WNL #16 2020-01-27
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: January 27, 2019
Subject: Weekly Newsletter: # 16
WORK DONE THIS PAST WEEK:
• Contractor delivered boulders and soil on site.
• Subcontractor poured & sawcut 12’ wide sidewalk.
• Subcontractor poured 2 radius wall footings in stage area.
• Subcontractor poured and sawcut second ADA parking area.
• Subcontractor poured, stripped, & smooth finished another terrace wall.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Parking lot light fixture footings to be placed.
• Electrical conduit installation.
• Irrigation main line installation.
• Radius walls to be formed in stage area.
• Concrete sidewalk to continue being formed and poured.
COMMENTS:
A meeting will be held Monday (1/27) morning at City Hall to discuss project schedule and
pending CCO’s.
A total of two non-working days due to weather delay have been recorded thus far. Project
completion has been adjusted accordingly.
Next progress meeting will be held on January 28th, 2020 at 10:30am.
Week Ending: January 25, 2020
% Time Elapsed: 55 %
Completion Date: April 13, 2020
Estimate of Actual Completion Date: April 13, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08