2021-02-08 VaughnRE: 2553 Coral Mountain Resort NOP [2553-MSA1.NRzfj - Consulting... https://outlook.office.com/mail/AAMkAGJiMWY1OTY1LTBhY2EtN...
<5 Reply all "/ ® Delete 0 Junk Block •
RE: 2553 Coral Mountain Resort NOP [2553-MSA1.NRzf]
JV
James Vaughn <JVaughn@szrlaw.com> <) <t 4
Mon 2/8/2021 4:52 PM
To: Nicole Criste (Contract Planner);Lee, Asia <alee@msaconsultinginc.com>;Consulting Planner;Ch
Cc: Witherspoon, Michelle <mwitherspoon@msaconsultinginc.com>;Depalatis, Paul <pdepalatis@r
** EXTERNAL: This message originated outside of the City of La Quinta. Please use proper judgement and
caution when opening attachments, clicking links or responding to requests for information. **
Hi Nicole and Cheri,
Here is the updated EIR schedule, based on the public hearing dates we discussed on our call last
week.
2/12/21: Issue NOP
3/15/21: Submit Final Batch of Draft EIR Sections for City Review (Prior batches to be submitted on
2/25/21 and 3/5/21)
4/5/21: City Completes review of Draft EIR
4/15/21: Release Draft EIR for 45-day public review period [4/15/21 — 6/1/21]
6/30/21: Submit draft responses to comments, MMRP and other Final EIR sections for City Review
7/30/21: City completes review of Final EIR
8/12/21: Distribute Final EIR to commenting agencies
8/23/21: Project ready for public hearings [Tentative Dates: PC on 9/14/21; CC on 10/5/21]
Thank you again for turning the NOP around so quickly. We will revise and resubmit ASAP.