2021-10-05 Overall Project - Travertine Schedule
ID Duration Start Finish Task Name0977 days?Tue 1/1/19Fri 10/28/22Travertine Entitlement Schedule177 daysTue 1/1/19Thu 4/18/19EVENTS/MILESTONES20 daysTue 1/1/19Tue 1/1/19TRG LAND - BECOMES PROJECT LEAD30 daysWed 1/16/19Wed 1/16/19TRAVERTINE TEAM KICK OFF MEETING40 daysThu 4/18/19Thu 4/18/19Meeting with Riverside County Fire / City of La Quinta50 daysThu 4/18/19Thu 4/18/19Meeting with IID60 daysThu 4/18/19Thu 4/18/19Meeting with City of La Quinta and MSA70 daysThu 4/18/19Thu 4/18/19Meeting with CVWD80 daysThu 1/17/19Thu 1/17/19CEQA Kick-off Meeting at City9393 days?Tue 4/23/19Fri 11/6/20TTM PREPERATION 1050 daysTue 4/23/19Sun 6/30/19Update Prior Site Plan 1123 daysFri 5/22/20Tue 6/23/20Prepare Utility Base12345 daysSun 6/30/19Fri 11/6/20Revise TTM Base1339 daysMon 8/3/20Thu 9/24/20Techincal Studies 14299 daysMon 8/3/20Fri 10/8/21Drainage Report 15289 daysMon 8/17/20Fri 10/8/21PWQMP16294 daysMon 8/10/20Fri 10/8/21Sewer 17294 daysMon 8/10/20Fri 10/8/21Water18416 daysThu 2/20/20Fri 10/8/21Prepare TTM for Submittal 19439 daysMon 4/1/19Thu 12/24/20Complete Updated Draft Technical Studies20638 daysMon 4/1/19Fri 10/8/21Hydrology - R32157 daysTue 10/1/19Tue 12/31/19Phase 1 - 25-Year Flood Study 22460 daysMon 4/1/19Tue 2/2/21Visual and Aesthetics2388 daysMon 4/1/19Wed 7/31/19Geotechnical Narrative2442 daysTue 10/1/19Mon 12/2/19 A. Geotechnical Report for Planning and EIR2525 daysFri 9/27/19Thu 10/31/19 B. Geotechnical Evaluation of Oversize Rock26638 daysMon 4/1/19Fri 10/8/21*Draft Traffic Analysis / Noise / Air Quality / VMT30348 daysMon 6/3/19Thu 10/15/20*Cultural Resources / Tribal Consultation33439 daysMon 4/1/19Thu 12/24/20*Biological / CDFW36562 daysMon 4/1/19Thu 6/24/21Water Supply Assessment (PREVIOUSLY APPROVED)39420 daysSun 7/7/19Mon 3/15/21Review of Techincal Reports40552 daysTue 1/1/19Fri 3/12/21Specific Plan Duration4119 daysTue 1/1/19Fri 1/25/19Revise per City Comments and Resubmit4260 daysMon 1/28/19Fri 4/19/19City 2nd Review of Administrative Draft SP4356 daysMon 4/22/19Mon 7/8/19Revise per City Comments and Resubmit4414 daysTue 7/9/19Fri 7/26/19City 3rd Review of Administrative Draft SP45308 daysMon 7/29/19Thu 10/15/204th Draft SP and Distribute4614 daysFri 11/13/20Mon 12/7/204th Review4760 daysWed 12/9/20Fri 3/12/215 th Draft SP and Distribute48255 daysMon 2/10/20Mon 2/15/21Public Roll Out Effort49283 daysMon 2/3/20Fri 3/19/21Prepare Public Presentation Package5045 daysMon 2/10/20Fri 4/10/20Field Trips with Mayor, City Manager, BLM, Archaeology, Com5141 daysTue 12/31/19Wed 2/26/20NOP Duration5210 daysMon 12/2/19Fri 12/13/19**Prepare Notice of Preparation (NOP) and Project Description5342 daysMon 12/16/19Fri 2/21/20**City Review of NOP5438 daysMon 1/6/20Wed 2/26/20**Revise NOP Per City Comments and Resubmit55132 daysThu 2/27/20Fri 8/28/20**Public Review of NOP and Scoping Session - 30 days56259 daysMon 8/31/20Fri 9/10/21EIR Duration5721 daysMon 10/4/21Mon 11/1/21Prepare Submittal of Completed Sections of Admin Draft EIR5835 daysTue 11/2/21Mon 12/20/21City Review of Administrative Draft EIR5921 daysTue 12/21/21Tue 1/18/22Revise per City Comments and Resubmit6016 daysWed 1/19/22Wed 2/9/22City Second Review6111 daysFri 2/11/22Fri 2/25/22Revise per City Comments and Resubmit6216 daysFri 2/25/22Fri 3/18/22City Third Review638 daysMon 3/21/22Wed 3/30/22Prepare Notice of Availability640 daysWed 3/30/22Wed 3/30/22Prepare Notice of Completion to SCH655 daysThu 3/31/22Wed 4/6/22Finalize Draft EIR and Distribute6645 daysThu 4/7/22Wed 6/8/22Public Review of Draft EIR - 45 days6731 daysThu 6/9/22Thu 7/21/22Prepare Adminstrative Final EIR (including RTC)6821 daysFri 7/22/22Fri 8/19/22City Review of Administrative Final EIR696 daysMon 8/22/22Mon 8/29/22Revise per Comments and Resubmit (2d AFEIR)7010 daysFri 9/2/22Thu 9/15/22Finalize FEIR and Distribute (10 day Agency review)7110 daysFri 9/16/22Thu 9/29/22Planning Commission Hearing7210 daysFri 10/14/22Thu 10/27/22City Council Hearing731 dayFri 10/28/22Fri 10/28/22File Notice of Determination3/3010/28JulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovQtr 3, 2020Qtr 4, 2020Qtr 1, 2021Qtr 2, 2021Qtr 3, 2021Qtr 4, 2021Qtr 1, 2022Qtr 2, 2022Qtr 3, 2022Qtr 4, 2022Review PeriodProject DurationTechnical StudyTaskMilestoneProject: Travertine Entitlement ScheduleDate: Tue 10/5/21