WNL #13 2020-01-05
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: January 06, 2019
Subject: Weekly Newsletter: # 13
WORK DONE THIS PAST WEEK:
• Contractor continued installing irrigation mainline.
• Contractor installed metal lath on cross over wall.
• Contractor fine graded second ADA parking area.
• Subcontractor formed 12’ wide sidewalk.
• Subcontractor poured terrace wall 03.
• Subcontractor sacked & smooth finished stage radius wall.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Parking lot light fixture footings to be placed.
• Electrical conduit installation.
• Irrigation main line installation.
• Terrace walls to be formed and poured.
• Concrete sidewalk to continue being formed and poured.
• 18” existing lake line to be repaired.
• Cross Over Wall to be plastered.
COMMENTS:
Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on
October 22nd, and will be every other week afterwards. Construction Manager Patrick will send
an invite and confirming the location.
December 26th was a non-working day due to rain.
Next progress meeting will be held on January 7th, 2020 at 10:30am.
Week Ending: January 4, 2020
‘% Time Elapsed: 54.2 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08