WNL #7 2019-11-25
To: Leonard, Construction Project Manager – City of La-Quinta
From: Zack Faqih, P.E., Senior CM – Patrick Fraire CM/Site Inspector
Date: November 25, 2019
Subject: Weekly Newsletter: # 7
WORK DONE THIS PAST WEEK:
• Contractor poured footing for screen wall.
• Contractor began excavating for irrigation main line.
• Subcontractor placed liner in lower pond.
• Subcontractor excavated and placed vault for lake pump.
• Contractor continued placement of permaloc asphalt edging in parking lot area.
• Subcontractor began trenching and placing C-900 pipe for fire line.
• Continue reviewing RFI’s and submittals, forward to designer upon prelim CM review.
WORK SCHEDULED FOR NEXT WEEK:
• Concrete veneer to be poured in lower pond next week.
• Gross gutter and curb to be poured near entrance next week.
• Fire and domestic water lines to be placed.
• Irrigation lines to be placed.
COMMENTS:
Contractor’s construction working hours are set at 7 am. The city may entertain a different
starting time at the request of Urban Habitat.
Weekly construction progress meeting set to start on Tuesdays at 10 am, commencing on
October 22nd, and will be every other week afterwards. Construction Manager Patrick will send
an invite and confirming the location.
Week Ending: November 22, 2019
‘% Time Elapsed: 24.6 %
Completion Date: April 09, 2020
Estimate of Actual Completion Date: April 09, 2020
City Of La Quinta
78495 Calle Tampico- La Quinta, CA 92253
The SilverRock Park Venue Site
CIP Project No. 2016-08