS and APPROVED SUBDIVISIONS.
Subdivision Improvement Permit - Class III
Minor Improvement Permit Class IV
DATE:2/16/06
LOCATION OF CONSTRUCTION (Street address or Description): Centre Pointe, TM 31116; SE corner of Washington and Miles Avenue
PURPOSE OF CONSTRUCTION: Precise grading (hotel)
DESCRIPTION OF CONSTRUCTION: See plan set number 05115
DIMENSION OFINSTALLATION OR REMOVAL: See plan quantities
APPROXIMATE TIME WHEN WORK WILL BEGIN:2/21/06 TIME OF COMPLETION:6/30/06
ESTIMATED CONSTRUCTION COST: $513,025.00 (Including removal of all obstruction, materials, and debris, backfilling,
compaction and placing permanent resurfacing and/or replacing improvements)
COMMENTS:
In consideration of the granting of this permit, the applicant hereby agrees to:
Indemnify, defend and save the City, its authorized agents, officers, representatives and employees, harmless from and against any
and all penalties, liabilities or loss resulting from claims or court action and arising out of any accident, loss or damage to persons or
property happening or occurring as a proximate result of any work undertaken under the permit granted pursuant to this application.
Notify the Administrative Authority at least twenty-four (24) hours in advance of the time when work will be started at (760) 777-
7075.
Comply with all applicable City Ordinances, the terms and conditions of the permit and all applicable rules and regulations of the City
of La Quinta and to pay for any additional replacement necessary as the result of this work.
ignature of Applicant or Agent
CP Development La Quinta, LLC - Rick Jacobs 77-564 Country Club Dr. #100 Palm DesertCA 92211 (760) 360-8001
Name of Applicant (please print) Business Address Telephone No.
}
Jacobsson Engineering P.O. Box 14430 Palm DesertCA 92255 (760) 340-0194 .
Name of Contractor and Job Foreman Business Address Telephone No.
650389 3026
Contractor's License No. City Business License No.
Lexington Insurance Company 2156620
Applicant's Insurance Company Policy Number
FEES: Subdivision Improvement Permit - Class III
Minor Improvement Permit - Class IV
Inspection Fee
Permit Fee
As -Built Deposit
Cash Deposit -Surety Bond,
if required
TOTAL
$15,390.00
$100.00
$ 0 ,000.00 )
$
$16,490.00
Public improvements: 3% of estimated construction costs
Private improvements: 3% of estimated construction costs
See attached schedule
PERMIT NO.5026
DATE APPROVED: 3 O 6
EXF AD
BY: T SON
Administrative Authority
4
.02/15/2006 4. 11:51 IAX -760 77.7 '715.5 City of La Quinta PDX
b02/002-
PUBLIC WORKS DEPARTMENT
APFUCATION FOR PERMIT
Name:
&tb
escription of Constructio See Plan Set No. 01234)_
Dimension -of Installation or Removal: ',,:g—;f, PLA, Wfi*S
Approximato-Coilstraction Start Date:
Approximate Construction Completion Date:
Estimated Construction Cost: $jQNWMM--"' -
ESU[02t<d CODAMOtIon Cost shall imIijdc,!ha 'M
rewval of nD absft=tI;Mq_
placing parm,amt resurflocinAwU or ToplujagImproyem6ts
Coidact Name:
Name of Applicant/owner. D it P"
-
ApplioantAddrllss:
2 -S4!q Qu
-APPlicant TdIe!)hone-Numbe'r: a. -36o :.-Ro(
Name of Contractor. '37p, ej6,5atD—E A&Ftjl
Cohtraetor Address:
Contractor -telephone Number:* :7A 1-_
Contractor State License Number.
Contiaddr City Business License Number.
bl§. anddcbT* back-ARIng, compRo6on and
'hone Number: -76 460��1
T— bk &vt NHA 1-r,
41ftei—
11-ACQRY-QVTYM-CjMRRNT
RMOCIz CERTiFic-&TE MUST BE PRO v=,64
Applicant or Cont et Gen6ral Liability hisurance-Company:
eM2. t-I LAI
Applicant or Contractor General Liability Insurarico Policy Number
1mvc0tionFee :
Penult Fee:
0o
As -Built
Deposit:0.0
0.1 (7 0
bust Control
Mposit:
Credit
-AMOM.t.—
TOTAL FM JDUE:
Office Use only: � ( \
Assigned PerniftNumabe
S�oaeY
Approval Dater
4L
Expiration
Ism
-Adinlnlmlivc Authorlrr.
Document A111 1997 .
Standard Form of Agreement Between Owner and'Contractor
where *the basis for payment is the COST OF THE WORK PLUS A FEE with a negotiated
Guaranteed Maximum Price
AGREEMENT made:as of this. 6th day of October in the year 2004
(In words, indicate day, month and year)
BETWEEN the Owner. '
(Name,. address and other information)
CP Development La Quints LLC
77-564 Country Club Lane Suite 100
Palm Desert, CA 92211
and the Contractor: '
(Name, address and other information)
Turner Construction Company
400 Exchange, Suite 250
Irvine, CA 92602'
The Project is:
(Name and location)
CP Development — Infrastructure
S.E. Corner.of Washington and Miles
La Quinta, California '
The Architect is:
(Name, -address and other information)
Knitter & Associates ,
20151 SW Birch, Suite.100
NewportBeach, CA 92660-1721
The Owner and Contractor agree as follows.
AMMONS AND DELETIONS:
The author of this document has
added.inforinaUon needt;d for its
completion. The author may also
have revised the text. of the
original AIA standard form. An.
Additions and D' 1etions.Ffeport
that notes added Information as
well as revisions to the standard
form text is available from the
author and should be reviewed.
A vertical line in the left margin of
this document indicates where
the author. has added necessary
Information and where the author
has added to or deleted from the
original AiA text.
This document has important
legal consequences..
Consultation with an attorney
Is encouraged with respectto
its completion or -modification.
This document is not Intended for
use In competitive bidding.
AIA Document A261=1997,
General Conditions of the
Contract for Construction, Is
adopted in this document by
reference. Do not use with other
general conditions unless this
document Is modified.
This document has been
approved and eridorsed by the
Associated General Contractors
of Amedaa.
AIA Document Aillm-1997. Copyright 01920. 1925,1951,1958,1901, 19&3,1967,1974,.1978,1887 and 1997 by The American Institute of Archflecls.
All rights reserved. WARNING: This AIA° Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or
distribution of this AIA® Document, or any portion of it,'may result in severe civil and criminal penalties, and will be prosecuted to the maximum
extent possible under the law. This document Was produced byAIA software at 10:45:25 on 10/29/2004 under Order No.1000102915 1 which expires on
=12905, and is not for resale.
User Notes: (509385124)
This Agreement is entered int6 as. of the day and year first written above and is executed in at least three original
copies, of which one is to be delivered t6 the Contractor, one to the Architect for use in the administration of the
Contract, and the remainder to, the Owner.
NER.(Signature) NT CT R Sig t re)
ose J. Kilar, V.P. arid_Cieneral Mana er
(Printed name and rid title)
AIA Document A111*" —1997. Copyright @ 1920,'1025,1951,1956.1961. ISM 1967,1974,1978, 198-7 and.1997 by The American institute of Architects
Ali rights reserved.. WARNING: This AI0 Document is protected by U.S. Copyright -Low and Intematianat Trealles. Uneuthwiged reproduction or • •14
distribution of this A10 Document, Or any portion of it, may result In severe civil and criminal penalties, and will be prosecuted to the maximum
extent posslble under the law.' This document was produced by AIA software at 10:46:26 on 1012812004 under Order•No.100010015 1 which expires an
31312005i and is not for resale.
User Notes: 1509365124)
•
GMP ESTIMATE
OCTOBER 11, 2004
CENTRE POINTE
(gUDGET ESTIMATE UPDATE 6124104)
HOTEL CASITAS SITE SUMMARY
ASPHALT PAVING
109,700
1.
329,50
PARKING AREA AC PAVINGIOASE
250
A
EEA
10.00
2,600
STRIPING
1
LS
15,000.00
15,000 .
HANDICAPPED SIGNAGE, STRIPING
'
E
34T,005
TOTAL • ASPHALT. PAVING
SITE CONCRETE
9,466
LF
10.0094.660
CONCRETE CURB & GUTTER
990
LF;
14,00
13 6
t3,80
RIBBON GUTTER
1
LS
26.000.06
25,000
MISC. CONCRETE
66
EA
500.00
32.500
LIGHT POLE BASES
o.
TOTAL - SITE CONCRETE
S
166,020
MISCELLANEOUS SITE FEATURES
0
SF
0
15.00
/ J
1�
HOTEL POOL SHADE STRUCTURES .
20
SF
55.00
11.000
HOTEL POOL EQUIPMENT ROOM
128
SF '
0.00
6.400
HOTEL TRASH ENCLSURES
120
SF'
S0.00
5
6.000
HOTEL STORAGE RM
4
EA
850.00
Z600
HOTEL- PEDESTRIAN GATES
2
EA
2,500.00
5,000
HOTEL- MONUMENT SIGNS
EXCLUDED'
HOTEL CARPORTS
1,900
LF
45.00
W7SALOFHfE
CASITAS-SITE FENCE Q MILES
550
LF.
50.00
27.600
CASITAS-•POOL FENCE
2
EA.
450.00
900
CASITAAS• PEDESTRIAN GATES.
300
SF
25.00
7.SDO
CASITAS POOL SHADE STRUCTURES
400
SF
50.00
20.000
CASITAS TRASH ENCLSURES
2
'-EA
1.500.00
3.000
CASITAS- MONUMENT SIGNS
EXCLUDED
I CASITAS- CARPORTS
S
103,650
TOTAL •MISCELLANEOUS SITE FEATURES
PAGE 16 OF 22
TURNER CONSTRUCTION COMPANY
^02/15/206 WED 11•; 51 . FAX 760 777 7155 City of La Quinta Pub.Wk
Dimension of Installation or Removal: ,54.E F(,A
Approximate Construction Start Date: 1- - 0 e,
Approximate Construction Completion Date: L -A O -6
Estimated Construction Cost: $ _77 lio , 761 —
Eslimttad Construction Cost shall include tho removal of all obshuetions, materials, and debris, back filling, compaction and
Placingp—�ncnt.resurfaciog-ond or rcplacing*improvements
Contact Name: Zi ke1= Z-K"65
Name of Applicant/Owner: _Lk .)>IN DLO f
�v Applicant Address: 77 5U y Cam �(L%j GL,u
/'11 Applicant Telephone Number: 76 0 A 6 o =
Phone Number: ILO -5 60 -'3861
Fq
Name of Contractor: SRGo6954t J Em&Ftj *aW(.
Contractor Address: t6, Ou
• Contractor Telephone Number: 76 o - lL{p - p i q
Contractor State License Number: 6Sa389
Contractor City Business License Number: . 36 2_�k
10- A COPY OF THE.CURRFNT INSURANCE CERTIFICATE MUST BE PROVIDED -4
Applicant or Con act r General Liability Insurance Company:
tiUL
Applicant or Con�ractor General Liabi ity surance Policy Number:
bN F(L5,
Office Use Only:
Inspection Fee: • ? O O. O U
Pcnuit Fee: J
I000u
As -Built
Deposit: G (io. O 0
Dust Control
Deposit
Credit
- -• A3nount.-.
TOTAL FEE pUE: t? y 00, 0 0
Office Use Only.
Assigned Permit Number: C 0 2 / .
Approval Date:
Expiration
Date:
Issuo
Date:
Authority.
&02/002
_V—
Feb.11. 2006 8:31AM Turner Construction
No.1470 P. 1
Turner
ly_IW7
Turner Construction Company
44-139 Monterey Ave. - #201
Palm Desert, CA 92260
Centre'Pointe Project
78875 Miles Avenue
La Quinta, CA 92253
To:
Mr, Anthony Colarossi, P.E.
From:
STAN BARNES
Fax:
760-777-7155
Fax:
760-238-5461
Phone: 760-777-7089 Phone: 760-238-5460
Re: Permit Info Pages: 7 Including cover
Date: 2/17/2006 CC: L
❑ Urgent ❑ For Review ❑ Please Comment ❑ Please Reply ❑ Please Recycle
• Comments / Notes:
Tony,
Thanks for the heads on the things you need for the permits at Centre Pointe. Let me knowrf this is
insufficient Otherwise, I'll wait for your call with fee amounts, etc.
Stan Barnes
Project Manager
Building die Future
Feb, 17.. 2006 8:31AM
Turner Construction
No.1470 P. 2
fi-=9;rA1A Document A111 -1997
Standard Form of Agreement Between Owner and Contractor
where the basis for payment is the COST OF THE WORK PLUS A FEE with a negotiated
Guaranteed Maximum Price
AGREEMENT made as of thtr. 6th day of October
(In words, indicate day, month and year)
BETWEEN the Owner:
(Nance, address and other information)
CP Development La Quinta LLC
77-564 Country Club Lane Suite 100
Palm Desert, CA 92211
and the Contractor. '
(Name, address and other information)
Tumer Construction Company
400 LExchange, Suite 250
Irvine, CA 92602
The project is. -
(Name and location)
CP Development = Infrastructure
S.L. Corner of Washington and Mites
La Quinta, California
The Architect is:
(Name, address and other information)
Knitter & Associates
20151 SW Birch, Suite.100
Newport Reach, CA 92060-172)
The Owner and :Contractor agree as follows.
in the year 2004
ADDITIONS AND DELETIONS:
The author of this document has
added Information needed for Its
completion. The author may also
have revised the text.of the
original AIA standard form. An.
Additions and Deletions Report
that notes added information as
well as revisions to the standard
form text Is available from the
author and should be reviewed.
A vertical Una In the left margin of
this document indicates where
the author has added necessary
information and wher® the author
has added to or deleted from the
original AIA text.
This document has Impodard
legal consequences.
Consultation with an attorney
Is w=uragea with respect.to
its completion or modification.
This document Is not Intended for
use in competitive bidding.
AIA Docuument A201.1997,
General Conditions of the
Contract for Construction, is
adopted In INs document by
reference. Do not use with other
general conditions unless this
document Is modified.
This document has been
approved and endorsed by the
Associated General Contraelor6
of America.
AIA Document A171'u-1987. Copyright 0 1920, 1926, 1951, 1956, 1961, 1963, 1967, 197d, 1978.1937 and 1997 by The American Institute of Archliects.
All rights reserved. WARNING: This AIA° Document Is protected by U.S. Copyright Lew and International Treaties. Unauthorized reproduction or 1
distribution of this AIA® Document, or any portion of It, may result In severe Civil and criminal penaltles, and will be prosecuted to the maximum
extent possible under the law. This document was prodyced by AIA software at 10:45:25 on 10/2912004 under Ordar. No.1000102915_1 which expires on
3r8l2005, and is not for resale.
User Notes- (S09365124)
Feb,17. 2006 8:32AM Turner Construction No.1470 P. 3
This Agreement is entered into as of the day and year first written above and is executed in at least three original
copies, of which one is to be delivered to the Contractor, one to the Architect for use in the administration of the
Contract, and the remainder to the Owner.
cam..
OWNER (Signature) QbNT0ACTbR Six re)
I Rs UA" 1z - CSt.,�
(Printed name and fu'X'►'wk,
AIA beeumerlt A111t" —1997. Copyright 01920, 1925, 1951,1958, 1961, 1963, 1967, 1974, 1978,1987 and•1997 by The American Inatitute of Architects.
All rights reserved WARNING: This AIA' Document Is protected by U.S. Copyright Lew and International Treaties. Unauthorized reproduction or
distribution of this AIA Document, or any portion of It, may result In severe civil and criminal penalties, and will be prosecuted to the maximum 14
extent possible under the, law. This document was produced by AIA software at 10;45:25 on 10/2B/2004 under Order No.1000102915_7 which expires on
3/312005. and is not for resale.
User Notes: (509365124)
r
..Feb..17. 2006 8:32AM Turner Construction
GMP ESTIMATE
CENTRE POINTS
HOTEL CASITAS SITE SUMMARY (BUDGET ESTIMATE UPDATE 6174104)
ASPHALT PAVING '
PARKING AREA AC PAVINGBASE
STRIPING
HANIDICAPPED SIGNAGE. STRIPING
TOTAL - ASPHALT PAVING
SITE CONGRETF
CONCRETE CURB & GUTTER
RIBBON GUTTER
MISC, CONCRETE
LIGHT POLE BASES
ToTAL - SITE CONCRETE
MISCELLANEOUS SITE FEA1UR1-1
HOTEL POOL SHADE STRU(71URES
HOTEL POOL EQUIPMENT ROOM
HOTEL TRASH ENCLSURFS
HOTEL STORAGE RM
HOTEL- PEDESTRIAN GATES
HOTEL- MONUMENT SIGNS
HOTEL- CARPORTS
CASITAS-STTE FENCE MILES
CASITAS- POOL FENCE
CASITAAS. PEDESTRIAN GATES
CARITAS POOL SHADE STRUCTURES
CASITAS TRASH ENCLSURES
CASITAS. MONUMENT SIGNS
CAStTAS- CARPORTS
TOTAL. MISCELL.ANEOUS SITE FEATURES
No.1470 P. 5
OCTOBER 11, 2004
199,700 SF 1.65 329.505
250 EA 10,00 2,500
1 LS 15,000.00 16,000
E 347.005
.00
84,660.00
13,860.00
25,0000.00
32.500166.0205.00
M
13.7505.00
11,00010.00
8.400
120
SF
50.00
6.000
4
EA
6So.00
2,800
2
EA
2.500.00
5,000 .
EXCLUDED
1.900
LF
45.00
W154OPERE
550
LF.
50.00
27,5D0
2
EA
450.00
No
300
SF
25.00
7,500
400
SF
50,00
20.000
2
EA
1.500.00
3.000
EXCLUDED
$ 103.950
TURNER CONSTRUCTION COMPANY
• PAGE 16 OF 22
City of La Quinta
The following General and Special Provisions are attached to and made a part of
Permit Number 5026
The following shall always apply:
ENCROACHMENT ON PRIVATE PROPERTY: This permit authorizes work to be accomplished within the City of La Quinta's right of way
ONLY. Whenever construction extends within private property, it is the responsibility of the permittee for his contractors to secure permission
from abutting property owners. Such authorization must be secured by the permittee prior to starting work.
TRACK -LAYING CONSTRUCTION EQUIPMENT: Cleated track -laying construction equipment shall not be permitted to operate on any paved
surface unless fitted with smoother -faced street pads. All mechanical outriggers shall be fitted with rubber street shoes to protect the paving
during excavations. Rubber -tired equipment only shall be used in backfill operation in paved areas. If the existing pavement is scarred, spalled,
or broken during the term of this contract or if the pavement is marred, City of La Quinta shall request that these portions of road be resurfaced
over their entire width. Resurfacing shall consist of one coat of two inches (2") of A.C. surfacing plus appropriate seal coat as specified above.
PROTECTION OF TRAFFIC: All excavations and work areas shall be properly lighted and barricaded as deemed necessary by the City
Engineer or City of La Quinta Public Works Inspectors. Suitable detours and detour signs shall be placed and maintained for the duration of the
project. The City shall be notified twenty-four hours (24) in advance of any traffic detours or delineation. .
CARE OF DRAINAGE STRUCTURES: Any drainage structure to include corrugated metal pipe, concrete pipe, steel culvert and concrete
structures encountered during excavation which necessitate removal shall be replaced in kind. In the event it becomes necessary to remove or
cut existing drainage structures, City of La Quinta shall be notified prior to commencement of this work. Drainage structures and open drains
shall be kept free of debris at all times for proper drainage.
RIGHT-OF-WAY CLEANUP: Any surplus material resulting from excavation and backfill operations shall be removed from the right of way. All
paved surfaces shall be broomed clean of earth and other objectionable materials immediately after backfill and compaction. Existing gutter line
and drainage ditches shall be replaced to their original standard or better. All excess material shall be removed prior to paving. Water tanker
shall be used, as required, to sprinkle the job site to keep down dust conditions and shall be used immediately after backfill.
DE -WATER OPERTATIONS: If de -watering operations are required and pumps are forcing water on City of La Quinta roads, it shall be the
responsibility of the permittee (contractor) to control this water and to provide off-street barricades when necessary.
CLOSING STREETS: No street shall be closed. A minimum of one lane of traffic shall be maintained at all times to provide limited access for
the adjoining property owners and emergency vehicles. In the event it is felt by the permittee that he must close a street for any length of time,
permittee shall contact this office to obtain the necessary permission.
SPECIAL PROVISIONS
The following shall apply when indicated:
® R1 NOTIFICATION: Permittee shall be notified the City at (760) 777 - 7097 at least forty-eight hours (48) in advance of starting
construction.
® R2 UTILITY CLEARANCE: (Substructures) Prior to making any excavations within the City of La Quinta right-of-way authorized
by permit, the permittee shall contact all concerned utility companies relative to the location of existing substructures.
Damage to existing substructures resulting from operations conducted under this permit shall be the sole responsibility of the
permittee.
® R3 UTILITY CLEARANCE (Surface Structures) No work shall be done under this permit until all utilities are clear of the
proposed work site.. The permittee shall notify all concerned utility companies of the proposed work.
❑ R4 PAVEMENT WIDENING: Area between the proposed concrete gutter line and the existing road pavement shall be surfaced
with (`" N/A "") inches of A.C. paving placed on ( "" N/A *') inches of ('* N/A ") aggregate sub -base course having an
"R" value of not less than ( " N/A ") and in conformance with the City of La Quinta Road Improvement Standards and
Specifications, Ordinance #461.
® R5 PARKWAY GRADING: Area between the property line and top of the proposed concrete curb shall be graded to a slope of
one-fourth inch (W) to one foot (1').
❑ R6 GRADE CHECKING: City of La Quinta shall check grades upon receipt of plan and profile and/or grades as established by
a licensed engineer.
❑ R7 CURB REMOVAL FOR DRIVEWAYS: A portion of the existing concrete curb and/or curb and gutter (" N/A ") feet shall
be removed. Curb and/or curb and gutter shall be saw cut prior to removal. Depressed curb, matching concrete gutter and
concrete driveway approach shall be constructed in conformance with City of La Quinta Standard #207.
❑ R8 DRIVEWAYS: A.C. driveways shall be constructed as not to alter existing drainage pattern. Surfacing between the property
line and the existing road paving shall be two and a half inches (2 %:") of A.C. paving on (" N/A ") of class (" N/A "" )
aggregate base.
® R9 SIGHT CLEARANCE: Sight Clearance of six -hundred feet (600') in all directions shall be assured and maintained at all
times.
❑ R10 SOIL STERILIZER: The area to be surfaced shall be treated with soil strerilizer. Rate of application shall comply with the
manufacturer's specifications.
City of La Quinta
® R11 COORDINATE WORK: The proposed work shall be subordinated to any operation, which the State of California or City of
La Quinta may conduct in this area during the period of this permit. Work shall be coordinated with the State or City of La
Quinta forces to preclude delay or interference with State or City of La Quinta projects.
® R12 SURVEY MONUMENTS: Prior to excavation or beginning of construction, all survey monuments which exist on the
centerline of all streets or property lines when included shall be completely tied out so they may be readily and correctly,
replaced by a licensed civil engineer or surveyor at the expense of the permittee. A complete set of notes showing the ties
to these monuments shall be furnished to the City Engineer prior to the removal of any monuments. This office shall be
notified upon completion or replacement of all survey monuments for proper clearance.
® R13 PAVEMENT CUTTING: Pavement will be mechanically saw cut to a straight edge prior to excavation. Method of pavement
cutting shall be approved through the office of the City Engineer. (Under no circumstances shall excavating equipment be
used to excavate prior to cutting or pavement.) Excavation material shall be placed in such a position as to best facilitate the
general flow traffic. Prior to final paving operations, any damage to pavement straight edges shall be corrected.
® R14 LIMIT OF EXCAVATIONS: Excavations shall be limited to one -thousand feet (1000') of open trench before backfill
operations must begin. All excavations shall be properly barricaded with lights overnight, on weekends and holidays for the
protection of the traveling public. The Public Works Inspector shall determine the suitability of excavation barricading in
each case. No excavation shall remain open for a period exceeding five (5) days. No excavation shall be made unless the
construction material is actually on the work site.
® R15 BACKFILL MATERIAL: Backfill shall be free of brush, roots or other organic substance detrimental to its use for purposes
of producing and adequately consolidated backfill. Ant material which the City of La Quinta deems unsuitable (spongy or
saturated material) which is encountered during excavation shall not be used for backfill, but shall be supplemented or
replaced by an approved sand or gravel.
❑ R16 BACKFILL SAND: Backfill shall be approved transit -mix sand or equivalent and shall be placed on lifts not greater than
three feet (3') and vibrated using vibrostamper or equivalent equipment. Alternate methods may be substituted, but in any
case, a relative compaction of ninety-five percent (95%) shall be maintained with the structural section of the roadway.
❑ R17 BACKFILL PLACEMENT: Backfill shall be applied in layers of not more than fifty percent (50%) of the total depth of the
trench before flooding or a maximum of five feet (5') lifts where trenches are of excessive depths. Care is to be exercised
that the backfill material is not subjected to extreme swell by flooding operations. Backfill material shall be placed so that the
resulting compaction shall not be less than ninety percent (90%) or equivalent to the surrounding ground, whichever is the
greater compaction. Where ponding or flooding is used for a maximum settlement, adequate dikes will be constructed to
retain the water. Where jetting is used, the jets shall be of sufficient length to reach the bottom of each layer and the water
supply shall be continuos.
❑ R18 COMPACTION TESTS: If so required by the inspector, compaction test shall be made at intervals of not more than one -
thousand (1000') feet and a maximum of one (1) test on each road. One (1) copy of each test shall be forwarded tot the City
Engineer for approval and filed prior to making permanent repairs. Compaction tests shall be made as outlined in Section
6.3.01 of the Standard Specifications, Division of Highways, State of California, dated January 1973.
® R19 COMPACTION TESTS: If so required by the Inspector, compaction tests shall be made for each crossing or service line.
One (1) copy of each test shall be forwarded to the City Engineer for approval and filed prior to making permanent repairs.
Compaction tests shall be made as outlined in Sections 6.3.001 of the Standard Specifications, Division of Highways, State
of California, dated January 1973.
® R20 TEMPORARY PAVEMENT REPAIRS: After completion of backfill and compaction operations, a temporary patch consisting
of two inches (2") of SC-800 shall be placed on a prepared sub -grade. The SC-800 temporary paving shall be placed after
a maximum of three -thousand linear feet (3000') or trench has been excavated and backfill operations completed, but in no
case shall the placement of the temporary pavement exceed a five (5) day limit.
® R21 PERMANENT PAVEMENT REPAIR: After backfill and compaction have been completed, a temporary patch consisting of
two inches (2") of SC-800 shall be placed immediately. A permanent patch of ( " N/A " ) inches of A.0 surfacing placed on
a ( " N/A ") inch (" N/A " ) aggregate base shall be placed no later than ( 5 ) days after completion of temporary road
repair.
❑ R22 FOG SEAL: A fog seal coat consisting of an application of asphaltic emulsion shall be applied over all patch areas as
determined by the City Engineer.
® R23 STREET RESTRIPING: Where street striping is still visible on street to be excavated, such striping shall be replaced upon
completion of permanent repairs.
® R24 TREE RELOCATION OR REMOVAL: Tree relocation within the City of La Quinta road right-of-way shall be accomplished
by a licensed, bonded and insured tree service, and handled safely without interference or hazard to the traveling public. It
shall be the responsibility of the permitte to maintain the tree in a vigorous growing condition at its new location.
Trees to be removed shall be in sections, which can be handled safely without interference or hazard to highway traffic. The
entire width of the tree stump, shall be removed and disposed of so that no debris remains in view of the highway. The
stump hole shall be backfilled and thoroughly compacted as specified in the following paragraph. Where it becomes
necessary to restrict traffic, the work shall be restricted to a maximum of five -hundred feet (500') at any one time. Adequate
signs, flagmen and or barricades shall be provided to protect the traveling public at all times.
Large holes resulting from tree removal shall be backfilled and compacted to not less than ninety percent (90%) or
equivalent tot the surrounding ground, whichever is the greater compaction as determined by the impact or field method.
Compaction tests shall comply with Section 6.3.01 of the Standard Specifications, Division of Highways, State of California,
dated January 1973.
PERMIT NO.5026
Centre Pointe / Precise Grading/Parcel No. 31116
In addition to the standard permit conditions, the following shall apply:
1. Pursuant to Section 14.16.320 of the La Quinta Municipal Code (Ordinance 10 § 1 (part), 1982), all
work shall be performed in accordance with the latest edition of the Standard Specifications For Public
Works Construction (SSPWC) and as directed by and to the satisfaction of the City Engineer.
2. This permit or copy of it shall be on the work site (usually the job trailer) for inspection during the
actual work performed.
3. Jacobsson Engineering and/or CP Development La Quinta, LLC, hereinafter referred to as
"Permittee", shall be responsible for providing continuous dust and erosion control.
4. Streets shall be kept clean. They shall be completely cleaned at the end of each working day and more
frequently, if required.
5. Pursuant to Section 6.08.050 of the La Quinta Municipal Code (Ordinance 18 § 1,1982), throughout the
work site, the Permittee shall comply with City regulated work hours. Operation and maintenance of
equipment within one-half mile of human occupancy shall be performed only during the following time
periods:
October 1st to April 30: Monday -Friday 7:00 a.m. to 5:30 p.m.
Saturday 8:00 a.m. to 5:00 p.m.
May 1 st to September 30: Monday -Friday 6:00 a.m. to 7:00 p.m.
Saturday 8:00 a.m. to 5:00 p.m.
Work shall be prohibited on legal holidays and Sundays.
Note: Construction work (including setting up traffic control devices) is not permitted on any Arterial
street (ie any 4 lane street) before 8:30 a.m. nor after 4:30 p.m.
6. Work within.500 feet of a signalized intersection shall be performed between the hours of 9 a.m. - 3
p.m. Traffic control shall be set up after 9 a.m. and removed before 3 p.m. The Permittee shall contact
the Riverside Country Traffic Signal Maintenance Department at (951) 955-6894 if signal operation at
the intersection is to be altered in any way.
7. The permittee and/or contractor shall provide surveyor staking information adequate for the City
Inspector to determine horizontal and vertical locations relative to the approved city plans. The
minimum required wood lath type stakes shall be placed at all proposed building corners, and they shall
state the horizontal location relative to building corner and the elevation of the top of hub next to the
lath.
Special Conditions Page 1 of 6
PERMIT NO.5026
Centre Pointe / Precise Grading /Parcel No. 31116
8. Pursuant to Section _14.16.110 of the La Quinta Municipal Code (Ordinance 10 § 1 (part), 1982),
Permittee shall assume respon'sibility for repair of any pavement damage to any public or private street
and for any damage to other City streets or facilities as a result of work performed under this permit.
9. Any land on which Williamson Act contracts apply shall remain undisturbed.
10. Pursuant to Section 14.16.250 of the La Quinta Municipal Code (Ordinance 10 § 1 (part), 1982),
advance warning signs and traffic control shall be installed and maintained in accordance with Cal
Trans Standards or the Work Area Traffic Control Handbook (WATCH Manual). A traffic control
plan shall be prepared in accordance with the WATCH Manual and submitted to the City for
review and approval one (1) week prior to starting any construction. It shall be the Permittee's
responsibility to appropriately detour and barricade all construction sites.
Pursuant to Section 14.16.290 of the La Quinta Municipal Code (Ordinance 10 § .1 (part), 1982), street
closures shall not be permitted. A minimum of two (2) travel lanes of paved surface shall be
maintained at all times.
11. Prior to excavating, if required, the Permittee shall contact Underground Service Alert at 1-800-422-
4133. It shall be the Pennittee's responsibility to notify the Public Works Department of anticipated
excavation which impact City facilities, including but not limited to traffic signal conduits and loops,
irrigation lines, electrical conduits, and storm drain facilities.
12. Should additional work, materials, or modifications of the work be required in order to meet City
standards, safety requirements, signage requirements, or to fit actual field conditions, the work shall be
performed by the Permittee as directed by and to the satisfaction of the City Engineer at no cost to the
City of La Quinta.
13. The permittee shall be responsible for notifying the inspection staff of import fill and overexcavated areas
on a daily base's. If the inspector's. phone number is unknown, the permittee shall call the Public Works
front counter phone at 777-7075 or the Associate Engineer at 777-7089 to determine the city inspector's
phone number.
If the imported fill or overexcavated locations indicate to the inspector that inadequate soils exist based on
the criteria set forth in the Project Soils Report, Public Works Greenbook, or Uniform Building Code, the
Public Works inspector may halt grading operations until the inadequate soil has either been removed or
the Public Works Director authorizes grading to continue.
The above testing or observations does not relieve the permittee's responsibility for future repairs due to
settlement at and near the locations of the work area.
Prior to the city issuing a building permit, the permittee's Geotechnical Engineer of Record shall submit a
certified letter indicating that the grading has been completed per the approved plan. A compaction report
on all fill is required following pad certification and prior to building permit issuance.
Special Conditions Page 2 of 6
PERMIT NO.5026
Centre Pointe / Precise Grading /Parcel No. 31116
14. The permittee shall be responsible for calling the city inspector to arrange the city inspector to observe
random trench compaction testing performed by a city approved material testing firm. If the inspector's
phone number is unknown, the permittee shall call the Public Works front counter phone at 777-7075 or
the Associate Engineer at 777-7089 to determine the city inspector's phone number. The inspector shall
determine the number and location of the test location/s. The above testing does not relieve the permittee's
responsibility for future repairs due to settlement at and near the locations of the work area. Materials
testing must be performed under direct supervision of a California Registered Civil Engineer.
15. The issuance of this permit and the City approval of the related construction improvement plans do not
provide a vested entitlement for all design parameters that may have been utilized for the plans. As such,
plans approved for this permit may be "at risk" for further modifications as it relates to any follow up
improvement plan requirements as required by the city or existing errors & omissions by the architect or
engineer of record.
16. This permit is not valid until the permittee submits, to the Public Works Department 2 weeks prior to start
of construction, the name of the City approved contractor, who shall submit to the City the following items:
a. General Liability Insurance Company and Policy Number
b. City Business License
c. Contractors State License Number
17. The permittee shall not encroach upon private property without prior written approval (submit to the Public
Works Department, attention to the Associate Engineer) of the private land owner whom is being
encroached upon.
18. Prior to performing construction work and closing any lanes in the Public Right of Way, the permittee shall
call the City at (760) 777-7097 at least 48hrs prior to work and request an appointment for a
preconstruction meeting with the City Inspection staff.
19. The permittee shall haul all offsite debris to a certified landfill. Prior to hauling debris, the permittee shall
inform the City (Inspection staff or 777-7089) of the name and location of the certified dump site.
20. Prior to excavating in native soils, the owner of the project shall have employed by proposal contract an
archaeological observer for the site excavations within native undisturbed soils. A copy of the contract
must be submitted to the Public Works Department and attention this to the Associate Engineer. If the
archaeologist determines the site note to be required to be observed, please submit a letter signed by the
archaeologist stating their determination.
21. If public traffic lanes are required to be closed, this permit is not valid until the permittee submits, to the
Public Works Department, an approved traffic control plan at least 2 weeks prior to start of construction or
parking on the paved R/W.
Special Conditions Page 3 of 6
PERMIT NO.5026
Centre Pointe / Precise Grading /Parcel No. 31116
22. Pursuant to Section 14.16.370 of the La Quinta Municipal Code (Ordinance 10 § 1 (part), 1982),
backfill compaction within street rights -of -way shall conform to Section 306-1.3 of the latest edition of
the Standard Specifications for Public Works Construction (SSPWC), except as otherwise specified
herein.
Native material may be used as backfill material provided that minimum compaction, achieved in the
manner prescribed herein, is achieved. Backfill shall be performed by mechanical means; no water
densified compaction via jetting or flooding or other means shall be allowed. It shall be the Permittee's
responsibility to provide appropriate geotechnical supervision, testing, and inspection, onsite, at all
times during backfill operations.
Backfill compaction shall be achieved by the following conditions:
A. When a firm foundation is not encountered due to soft, spongy or other unsuitable material, such
.material shall be removed .to the limits directed by the Geotechnical Inspector and/or the City
Inspector and the resulting excavation backfilled with pipe bedding material.
B. Backfill materials shall be brought to or maintained at appropriate moisture content for
compaction. The appropriate moisture content range shall be established at the onset of the
project and ensured prior to use of the materials through progress testing on the stockpiles.
C. The first length of trench backfilled shall be backfilled in the presence of the City Inspector.
Compaction shall be tested at random depths at approximate three-foot vertical intervals as
backfill is placed to ensure the effectiveness of the compaction methods and to establish the depth
of lift that can be compacted.
D. If lifts greater than one foot are attempted in this trial length of trench, compaction tests shall be
taken within the lifts to ensure that the full depth of the lift is compacted. Upon satisfactory
completion of this portion of trench, the City Inspector shall establish the maximum lift thickness
to be compacted for the remainder of the project.
E. In subsequent lengths of trench, the frequency of compaction tests shall equal one per each lift of
backfill, per 300-linear feet of open trench, at randomly selected locations within the open length
of trench. `
F. The depth of the randomly selected compaction tests shall also be randomly selected except that
where multiple tests are required in a given length of trench, the tests shall be no closer than three
feet (vertically) from each other.
G. If any compaction test fails, previously placed backfill (in the same length of open trench or
previous lengths of trench) which is represented by the failing test (as determined by the City
Inspector), shall be tested for compliance with compaction requirements.
Special Conditions Page 4 of 6
PERMIT NO.5026
Centre Pointe / Precise Grading /Parcel No. 31116
H.. All costs incurred due to the conditions above shall be borne by the Permittee. Copies of all test
results shall be furnished to the City Inspector.
23. All excavations within City of La Quinta right-of-way shall be backfilled, and temporarily paved if
within the existing travel way, at the end of every workday as directed by and to the satisfaction of the
City Engineer for the protection of the public. Lengths of open trench shall not greatly exceed that
which can not be backfilled in the same day. Excavated trenches shall not be allowed open overnight,
however, Permittee may leave a length of excavated trench, not to exceed twenty (20) feet in length,
open overnight at a point where construction will begin the next day, provided that this length of trench
is completely covered by steel plating.
24. All landscaping, irrigation, decorative rock, decorative concrete, lighting, etc., shall be replaced to its
original condition.
25. Access and egress to all local properties shall be maintained at all times.
26. Pursuant to Section 14.16.375 of the La Quinta Municipal Code (Ordinance 10. § 1 (part), 1982),
permanent pavement replacement shall be completed, no later than seven (7) days after the completion
of the work. Permanent pavement replacement shall conform to the following conditions:
A. Existing asphalt concrete pavement shall be sawcut one (1) foot beyond trench edges. Edges shall
be straight and clean.
B. Permanent pavement replacement structural section, within all trenches, shall be 1" thicker than
existing of asphalt concrete over the same existing thickness of crushed aggregate base or crushed
miscellaneous base, meeting the requirements of Sections 200-2.2 and 200-2.4 of the Standard
Specifications for Public Works Construction. The replaced pavement and base material shall be
compacted to 95% relative compaction and respectively tested, for each 300 linear feet of trench.
Verify exact structural replacement section thicknesses with the City prior to installation.
C. Permanent pavement replacement shall be installed using a City approved 3/" max medium
asphalt concrete as the base course lift and a City approved %" max medium finish course lift for
capping. Asphalt concrete mix design shall be approved by the City prior to its placement.
D. Cold -Mill and Overlay - The existing pavement which was properly protected in place during the
trenching operation located adjacent to the trench saw cut shall be cold -milled to a depth of 0.10
feet with butt joint created next to the existing unmilled pavement surface. The cold -milled area
and base asphalt concrete in the trench area shall be overlaid with a City approved C2-AR-4000
asphalt concrete mix. The width of the cold milling area shall be as follows:
• For longitudinal trenches located in a parking lane: three (3) feet outside the sawcut
removal lines.
Special Conditions Page 5 of 6
PERMIT NO.5026
Centre Pointe / Precise Grading /Parcel No. 31116
For longitudinal trenches located in a traffic lane: three (3) feet outside the sawcut removal
lines, or to the lane line striping, whichever is greater.
For transverse trenches across existing street: two (2) feet outside the sawcut removal lines.
E. If grinding and capping operations are not performed in the same day as base paving operations,
the base course lift of V max medium asphalt concrete shall be installed from saw -cut edge to
saw -cut edge flush with the existing street surface. The base course lift of paving shall not be left
0.10' low in anticipation of grinding and capping.
F. Any existing lane striping or any existing detour lane striping affected by this resurfacing shall be
replaced in kind by the Permittee, as directed by and to the satisfaction of the City Engineer.
Affected traffic signal loops shall be removed and replaced in kind. The finished pavement
surface shall be smooth, consistent, and shall conform to the surrounding�grades..
27. Permittee shall permanently stabilize any and all soil that was disturbed as a result of work performed
under this permit with an approved dust control treatment. Soil stabilization shall be done immediately
after completing the operation.
28. Pursuant to Chapter 12.56 of the La Quinta Municipal Code (Ordinance 10 § 1 (part), 1982) the City
has designated certain city streets as Truck Routes. The weight limit for restricted streets (i.e., streets
not part of the Truck Route network) is three (3) tons; trucks exceeding the weight limit may use a
restricted street if making a delivery or pickup on the subject street, or if this permit specifically grants
permission to use the street to deliver street construction materials and/or equipment.
29. The City of La Quinta reserves the right to revoke, suspend or void this permit at any time.
30. The permittee shall indemnify, hold harmless and assume the defense of the City from all damages,
delay costs, costs or expenses in law or equity that may arise out of work under this permit.
31. If it is the intent of the permittee to cut the pavement and have it restored by a third party, the
permittee shall postpone cutting the pavement until the intended third party has acquired a permit from
the City to perform the required restoration work.
Special Conditions Page 6 of 6
r: J
A i
�,-
�; ..
October 3, 2007
Matt Chapman
Turner .Construction Company
78875 Miles Avenue
La Quinta, CA 92253
Re: Encroachment Permit No. 5026, Precise Grading and Paving
Parcel Map No. 31 1 16, Centre Pointe
Dear Mr. Chapman:
Encroachment Permit number 5026 has expired as of March 6, 2007. In
order to avoid the issuance of a "Stop Work Order," please renew this
permit immediately.
The renewal fee as per City Council Resolution 96-27, states:
Encroachment Permit — renewal of expired permit shall consist of a
$100..00 permit renewal processing fee plus 10% of original fee to extend
the permit one additional year (until March 6, 2008).
ORIGINAL PERMIT FEE
10% of original permit
fee (one year extension)
PERMIT RENEWAL FEE
$15,390.00
$1, 539.00 .
$100.00
RENEWAL AMOUNT DUE:.
$1,639.00
If you have any questions or need additional information, please contact
Amy Yu at (760) 777-7047. 1 -
Cince
rely
Timothy on son, P.E.
Public Works Director/City Engineer
PC: Bryan McKinney, Principal Engineer
Amy Yu, Assistant Engineer II
Permit File, No. 5026.
Parcel Map 31116 File, Folder V
P.O. Box 1504 • LA QUINTA, CALIFORNIA 92247-1504
78-495 CA►_LE IAMPICO • LA QUINTA, CALIFORNIA 92253
(760) 777-7000 -FAX (760) 777-7101