Loading...
2020 Urban Habitat Change Order 05 - SRR Park Venue Project 2016-08 TO: Jon McMillen, City Manager FROM: Ubaldo Ayon, Assistant Construction Manager Via: Bryan McKinney, P.E., Public Works Director/City Engineer DATE: May 18, 2020 RE: Contract Change Order No. 5 SilverRock Park Venue Project No. 2016-08 Attached for your signatures is one (1) original Contract Change Order No. 5 between Urban Habitat and the City of La Quinta for the project referenced above. This Contract Change Order allows for the installation of the restroom building, a new electrical subcontractor, and replacing sod with stolon. Please sign and return the original to the City Clerk for final distribution. The following Budget Summary is provided: Project Budget $ 6,000,000 Original Contract Amount ($ 4,218,880) Contract Change Order No. 1 - 4 ($ 92,581) Contract Change Order No. 5 ($ 209,856) Balance Remaining $ 1,478,683 As indicated, adequate funding is available. REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE: _X_ Contract payments will be charged to the construction account number: 401-0000-60188-201608-CT Authority to execute this agreement is based upon: ___ City Manager’s signature authority provided under Resolution No. 2018-014 for budgeted expenditures of $50,000 or less. _X_ City Council approval on May 5, 2020 Digitally signed by Ubaldo Ayón DN: cn=Ubaldo Ayón, o=City of La Quinta, ou=Public Works/ Engineering, email=uayon@laquintaca.gov, c=US Date: 2020.05.18 17:05:47 -07'00' Adobe Acrobat version: 11.0.23 Digitally signed by Bryan McKinney DN: cn=Bryan McKinney, o, ou, email=bmckinney@laquintaca.g ov, c=US Date: 2020.05.18 17:10:11 -07'00'