WNL #10 2019-12-15
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: December 15, 2019
Subject: Weekly Newsletter: # 10
WORK DONE THIS PAST WEEK:
• Contractor began placing DG path from parking area to basin.
• Contractor poured footing for cross-over wall.
• Contractor began placing CMU block for cross-over wall.
• Subcontractor continued placing boulders in streambed.
• Subcontractor poured concrete for two bridge crossings and concrete veneer for stream
bed.
• Subcontractor poured concrete footings for terrace walls.
• Subcontractor pressure tested and backfilled domestic water line.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Parking lot light fixture footings to be placed.
• Boulders to continue being placed in streambed.
• Electrical conduit installation.
• Irrigation main line installation.
• Remaining Terrace walls to be formed and poured.
• Concrete sidewalk to continue being formed.
• 18” existing lake line to be repaired.
COMMENTS:
Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on
October 22nd, and will be every other week afterwards. Construction Manager Patrick will send
an invite and confirming the location.
Week Ending: December 15, 2019
‘% Time Elapsed: 36.9 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08