Subject: Request for Increased Regional Arterial Program Funding for the Dune
Palms Road Bridge Spanning the Whitewater River
Dear Mr. Kirk,
The City of La Quinta respectfully requests the Coachella Valley Association of
Governments (CVAG) approve Amendment No. 2 to the Agency Reimbursement
Agreement between the City of La Quinta and CVAG for the Design and Construction
of a new Bridge over the Whitewater River on Dune Palms Road increasing the
Regional Arterial Program Funding Contribution for the new Bridge from $1,506,750
to $5,395,230, an increase of $3,888,480. It also requests Amendment 2 extend
the term of the Agency Reimbursement Agreement through December 2024.
CVAG previously authorized and obligated the following:
Original Reimbursement Agreement, dated 12-03-2003 $1,506,750
Amendment 1, Dune Palms Road Widening, dated 09-16-2016 $1,862,250
Total CVAG Funding Authorization to date: $3,369,000
The Dune Palms Road widening between Blackhawk Way and the new bridge
approach is complete. The CVAG funding provided as part of Amendment 1 has
been expended and reimbursed by CVAG.
The new bridge project is partially funded with Surface Transportation Program
(STP) funds through the State’s Highway Bridge Program (HBP). The HBP will now
provide 88.53%, up to $17,652,222, toward “participating costs” associated with
the proposed all weather bridge spanning the Whitewater River on Dune Palms Road.
The following represents the estimated project budget and proposed funding shares
for the new bridge:
Phase Estimated Cost
New Bridge
Federal Funding
(Caltrans-HBP)
Non-Participating
Plus Local Share
Engineering/Design $1,750,000 $1,549,275 $200,275
Right of Way $1,570,554 $1,166,825 $403,729
Construction $16,695,276 $11,241,037 $5,454,239
Const. Engineering $2,504,292 $2,217,050 $287,242
Contingency $1,669,530 $1,478,035 $191,495
Total Costs: $24,189,652 $17,652,222 $6,537,430
Caltrans-HBP Funding Share: $17,652,222
City of La Quinta Funding Share: $1,084,100
*CVAG Funding Share: $5,395,230
CVWD Funding Share: $58,100
Total Cost: $24,189,652
*CVAG’s Funding Share includes 100% of the requested CV Link Project
Components estimated at $2,142,930.00. The detailed cost estimate for the
CV Link Components is attached for your reference. The costs presented were
prepared using the actual bid information CVAG obtained from bidders during its
recent bid advertisement and award of the CV Link.
The increased project costs of the bridge are primarily due to increases in
construction and right-of-way costs, along with the addition of the CVAG requested
CV Link Elements. The original construction cost estimates were prepared in
conjunction with the original HBP Funding Application in 2011. The original right-
of-way cost did not anticipate the need for eminent domain proceedings due to an
uncooperative property owner on the northeast corner. The original cost estimate
did not anticipate the enhanced CV Link project elements requested by CVAG.
The City of La Quinta is finalizing the right-of-way phase and anticipates having a
shovel ready project by March 2021. Construction is expected to begin as early as
June or July 2021.
CITY OF LA QUINTAPrinted on: November 12, 2020 at 1:52 PMDune Palms Road Bridge ImprovementsEngineer's Estimate100% Mylar Screen Check Submittal - CV Link Elements OnlyITEM NO.ITEM UNITESTIMATED UNIT PRICE ESTIMATED QUANTITY AMOUNT ESTIMATED QUANTITY AMOUNT NOTES1 Sawcut & Remove Conc. Slope ProtectionSF3.50 25,600 89,600.00 15,800 55,300.002Clearing and Grubbing LS 216,600.001 216,600.001 2,500.00 18" Storm Drain Outlet, west of DPRd3 Concrete Slope ProtectionCY500.00 1,970 985,000.00899 449,500.00 Inlcudes southern full length and undercrossing4 18" Storm Drain OutletEA 14,000.001 14,000.001 14,000.00 18" Storm Drain Outlet, west of DPRd5 18" HDPE, N-12 WT Joint SD PipeLF65.0058 3,770.0058 3,770.00 18" Storm Drain Outlet, west of DPRd6 Class 2 Aggregate Base (T = 4") (Trail)SF1.00 9,585 9,585.009,585 9,585.007 Concrete Trail (T = 6")SF10.00 9,585 95,850.009,585 95,850.00 Secondary trail concrete8 Curb Ramp (Case B)EA7,500.002 15,000.002 15,000.009 Metal Railing (Trail Retaining Walls)LF750.00274 205,500.00274 205,500.0010 Metal Railing (Trail Undercrossing)LF810.00730 591,300.00730 591,300.0011 Install City Furnished In Pavement Solar LightsEA300.0018 5,400.0018 5,400.0012 Thermoplastic Banding (Undercrossing)SF43.00 1,588 68,284.001,588 68,284.0013 6" Solid White Stripe (Paint) (Trail)LF2.40210 504.00210504.00 Undercrossing trail section.14 Paint Bridge Soffit & Exterior GirderLS9,600.001 9,600.001 9,600.0015 F&I Soffit Panels w/ Eletrical ConnectionsLS 126,500.001 126,500.001 126,500.0016 3" Sch. 40 PVC Conduit (CV Link)LF15.00725 10,875.00725 10,875.0017 Pull Box No. 3.5 (PCC) EA700.004 2,800.004 2,800.0018 4" Thick Decomposed GraniteSF4.00 5,090 20,360.005,090 20,360.0019 Structure Excavation (Ret Wall)CY75.00368 27,600.00368 27,600.00 South walls for secondary trail.20 Structure Backfill (Ret Wall)CY90.00501 45,090.00501 45,090.00 South walls for secondary trail. CV LINK ELEMENTS - CVAG OVERALL TOTALS ATTACHMENT 1
ITEM NO.ITEM UNITESTIMATED UNIT PRICE ESTIMATED QUANTITY AMOUNT ESTIMATED QUANTITY AMOUNT NOTES21 Structural Concrete (Ret Wall) CY 800.00 201 160,800.00 201 160,800.00 South walls for secondary trail.22 Bar Reinforcing Steel (Ret Wall) LS 1.20 20,000 24,000.00 20,000 24,000.00 South walls for secondary trail.Subtotal CV Link Items 1,948,118.00Contingency (10%)194,810.00$ Total Cost2,142,928.00$ Prepared by:Brad Donais11/12/2020 OVERALL TOTALS CV LINK PROJECT COST PARTICIPATING
1
Monika Radeva
From:Monika Radeva
Sent:Tuesday, November 17, 2020 1:41 PM
To:Julie Mignogna
Cc:Carley Escarrega; Nichole Romane; Monika Radeva
Subject:SIGNED: CVAG 2nd Request Ltr for Amend 2 to Reimbursement Agrmt Dune Palms Bridge 2011-05
Attachments:CVAG - Request 2 for Amend 2 to Reimburs Agrmt 2011-05 Dune Palms Bridge Project.pdf
Follow Up Flag:Follow up
Flag Status:Completed
The signed letter is attached and has been added to Laserfiche. সহ
Monika Radeva, CMC | City Clerk
City of La Quinta
78495 Calle Tampico, La Quinta, CA 92253
Tel: (760) 777‐7035
MRadeva@laquintaca.gov
From: Julie Mignogna <jmignogna@laquintaca.gov>
Sent: Monday, November 16, 2020 11:42 AM
To: Monika Radeva <mradeva@laquintaca.gov>; Nichole Romane <nromane@laquintaca.gov>
Cc: Carley Escarrega <cescarrega@laquintaca.gov>
Subject: RE: Cover Memo for CM signature on letters
Good morning, Monika!
Martin Magana at CVAG provided questions/comments to our initial Dune Palms Bridge funding
increase request letter. We have prepared a revised letter and ATT1 addressing all of his
questions to send back. Would you mind processing this hard copy for Jon’s signature and
mailing to CVAG again?
Please let me know if you (or Jon) have any questions. Thank you for all of your help!
Much appreciation,
Julie
From: Monika Radeva <mradeva@laquintaca.gov>
Sent: Tuesday, October 27, 2020 4:15 PM
To: Julie Mignogna <jmignogna@laquintaca.gov>; Nichole Romane <nromane@laquintaca.gov>
Cc: Carley Escarrega <cescarrega@laquintaca.gov>
Subject: RE: Cover Memo for CM signature on letters
Ok, thank you – we will process for signature and send back to you.
Monika Radeva, CMC | City Clerk
City of La Quinta
78495 Calle Tampico, La Quinta, CA 92253
Tel: (760) 777-7035
2
MRadeva@laquintaca.gov
Due to State Orders regarding COVID-19, City Hall is closed to the public. Please use
online submittal forms for public records requests and claims at
https://www.laquintaca.gov/business/city-clerk/forms. City Staff is available at (760)
777-7016, (760) 777 – 7092, (760) 777 – 7035, or via email at
CityClerkMail@LaQuintaCA.gov to answer any questions.
From: Julie Mignogna <jmignogna@laquintaca.gov>
Sent: Tuesday, October 27, 2020 3:47 PM
To: Monika Radeva <mradeva@laquintaca.gov>; Nichole Romane <nromane@laquintaca.gov>
Cc: Carley Escarrega <cescarrega@laquintaca.gov>
Subject: RE: Cover Memo for CM signature on letters
Not at this time, we would prepare an Amendment 2 to the agreement that their Executive
Board and City Council would approve before processing. This is just the request for
consideration of an amendment.
From: Monika Radeva <mradeva@laquintaca.gov>
Sent: Tuesday, October 27, 2020 3:44 PM
To: Julie Mignogna <jmignogna@laquintaca.gov>; Nichole Romane <nromane@laquintaca.gov>
Cc: Carley Escarrega <cescarrega@laquintaca.gov>
Subject: Re: Cover Memo for CM signature on letters
The letter is self explanatory but will it include amendment 2?
From: Julie Mignogna <jmignogna@laquintaca.gov>
Sent: Tuesday, October 27, 2020 2:55 PM
To: Monika Radeva <mradeva@laquintaca.gov>; Nichole Romane <nromane@laquintaca.gov>
Cc: Carley Escarrega <cescarrega@laquintaca.gov>
Subject: Cover Memo for CM signature on letters
Good afternoon!
I have a letter to CVAG prepared for Jon’s signature regarding our Dune Palms Bridge project
funding (attached). Do we have a cover memo template for something like this, or should I
either use the agreement cover memo or just provide Jon the necessary background via email?
Thank you for your help!
Much appreciation,
Julie
Julie Mignogna | Management Analyst
Public Works Department
City of La Quinta
78495 Calle Tampico | La Quinta, CA 92253
Ph. 760.777.7041
www.laquintaca.gov
www.playinlaquinta.com
3
Note: City Hall is now open on a limited basis by advanced appointment only.
Information on types of appointments being accepted, how to schedule and City-
implemented safety measures are available on our city website at HUB Appointments.
Issues or questions for Public Works can be submitted through GoRequest. Capital
improvement projects are still underway. City staff is available via phone or email to
answer project questions.
For additional updates visit: www.laquintaca.gov/COVID19
**Please note due to COVID-19 I will be working remotely until further notice, but will be
conducting business during regular business hours and will be available via phone and email.
Thank you for your understanding.**