WNL #17 2020-02-03
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: February 03, 2019
Subject: Weekly Newsletter: # 17
WORK DONE THIS PAST WEEK:
• Contractor installed landscape irrigation throughout site.
• Contractor applied waterproofing to one terrace wall.
• Contractor installed conduit under supervision of subcontractor.
• Subcontractor poured & sawcut 12’ wide sidewalk.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Parking lot light fixture footings to be placed.
• Electrical conduit installation.
• Irrigation line installation.
• Radius walls to be formed in stage area.
• Concrete sidewalk to continue being formed and poured.
• Waterproofing to be placed on terrace walls.
COMMENTS:
A field directive was issued to Urban Habitat to begin excavation for the missing 15” line.
The city paid Clint to have the 54” storm drain pipe scoped. No damage was discovered, and the
existing pipe will be adequate. Dan will send revised outlet structure plans in 1-2 weeks.
A total of two non-working days due to weather delay have been recorded thus far. Project
completion has been adjusted accordingly.
Next progress meeting will be held on February 11th, 2020 at 10:30am.
Week Ending: February 03, 2020
% Time Elapsed: 59 %
Completion Date: April 13, 2020
Estimate of Actual Completion Date: April 13, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08