RFP Addendum No. 1 - Construction Mgmt & Inspection Services - DP Bridge Project 2011-05
DATE: November 23, 2021
TO: All Prospective Dune Palms Bridge Project Construction
Management, Inspection, Survey, and Material Testing Services
Consultants
RE: Construction Management, Inspection, Survey, and Material
Testing Services for the Dune Palms Road Bridge Project, Federal
Project No. BRKLS-5433(014), City Project No. 2011-05.
RESPONSE TO QUESTIONS
The following are the City’s responses to the questions received:
1.) Will electronic signatures be allowable for the original Work
Proposal (envelope 1) and original Cost Proposal (envelope 2)?
Yes, electronic signatures are sufficient for both the original Work Proposal
and original Cost Proposal.
2.) Are prime consultants required to complete “Attachment 8 –
Acknowledgement of Receipt of Addenda” and “Attachment 9 –
Acknowledgement of Receipt of Addenda”?
Prime consultants are only required to complete “Attachment 8 –
Acknowledgement of Receipt of Addenda” with the Work Proposal.
Attachment 9 is” Federal Forms 10-K and 10-H1” and should be submitted
with the Cost Proposal.
3.) Are subconsultants required to complete the “Non-Collusion
Affidavit Form”?
Only prime consultants are required to complete the “Non-Collusion Affidavit
Form”
4.) Will the City send out the list of interested proposers?
Yes, after 11/15/2021, the list will be posted to the RFP website posting.
5.) Have all environmental permits been received?
Yes, though some will be expiring and need to be extended. A copy of the
permits are in the RE pending file.
6.) Will the resumes count toward the total page count?
No, they can be provided in the Appendix and not count toward the page
count.
7.) Will the City provide the Pre-Proposal PowerPoint presentation?
Yes, the Power Point from the Pre-Proposal Conference will be posted to the
RFP website posting.