WNL #11 2019-12-26
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: December 26, 2019
Subject: Weekly Newsletter: # 11
WORK DONE THIS PAST WEEK:
• Pre Con meeting with IID was held on Monday.
• Contractor began placing CMU block for cross-over wall.
• Subcontractor pressure tested lake lines.
• Subcontractor continued placing boulders in streambed.
• Subcontractor poured 8’ wide sidewalk path.
• Subcontractor formed terrace walls.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Parking lot light fixture footings to be placed.
• Boulders to continue being placed in streambed.
• Electrical conduit installation.
• Irrigation main line installation.
• Remaining Terrace walls to be formed and poured.
• Concrete sidewalk to continue being poured.
• 18” existing lake line to be repaired.
COMMENTS:
Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on
October 22nd, and will be every other week afterwards. Construction Manager Patrick will send
an invite and confirming the location.
Week Ending: December 22, 2019
‘% Time Elapsed: 36.9 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08