RE: Process Question Please
Cheri Flores <clflores@laquintaca.gov>
Wed 8/11/2021 4:43 PM
To: Diane Rebryna <drebryna@telusplanet.net>
Cc: Danny Castro <dcastro@laquintaca.gov>;Consulting Planner<ConsultingPlanner@laquintaca.gov>
Hello Ms. Rebryna,
Thank you for your questions. If the Planning Commission makes a recommendation to not
approve the request, the application still goes on to the City Council, with that
recommendation to not approve, and the City Council can still consider the application. The
La Quinta Municipal Code has provisions for Zone Changes in Chapter 9.220 at the following
link:
Chapter 9.220 - ZONE MAP CHANGES AND CODE AMENDMENTS I Municipal Code I La Quinta, CA I Municode Library
Have a wonderful day!
1 11 ♦ 1 . \ 1
Cheri L. Flores I Planning Manager
City of La Quinta
78495 Calle Tampico La Quinta, CA 92253
Ph. 760-777-7067
www.laquintaca.gov
PLEASE NOTE: City Hall is now open to the public during normal business hours: Monday through
Thursday from 7:30 a.m. to 5:30 p.m. and Friday from 8:00 a.m. to 5:00 p.m. (Counter closes at
4:30 p.m. daily), with the exception of nationally observed holidays. Please follow all CDC and State
recommended guidelines as they pertain to COVID-19 safety and awareness. All public services
continue to be available via phone, email or online web portal and the public is encouraged to utilize
these services when possible. Thank you.
From: Diane Rebryna <drebryna@telusplanet.net>
Sent: Wednesday, August 11, 2021 4:09 PM
To: Cheri Flores <clflores@laquintaca.gov>
Subject: Process Question Please
[--
**EXTERNAL: This message originated outside of the City of La Quinta. Please use proper judgement and caution when opening
attachments, clicking links or responding to requests for information. **
Good day Ms. Flores,
I have a Process question please that I hope you can help me with.
Now that the comments period has closed for the DEIR re: Coral Mountain Resort, I understand that the next phases are as
per Ms. Sauviat Criste indicated ( in red below)
My specific question is as follows:
What happens if the Planning Commission makes "a recommendation" to City Council to NOT proceed with the zoning
change request?
Is that officially the end of the Application?
If this is the end of the Application made by the Developer, can the Developer "appeal" directly to City Council?
If the Developer can not appeal directly to City Council, what are possible next steps in the Process ?
1 of 2 5/29/22, 2:21 PM
Firefox https://outlook.office.com/mail/deeplink?Print
Thank you for your assistance with these Process questions.
If there is a city website or reference that you can direct me to that further explains the Process, I would be most
appreciative.
Kind regards,
Diane Rebryna
60149 Honeysuckle Street
La Quinta, CA
92253
All of the comments on the EIR will be published in the Final EIR/Response to Comments.
The Draft and Final EIR will be provided to the Planning Commission in advance of the public hearing on the
applications.
The Planning Commission (PC) will hold a public hearing(s) to consider the application. No hearing date has
been set.
The hearing will be noticed at least 10 days prior to the hearing date.
The staff report, application materials and environmental documents will all be available the Friday before
the hearing on the City's website.
The PC will receive the staff report, application materials and EIR in advance, and will take public testimony,
ask questions and make a recommendation to the City Council at the hearing.
The Planning Commission has broad discretion to ask for further information from staff or from the
applicant.
The Planning Commission does not approve the project - they make a recommendation to the City Council,
which has final authority.