2020 Urban Habitat Change Order 05 - SRR Park Venue Project 2016-08 TO: Jon McMillen, City Manager
FROM: Ubaldo Ayon, Assistant Construction Manager
Via: Bryan McKinney, P.E., Public Works Director/City Engineer
DATE: May 18, 2020
RE: Contract Change Order No. 5
SilverRock Park Venue
Project No. 2016-08
Attached for your signatures is one (1) original Contract Change Order No. 5 between
Urban Habitat and the City of La Quinta for the project referenced above.
This Contract Change Order allows for the installation of the restroom building, a new
electrical subcontractor, and replacing sod with stolon.
Please sign and return the original to the City Clerk for final distribution.
The following Budget Summary is provided:
Project Budget
$ 6,000,000
Original Contract Amount
($ 4,218,880)
Contract Change Order No. 1 - 4
($ 92,581)
Contract Change Order No. 5
($ 209,856)
Balance Remaining
$ 1,478,683
As indicated, adequate funding is available.
REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE:
_X_ Contract payments will be charged to the construction account number: 401-0000-60188-201608-CT
Authority to execute this agreement is based upon:
___ City Manager’s signature authority provided under Resolution No. 2018-014 for budgeted expenditures
of $50,000 or less.
_X_ City Council approval on May 5, 2020
Digitally signed by Ubaldo Ayón
DN: cn=Ubaldo Ayón, o=City of La
Quinta, ou=Public Works/
Engineering,
email=uayon@laquintaca.gov,
c=US
Date: 2020.05.18 17:05:47 -07'00'
Adobe Acrobat version: 11.0.23
Digitally signed by Bryan
McKinney
DN: cn=Bryan McKinney, o, ou,
email=bmckinney@laquintaca.g
ov, c=US
Date: 2020.05.18 17:10:11
-07'00'