PWP2021-0005 InspectionsPermit Number: PWP2021-0005
Applied: 10/12/2021
Issued:10/13/2021
Status: ISSUED
Parent Permit:
Parent Project:
Details
Approved:10/13/2021
Finaled:
Description: SILVERROCK TM37730 MONTAGE RESIDENCES STREET &
STORM DRAIN
Site Address: SILVERROCK WAY AND AHMANSON LN
City, State Zip Code: , CA
Applicant: ROBERT GREEN RESIDENTIAL INC - BRUCE MAIZE
Owner: CITY OF LA QUINTA
Contractor: TAYLOR UNDERGROUND INC
LIST OF
SEQ
SCHEDULED DATE COMPLETED DATE TYPE INSPECTOR RESULT REMARKS
ID
6/17/2022 6/17/2022 JP-ONSITE STORM
JIM PETERS PARTIALLY
DRAIN
APPROVED
Notes:
1215 to 1400Weather - Clear - Temperature 77 to 104 - Breeze SE 6 mph - Humidity 17% Witnessed storm drain crossing at Station 23+17 on
Conchella Way pipe in place and placing aggregate bedding for the pipe Reviewed the catch basin forms they were building and want to place concrete
on TuesdayPrinted out plans in office after call to Amy
6/20/2022
6/20/2022
P-ONSITE STORM
P
JIM PETERS
PARTIALLY
DRAIN
APPROVED
Notes:
1015 to 1030Weather - Clear - Temperature 72 to 105 - Breeze NW 6 mph - Humidity 15% Contractor set form for Catch basin #ton north side of
Conchilla Court -OK to place concrete Also started excavating from the detention basin lake on south side outlet back north to the catch basins
6/21/2022
6/21/2022
JP-ONSITE STORM
I JIM PETERS
PARTIALLY
DRAIN
APPROVED
Notes:
1130 to 1300Weather - Clear - Temperature 72 to 106 - Breeze NW 2 mph - Humidity 26% Arrived at site contractor making final adjustments to
catch basin #1 and#2 OK to place Concrete tomorrowWhen checking the storm drain Pipe from the catch basin to the detention pond The contractor
has placed 30 inch HDPE pipe the complete distance - However my approved plan dated 5/16/2022 shows 265 feet for 4 - 18 inch HDPE pipe -
contractor and Kelly from Robert Green argues they had this changed back to the original plan - I have called Bryan and Amy for clarification and have
not gotten response back yet Later Amy called me and said she spoke with Bryan and it was ok for contractor/developer to change back to original plan
of only 130 inch storm drain
6/28/2022
6/28/2022
JP-ONSITE STORM
I JIM PETERS
PARTIALLY
DRAIN
APPROVED
Notes:
1030 to 1115 Weather - Clear - Temperature 85 to 111 - Breeze E 4 mph - Humidity 16% Contractor placing concrete for local depression for the 21
foot catch basin on the south side of the street and the north side 14 foot basin is formed and will be placed next weekConcrete placed is 560-C-3250
from Superior Ready Mix
6/29/2022
6/29/2022
JP-ONSITE STORM
I JIM PETERS
NOT READY
DRAIN
Notes:
1000 to 1015 Weather - Clear - Temperature 87 to 112 - Breeze WNW 5 mph - Humidity 20%No work going on until next week
Printed: Monday, 11 July, 2022 1 of 1