Loading...
WNL #5 2019-11-11 To: Leonard, Construction Project Manager – City of La-Quinta From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector Date: November 14, 2019 Subject: Weekly Newsletter: # 5 WORK DONE THIS PAST WEEK: • Contractor continued trenching and placing 18” HDPE storm drain. • Contractor continued placing Class II base in parking lot area. • Subcontractor began constructing stream bed. • Contractor placed 6” pump discharge line. • Contractor began placement of permaloc asphalt edging in parking lot area. • Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review. WORK SCHEDULED FOR NEXT WEEK: • Subcontractor is scheduled to begin domestic and sewer line placement. • Storm Drain placement to continue • Pond/Lake construction to continue COMMENTS: Contractor’s construction working hours are set at 7 am. The city may entertain a different starting time at the request of Urban Habitat. Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on October 22nd, and will be every other week afterwards. Construction Manager Patrick will send an invite and confirming the location. Week Ending: November 9, 2019 ‘% Time Elapsed: 16.4 % Completion Date: April 09, 2020 Estimate of Actual Completion Date: April 09, 2020 City Of La Quinta 78495 Calle Tampico- La Quinta, CA 92253 The SilverRock Park Venue Site CIP Project No. 2016-08