WNL #1 2019-10-14 To: Leonard, Construction Project Manager – City of La-Quinta From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector Date: October 14, 2019 Subject: Weekly Newsletter: # 1 WORK DONE THIS PAST WEEK:  Attended the weekly project progress site coordination meeting along with the contractor/subcontractors/stakeholders.  Conducted with attendees a project site walk through and discussed field issues and concerns  City staff and Construction Manager attended Valley-wide City, Agency, and Utility coordination meeting. Received a status update on our CVWD water meter application.  The city’s QA on call survey crew commenced placing survey stakes for the parking lot area and established BM’s for the contractor’s pick-up points.  City of La Quinta Construction Manager and Z & K Construction manager met with IID to the scope and progress of our permit for power connection along Avenue 52.  Continue to review and forward the Contractor’s submittals & RFI’s, forwarded to designer upon preliminary CM /Inspection review.  PM 10 sign placed near intersection of Avenue 52 & SilverRock Way. WORK SCHEDULED FOR NEXT WEEK:  The Contractor is scheduled to scarify and compact subgrade in parking lot area as first order of work.  Arrange and coordinate as needed compaction testing on the parking lot area and as requested  The contractor will have an open ticket with US DIG alert prior to any trenching as per plans and specs  Contractor to request survey staking for new waterline and storm drain locations. COMMENTS: Urban Habitat will begin working at 7am on the SilverRock Venue Site project. If issues arise City may revise start time to 8am. Week Ending: October 12, 2019 ‘% Time Elapsed: 4.1 % Completion Date: April 09, 2020 Estimate of Actual Completion Date: April 09, 2020 City Of La Quinta 78495 Calle Tampico- La Quinta, CA 92253 The SilverRock Park Venue Site CIP Project No. 2016‐08