Loading...
Traffic Impact Analysis Updated Scope Jan 30 - Feb 4 20201 Nichole Romane From:Steve Libring <SLibring@willdan.com> Sent:Wednesday, April 29, 2020 11:42 AM To:Nichole Romane Subject:Fw: Updated Traffic Scope ** EXTERNAL: This message originated outside of the City of La Quinta. Please use proper judgement and caution when opening  attachments, clicking links or responding to requests for information. **    per your request emails    From: Cheri Flores <clflores@laquintaca.gov>  Sent: Tuesday, February 4, 2020 3:11 PM  To: Nicole Criste (Contract Planner) <ncriste@Terranovaplanning.com>; Bryan McKinney <Bmckinney@laquintaca.gov>;  Steve Libring <SLibring@willdan.com>; Nicole Criste <Ncriste@laquintaca.gov>  Subject: RE: Updated Traffic Scope      সহ঺঻ Will do.        Cheri L. Flores | Planning Manager City of La Quinta 78495 Calle Tampico La Quinta, CA 92253 Ph. 760-777-7067  www.laquintaca.gov          From: Nicole Criste <ncriste@terranovaplanning.com>   Sent: Tuesday, February 4, 2020 2:51 PM  To: Bryan McKinney <Bmckinney@laquintaca.gov>; Steve Libring <SLibring@willdan.com>; Nicole Criste  <Ncriste@laquintaca.gov>; Cheri Flores <clflores@laquintaca.gov>  Subject: Re: Updated Traffic Scope     ** EXTERNAL: This message originated outside of the City of La Quinta. Please use proper judgement and caution when opening  attachments, clicking links or responding to requests for information. **     Thanks Bryan!     Cheri, when you come up for air tomorrow, please review and let me know!     Thanks!     Nicole     Nicole Sauviat Criste  Principal    2 
TERRA NOVA PLANNING & RESEARCH, INC.®  42635 Melanie Place, Ste 101
  PALM DESERT, CA 92211
  (760) 341-4800
  FAX#: 760-341-4455
  E-Mail: ncriste@terranovaplanning.com     From: Bryan McKinney <Bmckinney@laquintaca.gov>  Date: Tuesday, February 4, 2020 at 2:26 PM  To: Steve Libring <SLibring@willdan.com>, Nicole Criste <Ncriste@laquintaca.gov>, Cheri Flores  <clflores@laquintaca.gov>  Subject: RE: Updated Traffic Scope     I’m good with these.     Bryan McKinney, P.E. | Public Works Director/City Engineer  City of La Quinta  78495 Calle Tampico ◦ La Quinta, CA 92253  760.777.7045  Email: bmckinney@laquintaca.gov  Website: www.la-quinta.org        From: Steve Libring <SLibring@willdan.com>   Sent: Tuesday, February 4, 2020 1:04 PM  To: Nicole Criste <Ncriste@laquintaca.gov>; Cheri Flores <clflores@laquintaca.gov>  Cc: Bryan McKinney <Bmckinney@laquintaca.gov>  Subject: Re: Updated Traffic Scope     ** EXTERNAL: This message originated outside of the City of La Quinta. Please use proper judgement and caution when opening  attachments, clicking links or responding to requests for information. **     Bryan, let us know if you concur     Maybe clarify mitigation/fair share requirements as example in the scope so that there are no surprises? (Still  seems a little ambiguous and we'll argue with City later on these)     From: Nicole Criste <Ncriste@laquintaca.gov>  Sent: Tuesday, February 4, 2020 12:34 PM  To: Steve Libring <SLibring@willdan.com>; Cheri Flores <clflores@laquintaca.gov>  Subject: RE: Updated Traffic Scope      Steve and Cheri,     I have reviewed the scoping letter, and have the following comments:     1. The Specific Plan discusses “pop up villages” but does not define them. They are not listed in the TIA land uses.  Because I don’t know what is meant, I cannot assess whether they should be included in the TIA somehow. I will  3 point that out, and ask them to coordinate with MSA to determine whether they need to add these to their  calculations, either in the long term analysis or in the special event analysis.   2. I asked for an analysis of whether the proposed project intersections meet City separation standards (my  comment #4). They have not added it to the scoping letter. I will request that they do so.  3. I asked for an analysis of when each improvement is required (end of my comment #8). They are not clear that  this will be provided. I will request they do so.  4. I asked for a centralized list of all improvements and when they must be implemented (my comment #10). They  have not included that. I will ask that they do so.  5. In our meeting last week, Garrett Simon stated that special events would involve 7,000 guests. The scoping  letter cites 2,500 guests. I will point this out, and make it clear that this is a significant discrepancy, and if the TIA  stays at 2,500 guests, they will be conditioned to not exceed that number. If they were to, additional CEQA  review would be required as part of the Temporary Use Permit.     If these are acceptable to you, I will prepare an email, and include both of you in the chain. If you have additional  corrections, please provide ASAP. I would like to get them an answer by the end of the week (they submitted on 1/30, so  that would be just over a week).     Thanks!     Nicole     From: Steve Libring <SLibring@willdan.com>   Sent: Tuesday, February 04, 2020 11:11 AM  To: Nicole Criste <Ncriste@laquintaca.gov>; Cheri Flores <clflores@laquintaca.gov>  Subject: Fw: Updated Traffic Scope     ** EXTERNAL: This message originated outside of the City of La Quinta. Please use proper judgement and caution when opening  attachments, clicking links or responding to requests for information. **     Is this what you were expecting, do we need to discuss, or have they addressed city's concerns?     Let me know if you need anything from me     From: Nicole Criste <ncriste@terranovaplanning.com>  Sent: Thursday, January 30, 2020 1:03 PM  To: Garrett Simon <gsimon@meriwetherco.com>  Cc: Cheri Flores <clflores@laquintaca.gov>; Jon McMillen <jmcmillen@laquintaca.gov>; Ihrke, Bill <bihrke@rutan.com>;  dcastro@laquintaca.gov <dcastro@laquintaca.gov>; John Kain <jkain@urbanxroads.com>; Mike Rowe  <mrowe@msaconsultinginc.com>; Paul Depalatis <pdepalatis@msaconsultinginc.com>; Nicole Criste  <Ncriste@laquintaca.gov>; Bryan McKinney <Bmckinney@laquintaca.gov>; Steve Libring <SLibring@willdan.com>  Subject: Re: Updated Traffic Scope      Thank Garrett, I have circulated to our Traffic Engineer and City Engineer, and we will be meeting next week to  review. We will provide comments as soon as possible.     As regards fair share calculations, they are usually tied to what triggers the impact. So, for example, if at the  opening of the hotel there is a need for a traffic signal, the fair share is based on the trips generated by the  hotel (and any residences that are part of that phase), and the mitigation measure in the traffic study and EIR  requires payment or installation prior to the issuance of the certificate of occupancy for the hotel. Urban  4 Crossroads is quite familiar with this type of analysis, and should be able to help in crafting the language. If  you would like to discuss further, please feel free to give me a call.     Nicole     Nicole Sauviat Criste Consulting Planner  City of La Quinta TERRA NOVA PLANNING & RESEARCH, INC.® 42635 Melanie Place, Ste 101 PALM DESERT, CA. 92211 (760) 341-4800 FAX#: 760-341-4455 E-Mail: ncriste@terranovaplanning.com           From: Garrett Simon <gsimon@meriwetherco.com>  Sent: Thursday, January 30, 2020 12:37 PM  To: Nicole Criste <ncriste@terranovaplanning.com>  Cc: Cheri Flores <clflores@laquintaca.gov>; Jon McMillen <jmcmillen@laquintaca.gov>; Ihrke, Bill <bihrke@rutan.com>;  dcastro@laquintaca.gov <dcastro@laquintaca.gov>; John Kain <jkain@urbanxroads.com>; Mike Rowe  <mrowe@msaconsultinginc.com>; Paul Depalatis <pdepalatis@msaconsultinginc.com>  Subject: Updated Traffic Scope      Nicole and Team,     In follow up to our meeting last week and in response to the December 12, 2019 comments/questions from Nicole  regarding the draft TIA, I asked John and Marlie at Urban Crossroads to prepare a revised scope (see attached  pdf).  Although the Project land uses, cumulative database, weekday trip generation estimates and trip distribution  patterns are not anticipated to change, the following revisions will be included in the updated TIA:     1. Clarification that the surf facility is a private facility, serving Project resort and residential land uses.  2. Analysis of special events at this location (attendance of not‐to‐exceed 2,500 guests per day arriving or  departing on Saturdays, up to 4 events per year).  As shown on Table 6 of the attached scope, the Project is  anticipated to generate a net total of 8,932 trip‐ends per day on a Saturday during a special event with 906  vehicles per hour (VPH) during the arrival peak hour and 884 VPH during the departure peak hour.   3. In order to estimate background mid‐day Saturday peak hour volumes in the Project study area, weekday PM  peak hour counts will be adjusted.  The adjustments will be based upon a sampling of four Saturday intersection  counts (between 10:00 AM and 2:00 PM) in the study area.  4. The revised TIA will now include recommended improvements at Jefferson Street / Avenue 52 for relevant  analysis scenarios, based upon discussion with City staff and their consultants.  5. The revised TIA will include Project traffic share calculations for interim year scenarios (as opposed to  cumulative long range conditions), based upon Nicole’s request.     I would appreciate a timely review of this revised scope.  If technical concerns arise, please let me know so that a  conference call can be arranged.     I would also like to discuss how the share calculations at each phase may be applied.  Obviously the project share at any  point in time will vary, depending upon the occupancy of cumulative projects over time.  Isn’t it most appropriate to  determine the project fair share based upon future projections with buildout of the project and other cumulative  5 projects? I would like to get John moving forward ASAP and we can concurrently discuss our concerns of how the  calculations are applied to our project.    Please Add Good, Garrett Simon 970-596-6642 www.meriwetherco.com   Ofc:   1001 Dove St.      Suite 260      Newport Beach, CA 92660  Main:    260 E. Baker St.      Suite 200      Costa Mesa, CA 92626 urbanxroads.com   12615‐06 Revised Scope.docx  January 29, 2020  Mr. Steve Libring  City of La Quinta   78‐405 Calle Tampico  La Quinta, CA 92253    SUBJECT: REVISED SCOPING AGREEMENT FOR THE WAVE AT CORAL MOUNTAIN   REVISED TRAFFIC IMPACT ANALYSIS  Dear Mr. Steve Libring:  The firm of Urban Crossroads, Inc. is pleased to submit this scoping agreement for The Wave at Coral  Mountain (“Project”), which is located on the southwest corner of re‐aligned Madison Street at 58th  Avenue, in the City of La Quinta.  Proposed development activities within the Specific Plan (west of  Madison Street) are based upon the following land use quantities:  • Single Family Detached    496 DU  • Multifamily Housing (Low‐Rise) 104 DU  • Resort Hotel    150 RM  • Shopping Center    60 TSF  • Wave Pool Facility    12 AC  The preliminary land use plan for the proposed Project is shown on Exhibit 1.    The average number of attendees per day on a typical weekday as well as a special event day will be  discussed in the revised TIA.  Our goal is to obtain comments from City of La Quinta staff, to ensure that the traffic impact analysis  (TIA) fully addresses the potential impacts of the proposed Project.    The remainder of this letter describes the proposed analysis methodology, Project trip generation, and  trip distribution on the surrounding roadway network.  The following scoping assumptions have been  prepared in accordance with the City of La Quinta Traffic Study Guidelines (Engineering Bulletin #06‐13,  revised October 3, 2017).  Exhibit 2 depicts the location of the proposed project in relation to the existing roadway network.  Project  access locations are listed below:  • Madison Street / Main Access (full access)  • South Access / Avenue 60 (full access)  • Project Access 1 / Avenue 58 (full access)  • Project Access 2 / Avenue 58 (right‐in/right‐out access)  • Madison Street / Project Access 3 (right‐in/right‐out access)  Mr. Steve Libring  City of La Quinta   January 29, 2020  Page 2     12615‐06 Revised Scope.docx   TRIP GENERATION  The Project is anticipated to be constructed in phases, with Phase 1 (2021) including resort (wave pool  and hotel uses), 104 attached dwelling units, 26 detached dwelling units, and 10,000 square feet of retail.  Project Phase 2 (2023) adds 22,500 square feet of retail. Project Phase 3 (2026) adds 470 detached  dwelling units and 22,500 square feet of retail.  In accordance with the City of La Quinta’s Engineering Bulletin #06‐13, the Project trip generation rates  to be used for the traffic impact analysis will be based on the Institute of Transportation Engineers (ITE)  Trip Generation manual, 10th Edition (2017).  Trip generation estimates for the Project have been  determined by utilizing the published rates for the peak hour of the generator rather than for the peak  hour of adjacent street traffic, where possible.    Trip generation rates are presented on Tables 1 through 3 for Phase 1 through Project buildout  conditions, respectively. ITE trip generation rates for Single Family Detached Residential (Code 210),  Multifamily Housing (Code 220), Resort Hotel (Code 330), and Shopping Center (Code 820) are used.  The  surf pool is a private facility.  As indicated in the original approved TIA scope for this Project, trip  generation rates for the Wave Pool Facility from the San Diego Association of Governments recreational  park (developed) rates appropriately account for this private facility.  The project area land uses include a unique mix of commercial retail, resort, recreation and residential  uses, so reasonable assumptions regarding internal/pass‐by interactions between these uses are  included in the trip generation calculations. The wave pool facility will be utilized by hotel guests, but  outside trip generation is also included for things like off‐site lunch, wave pool employees, etc. Area  residents and visitors will use the commercial retail area facilities (which typically include merchandise,  service station and restaurant land uses). The total internal/pass‐by trip ends have been adjusted in a  manner to ensure that no “double counting” occurs before assigning the project trips to the roadway  network.  As shown on Table 1, Phase 1 of the proposed Project is anticipated to generate a net total of 2,227  external trip‐ends per day on a typical weekday with 114 external vehicles per hour (VPH) during the  weekday AM peak hour and 151 external VPH during the weekday PM peak hour.  Table 2 shows trip generation for Phase 2 of the proposed Project, which is anticipated to generate a net  total of 2,778 external trip‐ends per day on a typical weekday with 123 external vehicles per hour (VPH)  during the weekday AM peak hour and 208 external VPH during the weekday PM peak hour.  As shown on Table 3, at Project buildout, the site is anticipated to generate a net total of 6,994 external  trip‐ends per day on a typical weekday with 447 external vehicles per hour (VPH) during the weekday  AM peak hour and 638 external VPH during the weekday PM peak hour.  TRIP DISTRIBUTION  Trip distribution is the process of identifying the probable destinations, directions or traffic routes that  will be utilized by Project traffic.  The potential interaction between the planned land uses and  surrounding regional access routes are considered to identify the routes where modified project traffic  Mr. Steve Libring  City of La Quinta   January 29, 2020  Page 3     12615‐06 Revised Scope.docx   would travel.  The trip distribution pattern is heavily influenced by the geographical location of the site,  the location of surrounding uses, and the proximity to the arterial and regional freeway system.    The trip distribution patterns for the proposed Project residential and resort components are graphically  depicted on Exhibit 3.  Exhibit 4 shows the trip distribution patterns for the proposed Project shopping  center components.  The trip distributions have been developed based on RivTAM and local knowledge  in the vicinity of the Project site and refined to reflect the roadway network and the surrounding uses in  the vicinity of the proposed Project as they exist today and are planned for the future.  STUDY AREA  The traffic impact study area was defined in conformance with the requirements of Engineering Bulletin  #06‐13.  Based on this criterion, anticipated trip generation and trip distribution, the following  intersections will be evaluated (see Exhibit 2):  ID Intersection Location ID Intersection Location  1 Madison Street at Avenue 58 12 Monroe Street at Avenue 58  2 Madison Street at Avenue 56 13 Monroe Street at Airport Boulevard   3 Madison Street at Avenue 54 14 Monroe Street at Avenue 54  4 Madison Street at Avenue 52 15 Monroe Street at Avenue 52  5 Madison Street at Avenue 50 16 Monroe Street at 50th Avenue  6 Jefferson Street at Avenue 54 17 Jackson Street at 58th Avenue   7 Jefferson Street at Avenue 52 18 South Access at Avenue 60 ‐ (Future Intersection)  8 Jefferson Street at Pomelo 19 Madison Street at Main Access‐ (Future Intersection)  9 Jefferson Street at Avenue 50 20 Project Access 1 at Avenue 58‐ (Future Intersection)  10 Madison Street at Avenue 60 21 Project Access 2 at Avenue 58‐ (Future Intersection) 11 Monroe Street at Avenue 60 22 Madison Street at Project Access 3‐ (Future Intersection)  In addition, the following roadway segments will be evaluated:  Roadway Segment  1 Avenue 58, west of Madison Street 4 Madison Street, south of Airport Boulevard  2 Avenue 58, west of Monroe Street 5 Avenue 60, west of Monroe Street  3 Avenue 58, west of Jackson Street 6 Monroe Street, south of Airport Boulevard  TRAFFIC COUNTS  Traffic count data were previously taken on August 15th, 2017, April 9th, 2019, May 7th, 2019, and  September 9th, 2019  during the AM peak period of 6:00 AM to 8:30 AM and PM peak period of 2:30 PM  to 5:30 PM.  A 20% increase is applied to counts taken in August, 5% increase is applied to counts taken  in April, 10% increase is applied to counts taken in May, and 15% increase is applied to counts taken in  September per City of La Quinta’s EB#06‐13.  Table 4 shows that the average AM/PM peak hour  intersection growth between 2017 and 2019 counts data at selected study area and nearby intersections  Mr. Steve Libring  City of La Quinta   January 29, 2020  Page 4     12615‐06 Revised Scope.docx   is approximately 2.66%.  The additional 2.66% growth rate is applied to the study area intersections with  2017 counts to reflect 2019 conditions.  Exhibits 5 and 6 identify the count data utilized for each study  intersection and illustrate the resulting Existing (2019) morning and evening peak hour intersection  volumes.    ADT volumes are estimated using the formula below for each intersection leg (consistent with 2018  Travertine Specific Plan TIA, prepared by Urban Crossroads, Inc.) and compared to the 2017 ADT’s with  2.66% growth to reflect 2019 conditions, where 2019 counts are unavailable.   Weekday PM Peak Hour (Approach Volume + Exit Volume) x 12 = Leg Volume  ANALYSIS SCENARIOS  Consistent with Engineering Bulletin #06‐13, the following analysis scenarios are proposed for this traffic  study:   Existing (2019)   Existing Plus Project (E+P)    Existing Plus Ambient Growth Plus Project (E+A+P)   Existing Plus Ambient Growth Plus Cumulative Projects, with and without Project for each  of the following phases:  o Project Phase 1 (2021)  o Project Phase 2 (2023)  o Project buildout (Phase 3, 2026)  o Project buildout (Phase 3, 2026) – Special Event    General Plan buildout (2040) Without Project Conditions – establishes future year  baseline to evaluate the proposed Project   General Plan buildout (2040) With Project Conditions – represents future year baseline  traffic conditions with the proposed Project  In accordance with Engineering Bulletin #06‐13, improvements fully funded by the City of La Quinta’s  Capital Improvement Program (CIP) will be assumed to be in place for long range future conditions.   Improvements fully funded by the City’s CIP, the Development Impact Fee Program (DIF) and the  Transportation Uniform Mitigation Fee Program (TUMF) are assumed to be in place for Opening Year  Cumulative conditions.   LEVEL OF SERVICE (LOS) CRITERIA  Per Engineering Bulletin #06‐13, the following LOS criteria will be utilized for study area intersections:    Intersection Type    LOS Criteria  Signalized Intersection LOS “D” or better  All‐way Stop Controlled Intersection LOS “D” or better for all critical movements  Cross‐Street Stop Controlled Intersection LOS “E” or better for the side street  Mr. Steve Libring  City of La Quinta   January 29, 2020  Page 5     12615‐06 Revised Scope.docx   The City of La Quinta has established LOS “D” as the minimum level of service for its street segments.  PREFERRED ANALYSIS METHODOLOGY  The study area intersections will be analyzed using the Highway Capacity Manual (HCM) 6th Edition  methodology. The parameters provided in Attachment 2 of Engineering Bulletin #06‐13 will be utilized  for the purposes of this analysis, unless directed otherwise.  CUMULATIVE DEVELOPMENT PROJECTS  It is requested that the City of La Quinta Planning Department review the cumulative projects shown  on Exhibit 7 and listed on Table 5.   CUMULATIVE GROWTH VOLUMES   The background (non project) Opening Year Cumulative traffic projections will be determined by  interpolating between the existing traffic volumes and the year 2040 City and/or CVAG traffic  projections.  YEAR 2040 TRAFFIC FORECASTS  The Year 2040 forecast volumes are based upon an updated version of the Riverside County  Transportation Analysis Model (RivTAM) which became available in the CVAG region during 2016.  It is  consistent with the SCAG draft 2016 RTP for the Transportation Project Prioritization Study (TPPS) 2040  project.  For 2040 conditions, RivTAM projections will be examined to determine additional growth  beyond the 2035 peak hour intersection volumes identified in the 2012 traffic study prepared by Iteris  for the La Quinta General Plan Update.  Where necessary, the resulting 2040 volumes estimates will be  adjusted to achieve flow conservation, reasonable growth, and reasonable diversion between parallel  routes.  SPECIAL ISSUES  The following issues will also be addressed as part of the TIA:   Site Access Evaluation:  Recommendations regarding site access and queuing analysis will be  included in the traffic study.  It is anticipated that the project will be required to widen Avenue  58 frontage.   Eastbound left turn capacity will be evaluated along Avenue 58 approaching  Madison Street.  Project fair share participation in signal improvements will also be determined.   Jefferson & Avenue 52 Improvements:  The revised TIA will now include recommended  improvements at Jefferson Street / Avenue 52 for relevant analysis scenarios, based upon  discussion with City staff and their consultants.   Interim Year Project Share Estimates:  The revised TIA will include fair share calculations for  interim year scenarios (as opposed to cumulative long range conditions), based upon the City  consultant request.  Mr. Steve Libring  City of La Quinta   January 29, 2020  Page 6     12615‐06 Revised Scope.docx    Vehicle miles traveled (VMT):  Consistent with the Office of Planning and Research (OPR) updates  to CEQA guidelines which are responding to Senate Bill 743 (SB 743), VMT estimates for the  Project will be calculated.  Potential mitigation measures and estimated effectiveness in reducing  VMT in terms of percentage reduction of VMT for each measure will be identified in the traffic  study.   Special Events:  The applicant anticipates the potential occurrence of special events at this  location involving attendance of not‐to‐exceed 2,500 guests per day arriving or departing on  Saturdays (up to 4 events per year).  In order to estimate background mid‐day Saturday peak  hour volumes in the Project study area, weekday PM peak hour counts will be adjusted.  The  adjustments will be based upon a sampling of four Saturday intersection counts (between 10:00  AM and 2:00 PM) in the study area.    Table 6 shows the Saturday Project trip generation during a special event based on 2,500 guests  per day at the Wave Pool facility and approximately 25% of the guests arriving or departing during  the arrival or departure peak hour.  Weekend rates for other on‐site land uses represent typical  Saturday rates.  As shown on Table 6, the proposed Project is anticipated to generate a net total  of 8,932 trip‐ends per day on a Saturday during a special event with 906 vehicles per hour (VPH)  during the arrival peak hour and 884 vph during the departure peak hour.  Traffic management plan features will be identified for the typical Project special event (2,500  guests).  Exhibit 8 shows a high‐level event operations planning framework which will also be  included in the revised TIA as part of the discussion of future traffic control plan refinements for  special events.      If you have any questions, please contact John Kain at (949) 336‐5990 or Marlie Whiteman at (949) 336‐ 5991.    Respectfully submitted,    URBAN CROSSROADS, INC.    John Kain, AICP Marlie Whiteman, PE  Principal Senior Associate    JN: 12615 The Wave at Coral Mountain  Attachments  xc:  Mr. Bryan McKinney 58th Avenue Neighborhood Commercial Future Low Density Residential (3) Future Low Density Residential (2)FutureLow Density Residential (4) Low Density Residential (5)Madison Street60th Avenue 28.55 Ac. 46.61 Ac. The Farm 49.21 Ac. 54.50 Ac. 37.66 Ac. 7.77 Ac. ±118 Units ±122 Units ±136 Units ±94 Units Resort (5) Back ofHouse Pop-UpVillage 2 14.20 Ac.±41 Units The Hotel ±63 Units 2.53 Du/Ac. 2.50 Du/Ac. 2.50 Du/Ac. 2.48 Du/Ac. 2.21 Du/Ac. 2.89 Du/Ac Planning Area IX Resort (4) Resort (1) Future Planning Area VII Planning Area VIII Planning Area VIII Planning Area VIII Planning Area VIII PA IX Planning Area IX TheBeach Club Pop-UpVillage 3 Pop-UpVillage 4 Pop-UpVillage 5 The Farm Village 3.18 Ac. 15.38 Ac. 8.24 Ac. 11.32 Ac. 8.41 Ac.5.90 Ac. 4.24 Ac. 6.82 Ac. IRRI G A T I O N E A S E M E N T IR R I G A T I O N E A S EM E N T IRRIGATION EASEMENTIRRIGAT ION EASEMENT IRRIGATION EASEMENT PA X 53.56 Ac. Open Space Planning Area X 128 129 121 120 119 118 114 113 112 111 110 109101 100 99 98 97 96 95 93 117 89 88 87 86 75 76 77 78 79 80 81 82 83 84 85 62 61 60 59 58 57 56 43 42 41 40 39 38 44 45 46 47 4950 51 52 53 54 55 63 64 65 66 67 68 69 70 71 72 73 363534333231 7 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 4837 74 90 OS Resort (3) 11.06 Ac. Planning Area IX (Includes "The Farm" and "The Farm Village") Resort (2) 27.82 Ac. Planning Area IX The Wave (Includes "Resort Residential" (Lots 27-89) and "The Beach Club") (150 Keys)9.52 Ac. (Resort Residential (Lots 91-131) Open Space The Hotel Pop-UpVillage 1 3.40 Ac. 130 131 129 128 125 107106105104103102 124 123 116 115 108 94 92 91 1 2 3 4 5 6 8 9 142 135 140 146 145 144 147 139 132 133 134 136 137 138 143 148 149 122 OS OS OS OS OS OS 141 150 OS OSOS OS OS OS 90The Hotel OS OS OS 10 Low Density Residential (1) 44.09 Ac.±26 Units0.59 Du/Ac. Planning Area VIII 91.15 Ac. 9.52 Ac. 27.82 Ac. 53.56 Ac. 44.09 Ac. 46.61 Ac. 37.66 Ac. 104 Units (Attached Residential) 150 Hotel Keys N/A N/A 26 Units (Detached Residential) 118 Units (Detached Residential) 94 Units (Detached Residential) 384.55 Ac. 750 Units Resort (2) - The Wave Open Space (Recreation) Low Density Residential (2) Low Density Residential (3) Total 14.20 Ac.41 Units (Attached Residential)Resort (5) - Residential 54.50 Ac. 136 Units (Detached Residential) 49.21 Ac. 122 Units (Detached Residential) 28.55 Ac.63 Units (Attached Residential)Resort (4) - Residential Low Density Residential (4) Low Density Residential (5) N/A 15.76 Du/Ac. N/A N/A 0.59 Du/Ac. 2.53 Du/Ac. 2.50 Du/Ac. N/A 2.89 Du/Ac. 2.50 Du/Ac. 2.48 Du/Ac. 2.21 Du/Ac. 232.07 Ac.496 Units (Detached Residential)Low Density Residential Subtotal N/A PA VIII PA IX PA X LAND USE LEGEND Land Use Area Units Note:1.Planning Areas VII & IX will have a combined allowable retail area of 60,000 sf.2.All planning areas will distribute the overall total unit allowance based on market demand. Density / AcrePlanningArea 7.77 Ac.N/ANeighborhood Commercial N/APA VII Resort (3) - The Farm Resort (1) - Hotel 11.06 Ac. N/A N/A Resort Subtotal Low Density Residential (1) 7 8 In Out Total In Out Total Single Family Detached 210 26 DU 0.19 0.55 0.74 0.62 0.37 0.99 9.44 Multifamily Housing (Low‐Rise)220 104 DU 0.11 0.35 0.46 0.35 0.21 0.56 7.32 Resort Hotel 3305 150 RM 0.27 0.10 0.37 0.20 0.27 0.47 7.87 Shopping Center 820 10 TSF 0.58 0.36 0.94 1.83 1.98 3.81 37.75 Wave Pool Facility ‐4 12 AC 1.20 0.80 2.00 2.40 1.60 4.00 50.00 In Out Total In Out Total Single Family Detached 210 26DU5 1419161026245 Multifamily Housing (Low‐Rise)220 104 DU 11 36 47 36 22 58 761 Internal to Retail/Resort (2) (3) (5) (9) (7) (16) (141) 14 47 61 43 25 68 865 Shopping Center 820 10 TSF 6 4 10 18 20 38 378     Pass‐By (25%)3 (1) (1) (2) (5) (5) (10) (95) Internal to Residential/Resort (3) (3) (6) (4) (4) (8) (72) 20291120211 Resort Hotel 3305 150 RM 41 15 56 30 41 71 1,181 Internal to Residential/Retail (7) (8) (15) (11) (17) (28) (324) 34 7 41192443857 Wave Pool Facility ‐4 12 AC 14 10 24 29 19 48 600 Internal to Residential/Retail/Resort (8) (6) (14) (16) (12) (28) (306) 6 4 10 13 7 20 294 77 79 156 129 112 241 3,165 Internal Capture Subtotal (20) (20) (40) (40) (40) (80) (843) Pass‐By (Shopping Center) (1) (1) (2) (5) (5) (10) (95) 56 58 114 84 67 151 2,227 4   Since ITE does not have trip rates for a wave pool facility, similar use based on SANDAG's recreation park (developed) peak hour and daily rates are utilized. 5   Since ITE does not have daily rate for a ITE LU 330 (Resort Hotel), daily rate has been estimated based on ITE LU 210 (Hotel) peak to daily relationship. R:\UXRjobs\_12600‐13000\12615\Excel\[12615 ‐ Scope Rev.xlsx]Ph1 TABLE 1: PROJECT PHASE 1 (2021) TRIP GENERATION SUMMARY Trip Generation Rates1 Land Use ITE LU Code Quantity 2 AM Peak Hour PM Peak Hour Land Use ITE LU Code Quantity 2 AM Peak Hour PM Peak Hour Daily Daily Residential External Trips Trip Generation Results 2  DU = Dwelling Unit; RM = Occupied Room; TSF = Thousand Square Feet 3  Pass‐By Source: Shops at Coral Mountain TIA, prepared by Urban Crossroads, Inc. (November 2009). Shopping Center External Trips Resort Hotel External Trips Wave Pool Facility External Trips Project Subtotal Project Total External Trips 1  Trip Generation Source:  Institute of Transportation Engineers (ITE), Trip Generation Manual, 10th Edition (2017). 9 In Out Total In Out Total Single Family Detached 210 26 DU 0.19 0.55 0.74 0.62 0.37 0.99 9.44 Multifamily Housing (Low‐Rise)220 104 DU 0.11 0.35 0.46 0.35 0.21 0.56 7.32 Resort Hotel 3305 150 RM 0.27 0.10 0.37 0.20 0.27 0.47 7.87 Shopping Center 820 35 TSF 0.58 0.36 0.94 1.83 1.98 3.81 37.75 Wave Pool Facility ‐4 12 AC 1.20 0.80 2.00 2.40 1.60 4.00 50.00 In Out Total In Out Total Single Family Detached 210 26DU5 1419161026245 Multifamily Housing (Low‐Rise)220 104 DU 11 36 47 36 22 58 761 Internal to Retail/Resort (2) (5) (7) (10) (8) (18) (158) 14 45 59 42 24 66 848 Shopping Center 820 35 TSF 20 13 33 64 69 133 1,321     Pass‐By (25%)3 (4) (4) (8) (16) (16) (32) (330) Internal to Residential/Resort (5) (4) (9) (8) (8) (16) (144) 11 5 16404585847 Resort Hotel 3305 150 RM 41 15 56 30 41 71 1,181 Internal to Residential/Retail (8) (8) (16) (13) (19) (32) (370) 33 7 40172239811 Wave Pool Facility ‐4 12 AC 14 10 24 29 19 48 600 Internal to Residential/Retail/Resort (9) (7) (16) (17) (13) (30) (328) 5 3 8 12 6 18 272 91 88 179 175 161 336 4,108 Internal Capture Subtotal (24) (24) (48) (48) (48) (96) (1,000) Pass‐By (Shopping Center) (4) (4) (8) (16) (16) (32) (330) 63 60 123 111 97 208 2,778 4   Since ITE does not have trip rates for a wave pool facility, similar use based on SANDAG's recreation park (developed) peak hour and daily rates are utilized. 5   Since ITE does not have daily rate for a ITE LU 330 (Resort Hotel), daily rate has been estimated based on ITE LU 210 (Hotel) peak to daily relationship. R:\UXRjobs\_12600‐13000\12615\Excel\[12615 ‐ Scope Rev.xlsx]Ph2 TABLE 2: PROJECT PHASE 2 (2023) TRIP GENERATION SUMMARY Trip Generation Rates1 Land Use ITE LU Code Quantity 2 AM Peak Hour PM Peak Hour Land Use ITE LU Code Quantity 2 AM Peak Hour PM Peak Hour Daily Daily Residential External Trips Trip Generation Results 2  DU = Dwelling Unit; RM = Occupied Room; TSF = Thousand Square Feet 3  Pass‐By Source: Shops at Coral Mountain TIA, prepared by Urban Crossroads, Inc. (November 2009). Shopping Center External Trips Resort Hotel External Trips Wave Pool Facility External Trips Project Subtotal Project Total External Trips 1  Trip Generation Source:  Institute of Transportation Engineers (ITE), Trip Generation Manual, 10th Edition (2017). 10 In Out Total In Out Total Single Family Detached 210 496 DU 0.19 0.55 0.74 0.62 0.37 0.99 9.44 Multifamily Housing (Low‐Rise)220 104 DU 0.11 0.35 0.46 0.35 0.21 0.56 7.32 Resort Hotel 3305 150 RM 0.27 0.10 0.37 0.20 0.27 0.47 7.87 Shopping Center 820 60 TSF 0.58 0.36 0.94 1.83 1.98 3.81 37.75 Wave Pool Facility ‐4 12 AC 1.20 0.80 2.00 2.40 1.60 4.00 50.00 In Out Total In Out Total Single Family Detached 210 496 DU 94 273 367 308 184 492 4,682 Multifamily Housing (Low‐Rise)220 104 DU 11 36 47 36 22 58 761 Internal to Retail/Resort (10) (20) (30) (40) (29) (69) (595) 95 289 384 304 177 481 4,848 Shopping Center 820 60 TSF 35 22 57 110 119 229 2,265     Pass‐By (25%)3 (7) (7) (14) (28) (28) (56) (566) Internal to Residential/Resort (9) (7) (16) (21) (35) (56) (448) 19 8 27 61 56 117 1,251 Resort Hotel 3305 150 RM 41 15 56 30 41 71 1,181 Internal to Residential/Retail (14) (10) (24) (15) (21) (36) (416) 27 5 32152035765 Wave Pool Facility ‐4 12 AC 14 10 24 29 19 48 600 Internal to Residential/Retail/Resort (12) (8) (20) (26) (17) (43) (470) 224325130 195 356 551 513 385 898 9,489 Internal Capture Subtotal (45) (45) (90) (102) (102) (204) (1,929) Pass‐By (Shopping Center) (7) (7) (14) (28) (28) (56) (566) 143 304 447 383 255 638 6,994 4   Since ITE does not have trip rates for a wave pool facility, similar use based on SANDAG's recreation park (developed) peak hour and daily rates are utilized. 5   Since ITE does not have daily rate for a ITE LU 330 (Resort Hotel), daily rate has been estimated based on ITE LU 210 (Hotel) peak to daily relationship. R:\UXRjobs\_12600‐13000\12615\Excel\[12615 ‐ Scope Rev.xlsx]Ph3 TABLE 3: PROJECT BUILDOUT (2026) TRIP GENERATION SUMMARY Trip Generation Rates1 Land Use ITE LU Code Quantity 2 AM Peak Hour PM Peak Hour Daily Residential External Trips Resort Hotel External Trips Trip Generation Results Land Use ITE LU Code Quantity 2 AM Peak Hour PM Peak Hour Wave Pool Facility External Trips Shopping Center External Trips Project Subtotal Project Total External Trips 1  Trip Generation Source:  Institute of Transportation Engineers (ITE), Trip Generation Manual, 10th Edition (2017). 2  DU = Dwelling Unit; RM = Occupied Room; TSF = Thousand Square Feet Daily 3  Pass‐By Source: Shops at Coral Mountain TIA, prepared by Urban Crossroads, Inc. (November 2009). 11 12 13 AM PM TOTAL AM PM TOTAL 1 Madison St. / Avenue 58 410 540 950 433 601 1,034 5 Madison St. / Avenue 50 1,148 1,371 2,519 1,116 1,375 2,491 12 Monroe St. / Avenue 58 307 418 725 322 477 799 14 Monroe St. / Avenue 54 740 835 1,575 799 821 1,620 Monroe St. / Avenue 62 163 188 351 151 188 339 2,768 3,352 6,120 2,821 3,462 6,283 2.66% 1 Source: Travertine Specific Plan TIA, April 2018.  Prepared by Urban Crossroads, Inc. 2 Existing count data were collected in April 9, 2019.  In accordance with the City of La Quinta's traffic study guidelines, a 5% seasonal variation factor   has been applied to the April 2019 traffic count data. R:\UXRjobs\_12600‐13000\12615\Excel\[12615 ‐ Scope Rev.xlsx]Summary_(Existing Comparison1) TOTAL AVERAGE AM/PM GROWTH (to be applied to the remaining study intersections  with 2017 Counts to reflect 2019 conditions) TABLE 4: EXISTING 2017 & 2019 PEAK HOUR INTERSECTION VOLUMES COMPARISON SUMMARY ID Intersection Peak Hour Intersection Volumes Existing 20171 Existing 20192 14 15 16 LQ19 I3 I2 IW2 LQ29 I1 LQ28 IW1 LQ17 LQ6 LQ4 LQ7 LQ22 LQ13 LQ25 LQ11 LQ9 LQ31 LQ8 LQ15 LQ12 LQ18 LQ23 LQ27 LQ26 LQ32 LQ10 LQ24 LQ16 I4 LQ2 LQ14 I5 SITE RC1MONROE STJACKSON STJEFFERSON STMADISONSTIN D I O BLV D 50TH AVEWASHI N G T O NSTAVENUE 52 AIRPORT BLVD FRED WARING DR 62ND AVE HIGHWAY111 AVENUE 46 EISENHOWER DRAVENUE 48 60TH AVE AVENUE 50 52ND AVE 54TH AVEAVENIDA BERMUDASWASHINGTONSTIN D I O B L V D JEFFERSON STMILES AVE 58TH AVE 54TH AVE RI VI E R A 62ND AVE MADISON STADAMS ST61ST AVE 60TH AVE LIGA CLINTON STAVENUE 44 DUNE PALMS RDPGABLVD51ST AVE REQUA AVE AVENIDA RUBIO53RD AVE 55TH AVEWINGED FOOTHJORTH STWARNER TRLO DLUM D R IROQUOIS DR BURR STDARBY RD AVENUE 45 ME RION H E R M I T A G E MANDARINA C A L I FOR N IA DRMI SSION D R WCLUB DRPARKAVEAVENUE 53 VIA SAV O NAAVENUE 49 WEISKOPF ELLA AVE FAZIO LNN VILLA G E D R DO CTOR CARREON BLVD F A Z I O L N S CALHOUN STCREST AVE CO A CHEL L A D R JEREZA R A CENA NEW YOR K A V E KINGSTON DR YOUNGS LNUL R I C HDRA V EN ID A M O N T E Z U MA ALBION DRQUAILRUNL NAVENUE 43 FIRESTONECALLE QUITOVIAC A R M E L GRANT DR RUSTIC C A N Y O N D R L O M A VIS VIA PE S SARO BAFFINAV E CALLE TEMECULA GABLE DR VIA TESORO YAVAPA MUIRFIELD DR PLUM LN ALMONTEDESERT GROVE DRLAG O D R VECINO WAY PEARRY PL ADAM'S LNLA QUINTA INDIO INDIAN WELLS PALM DESERT I3 LQ34 IW2 LQ29 I1 LQ33 IW1 LQ17 LQ6 LQ4 LQ7 LQ22 LQ13 LQ25 LQ11 LQ1 LQ9 LQ31 LQ8 LQ15 LQ12 LQ23 LQ18 LQ27 LQ26 LQ20 LQ10 LQ24 LQ16 I4 LQ2 LQ14 LQ3LQ21 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community The Wave - Coral Mountain EXHIBIT 7: CUMULATIVE DEVELOPMENT MAP _N 12615 - CD.mxd 17 Page 1 of 2 # Project/Location Land Use 1 Quantity Units 2 LQ1 Desert Club Apartments Apartments 16 DU LQ2 La Quinta Penthouses Condo/Townhouse 8 DU LQ3 Mountain Village Residences Apartments 6 DU Apartments 104.000 TSF Medical Office 130.450 TSF LQ6 Washington Apartments Apartments 26 DU Multifamily Housing (Low‐Rise) 66 DU Hotel 108 Rooms Shopping Center 305.000 TSF LQ8 Codorniz SFDR 142 DU LQ9 Estate Collection at Coral Mountain SFDR 57 DU LQ10 Villas at Indian Springs SFDR 15 DU LQ11 Bellesera SFDR 320 DU Luxury Hotel 140 Rooms Condo/Townhouse 29 DU Lifestyle Hotel 200 Rooms Condo/Townhouse 66 DU LQ14 American Tire Depot Automobile Parts 6.720 TSF LQ15 Estates at Griffin Lake SFDR 78 DU LQ16 Monterra SFDR 40 DU LQ17 Andalusia at Coral Mountain SFDR 39 DU LQ18 Floresta SFDR 82 DU LQ19 California Desert Museum of Art Museum 18 TSF LQ20 Walsh Urology Medical Office 1.09 AC LQ21 Crabpot Restaurant 1.800 TSF LQ22 Residence Club @ PGA West SFDR 11 DU LQ23 Signature at PGA West SFDR 230 DU LQ24 Casa Mendoza Expansion Restaurant 1.053 TSF LQ25 Pavilion Palms Shopping Center Shopping Center 125.000 TSF LQ26 Griffin Ranch Amendment SFDR 4 DU LQ27 Andalusia Village SFDR 71 DU SFDR 1,200 DU Hotel 100 Rooms SFDR 152 DU Hotel 125 Rooms LQ31 Silverrock Temporary Clubhouse Recreational Facility 3.886 TSF LQ32 Canyon Ridge SFDR 74 DU LQ33 Shops at Coral Mountain Shopping Center 40.7 TSF LQ34 Coral Canyon SFDR 219 DU LQ29 Centre at La Quinta TABLE 5: CUMULATIVE DEVELOPMENT LAND USE SUMMARY City of La Quinta LQ4 Mayer Villa Capri LQ7 The Dune Palms Specific Plan LQ12 SilverRock ‐ Phase I LQ13 SilverRock ‐ Phase II LQ28 Travertine 18 Page 2 of 2 # Project/Location Land Use 1 Quantity Units 2 TABLE 5: CUMULATIVE DEVELOPMENT LAND USE SUMMARY SFDR 230 DU Equestrian Way Station 1.4 AC IW1 TTM No. 37467 SFDR 18 DU Condo/Townhouse 70 DU Hotel 263 Rooms Quality Restaurant 5.500 TSF Health Club 38.000 TSF Shopping Center 15.000 TSF Restaurant 6.300 TSF Retail 350.000 TSF Office 200.000 TSF Hotel 370 Rooms Condo/Townhouse 516 DU I4 La‐Z‐Boy Gallery Retail 15.600 TSF I5 Polo Community Senior & SFDR 560 DU 1 SFDR = Single Family Detached Residential 2 AC = Acres; TSF = Thousand Square Feet; DU = Dwelling Unit R:\UXRjobs\_12600‐13000\12615\Excel\[12615 ‐ Scope Rev.xlsx]Cumulatives I3 Polo Square City of Indian Wells IW2 Hotel Development County of Riverside RC1 Vista Soleada City of Indio I1 Jefferson and Hwy. 111 19 In Out Total Single Family Detached 210 0.50 0.43 0.93 Multifamily Housing (Low‐Rise)2206 0.38 0.32 0.70 Resort Hotel 3105 0.40 0.32 0.72 Shopping Center 820 2.34 2.16 4.50 Wave Pool Facility ‐4 In Out Total In Out Total Single Family Detached 210 496 DU 248 213 461 248 213 461 4,732 Multifamily Housing (Low‐Rise) 220 104 DU 40 33 73 40 33 73 847 Internal to Retail/Resort (18) (40) (58) (53) (25) (78) (600) 270 206 476 235 221 456 4,979 Shopping Center 820 60 TSF 140 130 270 140 130 270 2,767     Pass‐By (26%) (35) (35) (70) (35) (35) (70) (719) Internal to Residential/Resort (25) (33) (58) (35) (26) (61) (498) 80 62 142 70 69 139 1,550 Resort Hotel 330 150 RM 60 48 108 60 48 108 1,229 Internal to Residential/Retail (20) (28) (48) (24) (19) (43) (430) 40 20 60 36 29 65 799 Wave Pool Facility ‐4 2,500 Guests 260 14 274 14 260 274 2,084 Internal to Residential/Retail/Resort (42) (4) (46) (4) (46) (50) (480) 218 10 228 10 214 224 1,604 748 438 1,186 502 684 1,186 11,659 Internal Capture Subtotal (105) (105) (210) (116) (116) (232) (2,008) Pass‐By (Shopping Center) (35) (35) (70) (35) (35) (70) (719) 608 298 906 351 533 884 8,932 4  Vehicle trips are calculated based on estimated number of guests during special events and vehicle occupancy of 2.4. 5  Saturday data for Hotel (ITE Land Use 310) has been utilized. 6  Since Saturday peak hour in/out ratio is not available for ITE Land Use 220, the in/out Saturday split for ITE LU 210 (Single Family Detached Residential) has been utilized. R:\UXRjobs\_12600‐13000\12615\Excel\[12615 ‐ Scope Rev.xlsx]Ph3‐SE 9.54 8.14 8.19 46.12  Weekend Daily  Trip Generation Rates1 See Below DU DU RM TSF Guests Shopping Center External Trips Resort Hotel External Trips Wave Pool Facility External Trips 2  DU = Dwelling Unit; RM = Room; TSF = Thousand Square Feet 3  Source: Trip Generation Handbook, 3rd Edition (2017). Project Subtotal Project Total External Trips 1  Trip Generation Source:  Institute of Transportation Engineers (ITE), Trip Generation Manual, 10th Edition (2017).  Weekend Daily  Residential External Trips Trip Generation Results Land Use ITE LU Code Quantity 2 Arrival Peak Hour Departure Peak Hour TABLE 6: PROJECT BUILDOUT (2026) TRIP GENERATION SUMMARY ‐ WEEKEND SPECIAL EVENT Land Use ITE LU Code Units 2 Saturday Mid‐Day Peak Hour 20   12615‐06 Revised Scope.docx  EXHIBIT 8: EVENT OPERATIONS PLANNING FRAMEWORK                                              Source: Managing Travel for Planned Special Events Handbook: Executive Summary (June 2007) prepared by Federal Highway Administration (FHWA)          21