WNL #14 2020-01-13 To: Leonard, Construction Project Manager – City of La-Quinta From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector Date: January 13, 2019 Subject: Weekly Newsletter: # 14 WORK DONE THIS PAST WEEK: • Contractor plastered cross over wall. • Subcontractor poured 12’ wide sidewalk. • Subcontractor sawcut 12’ wide sidewalk. • Subcontractor stripped, sacked/finished and formed terrace walls. • Subcontractor repaired 18” line for existing pond per CCO #2. • Subsurface Imaging service was used to locate existing 15” irrigation line. • Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review. WORK SCHEDULED FOR NEXT WEEK: • Parking lot light fixture footings to be placed. • Electrical conduit installation. • Irrigation main line installation. • Terrace walls to be poured. • Concrete sidewalk to continue being formed and poured. • Cross Over Wall plaster to be completed. COMMENTS: Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on October 22nd, and will be every other week afterwards. Construction Manager Patrick will send an invite and confirming the location. December 26th was a non-working day due to rain. Next progress meeting will be held on January 21st, 2020 at 10:30am. Week Ending: January 11, 2020 ‘% Time Elapsed: 47.5 % Completion Date: April 09, 2020 Estimate of Actual Completion Date: April 09, 2020 City Of La Quinta 78495 Calle Tampico- La Quinta, CA 92253 The SilverRock Park Venue Site CIP Project No. 2016-08