WNL #15 2020-01-20
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: January 20, 2019
Subject: Weekly Newsletter: # 15
WORK DONE THIS PAST WEEK:
• Contractor placed mud cap on irrigation screen wall.
• Contractor completed final coat of plaster on cross over wall.
• Subcontractor poured 12’ wide sidewalk.
• Subcontractor sawcut 12’ wide sidewalk.
• Subcontractor stripped, sacked/finished and formed terrace walls.
• CM conducted drone flyover for project progress photos.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Parking lot light fixture footings to be placed.
• Electrical conduit installation.
• Irrigation main line installation.
• Terrace walls to be poured.
• Concrete sidewalk to continue being formed and poured.
COMMENTS:
January 20th is a city holiday thus there will be no work.
Next progress meeting will be held on January 28th, 2020 at 10:30am.
Week Ending: January 18, 2020
‘% Time Elapsed: 51.7 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08