WNL #2 2019-10-21
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: October 21, 2019
Subject: Weekly Newsletter: # 2
WORK DONE THIS PAST WEEK:
• Contractor commenced mobilizing equipment, material, and field office onto site
• Construction entrance installed at access gate off Avenue 52
• Contractor commenced subgrade preparation at the parking lot area.
• Compaction testing conducted on subgrade at the parking lot area.
• Contractor and Construction Manager attended Coachella Valley Fugitive Dust control
class on 10-17-2019, instruction given by South Coast AQMD
• Field office was delivered onto project site
• Continue reviewing RFI’s and submittals , forward to designer upon prelim CM review
WORK SCHEDULED FOR NEXT WEEK:
• The Contractor is scheduled to continue subgrade preparation in the parking lot area.
• Commence mobilization for the pond installation.
• Contractor to request survey staking for new waterline and storm drain locations.
• Commence installation of the 6” Irrigation mainline
• Continue attending the weekly construction coordination meeting
COMMENTS:
Contractor’s construction working hours are set at 7 am. The city may entertain a different
starting time at the request of Urban Habitat.
Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on
October 22nd, and will be every other week afterwards. Construction Manager Patrick will send
an invite and confirming the location
Week Ending: October 19, 2019
‘% Time Elapsed: 4.1 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08