General Technologies and SolutionsPROPOSAL FOR:
City of La Quinta
On -Call Traffic Engineering Services
GTS.230415
GTS
City of La Quinta
Public Works Department
SUBJECT: City of La Quinta On -Call Traffic Engineering Services
Dear City of La Quinta Selection Committee:
On behalf of General Technologies and Solutions (GTS), I am pleased to submit our proposal for the City of La
Quinta On -Call Traffic Engineering Services.
GTS provides traffic engineering, transportation planning, parking, and technology solutions for public agencies
and institutions across Southern California. Our team -members have worked with several cities either directly
as staff members or on an on-call basis, and as such we understand the importance of responsiveness while
ensuring top-quality deliverables. For this on-call project, we have carefully selected a team of seasoned
professionals who bring comprehensive systems engineering and multi -modal transportation planning services
to support the City of La Quinta throughout the duration of the project and the potential tasks outlined in the RFP.
As your project manager and main point of contact, I will oversee and coordinate the activities of our proposed
team. I have served in similar capacities for various cities most recently for the City of Rancho Palos Verdes
(helping with traffic calming, intersection analysis, and plan reviews), City of Hermosa Beach (assisting with
traffic engineering designs and studies), City of Hawthorne (performing warrant analysis and feasibility studies),
City of Glendora (carrying out signal warrant analysis), City of Buena Park (peer reviewing signal synchronization
plans), and City of Irvine (assisting with adaptive signal control and probe data analysis) among several others.
I will be supported by the GTS team which includes Chaouki A. Hosn, a seasoned professional and licensed
electrical engineer with over 30 years of experience, on street lighting and EV charging infrastructure services.
Our other team members were meticulously selected to ensure responsiveness on every task order. We have
added Rock Miller, who brings over 40 years of transportation planning, design, and operations experience. As
a local resident with experience working in the City, Rock brings invaluable knowledge and understanding of
the community's unique transportation needs. He is a national expert in traffic design and safety and a voting
member of the National Committee on Uniform Traffic Control Devices. Rock has prepared many transportation
engineering and planning projects and completed controversial and complex transportation studies, including
signal timing, neighborhood traffic calming, complete streets, pedestrian and bicycle studies, and projects with
intense public opposition. GTS and Rock collaborate closely on multiple ongoing projects.
We have also included Patrick Armijo on our team to provide signal systems engineering expertise building on
his many years of experience working with state and local governments. Patrick, who has provided valuable
contributions to multiple GTS projects, is a professional engineer with 30 years of experience exclusively in traffic
signal systems operations and signal timings.
Our team's combined experience allows us to seamlessly integrate with your staff and cover all elements of
the identified traffic engineering service areas. For a summary of our recent experience related to the various
services highlighted in the RFP, please refer to the table on the following page.
All information and pricing provided in the proposal is valid for at least ninety (90) days, and any individual who
will perform work for the City is free of any conflict of interest. If you have any questions regarding our submittal,
please feel free to contact me at any time. We appreciate your consideration of the GTS team and look forward
to working with the City of La Quinta.
Sincerely,
Rawad Hani, PE, TE
1100 Quail Street, Suite 202, Newport Beach, CA 92660
(949) 988-0832 1 rawad.hani@gentecsol.com
Our Experience in A Nutshell
City of La Quinta
Our Experience in A Nutshell
Traffic Engineering Tasks
GTS has successfully completed numerous traffic signal projects,
including signal timing and new installations/modifications funded by
federal (HSIP), state (ATP), and local (CIP) programs. Our recent
experience includes the cities of San Bernardino (signal design
Traffic Signal Timing
upgrades at 40 intersections) and Cathedral City (conceptual signal
design) among several others. Our team brings best -in -class service
for signal timing, leveraging GTS' modeling expertise, Rock Miller's
expertise in signal timing, and Patrick Armijo's expertise in McCain
Systems.
GTS has conducted capacity analysis to improve traffic flow and
Capacity Analysis
alleviate congestion in various projects, most recently in the City of
Rancho Palos Verdes.
As demonstrated in the following pages, GTS has a wealth of
experience in various traffic operations including traffic signal timing
Traffic Operations
and coordination studies, traffic management and control plans,
traffic impact assessments, traffic simulation and modeling, intelligent
transportation systems (ITS), and traffic data collection and analysis.
We have provided support to numerous clients in developing
Channelization and Signing Design
channelization and signing design, including recent projects in
Riverside County and the City of Lake Elsinore.
GTS has conducted comprehensive traffic studies for diverse
Traffic Studies
projects, including those in Coachella, Imperial County, and various
jurisdictions across Southern California.
GTS has successfully implemented traffic calming techniques, having
Traffic Calming Techniques
developed traffic calming policies for the City of Rancho Palos Verdes
as part of our on-call services.
GTS has assisted multiple agencies with grant funding, including
Grant Funding
programs such as HSIP, LRSP, and ATP. Some of the cities we
have supported include the City of Buena Park and City of La Habra
Heights, among others.
Street Lighting
GTS has provided street lighting services for projects in the City of
Upland, City of Pomona, and several other locations.
GTS has conducted comprehensive safety studies and analyses for
Safety Studies and Reports
numerous cities, including recent projects for the City of Colton ET&S,
City of Torrance SSARP, and City of Glendora LRSP.
Investigating Complaints and Claims
Our team has successfully investigated complaints and claims related
to traffic issues in various on-call assignments.
WATCH Manual
GTS is well -versed in relevant manuals such as MUTCD and WATCH,
and we have consistently applied this knowledge in our projects.
Effective public engagement is a priority for GTS. We regularly
Communicating with the Public
present to traffic commissions, city council members, community
stakeholders, and other relevant groups to ensure transparent and
collaborative communication.
1 TABLE
CONTENTS
Cover Letter
Firm Background, Qualifications, and Experience
References
Fee Schedule
Complementary Services
Staffing and Project Organization
Disclosures
Acknowledgement of Insurance Requirements
Non -Collusion Affidavit
Acknowledgement of Addenda
'11
2
5
27
29
30
31
32
33
34
Firm Background, Qualifications, and Experience
General Technologies and Solutions (GTS)
Years of Experience: 20+ / Years in Business: 5+
GTS is a Limited Liability Company (S Corp) under the sole management of Rawad Hani since 2017.
Taxpayer Identification Number: FEIN #821602943
GTS provides mobility solutions for all road uses: pedestrian, bicycle, transit, auto, and freight modes. We
employ state-of-the-art technologies to provide innovation in:
GTS was established with the goal of helping public agencies leverage advanced technology in transportation.
We believe in the power of technology to effect meaningful change in our local neighborhoods and communities.
Smart cities are the future, offering unlimited opportunities for smart government technology. GTS brings together
our understanding of smart technology solutions (what's on the horizon) with community needs and goals (what's
in demand).
At GTS results matter as much as the way getting there. We support our clients throughout the whole project
lifecycle, including communicating mobility initiatives, technology goals, and strategies to stakeholders at all
levels.
GTS currently works across Southern California from Ventura County to Los Angeles County, Orange County,
San Bernardino County, Riverside County and Imperial County. GTS supports projects with various clients
including Los Angeles Metro, Coachella Valley Association of Governments (CVAG), Caltrans, and the cities
of Coachella, Cathedral City, Beaumont, Moreno Valley, San Jacinto, Perris, Hemet, Lake Elsinore, Wildomar,
Murrieta, and San Bernardino among others on transportation engineering design and planning tasks ranging
from traffic signal design and modification to signing and striping, smart city solutions, revitalization plans,
systems engineering, safety studies, traffic calming, grant applications, and data analytics among others.
GTS has served in similar capacities for various cities most recently forthe City of Rancho Palos Verdes (supporting
on traffic calming, school access, intersection analysis, plan review among others), the City of Hermosa Beach
(providing traffic engineering designs and studies), City of Hawthorne (carrying out signal warrant analysis),
and California State University Dominguez Hills (supporting on campus -wide traffic analysis and parking). Our
project manager for this on-call has also served many cities on an on-call basis; Rawad worked with the City
of Commerce (delivering on traffic analysis and preparing HSIP and ATP grant applications), City of Glendora
(carrying out signal warrant analysis), City of Buena Park (peer reviewing signal synchronization plans), City of
Irvine (assisting with adaptive signal control and probe data analysis), and City of West Hollywood (carrying out
parking studies) among several others.
GTS 155 City of La Quinta On -Call Traffic Engineering Services
Key Personnel
The following is a brief introduction to the key personnel:
Rawad Hani, PE, TE, PTP, PTOE I Role: Project Manager
Rawad is a licensed civil and traffic engineer with over 20 years of experience in traffic engineering and
transportation planning. Rawad carried out various projects similar in scope to the project under consideration
and understands the importance of communications and timely follow through the success of on-call projects. He
will be the main point of contact for this project and will manage day-to-day activities of the project team.
Chaouki A. Hosn, EE I Role: Electrical Engineer
Chaouki is a registered electrical engineer with over 34 years of experience working with the private and public
sectors, specializing in high and low voltage design for infrastructure projects. Chaouki will lead on any EV
charging and street lighting tasks as needed.
Rock Miller, PE, TE, PTOE I Role: Signal Timing, Transportation Planning & Outreach
Rock is a registered civil and traffic engineer with more than 40 years of transportation planning, design, and
operations experience. Rock will build on his expertise in signal timing and transportation planning to advise on
the pedestrian, bicycle, and safety planning and design aspects, and will support in reviewing final plans as well
as public engagement/outreach.
Patrick Armijo, PE, PEng I Role: Signal Operations
Patrick is a professional engineer with 30 years of experience exclusively in traffic signal systems, operations,
and signal timings. Patrick will provide signal systems engineering expertise building on his many years of
experience working with state and local governments.
Ariel Godwin, AICP I Role: Senior Planner
Ariel is a certified Urban and Regional Planner with over 14 years of experience in community planning,
transportation/mobility planning, design, GIS, and project management. Ariel has worked on a wide variety of
projects from Complete Streets policy development to congestion management strategies, and will lead on traffic
analysis tasks.
Rudy Garcia, EIT I Role: Traffic Analysis
Rudy is an experienced Transportation Engineer with more than 10 years of experience in the design and studies
of transportation systems, specializing in traffic impact studies, parking, and feasibility studies. Rudy will support
on traffic analysis tasks.
Cassandra Garcia, EIT I Role: Design Engineer
Cassandra will provide traffic engineering and design services ranging from signal designs to signing and striping,
traffic control plans, and street lighting.
An organizational chart and one-page resume of each of our key team members are included in this proposal.
GTS 16 City of La Quinta On -Call Traffic Engineering Services
RAWAD HANIPE, TE, PTP, PTOE
Ar
PROJECT MANAGER
Rawad is a traffic engineer and transportation planner with over 20 years
of experience. He specializes in traffic engineering, parking analysis,
ourPROFILE
demand modeling, and technology applications. Rawad has managed
engineering design projects in the US and internationally where he advised
public, private, and institutional clients. His recent experience includes
assisting local governments across Southern California with transportation
plans, traffic studies, parking management strategies, and signal and
EDUCATION
street lighting designs. His on-call project experience includes the cities
• BE Civil Engineering,
of Hermosa Beach, Irvine, Buena Park, Commerce, Santa Monica, and
American University
Glendora among others. Rawad understands the importance of striking
• MS Civil Engineering,
the right balance between engineering (mobility and safety) and planning
American University
(livability and sustainability) considerations. He has worked on context -
sensitive design projects and has helped planning and transportation
agencies achieve effective solutions.
EXPERIENCE
• City of Rancho Palos Verdes Transportation and Traffic Engineering On -
REGISTRATIONS
Call, Rancho Palos Verdes, CA
• Civil Engineer in CA,
• Hermosa Beach On -Call Traffic Control Plans and Striping, City of
WA, and FL
Hermosa Beach On -Call
• Traffic Engineer in CA
• City of Commerce MixMaster Analysis and Alternatives Design, City of
• PTOE - Professional
Commerce On -Call
Traffic Operations Engineer
-Foothill Blvd and Oak Tree Dr Warrant Analysis, City of Glendora On -Call
• PTP - Professional
• Artesia Blvd and Knott Ave Signal Synchronization Review, City of Buena
Transportation Planner
Park On -Call
• RSP1 - Road Safety
• Date Palm and Victoria Street Conceptual Design, Cathedral City, CA
Professional 1
• Seaton Avenue and Perry Street Traffic Design, Riverside County
• Ramona Expressway and Brennan Avenue Traffic Design Services,
Riverside County
• Traffic Signal Modification Design of Palm Avenue and W Esplanade
Avenue, San Jacinto/Hemet, CA
AREAS OF EXPERTISE
• Wildomar Crossroads Traffic Engineering Design Services, City of
Wildomar
• Traffic Engineering
• Traffic Signal Modification Design Central Ave (SR 74) and Ardenwood
• Parking Analysis
Way, City of Lake Elsinore
• City of La Habra Heights Traffic Calming Analysis
• Transportation Planning
. City of Norwalk Rosecrans Ave and San Antonio Dr Traffic Control Plans
• Transportation Technology
• City of Commerce ATP and HSIP Grant Applications, Commerce, CA
Applications
• 20th Street Pedestrian and Bicycle Connection (ATP), City of Santa
Monica/Caltrans
• San Bernardino Traffic Signal Upgrade PS&E Services (HSIP), San
Bernardino, CA
• Carson Dominguez Channel and Figueroa St/Victoria St Intersection
(HSIP), Carson, CA
• Various LRSP Grant Applications, South Pasadena, CA; Buena Park, CA;
Hidden Hills, CA
• Sun Valley Signal Designs and Street Lighting, Los Angeles, CA
• 8888 Washington Blvd Signing, Striping, and Street Lighting, Culver City, CA
EDUCATION
• BS Electrical Engineering,
University of Washington,
(Seattle, WA)
REGISTRATIONS
• Electrical Engineer in CA
AREAS OF EXPERTISE
• Street Lighting
• Power and Lighting
Layout Design
• EV Charging Stations
• Lighting Photometric
• Dry Utility Services
• Design Management
CHAOUKI A. HOSNEE
9 -
ELECTRICAL ENGINEER
PROFILE
Chaouki is a California registered Electrical Engineer, specializing in high
and low voltage design for infrastructure projects. His experience includes
street lighting design, lighting photometric, communication infrastructure,
dry utility services as well as the electrical design for parking lots lighting
design. He has designed several electric vehicle charging stations as well
as electrical infrastructure designs for commercial, industrial facilities, and
residential facilities. Chaouki has over 34 years of experience working with
the private and public sectors mostly with the City of Los Angeles Harbor
Department and as such he understands first hand the demands placed
on the local agency staff. He works collaboratively with utility owners and
local agencies to ensure on-going communications and timely delivery of
projects.
Chaouki has over 34 years of experience working with the private and public
sectors mostly with the City of Los Angeles Harbor Department and as such
he understands first-hand the demands placed on the local agency staff. He
works collaboratively with utility owners and local agencies to ensure on-
going communications and timely delivery of projects.
EXPERIENCE
• Emergency Shelter Parking Lot, Pomona, CA — Design Manager: Light
poles layout, conduit and wires, communication, lighting photometric, load
calculations, specifications, and cost estimate.
• Santa Monica 20th Street Connection, Santa Monica, CA — Electrical
Design Manager: Laying out pedestrian and bicycle lighting along with
complete infrastructure design, new SCE services, specifications and cost
estimate. Project is in Caltrans right of way and involved working closely
with Caltrans.
• Palm Ave Street Lighting Design, Upland, CA — Design Manager: street
lighting improvement along Palm Ave between West 9th Street and Alpine
Street in compliance with ANSI/IES RFP -8-14 roadway lighting, which
includes street light poles layout, conduit and wires, communication, lighting
photometric, load calculations, specifications, and cost estimate.
• Melrose Complete Street Design, West Hollywood, CA— Design Manager:
(12) EV charging level II stations along streets, which includes power
and communication infrastructures, new SCE services and charge point
platform for billing. Advising on smart pole designs.
• Lincoln and Arlington Street Lighting and Undergrounding, Torrance,
CA — Design Manager: utility pole relocations, undergrounding, new SCE
services, load calculations.
• Navy Way Street Lighting, Port of Los Angeles — Design Engineer: lighting
and undergrounding design forthe 3 -mile roadway that included photometric,
utility coordination, light poles layout, load calculations, specifications, and
cost estimate. LED was later installed.
• Various Dry utility services, SCE rule 20B, parking lot lighting, and
complete electrical infrastructure for various development projects across
Southern California (Pasadena, Colton, Carlsbad, San Clemente, Dana
Point, Newport Beach, San Diego, Long Beach among others.
EDUCATION
• MS Civil Engineering,
UC Davis
• BS Civil Engineering,
UC Davis
REGISTRATIONS
• Civil Engineer in CA and HI
• Traffic Engineer in CA
• PTOE - Professional
Traffic Operations Engineer
MEMBERSHIPS
• Voting Member, National
Committee on Uniform
ROCK E. MILLERPE, TE
SIGNAL TIMING, TRANSPORTATION & OUTREACH
PROFILE
Rock is a registered Civil Engineer and Traffic Engineer in the State of
1 California with more than 40 years of transportation planning, design,
and operations experience. He is an expert in the latest capabilities and
requirements available and expected from cities and municipal governments.
For more than 25 years, Rock has been a consultant at the senior or
principal level in the field of traffic engineering, traffic safety, and circulation
design. He also has 10 years of public agency experience serving as City
Traffic Engineer for Costa Mesa and staff traffic engineer with the County
of Orange.
Rock has completed awidevarietyof unique transportation projects, including
traffic signals, signing and striping, street lighting, work site traffic control,
traffic impact analysis, and the design of street and highway improvements.
He has also prepared many transportation policy plans and completed
controversial and complex transportation studies, including neighborhood
traffic calming projects, complete streets, pedestrian and bicycle studies,
projects anticipating litigation by another public agency, and projects with
intense public opposition. Rock is a national expert in the traffic design and
safety for walking and urban bicycling infrastructure. He has frequently been
an invited speaker to regional and national conferences and committees on
many topics, including pedestrian circulation, innovative bikeway design,
traffic calming, and transportation policy. Rock served as International
President of the 15,000 member Institute of Transportation Engineers (ITE)
in 2012. He is a Professional Engineer (Civil) and Professional Engineer
(Traffic) in the State of California and a Certified Professional Traffic
Operations Engineer by the Institute of Transportation Engineers.
Traffic Control Devices EXPERIENCE
• International President, Rock has extensive experience in leading neighborhood traffic management
plans. He has led such studies for over ten communities.His role is key as
2012, Institute of the leader of public outreach efforts for this type of studies, taking advantage
Transportation Engineers of his effective presentation style in public workshops and events. Some of
• Member, Association of the larger studies of this type are highlighted below and a more extensive
Pedestrian and Bicycle resume can be provided upon request:
Professionals
• City of La Quinta Roundabout Designs
• Member, American Society
• CV Link Multi -Purpose Trail, Coachella Valley, California
of Civil Engineers
• Rancho Mirage Bikeway Design Assistance, Rancho Mirage California
• Past Section and District
• Newport Heights Neighborhood Traffic Management Plan, Newport
President, Institute of
Beach, California
• Los Alamitos Neighborhood Traffic Plan, Los Alamitos CA
Transportation Engineers
• Town of Piru Traffic Management Plan, Ventura County, CA
• Fellow, Institute of
• Fillmore River Street Traffic Circles, Fillmore, California
Transportation Engineers
• Berkeley Street Traffic Calming Project, Santa Monica, CA
• Vista Avenue Bicycle Boulevard, Long Beach, California
EDUCATION
• BS Civil Engineering,
California State University,
Sacramento
REGISTRATIONS
• Professional Engineer in
WA and Alberta, Canada
AFFILIATIONS
• Institute of Transportation
Engineers
• International Municipal
Signals Association
PATRICK ARMIJOPE, PEng
SIGNAL OPERATIONS EXPERT
PROFILE
Patrick Armijo is a Professional Engineer with about 30 years of experience
in the public and private sectors. His experience includes: municipal
infrastructure management; supervising traffic signal and railroad signal
operations engineering staff and signal maintenance crews; traffic signal
timing; traffic signal design; traffic signal construction; ITS operations; TMC
operations and design; highway design; bridge and roadway construction;
railway crossing signal operations; community lighting; capital Improvement
program budgeting; and writing requests for proposals.
EXPERIENCE
• Light Rail Signals Supervisor at Santa Clara Valley Transportation
Authority: Plan, schedule, and supervise inspections, maintenance, and
repair of signaling, crossing equipment, and rail safety systems. Conduct
safety training and monitor crew performance to ensure safe work practices,
procedures and compliance with FRA and CPUC regulations. Evaluate
traffic signal RR preemption and crossing safety. Advise VTA on intelligent
transportation systems and transit system priority.
• Technical Director, Intelligent Transportation Systems at Western Pacific
Signal, San Leandro, California: Advanced Traffic Management System
client liaison, advanced technical support, training, and proposal director.
Projects included adaptive traffic signal operations, transit signal priority,
connected vehicle research, railroad crossing signal preemption, and traffic
management center design.
• Project Manager at ADVANTEC Consulting Engineers, Irvine, California:
Traffic signal timing, traffic signal synchronization and railroad preemption
signal timing: Orange County (OCTA), San Bernardino Association of
Governments (SANBAG), Metropolitan Transportation Commission (MTC),
Caltrans and City of Glendale.
• Traffic Signals/Railroad Signals Manager at City of Lethbridge, Alberta,
Canada: Managed and supervised the traffic signal department for the City
of Lethbridge. The staff included a traffic signal operations engineer, five
traffic signal/railroad signal electricians. Served as Project Manager on
new traffic signal designs and construction projects. Managed traffic signal
synchronization projects. Supervised and approved upgrades to traffic
signal infrastructure such as signal interconnect, cabinets, controllers,
vehicle detection systems, emergency vehicle preemption systems, speed
enforcement/red light running camera systems, and Battery Back Up units.
• Traffic Signals Operations Engineer at Washington State Department
of Transportation: Managed traffic signal operations for over 250 state,
county, and municipal traffic signals for 18 years. Developed traffic signal
timing and signal coordination plans. Conducted traffic accident analysis
and recommended safety mitigation measures. Experience with transit
system priority programming and traffic signal railroad preemption timing
development.
ARIEL GODWINAICP
V�.
SENIOR PLANNER
''
PROFILE
Ariel is a transportation planner with over 14 years of experience in
planning, design, and project management. Throughout a career focused
on multimodal planning and transportation safety, he has worked on a wide
variety of projects, from Complete Streets policy development to pedestrian
and bicycle plans to congestion management strategies. His recent
EDUCATION
experience includes assisting local governments with creative solutions to
• Master of City and Regional
address unique traffic safety issues, as well as advising on regional transit
Planning, Ohio State
systems, pedestrian connectivity, and shared parking.
University
• BA, Grinnell College, Double
EXPERIENCE
major in Economics and
• City of Rancho Palos Verdes, Transportation and Traffic Engineering On -
German
Call (2022)
MEMBERSHIPS
• California State University Dominguez Hills, Transportation Planning and
• AICP (American Institute of
Engineering Support Services (2022)
Certified Planners)
• City of Douglas, Georgia Sidewalk Master Plan (2020, Recipient of the
NADO Impact Award)
AWARDS
• Douglas, Georgia Urban Redevelopment Plan (2020)
• Georgia Planning Service
• Valdosta -Lowndes Complete Streets Policy (2020)
Award — for serving as
• City of Nicholls, Georgia Zoning Code (2019, Recipient of the NADO
Professional Development
Impact Award)
Officer for the Georgia
• Downtown Tifton, Georgia Pedestrian & Bicycle Connectivity Plan (2018,
Chapter of the American
Recipient of the NADO Innovation Award)
Planning Association from
• Fitzgerald, Georgia Bicycle Plan (2018)
2018 to 2021.
• Valdosta -Lowndes Metropolitan Planning Organization Annual Crash
• NADO Impact Award — City
Reports (2017-2020)
of Douglas Sidewalk Master
• Local Comprehensive Plans (2015-2020)
Plan, 2020.
• Local Hazard Mitigation Plans (2015-2020)
• Polk County, Florida Broadband Plan (2012; Recipient of the NARC
• NADO Impact Award City
Major Metro Achievement Award, NADO Innovation Award, and FPZA
of Nicholls Zoning Code,
Outstanding Infrastructure Plan Award)
2019.
• Mid -Ohio Regional Planning Commission Complete Streets Policy (2010)
• NADO Innovation Award —
Tifton Downtown Pedestrian
PUBLICATIONS
Connectivity Plan, 2018.
• Godwin, Ariel and Anne M. Price. 2016. "Bicycling and Walking in the
• NARC Major Metro
Southeast USA: Why is it Rare and Risky?" Journal of Transport & Health
Achievement Award —
(3): 26-37.
Florida Broadband Planning
• Godwin, Ariel and Anne M. Price. 2016. "Bicyclists on Sidewalks: Why
Project, 2015.
They're Not Going Away and What We Can Do About It." Planetizen feature
• NADO Innovation Award —
article. http://www.planetizen.com/node/84910.
Florida Broadband Planning
• Godwin, Ariel and Anne M. Price. 2012. "Mapping Transportation
Project, 2014.
and Health in the United States" Planetizen feature article. http://www.
• FPZA Outstanding
planetizen.com/node/53728.
Infrastructure Plan Award —
• Godwin, Ariel. 2012. "Are Amoeba -Shaped Cities More Likely to
Broadband Planning Project,
Go Bankrupt?" Planetizen feature article. http://www.planetizen.com/
2013.
node/58658.
Cassandra provides traffic engineering and design services ranging from signal designs to signing and striping,
traffic control plans, and street lighting. Her recent experience includes the collection of data and creation of
design plans for resurfacing projects, bike path projects, and traffic signal upgrade projects. Cassandra strives to
improve communities through implementation of safe and effective methods of transportation.
EXPERIENCE
• San Bernardino Traffic Signal Upgrades, San Bernardino, CA
Created plans for the relocation, replacement and/or upgrade of traffic signal equipment including vehicle
heads, pedestrian heads, and pedestrian push buttons for multiple intersections in the San Bernardino region
• Traffic Signal Design of Figueroa St and Victoria St / 190th St, Carson, CA
Performed a field visit and prepared plans for the installation of poles, curbs, video detection cameras and
other traffic signal equipment at an intersection within the City of Carson.
• Dominguez Channel Bicycle Design, Carson, CA
Performed a field visit along multiple corridors for the purpose of implementing bike routes and bike lanes to
join disconnected portions of the Dominguez Channel Bike Path. Created signing and striping plans for all
connecting sections along the channel and paved street roads.
• Burbank Resurfacing Program - Signing & Striping Restoration and Loop Replacement Plans, Burbank, CA
Worked on creating signing and striping plans as well as loop replacement plans for multiple corridors pending
resurfacing within the City of Burbank.
• Eastman Ave/Medford Project, Los Angeles, CA
Performed a field visit and provided notes for two signalized intersections in the City of Los Angeles.
Rudy is an experienced Transportation Engineer with over 10 years of experience in the design and studies of
transportation systems. His experience includes traffic impact studies, parking, and feasibility studies. He has
also prepared various traffic signal design plans, traffic handling and detour plans, conceptual drawings for
mitigation and circulation studies. Rudy has working experience with various local and state design and studies
guidelines and he worked with the latest versions of AutoCAD, Synchro, and HCS, software.
EXPERIENCE
• Glendale Community College District Transportation Impact Analysis, Glendale, CA
• California State University Dominguez Hills Parking Needs Assessment, Carson, CA
• San Bernardino Traffic Signal Upgrades, San Bernardino, CA
• Notre Dame High School Traffic Impact Study, Los Angeles, CA
• Buena Park On -Call signal timing peer review of documents for the Artesia Blvd corridor.
• Garden Grove Unified School District conceptual signing and striping
• City of Commerce: provided support for the HSIP and ATP grant applications.
• Pasadena Commercial Vehicle Loading Zone Analysis, Pasadena,CA
• Alternatives Parking Assessment and Evaluation for California State University, Fullerton
• TRAFFIX Model Update Integrated with Microsoft Access Database, Beverly Hills, CA
• Mobility Plan GIS Data Creation, Santa Ana, CA
• Foothill Blvd Master Plan, Claremont, CA
• Various Traffic Impact Studies for mixed use and industrial developments in Orange County
Similar Work
City of Rancho Palos Verdes Transportation and Traffic Engineering On -Call
GTS is providing transportation and traffic engineering on-call services to the City of Rancho Palos Verdes.
GTS worked with the City on the traffic signal design review at the intersection of Palos Verdes Drive E &
Palos Verdes Drive S. The scope includes presenting recommendations to enhance the aesthetics at said
location by presenting features that better blend with the surroundings.
GTS also assisted with the traffic engineering and circulation analysis for several schools in Rancho Palos
Verdes (Silver Spur Elementary, Soleado Elementary, Ridgecrest Intermediate, and Vista Grande Elementary).
Our scope of work included working jointly with the City and the schools to confirm the current challenges through
site observations of the drop-off and pick-up areas and surrounding streets, analysis of the prevailing conditions
and providing recommendations for improvement, and documentation of findings. The results of the analysis will
be consolidated in single circulation plan/flyer that can be distributed to families and staff.
Contracting Agency: City of Rancho Palos Verdes
Reference Information: Ramzi Awwad I Public Works Director I rawwad@rpvca.gov 1310.544.5275
GTS has done an excellent job for the City of Rancho Palos Verdes. They have always responded
to our needs in a timely manner. Their analyses are rooted in traffic engineering best practices
while also being practical. I recommend GTS to any public works department.
- Ramzi Awwad, Public Works Director (City of Rancho Palos Verdes)
City of Hawthorne On -Call, Warrant Analysis and Feasibility Studies
GTS supported the City of Hawthorne (as part of the on-call) in carrying out traffic signal warrants studies at three
intersections of Freeman Ave & 118th St, 126th St & Birch Ave, and Kornblum Ave & 120th St. The purpose
of the analysis was to determine whether a traffic signal should be installed at the currently stop -controlled
intersections based on the analysis of the traffic signal warrants contained in the California Manual of Uniform
Traffic Control Devices (CA MUTCD). GTS carried out site visits, data collection, warrant analysis, feasibility
studies, and technical documentation.
Contracting Agency: City of Hawthorne
Reference Information: Alan Leung I Director of Public Works I aleung@cityofhawthorne.org 1310.349.2980
Encanto Residential Development Traffic Impact Analysis, City of Coachella
The purpose of this Traffic Impact Analysis (TIA) is to identify potential traffic -related impacts associated with the
Encanto Residential development located in the City of Coachella. The project proposes the construction of 119
residential lots including a community park on a 20 -acre vacant site.
This TIA is prepared consistent with the City's Traffic Impact Analysis Preparation Guide to evaluate the traffic
and circulation impacts of the proposed project. GTS documented the existing traffic conditions and future
traffic conditions With and Without project and determined the additional circulation system features and system
management actions needed to achieve the City's levels of service requirements with implementation of the
proposed project. GTS is also assisting with the VMT analysis using the RIVCOM model.
Client: Integrated Engineering Group
Reference Information: George Ghossain I Principal Engineer I george@intenggroup.com 1951.239.1546
GTS 113 City of La Quinta On -Call Traffic Engineering Services
Ramona Expressway and Brennan Avenue Traffic Signal and Signing and Striping, Riverside County
GTS is providing conceptual design services for an industrial development at the northeast corner of Ramona
Expressway and Brennan Ave in the City of Perris in Riverside County. The project includes a traffic signal
design at the intersection of Ramona Expressway and Brennan Road to accommodate the proposed street
improvement serving the project site, a signing and striping plan illustrating signal requirements and the frontage
of the project site, and coordination with City and County staff. Prior to plan preparation, GTS conducted research
of as -built and other available data, and performed a field review to prepare the base plan.
Client: EPD Solutions
Reference Information: Abby Pal I Project Manager I abby@epdsolutions.com 1412.636.2713
Seaton Avenue and Perry Street Signing and Striping, Riverside County
GTS is providing traffic engineering design services along Seaton Avenue in Riverside County. GTS is carrying
out various safety and operational upgrades as part of this design. This project will accommodate the Seaton
road widening from 2 to 4 lanes and provide safety improvements for road users and pedestrians.
The design services include working with the County.
Client: NLF DP Seaton, LLC
Reference Information: Ben Horning I Director of Development I benh@dedeauxproperties.com
Traffic Signal Modification Design of Palm Avenue and W Esplanade Avenue, San Jacinto/Hemet, CA
GTS is preparing the traffic signal modification for the intersection of Palm Avenue and W Esplanade Avenue
in the shared jurisdiction of the City of San Jacinto and City of Hemet. The traffic signal plan will accommodate
the proposed right turn phase overlap as well as signage for restricting right turns on red. The plan will depict
all proposed traffic signal equipment and loop detectors and reference any existing, proposed, and (to be)
removed pavement delineation, traffic signage, safety lighting, and utilities to accommodate the proposed traffic
signal design modification and installation. The plan will be designed at a scale of 1 "=20' per the City standards,
Caltrans Standard Plans, and other agreed-upon engineering standards and requirements.
Client: Camfield Partners, LLC
Reference Information: Dawn Martinez I Executive Assistant I dmartinez@camfieldpartners.com 1213.703.2028
Date Palm and Victoria Street Conceptual Design, Cathedral City, CA
As part of the conditions of approval for a new gas station at the southeast corner of the Date Palm Drive
and Victoria Drive intersection, GTS provided conceptual design support services for the project team. GTS
reviewed the proposed site plans, previous traffic impact study report, as-builts, the City's approval conditions,
and other relevant documents. A turning templates (Auto -Turn) analysis of a fuel truck accessing the site was
also developed. Based on the initial findings, two concepts were proposed for the project frontage area that
included a signal modification and widening of the Victoria Dr. The conceptual plans and costs for the two options
were developed and presented along with the pros and cons of each concept.
Client: The Altum Group
Reference Information: Rich Malacoff I Project Manager I rich.malacoff@thealtumgroup.com 1760.346.4750
CVAG ITS Master Plan Peer Review Services
GTS assisted with a third party review of the CVAG ITS Plan with a focus on the centralized Traffic Management
Center, roadway management strategies, and emerging mobility technologies and trends. Our review, which
included the concept of operations as well as the systems engineering plan provided valuable feedback on
integrating 5G as an enabler of Smart City applications and elaborating on the role of public -private -partnerships
as it relates to emerging technologies and trends.
Client: Fehr & Peers
Reference Information: Josh Peterman I Project Manager I j.peterman@fehrandpeers.com 1925.357.3368
Xenia Multi -Family Residential Project Peer Review, Beaumont, CA
GTS conducted a peer review of the Initial Study (IS) for the Xenia Multi -Family Residential Project to ensure
that the technical report is adequate for supporting the analysis, findings, and conclusions of the Traffic/
GTS 114 City of La Quinta On -Call Traffic Engineering Services
Transportation section of the environmental document. The project consists of 16 apartment buildings, totaling
192 multi -family residential dwelling units, on approximately 10.93 acres. The IS was evaluated in accordance
with CEQA guidelines. The City of Beaumont will use the IS to determine which CEQA document is appropriate
for the project.
Client: Chambers Group
Reference Information: Eunice Bagwan I Project Manager/Environmental Planner I ebagwan@
chambersgroupinc.com 1949.261.5414 x7325
Nature's Medicines Traffic Impact Analysis, Moreno Valley, CA
The purpose of this Traffic Impact Analysis (TIA) is to identify potential traffic -related impacts associated with
Nature's Medicines development located in the City of Moreno Valley. The project proposes two phases with the
first phase consisting of a 4,275 sq. ft. dispensary and the second phase consisting of a 5,625 sq. ft. medical office.
This TIA has been prepared consistent with the City's Traffic Impact Analysis Preparation Guide to evaluate the
traffic and circulation impacts of the proposed project. GTS documented the existing traffic conditions and future
traffic conditions corresponding to Phase 1 and Phase 2 With and Without project conditions Project conditions
and determined the additional circulation system features and system management actions needed to achieve
the City's levels of service requirements with implementation of the proposed project.
Client: Taro LLC
Reference Information: Rajan Patel I Project Manager I rajankp2@gmail.com
City of San Bernardino Traffic Signal Upgrade PS&E Services
GTS provided traffic engineering signal upgrade services for 40 of the 224 signalized intersections in the City of
San Bernardino where various safety, operational, and accessibility upgrades are required. This HSIP-funded
project will replace or install new equipment to the existing traffic signal system which include traffic signal head
improvements, pedestrian signal head improvements, and pedestrian pushbutton improvements among others.
Contracting Agency: City of San Bernardino
Reference Information: Azzam Jabsheh I City Traffic Engineer I jabsheh_az@sbcity.org 1909.384.7272
City of Glendora Local Road Safety Plan (LRSP)
GTS is assisting the City of Glendora in developing the City's Local Road Safety Plan (LRSP). The project
includes coordinating with City staff to develop a vision, goals, and objectives for the LRSP which are aligned with
the City's vision, documenting the existing safety efforts followed by analyzing the safety data, and conducting a
field review. GTS is developing both engineering and non -engineering countermeasures to address the identified
collision patterns and safety emphasis areas based on collision data analysis and stakeholder input. The results
of these tasks will be incorporated into an Administrative Draft Local Road Safety Plan for review by the City
followed by a finalized Local Roadway Safety Plan Report.
Contracting Agency: City of Glendora
Reference Information: Maliha Fatima Ansari I Principal Engineer I mansari@cityofglendora.org 1626.914.8294
Alpine Street, Vernon Drive and Palm Avenue Street Lighting, Upland, CA
GTS prepared professional engineering design services for construction plans, specifications and estimates
as required for removal of existing street lights and replacement with new concrete poles, mast arms and
luminaires. The project included voltage drop electrical calculations, conduit fill, proper lighting circuits, conduit
routing, breakers, lighting controls and groundings, electrical notes and diagrams on the design plans, and SCE
coordination for proposed power services/meter pedestal, in conformance with City of Upland's requirements.
Client: Kabbara Engineering
Reference Information: Leah Kabbara I Project Manager I leah@kabbara.net 1714.744.9400
Seneca Villas Residential Development VMT Analysis, Victorville, CA
The Seneca Villas Residential Development Project in the City of Victorville proposes the development of 310 -
unit multifamily housing in one phase. GTS utilized the City of Victorville VMT Analysis Guidelines to conduct
the VMT analysis for the project. The VMT analysis was based on the San Bernardino County Transportation
Authority (SBCTA) Transportation Analysis Model known as SBTAM.
GTS 115 City of La Quinta On -Call Traffic Engineering Services
The project evaluated the VMT per capita and compared it with the City's General Plan Buildout VMT per capita
to evaluate the project impact for the opening and the horizon years.
Client: David Evans and Associates, Inc.
Reference Information: James M. Daisa I Project Manager I jim.daisa@deainc.com 1909.912.7304
City of Hermosa Beach Transportation Planning and Traffic Engineering On -Call
GTS is providing transportation planning and traffic engineering on-call services to the City of Hermosa Beach.
We assisted the City in its COVID-19 relief efforts to support small businesses by providing traffic engineering
design services.
GTS produced plans, specifications and estimates (PS&E) for road re -purposing and installing Class II bicycle
facilities in the downtown area (Hermosa Ave and Pier Ave) to provide space for walking, biking, and outdoor
dining while ensuring social distancing. At the time of this proposal we have provided the design of over seventeen
parklets and carried out the traffic engineering feasibility study of closing a right turn slip lane.
Contracting Agency: City of Hermosa Beach
Reference Information: Douglas Krauss I Project Manager I dkrauss@hermosabeach.gov 1310.750.3603
GTS have been an absolute pleasure to work with. They have been extremely responsive,
especially during the difficult period of the pandemic. They are a very knowledgeable and
capable consulting firm and have proven to be very effective. They came through during
a difficult time to assist our city with a very challenging project and has continued to be a
tremendous resource and partner in this and other projects.
- Douglas Krauss, Project Manager (City of Hermosa Beach)
I
Burbank Resurfacing Program - Signing & Striping Restoration and Loop Replacement Plans
GTS supported the City of Burbank with the Phase X resurfacing program (for Zones 9, 10, 11, & 12) which
includes over 22 roadway miles. GTS utilized aerial imagery and performed field review prior to the base and
design preparation. The striping restoration utilized (when available) as -built and roadway rehabilitation plans
and included field reviews for lane widths, locations of speed bumps, fire hydrants, etc. The City is leveraging the
roadway resurfacing program to add bike lanes as well as crosswalks at various locations. GTS also prepared
the loop restoration for 18 signalized intersections that were impacted by the road rehabilitation.
Contracting Agency: City of Burbank
Reference Information: Omar Moheize I Principal Civil Engineer I omoheize@burbankca.gov 1818.238.3943
City of Carson Traffic Signal Design of Figueroa St and Victoria St / 190th Street
GTS provided traffic engineering signal upgrade services for the signalized intersection of Figueroa St and
Victoria St / 190th St in the City of Carson. GTS carried out various safety, operational, and accessibility upgrades
as part of this design. This HSIP-funded project will provide protected left -turn signal phases at all legs of the
subject intersection, safety improvements for road users and pedestrians, and ADA -compliant curb ramp design.
The design services included coordination with the City of Los Angeles (which has shared jurisdiction at the
intersection) as well as with Caltrans for funding administration purposes.
Contracting Agency: City of Carson
Reference Information: Ryan Kim I Traffic Engineer I rkim@carson.ca.us 1310.952.1700 x1815
GTS 116 City of La Quinta On -Call Traffic Engineering Services
Santa Monica 20th Street Connection
GTS carried out the traffic engineering tasks for this City of Santa Monica project that is closing a key bike and
pedestrian network gap and serving as critical linkage between the Michigan Avenue Neighborhood Greenway
(MANGO) and Bergamot Expo Station.
The project posed the challenge of designing as closely as possible to Caltrans Highway Design Manual
standards with limited space available for improvements. GTS worked closely and tirelessly with Caltrans and
the City on developing and testing various alternatives that are acceptable to both agencies. GTS performed the
traffic analysis, truck turning analysis, traffic signal design, signing and striping design, and traffic control plans.
GTS also designed the street lighting and emergency blue light phone services over a 4G network. Prior to this
project our team members also assisted the City with video detection standardization and the design of the
electronic parking guidance for the downtown area.
Contracting Agency: City of Santa Monica
Reference Information: Joseph SanClemente I Principal Transportation Planner I joseph.sanclemente@smgov.
net 1310.458.2204
City of Carson Dominguez Channel Bicycle Design
GTS provided traffic engineering design services for both Phase I and Phase II of the City of Carson bicycle
design project. GTS services included supporting the conceptual design elements of the project as well as the
design development to produce the final plans, specifications, and estimates. GTS carried out the design of
signing and striping as well as traffic signal designs and or modifications. The design is per the requirements of
the California Manual of Uniform Traffic Design as well as the Highway Design Manual. The design is geared
to address safety, operational, and accessibility considerations with a special focus on vulnerable modes of
transportation.
Contracting Agency: City of Carson
Reference Information: Ryan Kim I Traffic Engineer I rkim@carson.ca.us 1310.952.1700 x1815
City of Norwalk Rosecrans Avenue and San Antonio Drive Traffic Control Plans
GTS prepared the traffic control plans for the fiber optic construction works in the southern sidewalk of Rosecrans
Ave between Bloomfield Ave and Firestone Blvd. and the median of San Antonio Dr between Olive St and Metro
Center Dr. The plans showed the necessary street improvements, construction areas, and proposed temporary
traffic control devices per the CA MUTCD requirements. The plan set included the Caltrans Standard TCP Plans,
standard City traffic notes, sidewalk closures and signage, parking restrictions, etc. at 1 "=40' scale.
Contracting Agency: City of Norwalk
Reference Information: Raymond Velasco I Principal Engineer I rvelasco@norwalkca.gov 1562.929.5723
City of Colton Engineering and Traffic Survey
GTS is supporting the City of Colton by recommending the establishment and renewal of valid posted speed
limits for forty-four (44) street segments on twenty-seven (27) citywide streets within the City. GTS is conducting
a comprehensive Engineering and Traffic Survey (E&TS) to determine these results. This E&TS prepared for the
City as a record of existing conditions on the selected roadways provides the City with a basis for updating and
validating its currently posted speed limits on citywide streets. The GTS study includes an analysis of prevailing
speeds, as determined by traffic engineering measurements; an analysis of collision records for the most recent
available two-year period; and other highway, traffic, and roadside conditions not readily apparent to the driver.
Contracting Agency: City of Colton
Reference Information: Victor Ortiz I Assistant PW Director/City Engineer I vortiz@coltonca.gov 1909.514.4210
GTS I 1 7 City of La Quinta On -Call Traffic Engineering Services
Project Understanding and Approach
General Approach
Our general project approach to on-call traffic engineering and studies encompasses three components:
i. Research of Relevant Background Information: This includes items such as previous studies, records of prior
approvals or resolutions, conditions of approval that may be relevant to the project under consideration, etc.
ii. Application of our Engineering and Planning Knowledge: To discern prospective issues including controversial
issues and providing notice to the City staff. Our knowledge is based on the collective experience of our team
members coupled with the relevant background information. In delivering our services we build on:
a) Policies and Procedures at the Local, Regional, State, and Federal levels: Which include regulations and
guidelines impacting the municipal traffic engineering process from the City code to elements like SB 1,
SB743, the regional Green House Gas/SCS policies and plans, MUTCD, and the Complete Streets guidelines
among others.
b) Emerging Trends in Traffic Engineering Practice and Technology: Which includes elements such as Vision
Zero, concepts of Complete Streets, and Active Transportation considerations. Similarly, changes in the
MUTCD and the new Highway Safety Manual affect the practice of municipal transportation traffic engineering.
iii. Effective and Timely Communication: Whereby we expect ongoing interaction with City staff during each task
order where progress can be monitored. This could include weekly touchpoints to discuss the project and ensure
all parties are up to date on project progress. We anticipate that informal check in meetings will occur regularly.
Project Management Approach
GTS provides the capabilities needed to complete high-priority transportation projects or provide solid
recommendations to City staff and elected officials on how to address particular transportation issues. We
understand that communication, responsiveness, efficiency, and collaboration are critical to our successful
partnerships with local municipalities.
Rawad Hani will be City's main point of contact and will manage the task orders and staff to execute the required
tasks adequately and efficiently. His responsibilities include leading the project management, scoping, and
coordinating with experts from the GTS team among others. Upon receiving a task order request, our response
proposal will include the following:
• A description of the services to be provided (scope and methodology)
• The name and position of each person to be assigned to perform the services
• A schedule with the milestones
• The estimated number of hours and cost to complete the services
Upon notice to proceed and depending on the specific task order, a kick-off meeting may be required to coordinate
the specifics of our project approach and work tasks to ensure we meet the overall goals and objectives. This
meeting will be used to establish the goals and objectives for the task order, refine the approach and/or schedule,
establish project team communication and stakeholder coordination aspects, discuss data or design requirements,
and confirm deliverables and milestones. All project deliverables will be provided to the City in draft format, with
time for comments and feedback. Our approach to project delivery emphasizes quality control to ensure that all
work products are delivered free of errors. For this engagement, all work products will be reviewed by our quality
assurance manager or a key team member prior to submittal to the city. As can be attested to by our references,
our project team consistently collaborates to deliver a quality work product in a timely manner. At the end of every
task, GTS will conduct a task review process that may include a quick survey to gauge our success from your
perspective. We share the feedback among the project team in an effort to constantly improve.
GTS I 1 8 City of La Quinta On -Call Traffic Engineering Services
Scope of Work
The following sections describe typical task orders carried out as part of on-call contracts illustrating our work
plan.
1. Plans, Specifications, and Estimates;
GTS will prepare plans, specifications, and estimates (PS&E) to accommodate the construction requirements for
traffic signals, signing and striping, traffic control plans, and other ITS design tasks.
We typically anticipate producing plans for the following:
• Street Improvement Plans — to accommodate ADA compliant curb ramps and raised median noses
• Signing and Striping Design
• Traffic Signal Plan — to propose agreed upon traffic signal improvements and operations based on the
developed recommendations
The GTS team believes a detailed field review and as -built plan verification will provide a good base plan for a
high-quality design plan and will result in higher efficiencies (less time and costs). Prior to preparing a base plan
for the street improvement and traffic engineering design, GTS will obtain copies of available as -built drawings
and other available database/information pertaining to the project from the City and other agencies if needed.
The field review will include identifying design constraints, verifying as -built information, and observing general
site conditions. We will document our findings with photos taken as part of our field review. We will review the
preliminary utility information and prepare and send notifications to all utility companies known to operate within
the project area. Underground and overhead utilities will be identified, and potential conflicts will be noted and
resolved during final design.
Typical tasks could include:
1.1 Topographic Land Survey: The design survey will be developed at 1"=20' scale and will include the
following items:
• Sufficient spot elevations and breaklines to accurately develop contours at a 1.0' interval.
• Curbs, right-of-way (and jurisdiction boundary line), flowlines, and gutters.
• Paving types.
• Roadway crown elevations and striping.
• Above ground evidence of utilities.
1.2 Street Improvement Plan: GTS will modify the existing curb ramps to comply with ADA guidelines at the
intersection. GTS will utilize the topographic land survey to produce the street improvement plan. The street
improvements will be limited to ADA curb ramp reconstruction. GTS will perform a detailed ADA evaluation. We
will design all proposed curb ramps per the standards agreed upon with the City. The plans will clearly show
limits of construction and curb ramp grades and details. The curb ramp details will be prepared at 1"=10' scale.
1.3 Singing and Striping Design: GTS will incorporate any striping and signage modifications at the project
intersection on the corresponding traffic signal plan if it is part of a signal design project, or will produce separate
signing and striping plans.
Striping and signage services will include items like improving existing bike lane signages, reinstalling faded
striping, or other striping or signage that may be required.
1.4 Traffic Signal Plan: Utilizing the traffic signal as -built plans, survey, and field investigation data, GTS will
prepare a traffic signal base plan at the intersection. The base plan is the backbone to accurately design proposed
improvements. At this stage of the process, a thorough review is performed on the base plan to ensure accuracy
prior to design. The base plan will include centerline, right-of-way, relevant existing street improvements, and
existing traffic controls. We will prepare the base plan in accordance with City's format and standards. If the
intersection has shared jurisdiction with other cities we will also work with their standards.
GTS 119 City of La Quinta On -Call Traffic Engineering Services
GTS has extensive experience in traffic signal design and will utilize that knowledge to identify potential
conflicts before the project goes into construction. For example, proposed signal poles will be strategically placed
in the optimum location for driver/pedestrian visibility and will adhere to ADA guidelines. We will also evaluate
any current deficiencies or sub -standard equipment that should be upgraded to meet current City agreed-upon
standards.
We will provide a detailed traffic signal plan per City agreed-upon format, standards, and specifications. The
plan will propose approved signal phases, clearly identifying all existing, proposed, and removed traffic signal
equipment to correspond with the overall design intent and shown existing and proposed improvements. The
traffic signal plan will be 1 "=20' scale unless directed otherwise.
1.5 Utility Verification and Coordination: GTS will request a contact list from the City of utility companies with
facilities at the project intersection. We will request utility maps and compile underground and above ground
utilities in a separate digital file. This file will be referenced into all relevant design plans and clearly labeled to
identify utility type, size, and owner. This will allow us to identify any potential impacts and modify the design as
necessary.
We will also send a notification to all utility companies within the project limits at the 70% and/or final design
stage for their review to determine if there are any possible conflicts with the proposed improvements. GTS
will work closely with the utility companies and other City departments to resolve conflicts prior to final design.
A communication log will be preserved throughout the project and provided to the City upon request. GTS will
provide coordination with electric utility companies if the design includes modification to the service pedestal and/
or point of connection (POC).
1.6 Specifications and Cost Estimates: GTS will prepare the technical specifications using the City's boilerplate
template or Caltrans required template and required format. We will use the City -required standards and
specifications.
1.7 Pre -Construction Support: GTS will provide pre -construction support services for this project after plans
have been approved by the City and other agency. We will attend pre-bid meeting and answer the questions
during the construction bidding process regarding the design and specifications. If there are omissions or conflicts
in the design prior to the award to contractor, GTS will provide a plan revision.
1.8 Construction Support: GTS will provide construction support services for this project during construction.
These services include but are not limited to attending a pre -construction meeting, responding to questions
during the construction, reviewing contractor submittals within 72 hours, responding to contractor's requests for
information (RFIs) or Change Request (CR), revising design plans per CR, maintaining a log of all changes to
approved plan set, reviewing and making recommendations to Contract Change Order (CCO), and providing
progress reports.
1.9 As -Built Plan Preparation: After the completion of project construction, we will request the redline markings
prepared by the project inspectors and/or contractors on the signed design plans for preparation of as -built plans.
The as -built plans will be signed and submitted to the City for the completion of the project
Sample Recent Relevant Projects:
• City of Carson: Provided HSIP-funded PS&E signal design services at Figueroa St and Victoria St; also
provided PS&E services for the Dominguez Channel Bike Path Design working with the City and County
• City of Santa Monica: Provided ATP -funded PS&E signal design, signing and striping, and street lighting
designs as well as traffic analysis per Caltrans and City guidelines
• Los Angeles County TSSP: Myrtle/Peck Ave TSSP (GTS as sub to Michael Baker) and Eastern Ave TSSP
(GTS as sub to Kimley-Horn)
2. Review/Prepare Transportation Impact Studies;
We understand that typical task orders could include the review of traffic impact studies produced by others.
GTS will help the City review the Traffic Impact Study (TIS) of proposed development projects to ensure that the
technical report is adequate for supporting the analysis, findings, and conclusions of the Traffic/Transportation
section of the environmental document. The TIS will be evaluated in accordance with the City's criteria and
GTS 120 City of La Quinta On -Call Traffic Engineering Services
standards, as well as industry standards set forth by ITE, HCM, and other applicable standards.
The following scope of work is anticipated to be required for the peer review of the TIS:
• Review the most current project description to fully understand the scope of the proposed project and ensure
that it is consistent with the project as analyzed in the applicant's TIS.
• Review the TIS for consistency of the analysis methodology with City and industry -standard requirements,
including any measures identified in the report to reduce identified traffic impacts.
• Upon review of the TIS, we will discuss the peer review approach and initial findings with the City staff to
ensure that City requirements have been addressed.
• Provide a written summary of the peer review of the TIS in the form of a comments matrix identifying any
shortcomings or fatal flaws and outlining findings including items needing clarification or recommendations
to be addressed by the Project Applicants.
• Provide a review of the applicant's responses to the comments matrix to ensure that comments are addressed
We will conduct the review (or analysis) in a timely and thorough manner. After the TIS has been deemed
complete and adequate, the City can incorporate the findings and recommendations of the technical report
into the environmental document or the City Council staff report recommendations. Any measures outlined in
the technical report to reduce traffic impacts will be reviewed for their adequacy and ability to reduce identified
impacts to a level of less than significant.
It should be noted that GTS carries out various Transportation Impact Studies and VMT analyses and have the
in-house modeling capabilities to assist the City with running VMT analysis and/or verifying other studies and
model runs.
Sample Recent Relevant Projects:
• City of Moorpark Environmental On -Call: Conducted review of the Traffic Impact Study (TIS) of the Everett
Street Terraces
• Imperial County On -Call: Conducted review of the Traffic Impact Study (TIS) of the Energy Source Industrial
Project
3. Review/Prepare Traffic Signal Timing/Coordination Plans;
GTS will provide signal timing plan support to the City to address the changing traffic conditions due to COVID
so that City staff will have the opportunity to switch to different plans to accommodate a `new normal'. We will
provide recommendations to City staff on when a certain signal timing plan would be applicable based on our
monitoring of traffic conditions using the City's ATMS applications.
During the timing analysis, GTS will work with the City to consider the timing of adjacent corridors and
intersections and the potential to connect adjacent corridors/intersections in coordination or to maintain existing
cross coordination that exists. We will work with the City to bench test the timing using available emulators and
check all databases for errors prior to implementation.
Our project manager has peer reviewed various Traffic Signal Synchronization Projects (TSSP), reviewing before
and after study reports, the signal timing, optimization, and implementation reports and reviewing the final project
reports to ensure they meet City guidelines and objectives.
Sample Recent Relevant Projects:
• City of Rancho Palos Verdes Traffic On -Call: Carried out the Hawthorne and Via Rivera intersection,
Crenshaw signals coordination, and Hawthorne and Eddinghill left turn phase analysis
• City of Glendora: Carried out the traffic signal modification of Bennett Ave and Grand Ave
4. Review/Prepare Traffic Control Plans;
GTS often assists with maintenance of traffic requirements for CIP projects from resurfacing projects to projects
involving signal designs, signing and striping, and bicycle facilities design.
We will work with the City to efficiently review and approve plans and maintain schedules. We provide high quality
GTS 121 City of La Quinta On -Call Traffic Engineering Services
through the plan check cycle, from planning and design to construction completion. Typical projects include:
• New traffic signals or traffic signal modifications
• Power source and cabinet placement
• Required street lighting and integration with traffic control
• Conformance with ADA requirements
• Street improvement, rehabilitation, and widening plans
Sample Recent Relevant Projects:
City of Hermosa Beach Traffic On -Call: Conducted review (within one to two days) of outdoor dining designs
for about 17 parklets
• City of Santa Monica 20th Street: Carried out traffic control plans (following Caltrans standards) and invitations
to the meetings
5. Prepare Grant Applications;
We will assist the City with identifying and applying forfunding to realize the various CIP projects. GTS has assisted
various cities with grant applications and grant management. We recently carried out 3 grant applications for the
HSIP program for the cities of Buena Park and La Habra Heights to help upgrade signal hardware, construct
new signals, and upgrade guardrail. We understand not only the grant writing process, but equally important the
scoring rubric that is essential to ensure successful grant applications.
Our team has previously supported the City of Commerce on successfully obtaining HSIP and ATP grants.
As part of our project delivery, we also support cities with grant management and dealing with the funding agency
requirements such as E-76 and others.
Sample Recent Relevant Projects:
• City of La Habra Heights: Prepared HSIP applications for guardrail upgrades and new traffic signal
• City of Buena Park: Prepared HSIP application for signal modifications
• Prepared LRSP applications for various cities (South Pasadena, Hidden Hills, Buena Park, etc.)
6. Attend Meetings and Prepare Presentation Materials;
GTS often plans and attends council, commission, and community meetings to solicit input and feedback on
projects. The scope of our services ranges from one-on-one briefings to community at -large gatherings. These
meetings can take place at various milestones during the life of the project. Meeting topics range from presenting
initial findings to soliciting feedback from the community or council/comission.
GTS is prepared to assist with leading the meetings, note taking, and support services which will include
coordination of meeting times and locations, hand-outs, sign -in sheets, organization of facility details (venue
assumed to be provided by the City), and meeting set-ups. We will also work with the City to provide the notices
and invitations to the meetings.
Sample Recent Relevant Projects:
• City of La Habra Heights: Presented to the Council and Road Commission on the project progress
• City of Torrance Downtown Revitalization: Participated in community outreach presenting on circulation and
parking elements
7. Traffic Calming and Revitalization Plans;
GTS provides the experience and expertise to work on various revitalization projects. We are often called in for our
parking experience when it comes to downtown or corridor revitalization projects. We have a keen understanding
of parking management strategies and their impact on the economic viability along corridors and in downtown
areas. We approach parking not just from a transportation perspective, but from economic development and land
use frameworks.
GTS 122 City of La Quinta On -Call Traffic Engineering Services
At GTS we understand that successful neighborhood traffic calming plans are those "owned" by the community
and as such are developed through neighborhood collaboration and oftentimes consensus.
Our goal is to ensure that residents are well-informed about the alternatives and the process. We will assist
the City in the response and management of public requests (petitions) for neighborhood traffic calming, the
prioritization of study areas, data collection and analysis, attending neighborhood meetings, determination of
potential solutions, cost analysis, preparation of construction plans, refinement of plans, and study of effectiveness
of traffic calming measures after implementation.
Sample Recent Relevant Projects:
• City of La Habra Heights: Conducted traffic calming analysis along the City's roads
• City of Torrance Downtown Revitalization: Led mobility and parking aspects of the revitalization plan for the
downtown core
8. Other related services as requested/directed by City;
GTS will assist the City on a one -team basis and will serve as an extension to the City's staff that can be called
upon as needed.
In addition to the above listed services, GTS can support the City with the following:
Non -motorized Planning and Design: GTS has a deep understanding of active transportation related policies at
the federal, state, and local levels. We adopt the principles of the NACTO Urban Bikeway Design Guide as well
as local City and state guidance in the planning and design of bicycle facilities and intersections. Our staff has a
keen knowledge and expertise in applying Caltrans Highway Design Manual and California Manual on Uniform
Traffic Control Devices to bicycle and pedestrian projects.
Parking Studies: We understand that parking is a "sensitive" subject in many cities we work in. We understand
the dynamics at the resident, employee, business, council, and staff levels. As such, stakeholder engagement
and a data -guided approach are critical components in all work we do. Our typical approach for parking studies
includes the following:
• Reviewing of relevant documents and studies
• Assessing current parking supply and demand
• Stakeholder engagement
• Estimating future parking demand
• Recommending parking management strategies (demand, location, time, price and supply strategies)
• Developing an implementation plan that includes short-, medium-, and long-term projects
Safety Studies: The GTS approach to safety studies is first and foremost to obtain and collect the data necessary
to properly analyze the project roadways, identify the issues and suitable countermeasures, develop network-
wide assessments and comprehensive road safety programs, and assist the City with prioritization of safety
improvements based on cost-effectiveness analysis, cost benefit analysis, and resource availability and
allocation. After receiving the notice to proceed for a safety study, we will start obtaining available data, records,
as-builts from the City, and other available resources. We will coordinate with the City to determine assessment
criteria, field review schedule, and field survey templates prior to performing our field review and inventory work
to verify existing sign and traffic control device conditions.
GTS 123 City of La Quinta On -Call Traffic Engineering Services
Quality Assurance & Control Brief
GTS ensures project deliverables are free of errors, easy to understand, and executed in line with client
expectations. Our established quality control process builds on our experience to offer precision in delivery of
our work. Our quality assurance/quality control plan begins before the task order is assigned, during scoping
discussions. At this time, our project manager will work with the City to define the project tasks, establish roles
and responsibilities for project team members, identify communication protocols, and identify success criteria
for the project. Subsequently, we develop a draft definition of required project tasks, deliverables, budget, and
schedule. Risk assessment, change management strategies, and project communication plans are incorporated
into this planning process. Once these tasks have been reviewed, modified, and adopted by the project team,
GTS will proceed with the project as planned, providing continuous support and regular communication with the
City.
All deliverables and communications with the City will be reviewed by both the project manager and a key team
member (who is not otherwise involved in the task). This will be akin to a third -party QA/QC that not only ensures
that deliverables are free of errors, but also that we are meeting your needs in terms of our understanding of the
project and are aligned with the City's budget and schedule.
For design work in particular, our design plans will be field verified and reviewed by senior staff members during
the design preparation. A constructability review in the field will be carried out for the final plan prior to City's
approval. Formal quality control checklists and/or plan review comments are employed to control the quality of
deliverables.
At the end of every project, GTS conducts a project closure process that includes an online client survey to
gauge our success from the client's perspective. We share the feedback among the project team in an effort to
constantly improve.
GTS 124 City of La Quinta On -Call Traffic Engineering Services
Project Schedule
The schedule will vary based on the specific requirements and scope of each project. While the actual schedule
will be tailored to meet the needs of individual projects, the following provides an overview:
1. Project Initiation: Upon receiving ataskorder, GTS will initiate project discussions, review project requirements,
and establish clearcommunication channels.
2. Scope Definition: GTS will work closely to define the scope of work, objectives, and deliverables for the
project. This includes identifying any specific timelines or milestones that need to be considered.
3. Data Collection and Analysis: GTS will gather and analyze the relevant data, conduct site visits if necessary,
and utilize appropriate tools and methodologies to assess the project requirements.
4. Planning and Design Phase: Based on the analysis and project objectives, GTS will develop comprehensive
plans and designs that address the specific needs of the project.
5. Review and Approval: GTS will submit draft plans and designs for review, allowing for feedback and
incorporating any necessary revisions.
6. Documentation and Reporting: GTS will prepare detailed documentation and reports summarizing the
findings, methodologies used, and recommendations for implementation.
7. Project Closeout: Upon completion of the project, GTS will conduct a final review, address any outstanding
matters, and provide the client with the necessary project deliverables.
An example schedule from a previous project is included in the following page.
GTS 125 City of La Quinta On -Call Traffic Engineering Services
GENERAL
TECHNOLOGIES &
SOLUTIONS
PRELIMINARY PROJECT SCHEDULE
Hacienda Road Safety Improvement - Traffic Signal and Additional Safety Improvements Project (RFP 2021-05)
CITY OF LA HABRA HEIGHTS
M- INDICATES ESTIMATED REVIEW SCHEDULE FOR THE CITY AND OTHER ASSOCIATED AUTHORITIES
GTS 126 City of La Quinta On -Call Traffic Engineering Services
MILESTONES AND TASKS
2022 2023
1
2
3
4
5
6
7
8
9
30
11
12 1
2
3
4
5
3 10 17 24 31
7 14 21 28
7 14
21 28
4 11 M 25
2 9 M 23 30
6 13
20 21
4 11 18 25
1 8 15 22 29
5 12 19 26
3 10 17 24 31
7 14
21 28
S 12
19 26 3 10 17 24 31
1 14 21 28
7 14
21 28
4 11 18 25
2 9 16 23 30
TASK 1- Project Management
Coordination and Meetings
1/4
Task 2 - Pre -Design Research
2.1 Field review and Base Plan Preparation
2 wks
coo,crumoo
aev
2.2 Utility Verification and Coordination
3 weeks
Task 3 -Traffic Engineering Design Plans, Specifications and Estimates (PS&E)
3.1 Topographic Land Survey + Legal Plats
3 weeks
3.2 Street Improvement Plan (50%, 90%& 100% Final Submittal)
4weeks
2 -Is
3weeks
2 w1
2wks
3.3 Signing and Striping Design (50%, 90%&100% Final Submittal)
Concept
4weeks
2wks
3weeks
2wks
2wks
3.4 Traffic Signal Plan (50%, 90%&100% Final Submittal)
4weeks
2 k
3weeks
2wks
2 k
3.5 Utility Verification and Coordination
2 wks
3.6 Specifications and Cost Estimates (50%, 90% & 100% Final Submittal)
cost Estlme
3 weeks
2 wks
2 k
Task 4 - Bidding Phase Services (Optional) (T&M)
4.1 Pre -Construction Support
2 w1
Convactr cw&Award
Task 5 - Construction Phase Services (Optional) (T&M)
5.1 Construction Support
8weeks RFI's and Construction Drawin
5.2 As -Built Plan Preparation
wks
Task 6 - Other Optional Tasks
6.1 HSIP Funding- Process assisstance
wks
6.2 Traffic Signal Timing
3weeks
2wks
2wks
6.3 Hacienda Road Edge -lines and Centerlines
4weeks
2wks
3weeks
2wks
2wks
6.4 Potholing Services (Provision)
2 wks
M- INDICATES ESTIMATED REVIEW SCHEDULE FOR THE CITY AND OTHER ASSOCIATED AUTHORITIES
GTS 126 City of La Quinta On -Call Traffic Engineering Services
References
Ramzi Awwad I Public Works Director I City of Rancho Palos Verdes
30940 Hawthorne Boulevard, Rancho Palos Verdes, CA 90275 1310.544.5275 1 rawwad@rpvca.gov
Project: City of Rancho Palos Verdes Transportation and Traffic Engineering On -Call; 2021 - Ongoing
Azzam Jabsheh I City Traffic Engineer I City of San Bernardino
290 N D St, San Bernardino, CA 92401 1909.384.7272 1 jabsheh_az@sbcity.org
Project: City of San Bernardino Traffic Signal Upgrade PS&E Services; 2020 - 2021
Douglas Krauss I Environmental Programs Manager I City of Hermosa Beach
1315 Valley Drive, Hermosa Beach, CA 90254 1310-750.3603 1 dkrauss@hermosabeach.gov
Project: City of Hermosa Beach Transportation Planning and Traffic Engineering On -Call; 2019 - Ongoing
Omar Moheize I Principal Civil Engineer I City of Burbank
275 E Olive Ave, Burbank, CA 91502 1818.238.3943 1 omoheize@burbankca.gov
Project: Burbank Resurfacing Program - Signing & Striping Restoration and Loop Replacement Plans; 2020 -
Ongoing
Joseph San Clemente I Principal Transportation Planner I City of Santa Monica
1685 Main St, Santa Monica, CA 90401 1310.458.2204 1 joseph.sanclemente@smgov.net
Project: Santa Monica 20th Street Connection; 2019 - 2020
GTS 127 City of La Quinta On -Call Traffic Engineering Services
Fee Proposal
PROJECT/PROGRAM TITLE: City of La Quinta On -Call Traffic Engineering Services
Name: General Technologies and Solutions (GTS)
Rates Effective Beginning: July 1, 2022 Ending: June 30, 2023
Labor Category/Grade
Hourly Fully -Loaded Rate
Labor Category/Grade
Principal L7
$230.00
- $280.00
Engineer / Planner / Analyst (L6)
$190.00
- $230.00
Engineer / Planner / Analyst (L5)
$170.00
- $210.00
Engineer / Planner / Analyst (L4)
$150.00
- $190.00
Engineer / Planner / Analyst (L3)
$140.00
- $180.00
Engineer / Planner / Analyst (L2)
$120.00
- $160.00
Engineer/ Planner/ Analyst (L1)
$110.00
- $140.00
Project Admin / CAD / Graphics (L4)
$140.00
- $200.00
Project Admin / CAD / Graphics (L2)
$110.00
- $140.00
Intern (L1)
$90.00 -
$120.00
Yearly escalations are limited to the highest of consumer price index (CPI) or 5%.
Mileage is charged per the maximum allowable IRS rate.
Other expenses (surveys, printing, etc.) will be charged at cost plus 10%.
GTS 128 City of La Quinta On -Call Traffic Engineering Services
Complementary Services
In addition to the traffic engineering services highlighted in the RFP, we offer a range of complementary services
that can support and enhance our capabilities. These services include:
Transportation Planning: GTS has expertise in conducting comprehensive studies, analysis, and planning for
transportation networks. Our services include traffic calming studies, traffic impact analysis, transportation
planning, and vehicle miles traveled (VMT) analysis.
Electrical Engineering Design: From illumination calculations (photometrics) to street lighting designs and
electrical vehicle charging station designs, GTS offers our clients the full project life cycle experience—from
initial planning to design to utility coordination for electric services as well as construction support services.
Parking Studies: GTS believes that parking is more than just supply and demand; parking is about economic
development, land use, and multi -modal transportation. Our parking services include shared parking analysis,
parking management plans, parking design support, operations, and compliance audits.
Pedestrian and Bicycle Planning: GTS focuses on creating safe and accessible pedestrian and bicycle
infrastructure. Our expertise includes designing sidewalks, crosswalks, bike lanes, and shared -use paths to
promote active transportation.
Complete Streets Solutions: GTS specializes in context -sensitive solutions that accommodate all users of all
ages and abilities. From writing and adopting Complete Streets policies to planning, engineering, and design of
pedestrian and bicycle facilities, GTS has the tools communities need to create streets that carry all travel modes
safely, efficiently, and comfortably.
Intelligent Transportation Systems (ITS): GTS specializes in designing and implementing advanced technologies
and systems to optimize transportation efficiency. This includes expertise in traffic signal optimization, traffic
monitoring, and adaptive traffic control systems.
Prices for these complementary services depend on the specific requirements and scope of each project.
GTS 129 City of La Quinta On -Call Traffic Engineering Services
Staffing and Project Organization
Citv of
La Quinta
PROJECT
MANAGER
Rawad Hani*
PE, TE, PTP, PTOE, RSPI
PROJECT MANAGER
Q-----------------------------Q---------------------------Q---------------------------Q-----------------------------Q
rrano �1,"
11 rz�
-_ -- _ ---- .------ .----
Rock Miller* Patrick Armijo* Ariel Godwin Chaouki A. Hosn* Cassandra Garcia
PE, TE, PTOE PE, PEng AICP EE EIT
ATP, SAFETY & SIGNAL OPERATIONS SENIOR PLANNER ELECTRICAL ENGINEER DESIGN ENGINEER
OUTREACH
Alexa Cuyugan
GRAPHICAL
COMMUNICATIONS
Rudy Garcia
EIT
TRAFFIC ANALYSIS
o----------------------------- o ---------------------------Q ---------------------------- o ----------------------------- o
Support Staff
*Licenses: Rawad Hani: 83730 (Civil Engineer - CA); 2817 (Traffic Engineer - CA); PTP; PTOE; RSP1 I Rock
Miller: 29493 (Civil Engineer - CA); 1139 (Traffic Engineer - CA); PTOE I Patrick Armijo: 44201 (Civil Engineer -
WA) I Chaouki A. Hosn: 14083 (Electrical Engineer - CA)
cW GTS 130 City of La Quinta On -Call Traffic Engineering Services
Disclosures
GTS does not have any negative history including any alleged significant prior or ongoing agreement failures,
any civil or criminal litigations or investigations pending, which involved GTS or in which GTS has been judged
guilty or liable.
GTS 131 City of La Quinta On -Call Traffic Engineering Services
Acknowledgement of Insurance Requirements
cza
- Cr11.IFORNL\ -
ATTACHMENT 2
INSURANCE REQUIREMENTS ACKNOWLEDGEMENT
Must be executed by proposer and submitted with the proposal
Rawad Hani (name) hereby acknowledge and confirm that
General Technologies and Solutions (GTS)(name of company) has reviewed
the City's indemnification and minimum insurance requirements as listed in Exhibits E and
F of the City's Professional Services Agreement (Attachment 1); and declare that insurance
certificates and endorsements verifying compliance will be provided if an agreement is awarded.
I am Principal/Project Manager
(Title)
of General Technologies and Solutions GTS)
(Company)
GTS 132
City of La Quinta On -Call Traffic Engineering Services
Commercial General Liability (at least as broad as ISO CG 0001)
$1,000,000 (per occurrence); $2,000,000 (general aggregate)
Must include the following endorsements:
General Liability Additional Insured
General Liability Primary and Noncontributory
Commercial Auto Liability (at least as broad as ISO CA 0001)
$1,000,000 (per accident)
Personal Auto Declaration Page if applicable
Errors and Omissions Liability $1,000,000 (per claim and aggregate)
Worker's Compensation (per statutory requirements)
Must include the following endorsements:
Worker's Compensation Waiver of Subrogation
Worker's Compensation Declaration of Sole Proprietor if applicable
GTS 132
City of La Quinta On -Call Traffic Engineering Services
Non -Collusion Affidavit
NON -COLLUSION AFFIDAVIT FORM
Must be executed by proposer and submitted with the proposal
Rawad Hani
I am Principal/Project Manager
Zaau�a
ATTACHMENT 3
(name) hereby declare as follows:
of General Technologies and Solutions (GTS)
(Title) (Company)
the party making the foregoing proposal, that the proposal is not made in the interest of, or on behalf
of, any undisclosed person, partnership, company, association, organization, or corporation; that the
proposal is genuine and not collusive or sham; that the proposer has not directly or indirectly induced
or solicited any other proposer to put in a false or sham proposal, and has not directly or indirectly
colluded, conspired, connived, or agreed with any proposer or anyone else to put in a sham proposal,
or that anyone shall refrain from proposing; that the proposer has not in any manner, directly or
indirectly, sought by agreement, communication, or conference with anyone to fix the proposal price of
the proposer or any other proposer, or to fix any overhead, profit, or cost element of the proposal price,
or of that of any other proposer, or to secure any advantage against the public body awarding the
agreement of anyone interested in the proposed agreement; that all statements contained in the
proposal are true; and, further, that the proposer has not, directly or indirectly, submitted his or her
proposal price or any breakdown thereof, or the contents thereof, or divulged information or data relative
hereto, or paid, and will not pay, any fee to any corporation, partnership, company, association,
organization, proposal depository, or to any member or agent thereof to effectuate a collusive or sham
proposal.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and
cnrrPct
Proposer Signature:
Proposer Name:
Proposer Title:
Company Name:
Address:
Rawad Hani
Principal/Project Manager
General Technologies and Solutions (GTS)
1100 Quail Street, Suite 202, Newport Beach, CA 92660
GTS 133 City of La Quinta On -Call Traffic Engineering Services
Acknowledgement of Addenda
66(v
ATTACHMENT 4
ACKNOWLEDGEMENT OF RECEIPT OF ADDENDA
Must be executed by proposer and submitted with the proposal,
If no addenda has been issued, mark "N/A" under Addendum No. indicating
Not Applicable and sign
ADDENDUM NO.
SIGNATURE INDICATING RECEIPT
2
-�
GTS 134 City of La Quinta On -Call Traffic Engineering Services
Our Commitment to the City of La Quinta
We will provide the City with the team most capable of developing innovative solutions based on local needs and,
equally important, effectively communicating these solutions. In providing quality service to the City, the GTS
team will focus on: