2020-07-07 Staff Report re Public Interest Finding for Dune Palms BridgeCity of La Quinta
CITY COUNCIL MEETING:July 7, 2020
STAFF REPORT
AGENDA TITLE: ADOPT RESOLUTION TO APPROVE A PUBLIC INTEREST
FINDING TO RATIFY THE SELECT SOURCE CONTRACT EXTENSION OF BENGAL
ENGINEERING, INC. TO COMPLETE THE ENGINEERING PHASE OF THE DUNE
PALMS ROAD BRIDGE IMPROVEMENT PROJECT NO. 2011-05, FEDERAL AID
PROJECT NO. BRLKS 5433 (014)
RECOMMENDATION
Adopt Resolution to approve a Public Interest Finding to ratify the select
source contract extension of Bengal Engineering, Inc. to complete the
engineering phase of the Dune Palms Road Bridge Improvement Project
(Project No. 2011-05, Federal Aid Project No. BRLKS 5433 (014).
EXECUTIVE SUMMARY
x The Dune Palms Road Bridge Improvement Project (Project) will replace
the existing low water crossing with an all-weather access bridge on
Dune Palms Road at the Coachella Valley Storm Water Channel
(CVSWC) (Attachment 1) and is partially funded through the state’s
Highway Bridge Program.
x In June 2014 the City entered into a Professional Services Agreement
(PSA) with Bengal Engineering, Inc. (Bengal) to provide professional
engineering and environmental services for the Project after conducting
a two-step consultant selection process.
x Amendment No. 8 to the PSA with Bengal was approved by the City
Council on October 16, 2018 and extended the contract term after it had
expired.
x Extending the contract term after it had inadvertently expired is
considered by Caltrans procedures to be a select source procurement
and a Public Interest Finding (Attachment 2) must be adopted.
FISCAL IMPACT
The Dune Palms Road Bridge Project has an approved budget of $17,510,000.
This project is funded through a combination of Federal Surface Transportation
Funds through the state’s Highway Bridge Program. Federal funds will provide
up to $15,501,603 of the total project cost. The Coachella Valley Association
CONSENT CALENDAR ITEM NO.
123
of Governments (CVAG) will fund up to $1,506,750, and the City will fund the
remaining $502,250.
BACKGROUND/ANALYSIS
In June 2014, Council approved a PSA with Bengal to provide professional
engineering and environmental services for an all-weather bridge on Dune
Palms Road spanning the CVSWC.
While addressing other scope related changes which were ultimately included
within Amendment No. 8, and approved by Council on October 16, 2018, staff
realized that Bengal’s contract term had expired and included an extended
term as part of that Amendment. At this point, the project had experienced
several environmental and right of way processing delays. The environmental
document, special studies, and environmental permitting took nearly 4 years
to complete.
During the time frame leading up to the expired term, the City had just
received notification from Caltrans Environmental that the Project’s
environmental document was finally approved. The City and its Consultants
were working diligently to make up time and avoid losing the funding
authorized for the preliminary engineering phase. The project development
team was working through the requirements of the adopted environmental
document, environmental permitting requirements, initiating the right of way
acquisition phase and coordinating with utilities. The project could not
proceed with any of these steps until the NEPA/CEQA environmental
documents were adopted.
It was not feasible to stop all work with Bengal and initiate a new competitive
procurement process for the engineering services needed to complete the
Project. Doing so would have been detrimental to the project, the general
public, the City of La Quinta, the Coachella Valley Sub-Region, and the State.
The contract extension is considered a select source procurement in
accordance with Caltrans procedural requirements, which requires approval of
a Public Interest Finding. The City Council is being asked to ratify the select
source selection and the contract term extension approved with Amendment
No. 8 on October 16, 2018 for Bengal Engineering to complete it’s contract
work, and adopt a Public Interest Finding to satisfy Caltrans’s procedural
requirements.
The project development team is currently finalizing right of way acquisition,
utility clearance, and final design.
124
Prepared by: Julie Mignogna, Management Analyst
Approved by: Bryan McKinney, Public Works Director/City Engineer
Attachments: 1. Vicinity Map
2. Public Interest Finding
ALTERNATIVES
Staff does not recommend an alternative.
125
126
RESOLUTION NO. 2020 - XXX
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF LA QUINTA, CALIFORNIA, TO APPROVE
A PUBLIC INTEREST FINDING TO RATIFY THE
SELECT SOURCE CONTRACT EXTENSION OF
BENGAL ENGINEERING, INC. TO COMPLETE THE
ENGINEERING PHASE OF THE DUNE PALMS
ROAD BRIDGE IMPROVEMENT PROJECT NO.
2011-05, FEDERAL AID PROJECT NO. BRLKS
5433 (014)
WHEREAS, on October 15, 2013, the City Council approved the
program supplemental agreement with California Department of
Transportation and Federal Highways Administration; authorized the City
Manager to execute the agreement; and authorized staff to advertise the
request for proposal to obtain the professional engineering and environmental
services for the Dune Palms Road Bridge Improvement; and
WHEREAS, the City issued a formal Request for Proposal on October
15, 2013 and conducted the pre-proposal conference on November 12, 2013;
and
WHEREAS, the City received 4 proposals from qualified firms on
November 25, 2013, and conducted interviews with each of the 4 qualified
firms on January 17, 2014; and
WHEREAS, Bengal Engineering, Inc. was awarded a Professional
Services Agreement June 17, 2014 to prepare the plans, specifications, and
engineer’s estimate for the Dune Palms Road Bridge Improvement, City
Project No. 2011-05, Federal Aid Project No. BRLKS 5433 (014); and
WHEREAS,the City and Bengal Engineering, Inc. inadvertently allowed
the Professional Services Agreement to lapse on July 31, 2018; and
WHEREAS, it was not feasible to stop all work with Bengal Engineering,
Inc. and initiate a new competitive procurement process for the engineering
services needed to complete the Dune Palms Road Bridge Improvement
Project; and
WHEREAS, the City determined it was in the best interest of the public,
the City, the Coachella Valley Sub-Region, the State of California, and FHWA
to extend the contract term of Professional Services Agreement with Bengal
Engineering, Inc.
127
Resolution No. 2020-
Dune Palms Bridge Public Interest Finding
Adopted: July 7, 2020
Page 2 of 3
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City
of La Quinta, California, as follows:
The City Council approves a Public Interest Finding to ratify the select source
contract extension of Bengal Engineering, Inc. to complete the engineering
phase of the Dune Palms Road Bridge Improvement Project, City Project No.
2011-05 and Federal Aid Project No. BRLKS 5433 (014).
PASSED, APPROVED, and ADOPTED at a regular meeting of the La
Quinta City Council held on this 7th day of July 2020, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
________________________
LINDA EVANS, Mayor
City of La Quinta, California
128
Resolution No. 2020-
Dune Palms Bridge Public Interest Finding
Adopted: July 7, 2020
Page 3 of 3
ATTEST:
__________________________
MONIKA RADEVA, City Clerk
City of La Quinta, California
(CITY SEAL)
APPROVED AS TO FORM:
___________________________
WILLIAM H. IHRKE, City Attorney
City of La Quinta, California
129
130
Dune Palms Bridge
PROJECT LOCATION
HIGHWAY 111
Vicinity Map
AVENUE 48
ATTACHMENT 1
131
132
,'800%02* 8., 4. 08*4'8 88
:737X*IAD>Ag*j*3LDND]`X*`DQN/*ID:QXND*37T*X`L7N`c]37T*X`L7N`Q:`X*N]TQX`*`DQNQ:`X*N]TQX`*`DQN
& & &
4 duxxqukqq0;Y"!
!
4 duxo~qutu~u0;Y"!"
4 R|u
&
$!"&#!"&"#!#&!%&
$!"&&!%&
F5
V\SG82b^V82F=F2
2J,^^S==858\,J=eO5^'
&
69K9?+a96BE?BUYR;EK9
5F^b2S\b8VM
MeJbFVJ8V\SG82b^
& & & &
4 duxqu~~uuz~kutqkqkq1<Z$$l
4 duxo~qx~|utku~k0;Y"! %
4 duxqkq~zu|t|u|kqu~~uo~tt~z1<Z#!
4 duxktkot~k~u0;Y"! %
4 *tu~~zu~tu|kuu0;Y"!
4 hk~ux-+u~qkYu~uu0;Y"!
4 R|u
&
PB_aURaB9[
8^bFM,b852S^b=858\,J=eO5^
^b,b8iF58
@8O8\,J58^2\FVbFSOS=iS\H
X7*]QN]`A*`X7Wc7]`73*TTXQf*ID]/QN]D37X73`Q.7/Q]`7::7/`Df7QXDN`A7Tc.ID/].7]`DN`7X7]`]`*`7(
TX7T*X73*TTXQf73.jIQ/*I*>7N/j]X7TX7]7N`*`Df7N*L7*N3`D`I7(3mv(
X7TX7]7N`*`Df7
*TTXQf73.j3D]`XD/`IQ/*I*]]D]`*N/77N>DN77X3I*7 N*L7(3mv(
3I*7
*TTXQf73.j:Ag*.*vrmgmv:Ag*X7TX7]7N`*`Df7N*L7(3mv(
5p' Jsn ,{ws= w S{n ) 5J,8 2) 2n nVwsMnn{w 2y}w^C^
$77$&+0(17
BRKLS 5344 (014)
✔
✔
08-RIV-La Quinta
In the City of La Quinta along Dune Palms Road at the
Coachella Valley Storm Water Channel (Whitewater River)
✔
159,354.00180,000.00
Final design and ROW appraisals for the project to replace a 3 lane low
water crossing with 4 lane bridge.
See Attached.
Public Works DirectorBryan McKinney
133
,'800%02* 8., 4. 08*4'8 88
-13
#!3&6!+!118!3!/)&+3&-+5(&8+3!/!138&+&+$8
B 0,*3B(88:78:1(<,B)7@B=6+,:B7;<.,*<1>,B,<,:516(<176B$,9=1:,+B7:B#=)41*B6<,:,;<B
,<,:516(<176B$,9=1:,+ B
B 0,*3B4(;;B7-B=6+;B(;B-7447?;B 46<,:;<(<,B (16<,6(6*,B !!(<176(4B1/0?(AB%&#B
%<(<,B&:(6;87:<(<176B #:7/:(5B"<0,:B (44B7<0,:B*4(;;,; B
B #:7>1+,B<0,B,+,:(4(1+B#:72,*<BB6=5),:B16B-1:;<B*74=56 B
B +,6<1-AB(4<:(6;B1;<:1*<7=6<A%<(<,B$7=<,#7;<B 14,B7:B1<AB(6+B;<:,,<B16B;,*76+B*74=56 B
B 1;<B;<15(<,+B7;<B7-B<0,B 87:<176B7-B<0,B8:72,*<B;=)2,*<B<7B<01;B# B
B 1;<B<0,B (57=6<B7-B <0,B ,+,:(4B=6+;B16B <0,B87:<176B7-B<0,B 8:72,*<B;=)2,*<B<7B <01;B# B
B ,;*:1),B,6,:(4B7*(<176B(8841*()4,B<7B<01;B# B
B #:7>1+,B,6,:(4B ,;*:18<176B7-B'7:3B (--,*<,+B)AB <01;B # B
B @84(16B(6+B/1>,B $,(;76;B<0(<B:,9=,;<,+B(88:7>(4B1;B*76;1+,:,+B<7B),B*7;<,.,*<1>,B7:B16B<0,B
8=)41*;B),;<B16<,:,;< B#:7>1+,B*7;<B(6(4A;1;B7:B*758(:1;76B(;B,>1+,6*,B7-B*7;<,.,*<1>,6,;; B
B$,5(:3;B1;B-7:B<0,B 7*(4B/,6*AB$,8:,;,6<(<1>,B8:,8(:16/B <0,B16+16/ B
B%1/6(<=:,B!(5,B(6+B&1<4,B7-B7*(4B/,6*AB$,8:,;,6<(<1>,B8:,8(:16/B7:B(88:7>16/B#B(;B
(88:78:1(<,B (6+B(<, B
B%1/6(<=:,B(6+B!(5,B7-B1;<:1*<B 7*(4B;;1;<(6*,B6/16,,:B(88:7>16/B<0,B#B(;B:,9=1:,+B(6+B
(<, B
B%1/6(<=:,B(6+B!(5,B7-B'B:,8:,;,6<(<1>,B(88:7>16/B<0,B#B-7:B=AB5,:1*(B?(1>,:;B (6+B
(<, B
$!88-"88
!/5/788134
REASONS THAT REQUESTED APPROVAL IS CONSIDERED TO BE COST EFFECTIVE OR IN
THE PUBLIC’S BEST INTEREST (STATE)
In 2013, during the selection of Bengal Engineering to perform the professional engineering and
environmental services the City of La Quinta complied with the requirements set forth by the
Caltrans LAPM and conducted a competitive one-step RFP consultant selection process. The
following represents the chronology of events associated with the Consultant Selection Process:
The City Appointed a Consultant Selection Committee Consisting of Project Engineers and
Managers. The Request for Proposal was issued on October 15, 2013 and the Pre-Proposal
Conference was conducted on November 12, 2013 at 10:30 am. The City received four (4)
proposals from the following qualified consultants on November 25, 2013: Bengal Engineering,
Inc., CNS Engineers, Inc., IDC Consulting, Engineers, Inc., and RBF Consulting. The Consultant
Selection Committee met on December 16, 2013 and determined that all four (4) of the
engineering firms submitting proposals should be interviewed. Interviews were conducted on
January 17, 2014. Following the interviews, the Consultant Selection Committee recommended
Bengal Engineering, Inc. be awarded a Professional Services Agreement to prepare the plans,
specifications, and estimates for the Dune Palms Road Low Water Crossing Replacement at the
Coachella Valley Stormwater Channel.
The Professional Services Agreement with Bengal Engineering was prepared in accordance with the
requirements outlined within Chapter 10 of the Caltrans LAPM and was submitted for review and
acceptance by Caltrans Audit and Investigation. This included Exhibits 10K and 10H which outlined
key personnel. Caltrans Audit and Investigation issued the contract Conformance Letter Review on
May 22, 2014 . All deficiencies noted by Caltrans Audit and Investigation Conformance Review
were incorporated and submitted to City Council for award consideration. The City Council
considered and approved a Professional Services Agreement with Bengal Engineering, Inc. on June
17, 2014
While addressing other scope related changes which were ultimately included within Amendment
No. 8, and approved by Council on October 16, 2018, staff realized that Bengal’s contract term had
expired and included an extended term as part of that Amendment. At this point, the project had
experienced several environmental and right of way processing delays. The environmental
document, special studies, and environmental permitting took nearly 4 years to complete.
During the time frame leading up to the expired term, the City had just received notification from
Caltrans Environmental that that the Project’s environmental document was finally approved. The
City and its Consultants were working diligently to make up time and avoid losing the funding
authorized for the preliminary engineering phase due to the approaching reversion date. The
project development team was working through the requirements of the adopted environmental
document, environmental permitting requirements, initiating the right of way acquisition phase and
coordinating with utilities. The project could not proceed with any of these steps until the
NEPA/CEQA environmental documents were adopted.
135
It was not feasible to stop all work with Bengal and initiate a new competitive procurement process
for the engineering services needed to complete the Project. Doing so would have been
detrimental to the project, the general public, the City of La Quinta, the Coachella Valley Sub-
Region, the State, and Federal Highway Administration (FHWA).
Bengal Engineering is thoroughly aware of the issues surrounding the design and construction of
the Dune Palms Bridge. They had been working in partnership with City for over 4 years on the
project. They have coordinated with the Federal Emergency Management Agency, Riverside County
Flood Control, Coachella Valley Water District, Caltrans District 8, and are well aware of the
requirements for 1602 Streambed Alteration Agreement with the California Department of Fish and
Game, the 401 Water Quality Certification from the Regional Water Quality Control Board and the
404 permit from the Army Corps of Engineers. The City finds the continuation of Bengal
Engineering and Consulting, Inc. for the proposed project is in the best interest of the City of La
Quinta, the State of California, and Federal Highway Administration.
136