Thank you Nicole.
Please Add Good,
Garrett Simon
970-596-6642
www.meriwetherco.com
On May 7, 2020, at 3:52 PM, Nicole Criste <ncriste@terranovaplanning.com> wrote:
GareH,
I don’t know how much detail you are looking for, but I’ve detailed your three items a liHle
more.
1. Full applicaKon submiHal in coming weeks - geZng so close!
2. City review and determinaKon of completeness.
3. Then applicaKon is circulated to city departments and outside agencies for comments for
up to 60 days
4. Revisions by your team as needed based on city and agency comments.
5. ResubmiHal of revised materials.
6. City distributes CEQA document for comments – 20 day public comment period.
7. Prepare response to comments (as needed) and staff report.
8. Public hearing with PC and CC (3-4 weeks apart).
Hope this is helpful!
Nicole
Nicole Sauviat Criste
Consulting Planner
City of La Quinta
image001.png>TERRA NOVA PLANNING & RESEARCH, INC.®
42635 Melanie Place, Ste 101
PALM DESERT, CA 92211
760) 341-4800
FAX#: 760-341-4455
E-Mail: ncriste@terranovaplanning.com
From: GarreH Simon <gsimon@meriwetherco.com>
Date: Thursday, May 7, 2020 at 3:16 PM
To: Cheri Flores <clflores@laquintaca.gov>
Page 2 of 3
Cc: Nicole Criste <ncriste@terranovaplanning.com>, ConsulKng Planner
ConsulKngPlanner@laquintaca.gov>
Subject: Re: Coral Mt - Project Next Steps
Thank you and look forward to hearing from Nicole. I was informed by some neighbors that
some PC hearings have been postponed, and the insulated it was due to Covid and meeKngs
being help virtually. Sounds like that may not be the case.
Please Add Good,
Garrett Simon
970-596-6642
www.meriwetherco.com
On May 7, 2020, at 2:11 PM, Cheri Flores <clflores@laquintaca.gov> wrote:
Hello Garrett! Hope you are doing well.
For the Planning Commission meetings, at this time, we are
doing them all remotely through Zoom and they are being live
streamed on our website. That said, all of this is subject to
change based on how Federal, State and local orders may
change as the COVID-19 situation evolves. It is possible that
by the time your project is ready for Planning Commission, we
may be conducting meetings differently. But for the time
being, all is done remotely. You are welcome to tune into the
meeting next week on May 12 at 5 pm.
For the three items below regarding process, I’ll let Nicole
answer those since she is the case planner and is handling the
day-to-day processing. Take care and have a great day!
image001.png>
Cheri L. Flores | Planning Manager
City of La Quinta
78495 Calle Tampico La Quinta, CA 92253
Ph. 760-777-7067
www.laquintaca.gov
PLEASE NOTE: Due to State Orders regarding COVID-19, City
Hall is closed to the public. Applications may not be
submitted in person; however, they can be submitted online
through E-Trakit . City staff is available at (760) 777-7125 or
via email at customercenter@laquintaca.gov to answer any
questions.
Page 3 of 3
From: GarreH Simon <gsimon@meriwetherco.com>
Sent: Thursday, May 7, 2020 8:19 AM
To: Cheri Flores <clflores@laquintaca.gov>
Subject: Re: Coral Mt - Project Next Steps
EXTERNAL: This message originated outside of the City of La Quinta. Please use proper
judgement and cauKon when opening aHachments, clicking links or responding to requests for
informaKon. **
Also want to see if I can catch you for a quick cal today to discuss status of PC
meeKngs due to Corona. Do not want to get ahead of myself but would be great to
understand current protocol and potenKal backlog. Let me know the best number
to reach you and if there is a Kme that works best.
Please Add Good,
Garrett Simon
970-596-6642
www.meriwetherco.com
On May 6, 2020, at 8:09 PM, GarreH Simon
gsimon@meriwetherco.com> wrote:
Cheri,
I have some update calls with neighbors next week and want to make
sure I am accurate with process. Can you confirm or comment on the
following:
1) Full applicaKon submiHal in coming weeks - geZng so close!
2) Then applicaKon is circulated to city departments for comments for
up to 60 days
3) Then schedule public hearings with PC first then CC
Is there anything between 2 and 3?
Please Add Good,
Garrett Simon
970-596-6642
www.meriwetherco.com
Aid in Future COVID-19 Relief Funding and Get Your Community Counted! Take the 2020
Census Online Here: https://my2020census.gov/, Everyone Counts!