WORK DONE THIS PAST WEEK:
Attended the weekly project progress site coordination meeting along with the
contractor/subcontractors/stakeholders.
Conducted with attendees a project site walk through and discussed field issues and concerns
City staff and Construction Manager attended Valley-wide City, Agency, and Utility
coordination meeting. Received a status update on our CVWD water meter application.
The city’s QA on call survey crew commenced placing survey stakes for the parking lot
area and established BM’s for the contractor’s pick-up points.
City of La Quinta Construction Manager and Z & K Construction manager met with IID to
the scope and progress of our permit for power connection along Avenue 52.
Continue to review and forward the Contractor’s submittals & RFI’s, forwarded to
designer upon preliminary CM /Inspection review.
PM 10 sign placed near intersection of Avenue 52 & SilverRock Way.
WORK SCHEDULED FOR NEXT WEEK:
The Contractor is scheduled to scarify and compact subgrade in parking lot area as first order of
work.
Arrange and coordinate as needed compaction testing on the parking lot area and as requested
The contractor will have an open ticket with US DIG alert prior to any trenching as per plans and
specs
Contractor to request survey staking for new waterline and storm drain locations.
COMMENTS:
Urban Habitat will begin working at 7am on the SilverRock Venue Site project. If issues arise City
may revise start time to 8am.
Week Ending: October 12, 2019
‘% Time Elapsed: 4.1 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016‐08