WNL #3 2019-10-28
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: October 28, 2019
Subject: Weekly Newsletter: # 3
WORK DONE THIS PAST WEEK:
• Subcontractor commenced trenching and placing 10” pipe for lake.
• Contractor trenched and placed irrigation sleeves and conduits under parking lot area.
• Contractor commenced placing Class II base in parking lot area.
• Our first Bi-weekly construction progress meeting was held at field trailer on Tuesday
October 22nd.
• Contractor commenced placing 6” irrigation pipe in DG path along avenue 52.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Subcontractor is scheduled to continue installing 10” pipe for new lake.
• Placement of 6” irrigation pipe along avenue 52 will continue.
• Survey staking scheduled for Tuesday October 29th for storm drain lines.
• Continue attending the weekly construction coordination meeting.
COMMENTS:
Contractor’s construction working hours are set at 7 am. The city may entertain a different
starting time at the request of Urban Habitat.
Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on
October 22nd, and will be every other week afterwards. Construction Manager Patrick will send
an invite and confirming the location.
Week Ending: October 26, 2019
‘% Time Elapsed: 8.2 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08