zEngineer's EstimateX-Park Landscaping and Irrigation Improvements
City Project No. 2016-03G
Item Item Description Unit Quantity Unit Price Total Cost
1 Mobilization LS 1 50,330.00$ 50,330.00$
2 Traffic Control LS 1 10,300.00$ 10,300.00$
3 Dust Control LS 1 13,306.00$ 13,306.00$
4 Demolition and Disposal per Plans (including
bollard removal)LS 1 10,000.00$ 10,000.00$
5 Site Walls per Plan SF 12 55.00$ 660.00$
6 Clean/Paint Walls per Plan LS 1 7,000.00$ 7,000.00$
7 Concrete for Board Yard per Plans SF 108 $ 10.00 $ 1,080.00
8 Sidewalk Construction per Plans SF 600 10.00$ 6,000.00$
9 Stamped Concrete per Plans SF 483 10.00$ 4,830.00$
10 Drainage Concrete Box/Grate per Plans EA 7 210.00$ 1,470.00$
11
Full Depth Asphalt Concrete Grind (4"±), Compact
Existing Aggregate Base, and 4" Asphalt Concrete
Overlay
SF 8 40.00$ 320.00$
12 Modification of Existing Fence and Furnish and
Install Pedestrian Gate per Plans EA 1 1,000.00$ 1,000.00$
13 Trash Enclosure per Plans LS 1 20,000.00$ 20,000.00$
14 Keystone Block Wall 6" high block, 3-course.
Locations to be determined in field LF 100 80.00$ 8,000.00$
15 Clearing, Grubbing, Weed Abatement, and Soil
Preparation (including rock and debris removal)LS 1 11,741.00$ 11,741.00$
16
Curb, including mow curb, median type curb, and
modified median type curba as designated in the
Plans
LF 1,802 10.00$ 18,020.00$
17 3/4" Crushed Rock - Desert Gold SF 18,036 1.50$ 27,054.00$
18 6" Minus Baja Cresta Rubble SF 2,651 3.50$ 9,278.50$
19 3/8" Crushed Rock - Apache Brown SF 1,018 1.88$ 1,913.84$
20 3/8" Minus Decomposed Granite - Desert Gold SF 36,145 2.00$ 72,290.00$
21 3/8" Minus Stabilized Decomposed Granite -
Desert Gold SF 12,615 2.50$ 31,537.50$
22 Lawn - Sod SF 4,215 2.50$ 10,537.50$
23 Artificial Turf with Heatblock Technology SF 3,590 9.50$ 34,105.00$
24 Furnish and Install Boulders per Plans EA 36 125.00$ 4,500.00$
25 Furnish and Install Landscaping per Plans LS 1 18,005.00$ 18,005.00$
26 Furnish and Install Irrigation per Plans LS 1 43,613.00$ 43,613.00$
27 90 - Day Maintenance Period LS 1 2,375.00$ 2,375.00$
28 Apply Stained Arrow per Caltrans Standard Plan
A24A, Bike Lane Arrow, Three-part application EA 1 500.00$ 500.00$
419,766.34$
419,766.34$ Base Bid Only
Sub-Total Base Bid:
Engineer's Estimate - Base Bid