Travertine Specific Plan - Notice of Preparation (March 1 - April 1, 2020 - Public Review Period)�7C-5rt
Sun
PROOF OF
PUBLICATION
STATE OF CALIFORNIA SS.
COUNTY OF RIVERSIDE
CITY OF LA QUINTA
ATTN: WANDA WISE-LATTA
78495 CALLE TAMPICO
LA QUINTA, CA 92253
I am over the age of 18 years old, a citizen of the
United States and not a party to, or have interest in
this matter. I hereby certify that the attached
advertisement appeared in said newspaper (set in
type not smaller than non pariel) in each and entire
issue of said newspaper and not in any supplernent
thereof on the following dates, to wit:
3/1/20
I acknowledge that I am a principal clerk of the
printer of The Desert Sun, printed and published
weekly I the City of Palm Springs, County of
Riverside, State of California. The Desert Sun was
adjudicated a Newspaper of general circulation on
March 24, 1988 by the Superior Court of the
County of Riverside, State of California Case No.
191236.
I certify under penalty of perjury, under the laws of the
State of California, that the foregoing is true and
correct. Executed on this 2nd of March 2020 in Green
Bay, Wisconsin, County of Brown
0
Ad#:0000467520
P O: Travertine NOP
# of Affidavits: 1
750 N Gene Autry Trail
mediagrou p Palm Springs, CA 92262
Tela 760-77811578/Fax 760-778-4731
PART OFTHE USA TODAY NETWORK Email- Ir
crrr of " QUINTA
t�L NOTICE OF PREPARATION
GEM ofdx DESERT .� -•
Project Title: Travertine Specific Plan 1
Project Losatfon: Within the, City of La Oulnta, generally bounded by the extension of y
Avenue 60 en the rhonh: the edens on of Avenue 62 and CVWD Dike No. 4 on the usl;
and the tutu re alignment of Jefferson{ Street on the norm; and the Same Rosa Mountains d; Averhhse So
to the south. Lucaled in Section 33, Township 6 South, Range 7 East, wuf Sectlons 3 — 5 d ��
in Township 7 South, Range 7"East, San Bernardino Base Line and Meridian, Martinez
Mounlam and Valerie 7.5 minute quadrangles; Latitude 33" 35' 53" N Longitude 116°
15' 33'. W (approximate geographic center of the site)
The City of La 0uWa, acting as the Lead Agency, has determined that an Environmental 62rtid Ave
Impact Report pn) should ba prepared for the proposed amendment IA the Travertine Project She
Spears: Plan, The ER wilt bo prepared In atxardame with the Cahfornia Environmental
ouality Act [CEQA) to evaluate the patenflal environmental Impaets associated with
the Implementation of the Travertine Specific Plan. Land Use Plan, anticipated to be
developed over a 10 -year pedod beginning in 2026. There is no actual timetable for
ultimate build out to occur, as development wilt be driven by market forces and demand
for new residential units. However, a 10 -year development pian represents a reasonable
development period.
This Notice of Preparalion also solicits comments.and questions from rospar0ble agencies, trustee agencies, federal, Slate and loco
agertcies and the general public, on the scope and content of the environmental document fo be prepared 10 analyze the potential
environmental Impacts of Ilia proposed project. CommenFs received in response to this Natfca of Preparation will be reviewed and
considered in determining the scope of the Fin. The time period to submitt comments will begin March 2, 2020 and wi11 end AMM 1,
7020. Comments should be sent at the earfieal po..,ible date.
The proposed project is the development of a master planned cammunfty located in The City of La Quinta on the southern edge of the
Coachella Valley at the ham of the Santa Rosa Mountains, The most prominant physical features In the vicinity are Coral Mountaln,
€oc.Ated immediatefy nor t of the project site, and hlartinea Mountain and the Martinez Floe% Slide area tmmadiately to the south .The
project site is approximately B76 acres that would be developed with a mix of uses including up to 1,200 dwelling units of varylog
product types, a resort Facility with up to 100 roams, recreational hr5es such as a Of tacIII ty featuring a rdubhouse and a 12 -hole golf
course, a number of neigh0uhrxhrf parks, and public trail system and recreational open space. in ad0on,162.5 acres of the site would
remain in nahsrallresblcted open space In an area along lho southerly boundary of the site sdjeeont 10 the Martinez Rock Slide area
that hos been dasignatod as a buffer betvIa" the resldenkal development and The natural open space at the foothills of file Santa
Rasa Mountains.
A public Scoping Meeting will be held at 6:00 p.m. on March 16, 2020 at La Quinta City Hall in the Study Session Room located at
78-495 Calle Tampico, La Ouirita
Comments and gceOorbL may be directed m: Cheri Flores, Planning Manager, City of La Quinta, 78-495 Calle Tampico, La Quinta, CA
92253, 760-77i-7067 or DIIIores 3yrhouinLusr.ony. Please include the name, phone number, and address of your agency's contact
person in your response,
CITY OF LA QUINTA
NOTICE OF PREPARATION
— GEM ofthr DESERT --
Project Title: Travertine Specific Plan
Project Location: Within the City of La Quinta, generally bounded by the extension of
Avenue 60 on the north; the extension of Avenue 62 and CVWD Dike No. 4 on the east;
and the future alignment of Jefferson Street on the north; and the Santa Rosa Mountains
to the south. Located in Section 33, Township 6 South, Range 7 East, and Sections 3 — 5
in Township 7 South, Range 7 East, San Bernardino Base Line and Meridian, Martinez
Mountain and Valerie 7.5 minute quadrangles; Latitude 330 35' 53" N Longitude 1160
15' 33" W (approximate geographic center of the site)
The City of La Quinta, acting as the Lead Agency, has determined that an Environmental
Impact Report (EIR) should be prepared for the proposed amendment to the Travertine
Specific Plan. The EIR will be prepared in accordance with the California Environmental
Quality Act (CEQA) to evaluate the potential environmental impacts associated with
the implementation of the Travertine Specific Plan Land Use Plan, anticipated to be
developed over a 10 -year period beginning in 2026. There is no actual timetable for
ultimate build out to occur, as development will be driven by market forces and demand
for new residential units. However, a 10 -year development plan represents a reasonable
development period.
Avenue 60
62nd Ave
This Notice of Preparation also solicits comments and questions from responsible agencies, trustee agencies, federal, State and local
agencies and the general public, on the scope and content of the environmental document to be prepared to analyze the potential
environmental impacts of the proposed project. Comments received in response to this Notice of Preparation will be reviewed and
considered in determining the scope of the EIR. The time period to submit comments will begin March 2, 2020 and will end April 1,
2020. Comments should be sent at the earliest possible date.
The proposed project is the development of a master planned community located in the City of La Quinta on the southern edge of the
Coachella Valley at the base of the Santa Rosa Mountains. The most prominent physical features in the vicinity are Coral Mountain,
located immediately north of the project site, and Martinez Mountain and the Martinez Rock Slide area immediately to the south. The
project site is approximately 876 acres that would be developed with a mix of uses including up to 1,200 dwelling units of varying
product types, a resort facility with up to 100 rooms, recreational uses such as a golf facility featuring a clubhouse and a 12 -hole golf
course, a number of neighborhood parks, and public trail system and recreational open space. In addition, 162.5 acres of the site would
remain in natural/restricted open space in an area along the southerly boundary of the site adjacent to the Martinez Rock Slide area
that has been designated as a buffer between the residential development and the natural open space of the foothills of the Santa
Rosa Mountains.
A public Scoping Meeting will be held at 6:00 p.m. on March 16, 2020 at La Quinta City Hall in the Study Session Room located at
78-495 Calle Tampico, La Quinta.
Comments and questions may be directed to: Cheri Flores, Planning Manager, City of La Quinta, 78-495 Calle Tampico, La Quinta, CA
92253, 760-777-7067 or clflores@1aouintaca._gov. Please include the name, phone number, and address of your agency's contact
person in your response.
CITY OF LA QUINTA
NOTICE OF PREPARATION
Project Title: Travertine Specific Plan
Project Location: Within the City of La Quinta, generally
bounded by the extension of Avenue 60 on the north; the
extension of Avenue 62 and CVWD Dike No 4 on the east;
and the future alignment of Jefferson Street on the north;
and the Santa Rosa Mountains to the south. Located in
Section 33, Township 6 South, Range 7 East, and Sections
3 – 5 in Township 7 South, Range 7 East, San Bernardino
Base Line and Meridian, Martinez Mountain and Valerie 7.5
minute quadrangles; Latitude 33° 35’ 53” N Longitude
116° 15’ 33” W (approximate geographic center of the
site)
The City of La Quinta, acting as the Lead Agency, has
determined that an Environmental Impact Report (EIR)
should be prepared for the proposed amendment to the
Travertine Specific Plan. The EIR will be prepared in
accordance with the California Environmental Quality Act
(CEQA) to evaluate the potential environmental impacts
associated with the implementation of the Travertine Specific Plan Land Use Plan, anticipated to be
developed over a 10-year period beginning in 2026. There is no actual timetable for ultimate build
out to occur, as development will be driven by market forces and demand for new residential units.
However, a 10-year development plan represents a reasonable development period.
This Notice of Preparation also solicits comments and questions from responsible agencies, trustee
agencies, federal, State and local agencies and the general public, on the scope and content of the
environmental document to be prepared to analyze the potential environmenta l impacts of the
proposed project. Comments received in response to this Notice of Preparation will be reviewed and
considered in determining the scope of the EIR. The time period to submit comments will begin March
2, 2020 and will end April 1, 2020. Comments should be sent at the earliest possible date.
The proposed project is the development of a master planned community located in the City of La
Quinta on the southern edge of the Coachella Valley at the base of the Santa Rosa Mountains. The
most prominent physical features in the vicinity are Coral Mountain, located immediately north of the
project site, and Martinez Mountain and the Martinez Rock Slide area immediately to the south. The
project site is approximately 876 acres that would be developed with a mix of uses including up to
1,200 dwelling units of varying product types, a resort facility with up to 100 rooms, recreational uses
such as a golf facility featuring a clubhouse and a 12-hole golf course, a number of neighborhood
parks, and public trail system and recreational open space. In addition, 162.5 acres of the site would
remain in natural/restricted open space in an area along the southerly boundary of the site adjacent
to the Martinez Rock Slide area that has been designated as a buffer between the residential
development and the natural open space of the foothills of the Santa Rosa Mountains.
A public Scoping Meeting will be held at 6 :00 p.m. on March 16, 2020 at La Quinta City Hall in the
Study Session Room located at 78-495 Calle Tampico, La Quinta.
Comments and questions may be directed to: Cheri Flores, Planning Manager, City of La Quinta, 78-
495 Calle Tampico, La Quinta, CA 92253, 760-777-7067 or clflores@laquintaca.gov Please include the
name, phone number, and address of your agency’s contact person in your response.
Travertine Specific Plan NOP 1 February 2020
TRAVERTINE PROJECT
NOTICE OF PREPARATION
INTRODUCTION
The City of La Quinta is located in the Coachella Valley, Riverside County. Exhibit 1, Regional
Location Map, shows the City’s location within the larger Coachella Valley region. The
Travertine project site encompasses an area of approximately 876 acres in the southeastern
portion of the City of La Quinta. The 2018 NOP referenced 878 acres; however, an updated survey
modified the acreage to 876. As shown in Exhibit 2, Vicinity Map, the local area is characterized
as a developing area with a number of golf course and residential communities to the north and
east, the Santa Rosa Mountains to the west and the Martinez Rock Slide area to the south. Exhibit
3, Site Location Map displays a closer aerial view of the project site, outlining section lines,
project boundary, adjacent roadways and neighboring communities. In addition to the Santa
Rosa Mountains to the west, and the Martinez Rock Slide to the south, Coral Mountain is
situated north of the project property. The Santa Rosa Mountains and their foothills and peaks
are included in the Santa Rosa and San Jacinto Mountains National Monument and will remain as
open space in perpetuity.
The proposed project includes development of a mix of uses including up to 1,200 dwelling units
of varying product types, a resort/spa facility with 100 keys, recreational uses such as a golf facility
featuring a clubhouse and a 9 to 12-hole skills course, a number of neighborhood parks, a public
trail system, recreational open space and natural open space for conservation. The site currently
has an approved specific plan for a more intense golf course-oriented community. The Applicant,
The Hofmann Land Development Company, is requesting approval of a General Plan
Amendment to change the Land Use Map for the project area to: Low Density Residential,
Medium Density Residential, Resort/Spa Mixed Use, Tourist Commercial and Open Space; a
General Plan Amendment to change the General Plan Circulation Map to modify alignments of
Jefferson Street, Avenue 62 and Madison Street; a Zone Change to revise the City’s Zoning Map
to be consistent with the land uses proposed in the Specific Plan; a Specific Plan Amendment; a
Tentative Tract Map and Development Agreement.
In addition to these entitlements from the City of La Quinta, the Applicant is also requesting
additional right-of-way along Jefferson Street and Avenue 62 from the federal Bureau of Land
Management (BLM) and Bureau of Reclamation (BOR), respectively, in order to widen and/or
extend these roads into the project site. Offsite improvements are also included in the project and
described further in Section 3.2 Project Description. The Applicant has already received approval
from The Coachella Valley Water District (CVWD) for the Water Supply Assessment and
Drainage Master Plan.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Regional Location Map
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
1
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Vicinity Map
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
2
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Site Location Map
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
3
Travertine Specific Plan NOP 5 February 2020
Project Site Location
As shown in Exhibit 4, Conceptual Land Use Plan, the approximately 876-acre project site is
generally bounded by Coral Mountain on the north; vacant land, the Coachella Valley Water
District (CVWD) Dike No. 4, and related stormwater impoundments (Thomas Levy Groundwater
Replenishment Facility) on the east; the Martinez Rock Slide on the south; and vacant land and
the Santa Rosa and San Jacinto Mountains Conservation Area on the west. Further discussion of
the land uses adjacent and in proximity to the project property is included in the following section,
1.2 Surrounding Land Uses. The project is located in Section 33, Township 6 South, Range 7 East,
and Sections 3 through 5 in Township 7 South, Range 7 East, San Bernardino Base Line and
Meridian, Martinez Mountain and Valerie 7.5-minute quadrangles; and at Latitude 33° 35’ 53” N
Longitude 116° 15’ 33” W (approximate geographic center of the site).
Surrounding Land Uses
Land uses surrounding the project site are as follows (see the aerial photograph in Exhibit 3):
Direction Description
North • Coral Mountain and Coral Mountain Park immediately north
• Lake Cahuilla County Park and Lake Cahuilla approximately one mile north
• Golf course communities including Andalusia and PGA West approximately one
mile north
East • Vacant Land owned by
o Coachella Valley Water District (CVWD)
o Bureau of Land Management (BLM)
o Bureau of Reclamation (BOR)
• Private vacant lands are directly adjacent to the eastern boundary of the site
• The Trilogy Golf Club at La Quinta is approximately 2,500 feet northeast of
the intersection of Madison and Avenue 62
• Thomas Levy Groundwater Replenishment Facility
South • BLM (Martinez Slide) – Open Space/Wilderness Area and Coachella Valley
Multiple Species Habitat Conservation Plan (CVMSHCP) Santa Rosa and San
Jacinto Mountains Conservation Area
West • Vacant, private lands
• BLM - Open Space/Wilderness and CVMSHCP Santa Rosa and San Jacinto
Mountains Conservation Area
• BLM and BOR (Guadalupe Channel), managed and maintained by CVWD
Travertine Specific Plan NOP 6 February 2020
The site lies on an alluvial fan made up of material deposited by drainages emanating from the Santa
Rosa Mountains. The only known previous land use on the site consisted of 229 acres of grape
vineyards, irrigation lines and access roads. The vineyard is no longer active and based on historic
aerial imagery, appears to have ceased operation in 2005 or 2006.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Conceptual Land Use Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
4
Travertine Specific Plan NOP 8 February 2020
Project Site History
In 1988-1989 the project site was part of a land exchange, known as the Toro Canyon Land
Exchange, between the BLM, Berkey and Associates and the Nature Conservancy, to exchange
public lands that would be more suitable for development for private land further to the south that
provides important habitat for Peninsular Bighorn Sheep. A federal Environmental Assessment (EA)
was prepared for the land exchange. The EA concluded that the private land offered in the
exchange would be protected as federal resource land in support of Bighorn Sheep and critical
habitat. As part of the land exchange, the Travertine project site would be developable in
accordance with land use planning designations imposed by the County of Riverside. The
exchange consisted of the following:
• Five sections of land within the Santa Rosa Mountains was offered to BLM - four sections
owned by Travertine property owners and one section owned by the Nature Conservancy;
together comprising 3,207 acres within the Santa Rosa Mountain National Scenic Area
(SRMNSA).
• One section of land owned by the BLM comprising approximately 639 acres was
offered to the Travertine property owners.
• Upon approval of the Toro Canyon land exchange, the 639 acres were combined with
approximately 270 acres of adjacent acres to create the Travertine project site for a total of
approximately 909 acres of developable land.
The County of Riverside included the Travertine project site within its Eastern Coachella Valley
Community Plan (ECVCP). The ECVCP land use designation for the site’s lower elevation - the
flatter portions of the site - was “Planned Residential Reserve”. This designation was intended
to allow for large scale, self-contained Resort/Spa communities. The steeper portions of the site
were designated as “Mountainous Areas” in the ECVCP. Land uses permitted in this designation
included Open Space, limited recreational uses, limited single family residential, landfills and
resource development.
Once the Toro Canyon land exchange was approved, the City of La Quinta began annexation
proceedings for the Travertine project site. The annexation was completed in 1993 with the
project site designated for Low Density Residential (LDR, 2 to 4 du/ac) and Open Space (1 du/ac)
land uses1.
1 Bureau of Land Management, Environmental Assessment, Travertine Project Right-of-Way Grant, EA Number CA-
660-06-28, Page 5, April 2006.
Travertine Specific Plan NOP 9 February 2020
In June 1995, the Travertine Specific Plan was approved and an EIR was certified by the La Quinta
City Council by adoption of Resolution 95-38, subject to conditions of approval and a Mitigation
Monitoring and Reporting Program (MMRP). Along with the Specific Plan, the corresponding
General Plan Amendment and Change of Zone were also approved. The Specific Plan identified a
number of land uses including: Very Low Density Residential, Medium Residential, Medium High
Residential, Neighborhood Commercial, Tourist Commercial and Golf Course Open Space. The
Specific Plan established site-specific standards and guidelines for the project area and identified
a number of land uses, including those shown in Table 1, Approved Travertine Specific Plan Land
Uses.
Table 1: Approved Travertine Specific Plan Land Uses
Planning
Area
Land Use
Acres
Square Feet
Target Density
(du/ac)
Target
Units
RE-1 Very Low Density Res 17.7 771,012 2.0 35
RE-2 Very Low Density Res 72.9 3,175,524 2.0 149
RR-1 Medium Density Res 57.1 2,487,276 4.6 264
RR-2 Medium Density Res 66.7 2,905,452 4.6 307
RR-3 Medium Density Res 46.1 2,008,116 4.6 214
RR-4 Medium Density Res 65.1 2,835,756 4.6 299
RR-5 Medium Density Res 56.6 2,465,496 4.6 258
VR-1 Medium High Density Res 13.3 579,348 9.2 121
VR-2 Medium High Density Res 71.1 3,097,116 9.2 653
GC-n Golf Course (North) 187.8 8,180,568
GC-s Golf Course (South) 189.7 8,263,332
MN-1 Maintenance 3.2 139,392
MN-2 Maintenance 0.9 39,204
TC Tennis Club 3.7 161,172
R/H Resort / Hotel 27.2 1,184,832
C Commercial 10.0 435,600
Jefferson Street ROW 20.1 875,556
Source: The Keith Companies, Technical Appendices for The Travertine Specific Plan Draft
Environmental Impact Report, Figure II-4, January 1995
In June 2004, a request was submitted to the U.S. Fish and Wildlife Service (USFWS) to initiate
Section 7 consultation regarding potential impacts to the Peninsular Bighorn Sheep and its
designated critical habitat. A Biological Opinion (BO) was completed by the USFWS in December
2005 that evaluated the biological resources on the project site in a Biological Assessment (BA). The
Travertine property owners had acquired several areas off-site to preserve open space habitat
for the Bighorn Sheep and had proposed several mitigation measures in the time between the
initial Specific Plan approval (1995) and the start of the Section 7 consultations (2005).
Travertine Specific Plan NOP 10 February 2020
The BO concluded that the mitigation measures proposed by Travertine, including the setback
from habitat and the types of vegetation allowed near the southern and western property lines,
would be appropriate for preservation of any critical habitat that existed in the area and that
development of the site would not interfere with Bighorn Sheep of their critical habitat.
Implementation of the approved 1995 Specific Plan also required acquisition of additional right-
of-way along the major roadways (Jefferson Street, Madison Street, and Avenue 62) from the
BLM and BOR. This resulted in the need for another federal Environmental Assessment (EA No.
CA-600-06-28) to be prepared and circulated.
This EA was certified in 2006. Archaeological/paleontological surveys and jurisdictional delineation
were both completed as part of this EA process in addition to other special studies to evaluate the
impacts of project development. The consultations with the agencies and related documentation
resulted in several recommended mitigation measures that the project proponent was required
to incorporate into the project.
During this time the project proponent also worked closely with the Coachella Valley Association
of Governments (CVAG) to ensure that the proposed land uses were compatible with the
Coachella Valley Multiple Species Habitat Conservation Plan (CVMSHCP). It was concluded that
development of the project site is considered a “Covered Activity,” provided that the
mitigation measures are retained in the design of the project and conservation measures are
implemented (Fish and Wildlife ERIV – 2735.3). These conservation measures will be
incorporated into the Amended Travertine Specific Plan and will be fully described in the EIR.
In 2007, the project proponent continued work through the Conditions of Approval and Mitigation
Measures by authorizing the completion of the Cultural Resources Inventory and Evaluation
(2006), including limited subsurface testing on the project site. No prehistoric or historic-era
resources were identified within the project site. As part of this effort, four local Native American
tribes were contacted for comment regarding their knowledge of cultural resources in the area.
The Torres-Martinez Desert Cahuilla Indians indicated awareness of several cultural resources in
close proximity to the project site and requested a Native-American monitor be present during
any ground disturbing activities.
Also, during 2007, a report on the status of the vineyards within the project site was conducted.
In addition, a Supplemental Cultural Resources Survey Report was prepared to evaluate the
proposed access road from the extension of Madison Street and proposed access road from the
extension of Jefferson Street. Results for both areas were negative for prehistoric and historic-
era resources. As a result of all three surveys, the Specific Plan Land Use and other plans
(circulation, infrastructure) were designed to avoid areas that were found to have cultural and
paleontological sensitivity.
Travertine Specific Plan NOP 11 February 2020
3.0 PROPOSED SPECIFIC PLAN
3.1 Project Objectives
The Travertine Specific Plan serves as an overall framework to conscientiously guide
development of the proposed project. To ensure the functional integrity, economic viability,
environmental sensitivity, and positive aesthetic impact of this Specific Plan, planning and
development goals for the project were established and supported through an extensive
analysis. This analysis includes an examination of project environmental constraints, engineering
feasibility, market acceptance, economic viability, City General Plan goals, development phasing,
and local community goals.
The Travertine Specific Plan has identified the following Project objectives:
• To enhance the existing Boo Hoff trail system by adding a staging area at the northernly point
of the project with parking area and access from the proposed extension of Jefferson.
• Provide an interpretive trail element that circumnavigates the project and identifies the
unique features both historical and current within the project setting.
• To focus the activities for the community on walking and hiking as well as providing a major
recreational facility along the eastern edge of the project.
• The primary goal of the Amendment is to reduce the overall intensity of the 1995 approved
Specific Plan.
• Establish a distinctive community character through place-making elements that embrace
and respect the site’s special physical attributes, as well as authentic architecture that
reflects local heritage.
• Provide a comprehensive system of parks and recreation facilities and services that meet the
active and passive needs of all residents and visitors.
• Contribute to the preservation, conservation and management of open space lands and
scenic resources for enhanced recreational, environmental and economic purposes.
• Provide protection of the health, safety, and welfare of the community from flooding and
hydrological hazards.
The following Project objectives have been identified for the EIR:
• To contribute to the reduction of air emissions generated within the City.
• Provide a regulatory framework that facilitates and encourages energy and water
conservation through sustainable site planning, project design, and green technologies
and building materials.
• Assist in the protection and preservation of native and environmentally significant
biological resources and their habitats.
• Assist in the protection and preservation of cultural resources.
Travertine Specific Plan NOP 12 February 2020
• Contribute to the preservation, conservation and management of the City’s open space
lands and scenic resources for enhanced recreation, environmental and economic
purposes.
• Provide protection of the residents’ health and safety, and of their property, from
geologic and seismic hazards.
• Provide protection of the health and safety, and welfare of the community from
flooding and hydrological hazards.
• Provide protection of residents from the potential impacts of hazardous and toxic
materials.
• Provide a healthful noise environment which complements the City’s residential and
Resort/Spa character.
• Provide housing opportunities that meet the diverse needs of the City’s existing and
projected population.
• Provide public facilities and services that are available, adequate and convenient to all City
residents.
• Provide a circulation system that promotes and enhances transit, alternative vehicle,
bicycle and pedestrian systems.
• Provide domestic water, sewer and flood control infrastructure and services which
adequately serve the project development and the existing and long-term needs of the
City.
Travertine Specific Plan NOP 13 February 2020
3.2 Project Description
The proposed Specific Plan Amendment area covers an area of approximately 876 acres. As
shown in Exhibit 5, Proposed General Plan Land Use Map, the proposed project will be comprised
of a variety of land uses. Residential land uses will range from low density (2 to 4 dwelling units
per acre) to medium density (4 to 8 dwelling units per acre). A resort/spa facility will serve
residents, tourists and recreational visitors, including a 40,058-square-foot boutique hotel with
75 rooms and a 175-seat restaurant, and 52,500 square feet of resort villas supplying 25 rooms.
A golf skills course with 9 to 12 holes, 4,000-square-foot clubhouse and 46,378-square-foot
banquet facility will provide recreational opportunities. The resort/spa and golf club will also
allow for a 11,654-square-foot spa and wellness center, a 15,904-square-foot golf club restaurant,
and a 2,000-square-foot golf clubhouse locker room to serve the daily needs of the community
and its visitors. Table 2, Proposed Planning Area Summary, shows the land use associated with
each planning area. Exhibit 6, Planning Area Land Use Plan, shows the location of each project
planning area.
Project construction will occur in two phases. Each construction phase will provide two product
development phases totaling no more than 600 units. The primary intent of the construction
phasing plan is to ensure that complete and adequate public facilities are in place and available
to builders, residents, and first responders. All wet and dry utilities from Avenue 62 to the point
of connection for various product phases and water tanks will be installed in these two phases.
As shown on Exhibit 7, Construction Phasing Plan, construction Phase 1 is proposed in the
southern portion of the project property and construction Phase 2 is situated in the northern
portion.
Exhibit 8 Concept Product Phasing Plan shows the phasing in four phases and is for financing
purposes. The project will be constructed by a master developer who would provide the mass
grading and the rough grading pads for the builder product. They will also install all major and
common roads, as well as install all backbone sewer, water, and storm drains in addition to dry
utilities that will serve the individual builder pads in the project. All areas that are common in the
project will be landscaped though the master developer process. The individual builder
responsibilities will include any interior infrastructure associated with the builder’s product,
including interior streets, landscaping, common areas, amenities, as well as any of the utility
points of connection to the master system (sewer, water, storm drain and dry utilities).
Travertine Specific Plan NOP 14 February 2020
The project components shall include:
• 1,200 Dwelling Units of varying types
o 758 Low Density Units and 442 Medium Density Units
o Estate Homes, Single Family Luxury Homes, Single Family Mid Homes, Single Family
Entry Homes, Patio Homes, Single Family Attached Units
• 9 to 12-hole skills golf course
• 100-key resort
• Wellness Spa
• Tourist serving recreational facilities and amenities including restaurants, small shops, spa
facilities, lounge and activity rooms, outdoor activities, tennis, yoga, etc.
• Bike lanes throughout community, including Class II bike lanes located along both sides of
Jefferson Street
• Pedestrian walkways and a Travertine community trail – a network of trails suitable for
pedestrian use planned throughout the community
• Recreational Open Space uses, including picnic tables, barbeques, golf facilities, a tot lot
playground and staging facilities for the regional interpretive trail
• One staging area located to the south of the Avenue 62 extension with parking
• One staging area located to the north of the project with parking staging area for the Boo
Hoff trail, in addition to the Travertine community trail
• CVWD Well Sites (quantity to be determined by CVWD)
• Future 5-acre IID substation will be located off-site within a 2.5-mile radius of the project
area.
• Perimeter flood protection barrier along the western and southern boundaries to manage
alluvial fan flows. The barrier will consist of a raised edge condition with a slope lining to
protect against scour and erosion.
• Emergency Vehicle Access (EVA) during project construction will be located either (a) the
extension of Avenue 58 and Jefferson Street, or (b) the extension of Madison Street at
Avenue 60.
• Two off-site booster stations. One on Avenue 62, east of the project site, and the second at Avenue
58 and Dike #2, north of the project site.
• Two reservoir wells are proposed on the southwest portion of the project site.
Travertine Specific Plan NOP 15 February 2020
Table 2: Proposed Planning Area Summary
PA
Land Use
Acres
Density
Range (du/ac)
Target
Density (du/ac)
Target
Units
1 Opens Space Recreational 17.2
2
Resort/Spa
Boutique Hotel (175-seat restaurant) – 40,058 sf
Resort Villas – 52,500 sf
Spa and Wellness – 11,654 sf
38.2
100 rooms
3 Medium Density Residential 26.1 4-8 7.9 205
4 Low Density Residential 29.2 2-4 2.9 85
5 Low Density Residential 9.9 2-4 2.7 27
6 Low Density Residential 11.3 2-4 2.7 31
7 Medium Density Residential 20.7 4-8 7.9 163
8 Low Density Residential 18.1 2-4 3.4 61
9 Low Density Residential 21.7 2-4 3.4 73
10 Medium Density Residential 14.8 4-8 5.0 74
11 Low Density Residential 26.5 2-4 2.8 75
12
Resort / Golf
Banquet Facility – 46,378 sf
Golf Clubhouse Restaurant – 15,904 sf
Golf Clubhouse Locker Room – 2,000 sf
45.9
13 Low Density Residential 50.5 2-4 2.1 107
14 Low Density Residential 30.6 2-4 1.6 48
15 Low Density Residential 35.2 2-4 1.8 65
16 Low Density Residential 35.1 2-4 2.0 70
17 Low Density Residential 50.7 2-4 2.3 116
18 Open Space Recreational 18.1
19 Open Space Recreational 8.8
20 Open Space Recreational 22.0
21 Open Space Recreational (Golf) 122.0
22 Open Space Recreational 28.4
23 Open Space Natural 151.8
24 Open Space Natural 10.7
25 Master Planned Roadways 32.5
Total 876.0 1,200 DU
100 rooms
Master Planned Roadways
Roadways Acres
Jefferson Street 17.4
Loop West 9.4
Loop East 5.4
Section 5 Access 0.3
Total 32.5
Source: TRG Consulting, Travertine Specific Plan,
Table 2, Planning Area Summary.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Proposed General Plan (Land Use)
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
5
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Planning Area Land Use Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
6
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Construction Phasing Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
7
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Product Concept Phasing Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
8
Travertine Specific Plan NOP 20 February 2020
3.2.1 Residential Planning Areas
Residential areas account for approximately 43.4 percent of the project’s total land area. The
project proposes a maximum of 1,200 dwelling units based on a range of lot sizes. Residential
planning areas would vary in density from 2.0 du/ac to 8.0 du/ac, resulting in an overall average
density for the project of 1.4 du/gross ac. Residential Planning Areas vary in density from 1.6
du/ac.to 7.9 du/ac. Planning areas 3 through 11, and 13 through 17, totaling approximately 380.4
acres, are designated for residential land uses.
Planning Areas 4, 5, 6, 8, 9 and 13 through 17 will have a maximum overall density of 4 du/ac and
Planning Areas 3, 7 and 10 would have maximum overall density of 8 du/ac. Based on the target
density for each residential planning area the proposed project would include 442 medium
density (4-8 du/ac) residential dwelling units and 758 low density (2-4 du/ac) residential dwelling
units. The Low Density Residential category will be characterized by larger single family residential
lots (6,300 to 9,600 square feet). The Medium Density Residential planning areas are intended to
provide medium density, single-family residential products to accommodate lots ranging from
4,000 to 5,775 square feet.
In conformance with project goals, several housing styles are proposed that comply with the
maximum density for each planning area. Residential product types would vary to meet market
demand but are anticipated to include the following:
• Estate Homes
• Single Family Luxury Homes
• Single Family Mid Homes
• Single Family Entry Homes
• Patio Homes
• Single Family Attached Units
Travertine will offer a variety of housing sizes and styles designed to meet the needs of all age
groups. The Specific Plan Amendment incorporates neighborhood design and sustainability
principles.
3.2.2 Tourist Serving Recreational Facilities
A luxury resort, wellness spa and golf course are planned for an approximately 84.1-acre site
located in Planning Areas 2 and 12. These areas will consist of resort related amenities including
restaurants, small shops, spa facilities, lounge and activity rooms, outdoor activities, yoga, walking
and hiking trails. The resort planning areas are anticipated to provide 100-keys and a 12-hole skills
golf course. Table 3 Proposed Uses and Amenities for Resort/Golf Planning Areas shows additional
details.
Travertine Specific Plan NOP 21 February 2020
The proposed amendment would allow fractional ownership/time-share development in the
recreation/visitor-serving commercial zone. Approval of fractional ownership would be subject to
a Conditional Use Permit. The hotel/resort wellness center proposes 75 rooms and fractional
ownership development of 25 Villas within Planning Area 2.
Table 3: Proposed Uses and Amenities for Resort/Golf Planning Areas
Planning
Area Proposed Use Estimated Indoor
Area (Square Feet)
2 Boutique Hotel (175-seat restaurant) 40,058
2 Resort Villas 52,500
2 Spa and Wellness 11,654
12 Banquet Facility 46,378
12 Golf Clubhouse Restaurant 15,904
12 Golf Clubhouse Locker Room 2,000
3.2.3 Open Space/Recreation Planning Areas
Open Space Recreational areas include Planning Areas 1, 18, 19, 20, 21 and 22, and
encompass a total of 216.5 acres of the approximately 876-acre site. Exhibit 6 shows the
proposed planning area land use locations. Exhibit 9, Recreation Plan, shows areas designated as
Open Space, as well as the proposed recreational trails.
A golf course is located near the southeastern entry to the project on approximately 122 acres
(Planning Area 21). This will provide a high-end practice facility for both the residents and guests.
Equestrian/multi-use trails are provided in the Specific Plan. This plan will incorporate access,
signage, and detailed design. The area along the southern edge of this site, adjacent to the
Martinez Rock Slide, will be limited to recreational uses. As part of the recreational plan and trail
system, an interpretive design element will provide signage and educational information to
discourage trespassing on unauthorized areas of cultural significance. A cultural resources study
will be conducted for development near the Martinez Rock Slide, and local tribes will be contacted
as part of the procedures. This area is designated as a buffer between the residential development
and the natural open space of the foothills of the Santa Rosa Mountains. This area will not include
permanent structures as required by the Biological Opinion completed by the US Fish and Wildlife
Service in 2005. Planning Area 21 is reserved for the golf course and will provide an additional
buffer between the developable planning areas and the restricted open space near the southerly
boundary of the site.
3.2.4 Open Space/Natural Planning Areas
Open Space Natural Areas include Planning Areas 23 and 24 and encompass approximately 162.5
acres. An area of land along the southern, western and eastern boundaries of the site is restricted
Travertine Specific Plan NOP 22 February 2020
from development due to various environmental constraints including biological, geological and
cultural resources. This area will remain undisturbed to preserve these resources.
Portions of the open space/restricted area were determined to be of biological importance by the
US Fish and Wildlife Service (USFWS) through the Biological Opinion completed in 2005 and the
subsequent federal Environmental Assessment completed in 2006.
The Conceptual Land Use Plan was developed with consideration of the environmental constraints
associated with the surrounding land, including adjacency to the Santa Rosa Mountains and
Martinez Rock Slide area to the south, Coral Mountain to the north, and the CVWD spreading
grounds to the east and northeast. Exhibit 6 (Planning Area Land Use Plan) shows the proposed
land use locations.
3.2.5 Recreational Amenities
The Travertine project will offer a range of amenities that will be accessible to neighborhood
homeowners and the public. These recreational amenities include a two-mile long public trail
that will be developed around the perimeter of the project site to connect to the Boo Hoff trail to
the northwest; a central private spine trail that bisects the residential areas of the property; on-
street biking paths; preservation of natural open space; and additional private parks located within
the development areas. A 9 to 12-hole skills golf course and driving range with club facilities such
as banquet facilities and wellness facility, will be open to residents, citizens of La Quinta and
tourists. A resort and spa with restaurants, shops and activities will attract both residents and
visitors to the community.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Recreation Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
9
Travertine Specific Plan NOP 24 February 2020
3.2.6 Master Planned Roads
The development of the Travertine site provides for substantial improvements to several
roadways, including the southerly extension of Jefferson Street as a private Modified Secondary
Arterial south of the proposed Coral Mountain property and the westerly extension of Avenue
62 as a Modified Secondary Arterial. Loop roads extended from both sides of the Jefferson Street
spine via two roundabout intersections. Per the La Quinta 2035 General Plan Street Cross
Sections, both Jefferson Street and Avenue 62 have an 84’ Right of Way width as Modified
Secondary Arterials.
The construction phasing of the project site will ensure that complete and adequate public
facilities are in place and available to first responders, residents, and visitors to the community
using a single point of access via Avenue 62 and one emergency vehicle access (EVA) for the first
product phase of the project. The project proposes two alternative access points in the first
Phase and a maximum of 600 dwelling units would be allowed by both alternatives. The two fire
access road alternatives are as follows:
• Alternative I proposes an EVA extending from Avenue 58 to the northern edge of
development, see Exhibit 10, Phase I Alternative I Interim Circulation Plan. The EVA will
be 24 feet wide and follow the ultimate alignment of Jefferson Street. A license
agreement with the BOR for the Dike #2 crossing and access through Coral Canyon, a
temporary access easement/license agreement with the BLM, and a crossing of
Guadalupe Dike specified by CVWD are required as part of Alternative I.
• Alternative II proposes an EVA extending from the southerly extension of Madison Street
from Avenue 60, see Exhibit 11, Phase I Alternative II Interim Circulation Plan. The
Madison Street extension will be a 24-foot EVA that crosses Dike #4 and continues over
the CVWD recharge basins to the project site. The project proponent will obtain
permissions from CVWD to cross Dike #4 and its recharge basins, should Alternative II be
chosen. This Alternative may also be in permanent place if chosen.
The proposed EVA access point to the project (in both alternatives) will be designed to have two
lanes contained within a 24-foot pavement section. The local loop streets will have a typical right-
of-way of 70 feet, with curb to curb distances of 40 feet with 9-foot curb adjacent landscaped
parkways and a 6-foot wide pedestrian walkway on both sides. Additionally, local roads are
planned to be utilized within the project. The local roads will be comprised of a curb to curb
dimension of 32 feet if single loaded and 36 feet if double loaded, street parking will only be
allowed on the loaded side of the street. These residential local roads will provide a landscaped
easement at a minimum of 12 feet on each side of the street and 15 feet to residential building.
Travertine Specific Plan NOP 25 February 2020
Exhibit 12, Circulation Plan, shows the proposed alignment of Jefferson Street and the main
loop road within the project site. Access to the southwest portion of the development area
(access to the proposed water tanks) will be provided from the internal loop road. This area is
Restricted Open Space, and development of this area will be limited to the project’s water tanks
and related infrastructure.
Access to Planning Area 1 would be limited to a pedestrian trail that would either extend from
the trailhead at the northwest corner of Planning Area 2 through BLM land to the southwest
corner of Planning Area 1. Planning Area 1 is designated Open Space/Recreation, so the
Applicant does not propose vehicular access to the area. Once a final trail alignment to Planning
Area 1 is chosen, all applicable technical studies will be undertaken, and analysis will be included
in the EIR.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Phase 1 Alternative I Circulation Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
10
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Phase 1 Alternative II Circulation Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
11
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Circulation Plan
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
12
Travertine Specific Plan NOP 29 February 2020
3.2.7 Infrastructure
Existing infrastructure on the project site is very limited as the site has not been previously
developed. The former vineyard area was provided with water from an on-site well. In addition
to the Master Planned Roadway system, the project also includes a master plan for infrastructure
including drainage features, underground utilities and water tanks.
Grading and Drainage
The project site slopes gently in a downslope direction from west to east and is subject to two
types of drainage conditions: alluvial fan flow and incised drainage corridors along inactive fans.
Existing drainages originate in the Santa Rosa Mountains to the west. Exhibit 13, Conceptual
Hydrology, illustrates the off-site and proposed on-site water flow., The exhibit also shows a
proposed perimeter flood barrier to divert watershed flows. The project’s flood control berms will
be constructed to shield and encompass the project’s developable planning areas and convey
upstream flow from Devils Canyon/Guadalupe Creek, Middle North Canyon, Middle South
Canyon, and Rock Avalanche Canyon downward towards Dike No. 4 south of the proposed
Avenue 62 crossing.
The drainage plan proposes to capture on-site flows and direct them across the project to the
eastern side of the project site. The intent is to capture all flows and detain them on-site in a
series of basins that will be developed with water quality best management practices (BMPs) to
treat the water before percolation into the ground. The proposed series of basins are designed
to detain and percolate the projected on-site flows created from impervious surfaces. Excess
water relative to existing flows will not be released unimpeded into the adjacent CVWD
groundwater recharge ponds.
Water
The Coachella Valley Water District (CVWD) currently has jurisdiction over domestic water service
to the project property. Currently, domestic water service lines exist in three areas near the
project. These include the intersection of Avenue 60 and from the Jefferson extension and
Avenue 62. Water lines will be extended from Avenue 62 and one of the proposed EVA
alternatives to serve the project.
As discussed previously in Section 3.2.6, Master Planned Roads, the project proposes two
alternative EVA routes that will be developed during Phase 1 of project construction. EVA
Alternative I and II will include the development of domestic water mains extending from
Jefferson Street, or Madison Street, respectively. Water lines will be connected prior to any
construction. Additional well sites are necessary to serve the project. The locations of the future
well sites are currently under discussion with CVWD and will be identified and analyzed in the
EIR.
Travertine Specific Plan NOP 30 February 2020
Additional facilities will include two water reservoirs and booster station(s) to collect well water
and store it at the appropriate elevation to provide the required water pressure for the site. Two
off-site booster stations currently exist near the project property. One booster station is located
on Avenue 62, east of the project site, while the second booster station is located at Avenue 58
and Dike #2, north of the project site. The project site will be served with a thirty-inch main line
within Jefferson Street/Madison Street alignments. Twelve-inch and smaller lines will then feed
off the main line to serve the individual developments along these public streets.
Water tanks are proposed to be developed to serve the site in Planning Area 23. The water tank
locations, including related facilities (road, pipelines, etc.), are subject to review and approval by
the USFWS. Permanent structures, with the exception of two water reservoirs, service roadway,
underground pipelines and ancillary facilities, as allowed through the consultation with the
USFWS, will be prohibited in the Restricted Open Space (Natural) area. A portion of the Open
Space Natural Planning Areas is located in a conservation area of the Coachella Valley Multiple-
Species Habitat Conservation Plan (CVMSHCP). The project will be required to undergo Joint
Project Review (JPR) for development of the water infrastructure improvements within the
conservation area. During the JPR process, the Coachella Valley Conservation Commission and
other interested Wildlife Agencies have the opportunity to comment on the proposed
development. The JPR will be analyzed in the EIR.
Sewer
The closest Coachella Valley Water District sewer connection currently exists at Monroe Street
and Avenue 62, approximately one mile east. The proposed facilities are comprised of a series
of eight-inch sewer lines serving the individual developments and flowing into the main sewer
line located within Jefferson Street/spine road alignment. The main sewer line increases in size
as it extends eastward, ranging from eight inches on the west side to 15 inches at Madison Street,
where the line exits the project site. The offsite sewer alignment and improvements will come
from the east in Avenue 62. The EIR will further analyze the impacts to sewer and the offsite
extension.
Utilities
Southern California Gas Company provides natural gas to the project site. Electric service to
Travertine will be provided by Imperial Irrigation District. An offsite substation will be required for
the Travertine development and will be located and constructed during Construction Phase I. The
five-acre site required by IID for a substation will be studied in the EIR.
The location of the five-acre site will be within a two-mile radius of the project. The routing of the
proposed service lines along the route to the site will be studied in the EIR.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Conceptual Hydrology
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
13
Travertine Specific Plan NOP 32 February 2020
3.2.1 Requested Entitlement
The proposed project includes a General Plan Amendment, a Zone Change, Specific Plan
Amendment, a Tentative Tract Map, and Development Agreement.
A General Plan Amendment will be required to change the Land Use Map for the project area to:
Low Density Residential, Medium Density Residential, Resort/Spa Mixed Use, Tourist Commercial
and Open Space. A General Plan Amendment will also change the General Plan Circulation Map
to modify alignments of Jefferson Street, Avenue 62 and Madison Street. A Zone Change will
revise the City’s Zoning Map to be consistent with the land uses proposed in the Specific Plan.
Additionally, a Specific Plan Amendment and a Tentative Tract Map are a part of the required
entitlements. A Development Agreement will also be prepared to address the obligations,
standards, and conditions to be agreed upon by the City and the Applicant.
3.3 1995 Approved Specific Plan vs. Proposed Specific Plan
Amendment
The land uses proposed within the Travertine Specific Plan are similar to the land uses within the
Specific Plan approved in 1995, but the overall intensity of the land uses has been reduced. The
proposed Specific Plan reduces the maximum development from 2,300 dwelling units to 1,200
dwelling units, reduces the size of the golf course from 36 holes to a golf facility featuring a
clubhouse and a 9 to 12-hole skills course, removes the tennis club, modifies land use
configurations, and reduces the Resort/Spa hotel from 500 keys to 100 keys, including a clubhouse
restaurant and a banquet facility.
Exhibit 6, Planning Area Land Use Plan, shows the proposed specific plan land use planning areas
with associated acreages and dwelling units. Table 4, Approved VS. Proposed Specific Plan Land
Use, provides a detailed breakdown of the difference between the approved Specific Plan (1995)
and the proposed Travertine Specific Plan project.
Travertine Specific Plan NOP 33 February 2020
Table 4: Approved VS. Proposed Specific Plan Amendment
Previously Approved Specific Plan (1995) Proposed Specific Plan Amendment
Bounded by Avenue 60 to the North, Avenue 64
and BLM Land to the South, Madison Street to East
and future Jefferson Street to the West
Bounded by Avenue 60 to the North, Avenue 64
and BLM Land to the South, Madison Street to East
and future Jefferson Street to the West
909 Acres 876 Acres
2,300 Dwelling Units
1,200 Dwelling Units
10 Acres of Commercial
500 keys Resort / Hotel
100 keys Hotel Resort/Spa and
Wellness Center and Golf Club with
associated Recreation/Commercial
Elements
36 – Hole Golf Course 9-12 Hole Skills Golf Course
Tennis Club Tennis Club Removed
Private Recreation in Individual Developments Private Recreation in Individual Developments
378 Acres of Open Space (including golf course) 380 Acres of Open Space/Golf/Recreational &
Restricted
Source: Travertine Specific Plan Amendment, Land Use Plan, Table 1, Approved Specific Plan and Proposed Specific Plan
Amendment.
Although the proposed Travertine project would be developed on approximately the same
amount of land (909 approved vs. 876 proposed) the density and intensity of land uses would be
greatly reduced, as shown above in Table 4. The reduction of the site is due to the revision to
the project boundary along the west and south sides of the property. Thirty-one acres of the
previously approved project site have been set aside as a resource protection area for Cultural
Resources.
Travertine Specific Plan NOP 34 February 2020
4.0 Environmental Impact Report (EIR)
The Applicant, The Hofmann Land Development - Company, is requesting approval of a General
Plan Amendment to change the Land Use Map for the project area to: Low Density Residential,
Medium Density Residential, Resort/Spa Mixed Use, Tourist Commercial and Open Space; a
General Plan Amendment to change the General Plan Circulation Map to modify alignments of
Jefferson Street, Avenue 62 and Madison Street; a Zone Change to revise the City’s Zoning Map to
be consistent with the land uses proposed in the Specific Plan; a Specific Plan Amendment; a
Tentative Tract Map; and a Development Agreement. In addition to these entitlements, the
Applicant is also requesting additional right-of-way along Jefferson Street and Avenue 62 from
the federal Bureau of Land Management (BLM) and Bureau of Reclamation (BOR) in order
to widen and/or extend the roads into the project site. The applicant has previously received
approval from CVWD for the Water Supply Assessment and Drainage Master Plan.
4.1 Need for an EIR
The Travertine Specific Plan and the adjacent Green Specific Plan were the subject of an EIR
certified by the City of La Quinta in 1995. A Mitigation Monitoring and Reporting Program
(MMRP) was also adopted. The currently proposed project only addresses development of the
Travertine project site. The EIR and the MMRP, along with the conditions of approval specific to
the Travertine project and project site, required the project proponent to undertake a number
of additional activities prior to commencing with the development of the project site (see Section
2.0, Project History).
An EIR is being prepared for the proposed project in conformance with CEQA (California Public
Resources Code, Section 21000, et seq.), and the CEQA Guidelines (California Code of
Regulations, Title 14, Section 15000, et seq.).
The proposed project represents a substantial change compared to the Travertine Specific Plan
approved in 1995, as shown in Table 4. Since the EIR was certified, a number of new
environmental rules and regulations have been adopted that would have an effect on how the
project site would be developed. Therefore, the preparation of an EIR that evaluates the
proposed project is appropriate and will include a discussion of the full range of environmental
issues as required by CEQA Guidelines Appendix F and Appendix G.
The EIR will identify the project description, evaluate the environmental effects of the project,
determine or identify new mitigation measures based on impacts of the proposed project and
the latest regulatory requirements, and evaluate a reasonable range of alternatives to the
proposed specific plan.
Travertine Specific Plan NOP 35 February 2020
4.2 Summary of Environmental Issues
The EIR will evaluate all environmental issues set forth in the CEQA Environmental Checklist (per
Appendix G of the CEQA Guidelines) at an appropriate level of detail. The following is a brief
summary of the Existing Environmental Setting on the project site and vicinity. The issue areas
that will be evaluated in the Draft EIR include:
• Aesthetics • Greenhouse Gases • Public Services
• Agricultural and Forestry Resources • Hazards/Hazardous Materials • Recreation
• Air Quality • Hydrology • Transportation
• Biological Resources • Land Use and Planning • Tribal Resources
• Cultural Resources • Mineral Resources • Utilities
• Energy • Noise • Wildfire
• Geology and Soils • Population and Housing
4.2.1 Aesthetics
The City of La Quinta is located along the base of the Santa Rosa Mountains that form the
backdrop to the City’s western boundary and the project site. The Santa Rosa Mountains and
their foothills and peaks are part of the Santa Rosa and San Jacinto Mountains National
Monument that will remain as open space in perpetuity, thus affording residents and visitors
with permanent scenic vistas. The project will involve the construction of various types of
residential and resort-related structures that would have a potential effect on the aesthetic
resources. Visual simulations from adjacent viewpoints will be included and effects evaluated,
in the EIR. Additionally, since the proposed project is adjacent to a CVMSHCP conservation area,
the applicant will be required to comply with the lighting and landscape requirements in the
CVMSHCP adjacency guidelines. Finally, the project site is located within Zone 2 of the Mt.
Palomar Observatory located in San Diego County. Zone 2 encompasses a radius of 45 miles
around the observatory where development projects are required to adhere to lighting
guidelines. The EIR will therefore evaluate these impacts and provide mitigation, if necessary, in
order to reduce these impacts.
4.2.2 Agricultural Resources and Forestry Resources
Although most of the subject property consists of native desert vegetation, the project site
does contain an abandoned vineyard (229 acres) that has not been in operation since 2005 or
2006 (based on historic aerial photos). Although abandoned, this portion of the project site will
be required to be evaluated in the EIR. Potential impacts associated with the loss of agricultural
Travertine Specific Plan NOP 36 February 2020
farmland will be analyzed and if needed, mitigation will be provided in order to reduce
potential impacts. However, according to the most recent map (2016) issued by the California
Department of Conservation’s Farmland Monitoring Mapping Program (FMMP), the project site is
located within an area that is designated as “Other Land” and “areas not mapped”. Areas not
mapped are areas that fall outside of the NRCS soil survey and are not mapped by the FMMP.
Other Land is land that does not meet the criteria of any other category. Other Land typically
includes low density rural development, heavily forested land, mined land, or government land
with restrictions on use.
4.2.3 Air Quality and Greenhouse Gases
The project site is located within the Riverside County portion of the Salton Sea Air Basin (SSAB),
under the jurisdiction of the South Coast Air Quality Management District (SCAQMD). Existing air
quality in relation to the applicable air quality standards for criteria air pollutants is measured at
established air quality monitoring stations throughout the SCAQMD jurisdiction. The three
permanent ambient air quality monitoring stations in the Coachella Valley are in Palm Springs
(AQS ID 060655001), Indio (AQS ID 060652002), and Mecca (Saul Martinez - AQS ID 060652005).
The project has the potential to generate criteria emissions and greenhouse gas emissions in
excess of SCAQMD standards. The EIR analysis will include a stand-alone air quality study to
evaluate whether construction and operation of the proposed development will comply with the
applicable SCAQMD air quality standards. The EIR analysis will also include a greenhouse gas (GHG)
study to evaluate project-related construction and operational emissions and determine the level
of GHG impacts as a result of constructing and operating the proposed Project.
4.2.4 Biological Resources
The Travertine property is located on an alluvial fan at the base of the Santa Rosa Mountains and
comprised of broad, gently sloping terrain. The project consists primarily of native vegetation and
an abandoned vineyard. A comprehensive description of the natural resources that exist on the
site, as well as an analysis of the impacts of the project on those natural resources was prepared
for the certified final EIR (1995) and subsequent Section 7 consultation (2005) and an
Environmental Assessment, EA No. CA-600-06-28 (2006). Both the certified EIR and the EA
included extensive biological surveys to determine the status of wildlife and habitat on the
project site. The biological report will be updated, and new field surveys will be completed. A
jurisdictional delineation (JD) will be completed for the site to identify and analyze impacts to
waters of the State and waters of the US. The EIR will analyze the potential for adverse effects on
biological resources.
Travertine Specific Plan NOP 37 February 2020
4.2.5 Cultural Resources and Tribal Cultural Resources
Archaeology and paleontology were evaluated during the initial CEQA process and subsequent
certified final EIR (1995), and again during the EA process in 2006. As a result, of the cultural
findings the Project was redesigned to avoid impacts to archaeological resources which have
been recommended as eligible for the National Register of Historic Places (NRHP). The proposed
Specific Plan will require an updated cultural resources report in order to determine if
development of the proposed project will impact cultural resources. The analysis in the EIR will
include a review of the updated cultural evaluation, an assessment of the potential impacts to
cultural and tribal cultural resources associated with project construction, and the results of AB
52 consultation with Native American Tribes.
4.2.6 Energy
The project site lies within the service area boundaries of Imperial Irrigation District (IID) for
electricity and Southern California Gas Company for natural gas. An offsite substation will be
required and will be constructed during the Construction Phase I stage. The location of the
future offsite substation will be analyzed in the EIR. Additionally, potential impacts regarding
the project’s consumption of energy will be analyzed in the EIR. The EIR will evaluate the
project’s potential energy impacts and provide mitigation, if necessary, in order to reduce these
impacts.
4.2.7 Geology, Soils and Seismicity
Geology
The project site lies on an alluvial fan consisting of material deposited by drainages emanating
from the Santa Rosa Mountains to the south and southwest. See Exhibit 14, Topography -
Slope. The Martinez Rockslide on the southern edge of the property is a seven-mile long
geological formation likely created by seismic activity. There is potential for additional
rockslides on the Martinez Slide as a result of future seismic events. Analysis of potential
hazards associated with Martinez Slide and other seismic issues will be provided in the EIR.
Seismicity
The project site is not located within an Alquist-Priolo fault zone. However, seismic activity that
may occur on either the San Andreas fault zone (approximately 10 miles northeast of the
project site), or San Jacinto fault zone (approximately 10 miles southwest of the project site)
could result in severe ground shaking. Exhibit 1 5 , Fault Zones, displays the project site’s
distance in relation to the San Andreas and San Jacinto fault zones. The California Building Code
contains specific requirements and standards to ensure safe building design. The EIR will analyze
the project’s potential for seismic impacts.
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Topography - Slope
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
14
N.T.S.
MSA CONSULTING, INC.
> PLANNING > CIVIL ENGINEERING > LAND SURVEYING
34200 Bob Hope Drive, Rancho Mirage, CA 92270
760.320.9811 msaconsultinginc.com
Fault Zones
TRAVERTINE
ENVIRONMENTAL NOTICE OF PREPARATION
EXHIBIT
15
Travertine Specific Plan NOP 40 February 2020
Soils
The project site is comprised of predominantly alluvial material, with some exposed granite
bedrock, including well-drained, fine to coarse sand with some cobbles. Soil types were
identified through the USDA Natural Resource Conservation Service Web Soil Survey as
follows:
• CcC – Carrizo Stony Sand, 2-9% slopes: This soil is found on alluvial fans. The parent
material is alluvium derived from granite. Depth to a root restrictive layer is more than
60 inches. The soil is excessively drained and water movement in the most restrictive
layer is very high. Organic matter in the surface horizon is close to 0 percent.
• CdC – Carsitas Gravelly Sand, 0-9% slopes: This soil is also found on alluvial fans. The
parent material is gravelly alluvium derived from granite. Depth to a root restrictive
layer is more than 60 inches. The soil is excessively drained and water movement in the
most restrictive layer is very high. Organic matter in the surface horizon is about 1
percent.
• Rock Outcrop (RO) and Rubble Land (RU) apply to the areas in the north near the Coral
Mountains.
Topography and Slope
The project site is comprised of broad, gently sloping terrain that is typical of the western
portions of the Coachella Valley. These gentle slopes originate in the Santa Rosa Mountains
which border the Coachella Valley and the project site on the west side. The southern boundary
of the project site lies at the base of the Martinez Rock Slide, a seven-mile long geologic
formation of slumped mountain slopes. Table 5 provides a summary of the slope area.
Elevations range from approximately 40 feet above mean sea level (msl) at the northeastern
boundary to approximately 320 feet msl at the western limits. The site is generally flat with 5
percent slopes extending generally downward from the south and west. There are no significant
on-site topographic features with the exception of some outcroppings (the southernmost end
of the Coral Mountains) on the northern end of the property. The majority of the site is
comprised of land with slopes of less than 10 percent.
The steeper areas, those with slopes greater than 20 percent are confined to limited percentages
of the project site (see Table 5) and are generally located in the southern portions of the
property. The requirements of Chapters 9.120 and 9.130 (Open Space Regulations) and 9.140.040
(Hillside Conservation Regulations) of the Zoning Ordinance will govern these areas of the site
with regard to implementing conservation practices and adherence of development standards
on Open Space and Hillside areas.
Travertine Specific Plan NOP 41 February 2020
Development of the proposed project will be evaluated in the EIR using the most recent local,
regional and State requirements for site preparation and development.
Table 5: Project Slope Area Summarization
Slope Degree Category Acres Percent of Site
0 to 10 percent 788.4 90
10 to 12.5 percent 26.28 3
12.5 to 15 percent 8.76 1
15 to 17.5 percent 8.76 1
17.5 to 20 percent 0 0
Over 20 percent 43.8 5
Total 876 100 percent
4.2.8 Hazards
Implementation of the Travertine Specific Plan would facilitate new growth and development
throughout the project area. Resort/Spa, commercial and residential developments would result
in an increased population of residents and non-residents that would have both the potential to
be susceptible to hazards, and to utilize hazardous materials. Therefore, the EIR will analyze
potential impacts related to hazards and hazardous materials and incorporate mitigation where
necessary to ensure the proposed project maintains consistency with applicable policies to reduce
impacts to less than significant levels
4.2.9 Hydrology and Water Resources
The project site is located on a bajada extending eastward from the base of the Santa Rosa
Mountains toward the Coachella Valley floor. The slopes and canyon drainages of the Santa Rosa
Mountains occur west of the project site, while the Martinez Rock Slide formation occurs to the
south. To the north, the project site abuts Coral Mountain. To the east, the site abuts the Thomas
Levy Groundwater Replenishment Facility and Dike No. 4. The replenishment facility consists of
multiple percolation ponds designed to accept water conveyed from the Colorado River, while
Dike No. 4 is an earthen levee forming part of the flood control system for the Eastern Coachella
Valley.
The project site represents the lower extent of the watershed area tributary to Dike No. 4. The
Guadalupe Creek Diversion Dikes, located off-site on the northern end of the project, are also
designed to convey natural flows to Dike No. 4. The proposed project will include drainage and
stormwater management as part of its Infrastructure Plan. To identify the appropriate grading,
drainage, and infrastructure considerations, the EIR will include a project-specific Drainage Master
Plan, which will include a detailed watershed assessment, including regional and local hydrology,
flood hazard analysis, and hydraulics for the proposed development. This Drainage Master Plan
Travertine Specific Plan NOP 42 February 2020
will also identify the appropriate level of flood protection for the public, non-CVWD storm water
facilities, and impacted CVWD storm water facilities.
Based on the most current Federal Emergency Management Agency (FEMA) Flood Insurance Rate
Map (FIRM No. 06065C2900H), the project site is located in Zone D, a FEMA designation which
applies to areas where there are possible but undetermined or unmapped flood hazards.
The proposed project places planned development within the inactive alluvial fan areas while
establishing a perimeter flood protection system around the development, such that the principal
flows continue to be conveyed to the downstream retention areas constructed along Dike No. 4.
The EIR analysis will consider how the flood protection solutions set forth in the Drainage Master
Plan are incorporated into the site design, storm drain infrastructure, and water quality
management practices in relation to the applicable regulatory standards that apply during
construction and operation of the proposed development.
The EIR will analyze the project’s site design measures to prevent interference with the existing
groundwater recharge operation located east of the project. A Water Supply Assessment and
Water Supply Verification has been completed and adopted by CVWD in February 2017. This
report analyzes the most current project demand for water and the supply availability for the
project area.
The introduction of impervious land cover (i.e., roadways, hardscape, buildings) resulting from
project implementation would result in an increase in the rate and amount of surface runoff
produced by a site. The project will include an on-site stormwater retention system designed to
capture, convey, and retain stormwater runoff from within the proposed development.
4.2.10 Land Use Planning
The proposed project consists of a variety of land uses including Residential, Resort/Spa – Golf
Club Facilities, Open Space – Golf, and Open Space – Restricted. Residential land uses will range
from low density to medium density. A Resort/Spa facility will serve tourists and recreational
visitors. A 9 to 12-hole golf skills course will provide recreational opportunities as well. Related
commercial uses, such as restaurants and shops, will be combined with the resort/spa and golf
club to serve the daily needs of the community and its visitors. Entitlement procedures for this
project will include a General Plan Amendment to revise the existing City of La Quinta General
Plan Map to be consistent with the proposed land uses.
The General Plan Amendment will also change the General Plan Circulation Map of the General
Plan to (1) remove Jefferson Street as a General Plan roadway south of the hypothetical westerly
extension of Avenue 60; (2) remove Avenue 62 west of the hypothetical southerly extension of
Madison Street; and (3) remove Madison Street as a General Plan roadway from south of Avenue
60 to Avenue 62. A Zone Change is required to revise the City’s Zoning Map to be consistent
Travertine Specific Plan NOP 43 February 2020
with the proposed land uses. These are in addition to the Specific Plan Amendment, Tentative
Tract Map and Development Agreement. The EIR will analyze the goals, policies and objectives
of the Specific Plan for consistency with the City’s General Plan and zoning.
4.2.11 Mineral Resources
The Coachella Valley contains valued mineral resources due to the region’s highly active geologic
nature. The numerous earthquake faults throughout the region create massive uplifting and
folding of the land and expose mineral resources on the surface. Mineral resources found
throughout the region include sand, gravel, crushed stone, copper, limestone, and tungsten.
Many of these resources are important for common construction projects including asphalt,
concrete, road base, stucco, and plaster. There are currently several active sand and gravel mines
in the Coachella Valley, but none are in the City of La Quinta. Future mining within the City of La
Quinta is unlikely due to the establishment of conservation areas, such as the Santa Rosa
Wilderness Area, and due to existing urbanization. In compliance with the California Surface
Mining and Reclamation Act of 1975, the Californian Department of Conservation created
Production-Consumption Regions, which are areas where significant mineral resources of
statewide importance and regional significance are produced and consumed and a classification
system that identifies lands where significant mineral resource deposits are located. A majority of
the City of La Quinta is located in the Palm Springs Production-Consumption Region. Small portions
of La Quinta, including lands south of Avenue 60, such as the project property, are located outside
the Palm Springs Production-Consumption Region, and therefore, are not located within a Mineral
Resource Zone. Thus, impacts to Mineral Resources are not anticipated and will not be analyzed
in the EIR.
4.2.12 Noise
The proposed project is consistent with the City’s residential and Resort/Spa character. Potential
impacts of noise associated with project construction and operation will be analyzed and
addressed in the EIR. Additionally, since the proposed project is adjacent to a CVMSHCP
conservation area, the applicant will be required to comply with the noise requirements in the
CVMSHCP adjacency guidelines. Appropriate design measures and all applicable restrictions and
requirements will be identified within the EIR and mitigation will be incorporated where
necessary in order to ensure that potential noise impacts are reduced.
4.2.13 Population and Housing
A maximum of 1,200 dwelling units are proposed to be developed within the Travertine Specific
Plan. These residential dwelling units would provide a variety of proposed options including:
Estate homes, Single Family Luxury Homes, Single Family Mid Homes, Single Family Entry Homes,
Patio Homes, and Single Family Attached Homes.
Travertine Specific Plan NOP 44 February 2020
The Project would not displace existing dwelling units or residents necessitating the construction
of replacement housing elsewhere. The maximum potential units for each residential planning
area will be used for analysis in the EIR. Potential population and housing impacts associated
with the project as they relate to population growth presented in the La Quinta 2035 General
Plan will be evaluated in the EIR and mitigation will be incorporated where necessary to reduce
impacts.
4.2.14 Public Services
The Riverside County Fire Department (RCFD), under contract with the City of La Quinta, provides
24-hour fire protection and emergency medical services to the City. Law enforcement services are
provided to the City of La Quinta through a contractual agreement with Riverside County Sheriff’s
Department. The Sheriff’s department provides 24-hour municipal police services associated with
a City police department. The City of La Quinta is served by two school districts; Desert Sands
Unified School District (DSUSD) and Coachella Valley Unified School District (CVUSD). DSUSD
serves the portion of the City west of Jefferson Street and north of Avenue 48, which includes the
northern Sphere of Influence. CVUSD boundaries include the areas of Jefferson Street and east of
Avenue 48. Implementation of the proposed Travertine Project may increase the permanent
population which could have an impact on the City’s public services. The EIR will analyze the
potential impacts of the demand to public services and determine if mitigation would be required
to maintain acceptable levels of services.
4.2.15 Recreation
Approximately 257 acres of the project area are planned for Open Space – Recreation and Open
Space – Natural uses, designed to offer both passive and active opportunities. Proposed Open
Space – Recreation elements include picnic tables, barbeques, a tot lot playground, and staging
facilities for the regional interpretive trail. Open Space Natural uses will include a network of
trails suitable for pedestrian use throughout the community, offering recreational opportunities
to all residents. A variety of amenities would be provided along the trails, including rest stops,
and interpretive signage that would serve to further enhance the natural experience afforded by
the trail network. The EIR will analyze potential impacts to Recreation facilities and the goals and
policies of the City’s Parks and Recreation Master Plan and incorporate mitigation if necessary.
4.2.16 Transportation
The project area is generally bounded by the extension of Avenue 60 on the north; the extension
of Avenue 62 on the south; Coachella Valley Water District (CVWD) Dike No. 4 with related
stormwater impoundments on the east as well as the extension of Madison Street; and the
extension of Jefferson Street on the west.
Travertine Specific Plan NOP 45 February 2020
The development of the proposed project would provide for substantial improvement to several
roadways, including the southerly extension of Jefferson Street on- and off-site as a Modified
Secondary Arterial south of the proposed Coral Mountain property and the westerly extension
of Avenue 62 on- and off-site as a Modified Secondary Arterial. Loop roads emanate from the
Jefferson Road spine via two roundabout intersections.
The project proposes two alternative emergency vehicle access (EVA) route as a part of Phase 1
of project development. A maximum of 600 dwelling units would be allowed under both
alternatives. In both alternatives, Avenue 62 acts as the primary access road. Alternative I
proposes an EVA extending from Avenue 58 to the northern edge of the development, while
Alternative II proposes an EVA extending from Madison Street at Avenue 60. A traffic impact
analysis (TIA) will be conducted to assess potential traffic-related impacts to be analyzed within
the EIR and incorporate any necessary mitigation.
4.2.17 Utilities and Service Systems
Water and wastewater services would be provided by the Coachella Valley Water District (CVWD).
Currently, domestic water service lines exist in the area of the intersection of Avenue 60 and
Monroe from Jefferson extension and at Avenue 62. Additional well sites will be necessary to serve
the project. Well sites will be identified and analyzed in the EIR. Additional facilities will include two
water reservoirs and booster stations to collect the well water and store it at elevations appropriate
to provide the required water pressure for the site.
The project is subject to the CEQA process and is a subdivision as defined by the California
Government Code Section 66473.7. The City of La Quinta as the Lead Agency, and CVWD as the
Public Water System (PWS) provider of the project requires a Water Supply Assessment (WSA) to
complete CEQA compliance, and a written Water Supply Verification (WSV) is required pursuant to
the Subdivision Map Act. The proposed development is a "Project" as defined by Water Code
Section 10912 and requires a WSA because it proposes over 500 dwelling units.
A Water Supply Assessment (WSA) and Water Supply Verification (WSV) was completed for the
proposed Project and adopted in February 2017. The WSA/WSV addresses the projected water
demand and supply conditions associated with full buildout of the Project. The WSA/WSV analyzed
two options for planning development. The primary option (referred to as Plan A) would be
developed as a residential gated community with resort related uses. The secondary option (Plan
B) would be developed as a residential-only gated community. Under Plan A, the Project at buildout
is expected to demand approximately 1,255.13 acre-feet per year (AFY) or 1.43 acre-feet (AF) per
acre. Plan B is expected to consume approximately 639.46 AFY, or 0.72 AF per acre. The following
table from the approved WSA outlines the Project’s water demand at total buildout.
Travertine Specific Plan NOP 46 February 2020
Impact of Project Demand on Groundwater Supply
Based upon the supply/demand analyses conducted in the WSA/WSV for the project, CVWD made
the finding that there is sufficient water supply available to meet the demand of the proposed
project.
Electrical service to the Project would be provided by the Imperial Irrigation District (IID). An offsite
substation is required in order to provide electrical power to the Project.
CVWD will also provide wastewater services to the site. The offsite sewer alignment and
improvements will come from the east in Avenue 62. Wastewater will go to CVWD’s water
reclamation plan number 4 (WRP-4) located at 63-002 Fillmore St., Thermal CA.
Southern California Gas Company is the provider of natural gas, telephone and internet
communications will be provided by Spectrum. Burrtec will provide solid waste and recycling
services.
The development of the proposed Travertine Project would increase the demand for utilities in the
City and require the expansion of the City’s public utility infrastructure in the Project area. The
service, location, timing and construction of on- and offsite improvements required for all utilities
will be included in the EIR analysis. Project design features and mitigation measures during
construction and operation would be identified in the Draft EIR.
4.2.18 Wildfires
The City of La Quinta is situated in a Valley, along the base of the Santa Rosa and San Jacinto
Mountains. Much of the western portion of the City Planning Area is located near the urban-
wildland interface. The wilderness areas that surround La Quinta, as well as other areas along the
base of the Santa Rosa and San Jacinto Mountains, are made up Granitic rock and sparse desert
vegetation. The sparse desert vegetation along the mountainsides does not provide the explosive
fuels needed for wildfires, according to the La Quinta General Plan EIR. The California Department
of Forestry and Fire Protection (CAL FIRE) is required by Government Code 51175-89 to identify
areas of very high fire hazard severity zones within Local Responsibility Areas (LRA).
Travertine Specific Plan NOP 47 February 2020
According to the most recent CAL FIRE Very High Fire Hazard Severity Zone (VHFHSZ) Map,
provided in January 2010, the project property is located in an area designated as non-VHFHSZ.
The mountainous area south and west of the project, however, is located within State or Federal
Responsibility Areas and designated as VHFHSZ, per the Map. These areas are not a part of project
development. The project location will be analyzed in the EIR in order to determine if mitigation is
necessary.
5.0 Conclusion
An EIR will be prepared for the proposed project that addressed the environmental impacts
associated with the development of the Travertine Project. The EIR will also analyze a reasonable
range of alternatives to the Project, including the CEQA-mandated “No Project Alternative”, and
other potential alternatives that may be capable of avoiding or substantially reducing any of the
significant effects of the Project. All environmental issues identified in the CEQA Guidelines
Appendix G, and other issues that may be raised by responsible or trustee agencies or other parties
commenting on this Notice of Preparation will also be fully addressed in the EIR.