2024 CVAG Reimbursement Agrmt ATP Amendment 3 - Avenue 48 Art & Music Line Design Proj. 2020-0874-199 El Paseo Drive, Suite 100
CVAG Palm Desert, CA 92260
TRANSMITTAL
Date: February 16, 2024
To: Bryan McKinney
Public Works Director/City Engineer
City of La Quinta
78-495 Calle Tampico
La Quinta, CA 92253
Re: Amendment No. 3 to the Reimbursement Agreement for the ATP — Arts and Music Line Project
CVAG Contract No. CVAG-20-018-03
Enclosed please find a fully executed original hardcopy of Amendment No. 3 to the Reimbursement
Agreement Between CVAG and the City of La Quinta for the ATP —Arts and Music Line Project.
If you have any questions or would like additional information, please feel free to contact me by email at
arncmillen@cvag.org or by telephone at (760) 346-1127.
Sincerely,
741ee"r �a/fillew
Allen McMillen C�
Contracts Analyst II — Contracts and Procurement
Coachella Valley Association of Governments
ITEM 12B
Coachella Valley Association of Governments .
Joint Meeting of tine Executive
& Transportation Committees CVAC
December 4, 2023
STAFF REPORT
Subject: Next Steps for the Arts and Music Line Project
Contact: Randy Bowman, Transportation Program Manager (rbowman(cvag.orcl)
Recommendation: Authorize the Executive Director to take the following actions for the
Arts & Music Line project:
1. Execute a professional service agreement with Anser Advisory, LLC in an amount
not to exceed $509,333, including 20 percent contingency, to provide pre -
construction and construction management services;
2. Execute a professional service agreement with T.Y. Lin International in an amount
not to exceed $50,000 to provide pre -construction and construction management
services;
3. Execute a professional services agreement with Chen Ryan Associates, Inc. in an
amount not to exceed $934,730, including 20 percent contingency, to provide non -
infrastructure program professional services; and
4. Negotiate and execute amendments to existing reimbursement agreements with the
Cities of Coachella, Indio and La Quinta to adjust the local share of pre -
construction, construction management, and non -infrastructure program services
Background: In December 2022, the Executive Committee, at the recommendation of the
Transportation Committee, authorized the Executive Director to take the necessary steps to
accept $36.483 million in Active Transportation Program funding for the Arts and Music Line
(AML). This project will provide nearly nine miles of protected bicycle facilities (Class 1 and Class
4) along Avenue 48, Van Buren Street, and Dillon Road in the Cities of La Quinta, Indio and
Coachella. The project will also construct more than six miles of new or upgraded Class 2 and
Class 3 bikeways that directly connect the project to 11 disadvantaged schools.
The project scope includes branded elements like colored concrete, special markings and
signage, lighting, two bridge under -crossings, traffic signal construction, paving, concrete channel
modifications as well as connections to the CV Link and to the polo grounds, which is home to
the world-renowned Coachella and Stagecoach art and music festivals. It also features innovative
safety features including bicycle signals with fully protected bicycle movements, raised and/or
recessed bike/pedestrian crossings, and bicycle signal indicators to alert cyclists that they have
been detected by the traffic signal.
On September 30, 2019, the Executive Committee authorized a contract for the design of the
AML project with Webb and Associates. The project design is now 65% complete and the project
plans will be 90% complete in February 2024. Construction is anticipated to start in 2025. With
this item, staff is recommending several contracts that will get the project construction -ready and
plan ahead for when it is complete.
Construction Management Services
Similar to the CV Link and CV Sync projects, CVAG staff has identified the need for professional
engineering services to assist with pre -construction activities and construction management and
inspection during construction. A Request for Proposals (RFP) was properly advertised and
posted on July 12, 2023. Four proposals were received by the August 23, 2023 submittal deadline.
CVAG assembled a proposal review committee comprised of staff from CVAG and the Cities of
Indio and La Quinta. Proposals were evaluated on September 12, 2023, and a short list of two
proposers was selected for interviews. Interviews of the top scoring firms were conducted on
September 27, 2023.
Consultant
Anser Advisory, LLC
Southstar Engineering & Consulting, Inc.
TKE Engineering, Inc.
T. Y. Lin International
Location
Palm Desert, CA
Riverside, CA
Palm Desert, CA
Ontario, CA
Anser Advisory, LLC received the highest ranking from the proposal evaluation committee. The
consultant is an established engineering consultant with office in 12 states, including a local office
in Palm Desert. The consultant has performed construction management for several cities in the
Coachella Valley and the region and is currently the construction manager for CVAG's CV Link
project. Based on the proposal evaluation committee's feedback, staff is recommending the
Executive Director be authorized to execute a contract with Anser that is limited to bid
administration and pre -construction assistance. Upon successful completion of the pre -
construction activities and satisfactory performance, CVAG staff would negotiate fees and bring
back any recommendations related to a contract for the construction management services
needed during construction. CVAG staff reserves the right to hire other consultant(s) as necessary
or if it is determined that Anser is not performing to CVAG's satisfaction.
In addition, CVAG staff is recommending the Executive Director be authorized to execute a
construction management services contract with T. Y. Lin International, the second highest -
ranked consultant from the proposal evaluation committee. The consultant has substantial
experience with member jurisdictions, including Indio and La Quinta. The Arts and Music Line
project may require independent value engineering or design review, which would be provided by
T. Y. Lin International.
Non -Infrastructure Program Professional Services
CVAG's application to the CTC also included a non -infrastructure component that requires
professional engineering and public outreach services. The program will include engagement
with schools, residents, businesses, the organizers of music festivals such as Coachella and
Stagecoach and other stakeholders. Data will be collected during the program and an Outreach
and Engagement Plan will be developed. The goal of the education and encouragement activities
is to increase interest in active transportation and safe routes to schools. The program will
commence prior to construction, continue during construction and following construction, to be
concluded in a program evaluation in 2027. v V
A RFP was properly advertised and posted on July 26, 2023. Three proposals were received by
the September 6, 2023 submittal deadline. The proposal review committee was comprised of staff
from CVAG, the Cities of Indio and La Quinta, and from Riverside University Health. Proposals
were evaluated on September 28, 2023, and a short list of two proposers was selected for
interviews. Interviews of the short list were conducted on October 4, 2023.
Consultant Location
Chen Ryan Associates, Inc. San Diego, CA
Kounkuey Design Initiative, Inc. Los Angeles, CA
Southstar Engineering & Consulting, Inc. Riverside, CA
Chen Ryan Associates, Inc. received the highest ranking from the proposal evaluation committee.
Chen Ryan Associates, IncJs an established engineering consultant based in San Diego, CA,
and has extensive knowledge of the AML, having assisted in the preparation of the ATP grant
application. The consultant is presently assisting in the design of the project as a subconsultant
to Webb. Based on the proposal evaluation committee's feedback, staff is recommending the
Executive Director be authorized to execute a contract with Chen Ryan Associates, Inc.
In addition to recommending execution of all three contracts, staff is seeking authorization to
negotiate and execute amendments with the cost -sharing agreements that CVAG has with the
Cities of La Quinta, Indio and Coachella. These recommended actions would also authorize the
Executive Director and/or Legal Counsel to make clarifying revisions before execution.
Fiscal Analysis: Staff is recommending three contracts related to the AML.
Two of these contracts are for pre -construction and construction management services. The
professional service agreement with Anser Advisory, LLC is recommended for a not -to -exceed
amount of $509,333, including 20 percent contingency. The professional service agreement with
T.Y. Lin International in for an amount not to exceed $50,000.
Staff is also recommending an agreement with Chen Ryan Associates, Inc. in an amount not to
exceed $934,730, including 20 percent contingency, to provide non -infrastructure program
professional services.
The cost for AML, from design through construction, is estimated at $46.099 million. The project's
construction is primarily funded through the $36,483,000 ATP grant.
Local and regional funding are being used to cover the remaining costs, including design, right-
of-way acquisition, utility relocation, construction management, and non -infrastructure program
activities. The three contracts proposed with this staff report would also be covered by local and
regional funding. These costs would follow the 75 percent/25 percent funding formula that is
standard for regional projects.
Because the AML local share spans more than one jurisdiction, the approved reimbursement
agreements have split the 25 percent city share based on the project's centerline miles. That
means it is split with the City of La Quinta contributing 6.25%, City of Indio contributing 16.75%
and the City of Coachella contributing the remaining 2.00%. CVAG staff will work with its member
jurisdictions to revise the agency reimbursement agreements to account for the additional
$1,494,063 for pre -construction construction management and non -infrastructure program
services.
Looking ahead, CVAG staff continues to look for additional funding opportunities for the AML.
Construction costs continue to rise and are being tracked as the project design continues. Staff
will also work with its member jurisdictions to address cost -sharing of the local share of the
construction phase, allowing them to budget for future fiscal years.
Attachments:
1. Anser Advisory, LLC Technical & Fee Proposal: httos://cvag.oralpdf/aml/AMLAnser.pdf
2. Chen Ryan Associates, Inc. Technical & Fee Proposal:
htl s://cva .or 1 df/aml/AMLChenR an. df
3. T. Y. Lin International Technical & Fee Proposal: https:Hcvag.oM/pdf/aml/AMLTYLin.odf
4. Professional services contract for Anser Advisory, LLC
5. Professional services contract for Chen Ryan Associates, Inc.
6. Professional services contract for T. Y. Lin International
tA
F z
1 w
7ALLETAMPICO
AVENUE 52
frt N
00 8,600 Feet
� � r
islmrizu ��lea...
�i
i
46 lr�rlfan a.
�c✓r.
IdiVq":€ YU COUNTY-
Jy UhCT LOCATION
w
4 T
s
Legend
Proposed Improvements
Arts and Music Line and
School Connection Spurs
Connection to CV Link
Existing/Planned Conditions
CV Link
Bicycle Lanes
Bear Creek Trail
Schools
Polo Fields/Local Event Venue
Jurisdictions
Coachella
Indio
r �
y■
3•YR
La Quinta
Unincorporated Riverside County
- - i
CVAGAt-is and MnsicLine Project Location Map
Acliue Trrnuporlalion Program Cycle 6 Grant Application
Contract No. CVAG-20-018-03
Project: ATP — Arts and Music Line
AMENDMENT NUMBER THREE
TO THE
REIMBURSEMENT AGREEMENT BY AND BETWEEN
CVAG AND THE CITY OF LA QUINTA
FOR THE
ATP —ARTS AND MUSIC LINE
This AMENDMENT NUMBER THREE is made and entered into this 4' day of December 2023,
by and between the Coachella Valley Association of Governments, a California joint powers
agency (CVAG), the City of La Quinta (Agency) and is made with reference to the following
background facts and circumstances. All other terms and conditions shall remain the same as
stated in the original agreement dated March 18, 2020 for the ATP — Arts and Music Line Project.
This Amendment Number Three extends the term of the contract to December 31,
2025.
2. This Amendment Number Three authorizes the scope of services in accordance with
the attached Anser Advisory Management, LLC Technical and Fee Proposal for the
not -to -exceed amount of $509,333, including 20 percent contingency, to provide pre -
construction and construction management services.
3. This Amendment Number Three authorizes the scope of services in accordance with
the attached T. Y. Lin International Technical and Fee Proposal for the not -to -exceed
amount of $50,000 to provide supplemental pre -construction and construction
management services.
4. This Amendment Number Three authorizes the scope of services in accordance with
the attached Chen Ryan Associates, Inc. Technical and Fee Proposal for the not -to -
exceed amount of $934,730, including 20 percent contingency, to provide
professional engineering and public outreach services.
5. This Amendment Number Three increases CVAG's Regional Share to $3,964,470,
and the Local Share to $1,321,490.
6. This Amendment Number Three authorizes CVAG to amend the cost -sharing
agreements between CVAG and the Cities of La Quinta, Indio and Coachella for
design costs related to the ATP - Arts and Music Line, by adding $1,494,063 to the
total costs for a revised total of $5,285,960 which represents an additional $1,120,547
totaling $3,964,470 for the 75 percent CVAG share and an additional $373,516
totaling $1,321,490 for the 25 percent local share.
Original Contract March 18, 2020
Amendment Number One February 28, 2022
Amendment Number Two December 5, 2022
Amendment Number Three December 4, 2023
Total Contract not -to -exceed
Amendment Regional Local
Amount Share Share
$2,731,897 $2,048,923 $682,974
No Cost $0 $0
$1,060,000 $795,000 $265,000
$1,494,063 $1,120,547 $373,516
$5,285,960 $3,964,470 $1,321,490
Contract No. CVAG-20-018-03
Project: ATP — Arts and Music Line
Based on the revised additional $373,516 to the local share, the revised 25 percent local share
which totals $1,321,478 per this amendment will be split between the cities of La Quinta,
Coachella and Indio as follows:
Total Local
La Quinta
Indio
Coachella
Share (25%)
$330,372
$885,398
$105,719
$1,321,490
25%
67%
8%
100%
SIGNATURES ON NEXT PAGE
Contract No. CVAG-20-018-03
Project: ATP — Arts and Music Line
The parties hereto have caused this Amendment Number Three to be executed by their
duly authorized representatives on the above -reference date.
ATTEST CITY OF LA QUINTA
By: By:
Jon McMillen, City Manager Linda Evans, Mayor
ATTEST
PrkCVAG
By:
TExecutive Director
COACHELLA ASSOCIATION OF
GOVERNMENTS
By: 6.
Scott Matas, CVAG Chair
Contract No. CVAG-20-018-03
Project: ATP — Arts and Music Line
Attachment A-1
Anser Advisory Management, LLC
Technical and Fee Proposal
UNDERSTANDING OF SPECIAL ISSUES (IV)
Construction Management Reimagined
The Anser team is comprised of individuals who truly take
ownership of the project and are willing to go the extra mile to
ensure the project is built right the first time. We are constantly
looking for design and construction enhancements that will
result in a pristine finished product.
An example of this on the CV Link project was at the Palm Springs
Visitor Center access point. The design drawings had laid out the
top of footings in line with the proposed finished grades. Our
Resident Engineer, Tyson Atwood, realized early that the visual
roof line would look odd once complete. As such, he made slight
modifications to the top -of -footing elevations so that the shade
structures would visually be shaped like a "V," which also cast a
much more appealing shadow.
It is this high attention to detail which separates the Anser
team from any other construction management firm.
Plans are heavily scrutinized both in the office and in the
field to ensure that the design intents are being met during
construction. The Anser team is very accustomed to making
minor design changes in the field as nearly all of the proposed
tie-in elevations on the CV Link project have been significantly
off. The way we have efficiently overcoming these challenges
is by being very proactive. Once construction stakes are set,
the Anser team will go out a minimum of two days ahead of
the Contractor's planned activities to ensure design feasibility.
Minor adjustments can then me made with have zero to
minimal impacts to the contractors means and methods and
schedule. We can make such adjustments easily because, as
part of our standard tools, Anser has invested in a builder's laser
level so that our inspection team can not only verify grades and
forms without the assistance of a contractor. This also allows
us to gather simple field topo without the need of additional
survey costs.
Unique Design Elements
The AML has many unique features
and elements which are being custom
developed for the project. Anser has
extensive experience in dealing with
unique design elements andthe challenges
that it brings to an owner. The first decision that CVAG must
make is whetherthe agency should procure these items under a
sole source agreement and then provide them to the contractor
as owner furnished material. This is always heavily scrutinized
by Caltrans and puts funding at risk if the proper procedures
are not followed. Furthermore, California Public Contract Code
section 3400 also prohibits the use of specific brand names
when bidding outwork. On the CV Link project, Anser provided
guidance to CVAG about the best way to procure specific design
elements while still being in compliance with California Public
Contract Code section 3400.
Through our guidance, the Segment i contract was able to
procure the exact benches, trash receptacles and bicycle racks
that were desired by CVAG.
As part of the Infrastructure Investments and Jobs Act (II)A),
the Build America, Buy America Act (BABA) was enacted in
November of 2o21. This act greatly increased the number of
products which now fall within the Buy America requirements.
This may include many of the fiberoptic and specialty lighting
that is currently shown in the AML drawing package. During
the pre -construction phase, Anser will ensure that all specified
products meet the BABA requirements. The newly updated
Caltrans 2023 standard specifications largely incorporate all
these new Buy America requirements, however at this time it
is unclear what the base specifications will be. If the Caltrans
Standard Specifications are not used, the Anserteam will ensure
that all the newly updated Buy America language is in the
contract specifications so that the contractor may accurately bid
the project. Finally, during construction, our Resident Engineer
will ensure that all Buy America requirements are being met
and the paperwork is meticulously filed in preparation for any
audit.
Understanding of Regional and Community Needs
Anser has worked extensively in the region for over five years
and has had an established local office foroverthree. Over75%
of the daily Anser team staff that will be working on the Art
and Music Line Project call the Coachella Valley home.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 12 1 Anser Advisory
SECTION 4 (CONTINUED)
As such, we have a strong understanding of the unique
community needs of the Art and Music Line project, both as it
relates to its local residents and tourism, driven in large part to
the music festival season and other special events.
Connections to Schools: The AMLwill connect to over half a dozen
schools, all of which are within disadvantaged communities
where over 8o9/o of the children are on Free and Reduced Priced
School Meals. Many of these children rely on public or active
transportation to get to school. The AML will provide safer
routes to children who are already using active transportation
means to get to and from school each day.
Tourism: April is one of the most important months to the region.
Each weekend, over 1oo,000 festival goers visit the Empire Pole
Grounds to attend Coachella Music and Arts and Stagecoach
music festivals. This is not including the thousands of vendors
that it takes to support these events. These grounds are also
increasingly the home to additional festivals taking place in
October. Consideration for these high traffic events must be
accounted for both during the design and construction phase.
The design must be thoughtful enough to recognize that there
are io's of thousands of people who would use the facilities no
more than once a year. Likewise, during construction, we must
ensure that our project is of minimal impact to the traveling
public, espciallyduring these high-volumeweekends. The Anser
team iswell experienced workingwith in the region duringthese
timelines.
During construction of our CV Link project, we ensured that our
contractor took extra precautions by utilizing a combination of
chain link andsnow fence to keep tourism outof the construction
zones. We also added additional signage above and beyond the
requirements of the CA MUTCD to ensure clear communication
to all tourists.
Understanding of the Dillon Road Connection
The Dillon Roadconnection isthe eastern mostconnection to CV
Link. Anser is aware that the existing Dillon Road Bridge over the
Coachella Valley Stormwater Channel is structurally deficient
and functionally obsolete. Dillon Road is also a principal arterial
serving the two tribal reservations: Cabazon Band of Mission
Indians and Twenty -Nine Palms Band of Mission Indians, and is
the only access to the City of Coachella connecting to Interstate
io freeway. The risks and reliabilities are extremely high and
Anser is ready to work through any and all challenges, including:
4 Coordination with Caltrans, Coachella Valley
Associations of Governments, Coachella Valley Water
District, City of Indio, City of Coachella, Cabazon Band
of Mission Indians, Twenty -Nine Band of Mission Indians,
utility companies and school districts on a consistent
basis.
4 Possible closing o f Dillon Road Bridge during construction
which may require long detours through Avenue 50 via a
low-water crossing (not accessible during flood event) or
Avenue 52, which will significantly increase emergency
response time.
4 Understanding that there is a Joint Powers Authority
between the City of Indio, City of Coachella, Cabazon
Band of Mission Indians and Twenty -Nine Band of
Mission Indians, established in September 2018, related
to the Dillon Road Bridge Project.
4 Understanding that the Dillon Road Bridge Project is
one of Coachella Valley Associations of Governments
transportation projects in the Transportation Project
Prioritization Study and how this relates to the Art and
Music Line Project which is funded by federal ATP and
local funds.
4 Managing environmental clearances (i.e., AB52 and
Section 7o6 consultations).
4 Managing and conducting biological studies during
breeding seasons only which may cause delays.
4 Strategizing the political process and facilitating
discussion among stakeholders that may have differing
opinions or priorities.
Anser has built a team who is ready to take on these challenges.
Martin Magana of Magana Consulting Services joins the Anser
team with extensive existing relationships and knowledge of
the rich history of the surrounding area. We will guide CVAG in
addressingthese challenges by including City and Tribal staff in
pre -construction meetings and progress meetings, implement
City and Tribal punch list items during project closeout and
coordinate acceptance walks with the City and Tribal staff as
part of the final punch list process.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 13 1 Anser Advisory
SECTION 4 (CONTINUED)
`y 0Q Design and Practical Experience
�.n.� Anser has extensive knowledge of the ADA
requirements and bikeway construction
�a as outlined in the California MUTCD.
We've also kept up on all changes as these
manuals are updated. This gives us a strong understanding
of the critical elements not only during the constructability
review phase, but also during construction. For example, we
understand that there has to be 2-foot clear zone from the edge
of path from any obstacles while the path.
During the construction of CV Link behind the Palm Desert
High School, this understanding of design criteria was critical
as the proposed pathway alignment encroached into this buffer
zone against an CVWD chain link fence. Since our contract
stated to protect the fence in place, the Anser team made
alignment modifications in the field to ensure that our edge
of pathway was at least 2-feet away from the existing fence.
This change was made a zero cost to CVAG. Had we not had this
understanding, post solution would have certainly cost tens of
thousands of dollars.
Anser also understands that even though a design may work
on paper and is within the guidelines of design standards, new
features may cause confusion with drivers. As new sections of
travel are opened, Anser will observe how traffic reacts to the
changes, recognizing that there is a typical time period where
locals will need to adjust to the changes. If any element of the
design is not working as intended, Anser will take immediate
action to add any temporary fixes as necessary while the design
team provides a final solution. Signal timing adjustments are
frequently required on these types of projects. Anserwill work
with the local agency to ensure that signals are adjusted ahead
of opening new routes to traffic.
Levee and Undercrossing Construction
One of the more important connections to the Arts and Music
Line is connectivity with CV Link at the La Quinta Promontory
PointAccess Point. In orderto make this connection, the proposed
pathway will travel from Avenue 48 along the La Quinta
Evacuation Channel and then drop under both the Highway iii
and Werson bridges. Anser has unmatched knowledge of the
challenges of obtaining both design approval and constructing
within Coachella Valley Water District (CVWD) right-of-way.
Our Resident Engineer, Tyson Atwood, has spent the past three
years working very closely with CVWD, especially David Wilson
and Chad Austin, in getting both design approvals, as well as
construction coordination within the channel. Anser recognizes
that CVWD has strong reservations about constructing the
undercrossings as proposed due to both safetyand engineering
concerns.
Engineering Concerns. One example of the engineering concerns
CVWD will likely have is with capacity and scour analysis. The
proposed design will reduce capacity of the existing channel
by the addition of a retaining wall, and/or fill slope. As this
channel is designated as a Zone A by the FEMA Flood Insurance
Rate Maps (FIRM), CVWD will likely require a hydrologic/
hydraulic (HH) analysis which shows that the impacts have
negligible effects on the existing water surface elevations and
scour depths. CVWD traditionally has Northwest Hydraulic
Consultants (NHC) complete their third -party review of all HH
studies. Through this process, Tyson has working knowledge of
the types of analysis that NHC will be looking for, as well as how
they prefer the data presented. Having previously worked as a
HH design engineer, Tyson has a strong understanding of the
software and types of analysis used to complete these studies.
During the approval process of the CV Link under crossings,
Tyson performed Quality Assurance of the designers' analyses
and report prior to submitting to CVWD for review. During this
process, he caught several inconsistencies in the report which
had traditionally been flagged by NHC; avoiding an additional
costly round of reviews and loss in schedule.
With his extensive knowledge of what kinds of issues CVWD and
N HC traditionally lookfor in their review, theAnserteam will be
able to perform independent Quality Assurance checks ahead of
design submittals to CVWD which will cut down on the number
of submittal reviews required ahead of CVWD approval.
Safety Concerns. Through our conversations with CVAG, we also
understand that CVWD has safety concerns about building the
pathway underneath the Jefferson and Highway iii bridges,
respectively. During our field visit, the Anser team did observe
one homeless encampment in the Jefferson bridge abutment,
opposite of where the pathway is proposed.
The Anser team has vast experience in working with the homeless
of similar under crossings during construction of CV Link. The
Monroe under crossing had proven to be the most challenging
location as there was a very well establish encampment within
ourconstruction limits. Prior to construction ofthe undercrossing,
Anser teamed with the CVAG Homeless outreach team so that
contact could be made with the individuals. Once that initial
contact failed, Anser worked with local law enforcement to have
the individuals removed. Anser also came up with some additional
design elements which helped as homeless deterrents. Through
persistent work, there are no longer homeless encampments at
any CV Link under crossing locations.
COACHELLA VALLEY ASSOCIATION OFGOVERNMENTS
Professional Engineering Services, Arts and Music Line Project
14 1 Anser Advisory
SECTION 4 (CONTINUED)
Anser will work closely with CVAG to help ensure the safest
possible route to access CV Link at the La Quinta Access Point.
We will look at all options, including additional lighting which
would not have adverse environmental impactswhile enhancing
the safety of users after dark.
Retaining Wall Construction
The current plan shows two different types of walls being
constructed within the channel, a tieback wall and a cast -in -
place wall. In our initial review of the plans, as demonstrated in
Figure 1, it appears that CVAG may need to acquire additional
right-of-way in order to construction the tiebacks. This appears
to be most prominent at the Highway iii undercrossing,
especially towards the northerly side where there is an existing
shopping center adjacent to the channel. These kinds of right-
of-way constraints will be one of our top priorities during our
constructability review. It will be critical to both the schedule
and design that these kinds of restrictions are identified early so
that proper action can be taken to mitigate the design.
c
n..K ow — — — —ir. I
ti =Me %-4p.� --
L ,�.._=�
Figure i
Another challenge that the project may face is with the current
design of the cast -in -place (CI P) wall. In order to cost effectively
construct the CIP wall, the contract will need room to excavate
for the footing. This is demonstrated in Figure2.
saceo,e r.,s I.r.
J u
Figure 2
As demonstrated in this figure, this back cut will likely affect
the columns of the existing bridge. During the constructability
phase, we would review the both the Jefferson and Highway
iii as -build drawings to ensure that future construction would
not impact the structural integrity of the bridges and that any
potential back cuts would be above the existing pile caps.
Additionally, access during construction of the CIP wall will
be restrictive due to the placement of the existing columns.
Extreme caution must be maintained at all times so that
equipment does not strike and damage any of the structural
components of the bridges. The Anser team will also ensure
that the environmental clearance areas also accurately account
for construction activities.
As a lesson learned from the CV Link project, the environmental
boundary of the under crossings did not account for the back cut
required for the cutoff wall construction. The Anser team has
worked with both CDFW and CVWD to mitigate these impacts
so that the project could be built per plan.
On -Street Construction
While the levee and
undercrossing may appear to be
the most technically complex
component of the project, the
on -street work will have its own unique set of challenges, from
both a constructability and engineering perspective.
Project Staging and Schedule. One of our lessons learned from our
City of Indio Herbert Hoover Pedestrian Improvement project
is the success of breaking the project in to manageable stages
of work. Because the project is spread out through commercial,
residential, and school zones, it is important that the contractor
is diligent when they start construction. For example, we would
not want the contractor to start demo work in La Quinta, near
Desert Sands Unified School District and then move into the City
of Indio, and not complete the work within the City of La Quinta
for weeks, or even months later. We will work with CVAG and
the design team to establish reasonable work zone areas which
would not substantially drive costs, while minimizing impacts
to the public as much as possible.
Prior to starting the project, we will review and agree on the
Contractor's baseline schedule. Our team will discuss the
project schedule with the contractor prior to mobilization and
listen to any concerns or enhancements they have relating to
the schedule. When both Contractor and Construction Manager
agree on a schedule prior to starting the project, the project has
a much higher rate of success! —
_ _ _ _ - - - Joints will be separate pours. _ _ _ _ _
Saw cuts recommended (TY
-Dal---I Concrete Mixes Very Ihln pour. suscepUble to cra&ing.-
Patterned Colored Concrete. The ambition of the AML is to truly
live up to its name to where it will be a piece of art. The pathway
will create an amazing user experience with its blends of colors
and shapes. The issue is that each one of these colors and shapes
will require separate concrete pours, which drives up costs and
can lead to challenges with differential settling, joints/cracking,
and color inconsistency between pours. The Anser team is very
familiar with these types of challenges through our work on the
North Park Mid -City project and the CV Link project.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 15 1 Anser Advisory
SECTION 4 (CONTINUED)
Our Lead Inspector, Kenny Casados, has worked through
all these types of challenges during the construction of the
CV Link access points and branded banding. These sections
consisted of similar intricate patterns which required their
own separate pours. We worked hand -in -hand with the
contractor to develop pour plans and methods to cut relief
joints which have avoided over 90/oof cracking.
Prior to bid, Anserwill share our lessons learned with the design
team to ensure contract specification language requiring sample
panels, pour plans, doweling and saw cutting are all in the bid
package. In addition, we'll recommend that language is in the
contract which requires that the same mix design be used in
sections, which ensures a consistent color product throughout
the project
Coordination with Cities, Utilities, and Future Projects
We recognize the need to coordinate with many different
stakeholders on this project, all of which the Anser team has
existing working relationships with. A detailed description of
our communication plan is discussed later. We also recognize
that the AML is not the only planned project within the same
footprint of work and that other agencies have their own
projects to manage.
The AML project is not scheduled to go to construction until Q2
of 2025, meaning there is ample time to coordinate any future
projects currently planned with the stakeholders. However, this
also means that it's likely that projects within our work limits
will be completed ahead of the AML going to construction. The
Anser team has extensive experience coordinating these kinds
of efforts on many different projects including North Park Mid -
City, Bayshore Barrio Logan, and of course CV Link.
■ On the North Park Mid -City project, we actively had to
coordinate with the City of San Diego for outside projects
such as annual slurry seal maintenance, installation of fiber
optics lines, and new building development; all of which
impacted our work zones. Our proposed Assistant Resident
Engineer, Brandon McKay, actively managed each of the
conflicts with our contractor. Preferred critical path activities
were altered, and re -design work arounds were just some of
the solutions the Anserteam came up with.
■ On the Bayshore Barrio Logan project, we are actively managing
a scenario where a local City sewer project within our
work limits has been substantially delayed, which in turn
has caused the Anser-managed project to pivot. We have
proactively worked with our contractor to sequence the
preferred critical path components of the project, so that
construction activities could continue.
We have many simi larexperiences on the CV Link project. CVWD
has hadtwo projectswithin the channel which have affectedour
ability to perform work in the areas, causing us to re -sequence
work. The Dune Palms bridge replacement falls within the
footprint of the current Segment 1 project which required the
Anser team to revise start/stop locations.
In the City of Palm Springs, the City had completed a small traffic
calming project within the CV Link limits which was unknown toCVAC
and the design team. Once construction began, our proposed Resident
Engineer, Tyson Atwood, and Lead Inspector, Kenny Casados, actively
worked with Donn byeno, then with Palm Springs, to incorporate the
existing speed humps into the CV Lintz project.
The Anser team is prepared to actively deal with any curvebal I
that the AML project throws our way and our proposed team
has a proven record of success in keeping projects actively
progressing through all of these types of scenarios.
ADA Compliance
Public safety is a key component to the success of this project.
Nearly every aspect of the project has to be within compliance
of ADA standards. That means pathway cross slopes cannot
exceed 29/oand anythingover5% in the travel path is considered
a ramp and must be treated as such in the design. Through
our workon many projects, but especially on CV Link, our
inspection team has developed comprehensive spreadsheets
which ensure compliance with all ADA standards, while being
able to complete the checks in a timely manner. Our inspection
team will document all ADA components using tape measures
to a 1/16 of an inch and smart levels to the tenth of a degree
to ensure features do not exceed the maximum allowable
slopes.dimensions. If features are found to be out of toerance,
the Contractor will not be compensated for the work until the
ramp meets protect requirements. In addition to permanent
ADA facilities, temporary facilities may be needed to guide
pedestrians during stage construction and closed ramps. We
could not find any mention of how the Contractor should
contruct temporary ADA facilities in the contract documents,
therefore we recommend that these temporary facilities follow
the Caltrans Temporary ADA Facilities Handbook.
COACHELLA VALLEY ASSOCIATION OFGOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 16 1 Anser Advisory
SECTION 4 (CONTINUED)
APPROACH/ WORK PLAN TO SCOPE OF
SERVICES
Bid Administration and
Pre -Construction Assistance
Schedule (a): Anser currently employs a team of
critical path method (CPM) scheduling experts
who are experienced in a variety of scheduling
software, including Primavera P6 and Microsoft Project. For the
Art and Music Line project, there will be three critical phases
to completing the project which are: Completion of Design,
Obtaining E76/Advertise/Award, Construction. A detailed
schedule is shown toward the end of the proposal.
Completion of Design is much more than simply just how long it
will take for the designer to complete the drawings. This is the
critical phase in which all the project stakeholders will have
the majority of their input on the design. Anser has extensive
experience working with all of the stakeholders on the project,
including: Coachella Valley Water District (CVWD), Cities of La
Quinta, Indio, and Coachella, as well as coordination with the
Cabazon Tribe. Having worked with these agencies, Anser has
extensive working knowledge of which agencies tend to stretch
beyondtheir initiallystated review period. We also have a strong
understanding that it will likely take multiple reviews before
obtaining approvals. In order to setup an accurate schedule, it
is critical to set realistic activity durations, as well as allowing for
multiple reviews.
Obtaining E76/Advertise/Award. There is an extensive package
which is required as part of the approval package from Caltrans.
The proposed Anser team are subject matters experts which
in comes to the Caltrans Local Assistance Procedures Manual
(LAPM) has successfully supported CVAG on a number
construction package related to the CV Link program.
Most recently, Anser was asked by CVAG to put plan packages and
provide cost estimates for multiple Caltrans packages with just a few
days turnaround deadline. Anser was able to quickly allocate resources
and completed over 80 manhours of work in just 48 hours.
Once the E76 is obtained, Anser will support CVAG in putting
the bid package out for construction. Again, there are strict
guidelines which must be followed in accordance with the
LAPM. The advertise and award package is always the first item
which is reviewed by Caltrans auditors during the initial project
audit.
Construction. Having managed dozens of bikeway projects,
the Anser team are experts in not only putting together but
managing these linear projects in which the critical path
activities may frequently change. As part of this procurement,
Anser has developed a probable construction sequence which
the contractor would likely follow. This schedule will be further
updated as we progress from 65 to i00% design drawings.
Additionally, as discussed in our Special Issues section, we will
be sure that we capture any outside agencies projects which
could potentially affect our project.
Bid Processes (e): Once our constructability
review is com plete, Anserwi I I then assistCVAG
with putting out a bid package. As discussed
0 above, Anser has extensive experience putting
!0 ui together bid packages in conformance with
the Caltrans LAPM. Once the project is advertised, as we did with
CV Link, we can take the lead in answering any questions which
may arise from potential contractors during that process. Once
bids are open, Anser will complete a comprehensive analysis
of the bid items to ensure that there are significant bid items
which are unbalanced. We will also review each bidder package
to ensure that they submitted complete and responsive bids. A
large part of that review wil I be to ensure that the contractor has
made accurate claims of the DBE goal participation, or a review
of the "good faith effort," which would ultimately need Caltrans
approval.
Budget b : Every successful construction project starts with a great
estimate! Financial expectations determine which projects are
started, but only accurate cost estimates determine which are
completed within budget. Our in-house Cost Estimating group
lead by Andy Kleimola, recognizes the importance of having
reliable construction cost estimates before a shovel ever hits
the ground. Accurate cost estimates are required to create
project budgets, evaluate cost implications of numerous design
decisions as design advances and to analyze the accuracy and
fairness of contractor's estimate submissions.
Not only does the AML add complexities to standard concrete
pathway construction, it also incorporates a number of unique
fiberoptic and other unique lighting elements, all of which are
key to making the pathway a work of art. This is all in addition to
the structural elements that wil I need to be bui It to connect the
AML to CV Link at the La Quinta Access Point. These elements
all come at a cost where budgets are limited. The success of
a project hinges on getting the alignment of budget, scope,
and quality right at the beginning of the project, as well as
the maintenance of that alignment as design progresses. Our
team of estimators will help confirm engineer's estimates, and
when needed we can provide guidance to any discrepancies so
that CVAG may have the most accurate information to make
decisions from.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 17 1 Anser Advisory
SECTION 4 (CONTINUED)
Communication Plan. Given the number of stakeholders on
the project, having a formal communication plan and having
contact information for all members is critical. The Anser team
is unmatched not only its understanding of this, but also with
having already established much of the groundwork requiredas
part of this project.
Through our work on the CV Link project, Anser and Burke Rix have
already developed acommunication plan which contains most contacts
which will be part of the AML communication plan.
We will work with CVAG to refine this list and ensure that
contact information is captured in an organized manner in a
way that anyone new to the project could be brought up to
speed with who the key stakeholders are by simply reviewing
the document. Given the length of the project, it's likely that key
stakeholders may move positions. As such, we recognize that
our communication plan will always be a working document
which will needto be updated throughout the life ofthe project.
Constructability Review (c): As discussed in the Special
Issues section, the Anser team brings knowledge of not only
constructability issues, but also design guidelines, especially as
it relates to bikeway facilities. As shown in the appendices, Anser
has already began its initial list of field observations with the
provided 659/o drawings. A thoughtful review of work adjacent
to right-of-way lineswill be required throughout the project.
During the construction of CV Link, Anser was able to identify several
areas which required either a Temporary Construction Easement or
Slope Easement. By identifying early, Anser was able to put all the
document required in order to obtain these easements with zero delay
to the project.
In addition to constructibility review, Anser will utilize Steve
Latino from Michael Baker to perform a comprehensive
engineering review. Steve has recently worked side -by -side with
Tyson on a number of bikeway project forthe City of Palm Desert.
Their different backgrounds allow for highly detailed review of
drawings which far expand beyond the typical constructibility
review comments.
Bluebeam RevuTM has become the standard software for
constructability review comments, however not all firms use it
to its full capabilities. Effective use of studio sessions, thoughtful
layers, and summary reports are what set Anser constructability
reviews apart. Anserwill mark up a set of plans on the PDFeditor.
There are two benefits with this software which can improve
efficiency and reduce review times between the project team.
First, we can place the drawings in a cloud -based server where
multiple team members can comment directly on the PDF.
This will allow simultaneous reviews rather than back and forth
commenting between the team.
Second, once all the comments are compiled on the marked -
up pdf set, the software can export a review sheet, which
clearly identifies the page number, comment and most
importantly a picture of the item being discussed. This report
is to supplement or replace the excel spreadsheet typically
issued as the tracking log for the constructability comments.
When reviewing comments, there is no need for a set of plans
and excel sheet. This report will combine both and make for
more efficient, productive meetings with the team. Additional
sketches and drawing details containing recommendations for
package improvements will be provided to supplement the
comment log to ensure clarity. The comment/response log will
be supplemented with full-size sheet plans with markups for
each project.
Mitigation Measures and Environmental Requirements (d):
Through our experience on CV Link and other projects, Anser
has a strong understanding of the environmental requirements
required to complete the Art and Music Line. These will include
mitigation measures for burrowingowls, nesting birds, and bats,
among others. Additionally, there will be cultural requirements,
at minimum, for work that takes within the Cabazon and
Twenty -Nine -Palms right-of-way. Anser has teamed with LSA
who has a local office in Palm Springs and had been providing
local support to the Coachella Valley foryears. Along with Anser,
LSA has personal working relationships with the local agency
representatives, including)acob Skaggswith the Departmentof
Fish and Wildlife (CDFW).
Anser, with the support of LSA, will complete a thorough review
of all environmental documents and place relevant items in
our CPM schedule. A risk analysis of the current construction
schedule will be reviewed with the CVAG so that thoughtful
decision on when to release projects to bid can be made.
We will take extensive care to ensure that all environmental
requirements are capture in the projects Special Conditions and
the time of bid.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 18 1 Anser Advisory
SECTION 4 (CONTINUED)
Construction Management
O Project Administration (3)
, Procedures Manuals (c, g, h): The Anser Team
understands that we will have to create and
maintain hundreds of documents throughout
the project duration to provide proof that the project was
administered in accordance with Local, State and Federal
guidelines. The requirements of the Caltrans Local Assistance
Procedures Manual (LAPM) provide the minimum filing system
thatwe must adhere to. However, a project of this size wi I I require
that we implement the full filing system established in the
Caltrans Construction Manual. Anser's Resident Engineer, Tyson
Atwood, and Document Control specialist, Amelia Fitchett, have
expansive experience utilizing the Caltrans filing system and
together have successfully passed many Caltrans audits, including
ones for CVAG, typically with just minorcomments.
Coordination & Reporting (b, d, j): Open communication is one
of the keys to success of any project. The Anser team has an
existing working relationship with not only CVAG, but the
majority of stakeholders on the project. As discussed above,
Anser understands the importance of having a written plan
when dealing with so many stakeholders and partners on the
project.
Once the project is awarded, the Anser team will kick-off the
project with a pre -construction meeting which will include all
project stakeholders. Clear lines of communication through the
Anser construction management team will be reinforced at this
meeting. During the construction phase, it is crucial to keep all
stakeholders informed of the progress of the project. In order
to manage the flow of information and keep the focus on the
important issues, Tyson will institute weekly contractor progress
meetings. Again, all stakeholders, such as the contractor, CVAG,
the design engineer, CVWD, RCTD, and all Cities and Public
Relations Officers will be invited to attend. Minutes of issues,
discussions, statements, and commitments will be recorded
and distributed after every meeting. Weekly and monthly
Construction Progress Report will be provided to CVAG staff
and other stakeholders as approved by CVAG identifying the
progress made, upcomingwork, and any issues that have or may
be developing.
Anser is very familiar with the formatting requirements for these
reports as Anser helped develop many of the standard reportsstill used
by CVAC as part ofsetting up the document control system on the CV
Link project.
Progress Payments (a, e, 0: Priorto biddingthe project, Anserwill
ensure that there is specification language which clearly define
the payment schedules of the project. Anser will follow the
time -tested procedures established in the Caltrans Construction
Manual for the tracking and payment of materials placed by
the Contractor each month. Daily reports become the basis
of documenting the material placed by the Contractor. This
information is transferred to quantity (or Q) sheets that are
established for each item of pay. All quantity sheets are backed
up with calculations, photos or other means of verification, and
are checked by an independent party prior to being submitted
to Tyson. Payment vouchers are generated, along with a
breakdown of reimbursement from the various funding buckets
on the project. Monthly estimates are submitted to CVAG after
discussion with the Contractor and confirmation that payment
items are accurate. A detailed discussion on the process can be
found in the Cost and Schedule section.
Monitor Contractor's Schedule (i): We will ensure that the
Contractor is complying with the requirements of the monthly
schedule updates and closely monitor the critical path to avoid
delays and disruptions whenever possible. Non -working days
anddays added bythe change order processwill be incorporated
into schedule updates. Our unique approach to scheduling is
discussed in detail in the Cost and Schedule section.
Partnering (1): Anser firmly believes and
practices proactive management on the job
and will make every attempt to resolve issues
at the lowest level possible. As discussed later
in our approach to claims, even when there
are disputes on a project, Tyson maintains the highest level
of professionalism and never takes a difference of opinion
personally. While we have a proven track record of being able to
resolve disputes, should CVAG feel that a partnering session is
needed, Anser will participatewith an open mind.
Quality Assurance Program (QAP) Manual (m): Anser has
managed hundreds of millions of dollars in federally funded
projects, as such, we are extremely familiar with the Caltrans
Quality Assurance Program in addition to the approved CVAG
Quality Assurance Plan (QAP). The Anser team is currently
administering the CVAG QAP by accurately tracking the
quantities of all materials placed on the project to ensure that
we are meetingthe minimum testing requirements as outlined
in the CVAG QAP. To increase cost effectiveness, Anser has
teamed with Earth Systems who will perform all of our Quality
Assurance Material Testing. Earth Systems has a Caltrans
accredited laboratory locally in the Coachella Valley, along
with local staff who are also Caltrans certified. It is through
these accreditations that we will comply with the Independent
Assurance (IA) requirements of the QAP Manual.
Labor Compliance (n): Standards established by the Department
of Industrial Relations (DIR) require that Contractors adhere
to specific pay requirements and submit certified payrolls to
the managing body. Daily reports, along with employee EEO
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 19 1 Anser Advisory
SECTION 4 (CONTINUED)
interviews form the basis for reviewing contractor certified
payrolls. During audits of construction records, certified
payroll records are an area that is most often reviewed.
Tyson has extensive experience providing Labor Compliance
administration and will be supported by Chia -Chi Wang of our
DBE subcontractor, DESI. Any deficiencies will be reported and
pursued. Withholding of payment may be utilized to achieve
compliance.
Environmental Compliance (h): As previously discussed, Anser
and LSA will ensure that we are meeting all the environmental
requirements set forth in the environmental documents. In
the construction phase, we will ensure that our contractor is
complying with all of the environmental requirements for the
project that would now be in the special provisions. We are
anticipating that the majority of the environmental monitoring
will be required to take place at the two ends of the projects
which tie into CV Link.
Through our work on CV Link, we know that the surrounding area
around Promontory Point has cultural resources which require
additional monitoring. We also know of similar requirements at the
Dillon Road connection, which takes place on tribal lands.
In addition, monitoring of burrowing owls, bats, and other
nesting bird will be required along the channels and under the
bridges. From our initial site walk of the evacuation channel, we did
notice a hest inside one of the bridge abutments which will need to be
addressed prior to construction.
SWPPP AQMD, and Environmental Coordination (o, p):
Construction activities are ever changing for various reasons
throughout a project, thus the reasons for continuous
monitoring on a project. Knowing the appropriate BMP's for
various construction activities is key to properly implementing
a SWPPP and Dust Control Plan, especially on a project with so
many working locations. Our team is extremely experienced in
both Storm Water and Air Quality as Tyson is a Qualified SWPPP
Developer's (QSD) and is also SCAQMD Coachella Val ley Fugitive
Dust Control certified. Tyson and members of the Anser team are
well versed in the new requirements set forth in the 2022 Construction
General Permit which will become effective September7, 2023.
Projectdust is always a challenge when working in the Coachella
Valley, thus the additional requirement unique to the Coachella
Valley in which the contractor will be required to submit a
Dust Control Plan to AQMD. We have found that dust can be
especially challengingwhen workingwithin the channels. Often
times, dust complaints are blamed on the project, when in fact
the dust in large part is a biproduct of high winds and regional
dust. Anser has extensive experience with managing dust
throughout the valley.
On the CV Link project, Anser wrote a change order to the contractor to
apply temporary tachi Fier to areas within the channel so that it could
be proven to AQMD that the project was doing everything possible to
stay within compliance. We will take this lesson learned and ensure
that such dust control measures are requirements in the contract
documents during the constructability review phase.
In addition, Anser will ensure that the Contractor maintains
properly permitted dust levels, as well as minimizes project
track out from the site. Each project will have some scope
of work requiring concrete, so our inspectors will ensure the
contractor has washouts setup to rinse out the trucks. Tyson will
continually monitor the site for compliance and strictly enforce
that all mitigation measures described in the Dust Control Plan
and/or SWPPP are being implemented and documented on a
daily basis.
As-Builts (q): As part of our daily and monthly documentation
we will maintain "As -Built" drawings. Developing these items
in a contemporaneous fashion ensures the most accurate
memorialization of the activities as they occur in the event of a
time impact or dispute. We will keep a "Live" as built set of plans
using Bluebeam Studio Software. This will be a tool that each
memberoftheAnserTeam can utilize andwill have access tothe
most current set of plans at any time. At the end of the project,
these electronic files can easily be bundled and transmitted
to be updated into the electronic plan set and transmitted to
CVAG, and all applicable stakeholders, for archiving.
iTConstruction Coordination (3)
❑ Active construction coordination is discussed
a through various section of the proposal
0 = such as our under of project stakeholders,
a=
communication plan, and SWPPP coordination.
As demonstrated throughout this proposal, Anser has a strong
understand of the coordination required to complete the AML
project. Tyson Atwood, will lead the Anser Team as the Resident
Engineer and looks forward to continuing his work as being the
day-to-day contact with many of the same parties associated
with the projectwhich he is currently workingwith through his
workwith the CV Link project.
Construction Inspection (4)
Field Inspection (a-q): Anser offers experienced
Fzzoand qualified inspectors with extensive
experience with Greenbook and Caltrans
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 20 1 Anser Advisory Nkl
SECTION 4 (CONTINUED)
standards. These individuals will provide daily on -site
observation and inspection of required materials, equipment,
and methods of construction and assure that the project
remains in compliance with all contract documents, permits
and regulations. Our inspectors are also cross trained and versed
in compliance as it relates to ADA, traffic control, SWPPP and
AQMD PMio inspections. Our digital daily inspection reports
discuss conversations, labor, equipment, quantities, location
and full description of work completed during the shift, as well
as adherence to the compliance aspects of the Contract backed
up with photographs. These daily reports are the backbone of
hour our quantity (Q sheets) are generated during the progress
payment, which is discussed in the above section.
Our work plan is to eliminate surprises to CVAG by being
proactive in working with the Contractor to identify and
resolve deficiencies or problems as quickly as possible at the
field level. Our inspectors will utilize the three (3) week -look -
ahead -schedule to properly advance the construction effort
by looking ahead, and by assisting the Contractor in resolving
issues before they become problems. All work will be inspected
for conformance with contract plans, specifications, and current
specified and standards. Inspection documentation, processes,
materials testing, and quality assurance will all be in accordance
with CVAG and Caltrans Quality Assurance Manual.
Comprehensive and accurate daily records of field activities
become the go -to document when a dispute comes to light.
Early recognition of an issue allows added opportunities for
resolution. If extra work is required, accurate documentation is
critical to determine the actual costs incurred and come to an
accurate evaluation of cost. When disputed work is not resolved
by change order, it must continue under a potential claim. In
this case, the Anser Team will create a file number to track the
Contractor's effortwith added scruti ny. Accurate documentation
of manpower, equipment, and materials will allow us to disallow
or minimize the cost of disputed extra work.
Project Support (5)
Construction Surveys (a-d): Anser has teamed once again with
the local branch office of Michael Baker International (MBI) to
provide surveying services. MBI understands the importance in
providing high quality services. The team we have assembled for
this project propose to carry out those services to enhance the
CVAG's outstanding reputation in providingtheCoachellaValley
with safe, reliable transportation and amenities throughoutthe
COACHELLA VALLEY ASSOCIATION OFGOVERNMENTS
Professional Engineering Services, Arts and Music Line Project
Valley. Our approach to the project is a proven and efficient team
approach with California Licensed Land Surveyors engaged in
every work task throughout the scope of work. The local Palm
Desert Office currently has four (4) Licensed Surveyors and four
(4) fully capable field crews employed full time working on
Coachella Valley Projects.
Many times, it is the surveyorwho discovers an inconsistency or
deviation from design. While it is intended that deviations from
plans do not occur, they inevitably may. Minor deviations are
normal and can be dealt with routinely by the Party Chief and
the Resident Engineer, who will keep the staff informed. When a
plan deviation is other than minor in nature, the Party Chief will
assess the problem and gather enough survey information for
the Resident Engineer to resolve the issue without undue delay.
TheAnserand MBI team have an extensive working relationship when
it comes to fixing errors in the {geld, as the CV Link project has been
rattled with elevation busts throughout the project. TheAnserandMBI
team have worked together to obtain additional pothole and elevation
data ahead of when the contractor wants to begin their work. Working
together, we have saved CVACio's, if not, ioo'softhousands ofdollars
in additional re -work costs.
In addition to construction staking, the Anser and MBI teamed
have worked through a number of right-of-way issues on
the CV Link project as well. MBI has assisted Anser and CVAG
in preparing legal documents which have enabled CVAG to
get necessary temporary construction easements and slope
easements which were not previously identified but required in
order to complete the CV Link project.
Material Testing/Source Inspection (e): Anser has teamed
with Earth Systems who will perform all material testing and
source inspection. Earth Systems has extensive experience
throughout the Coachella Valley and currently provides on -call
geotechnical service to Riverside County Flood Control and
Water Conservation District, Riverside County Transportation
Department, the Cities of Rancho Mirage and Indio. They also
often work on projects for the Cities of Palm Springs, Cathedral
City, Palm Desert, La Quinta and Coachella, as well as Coachella
Valley Water District. They have a local, Caltrans certified
laboratory located in La Quinta.
Public Outreach (c): Anser has once again
teamed with local small business, Burke Rix
Communications (BRC) to helpsupportourpublic
outreach effort. BRC has extensive experience in
providing a wide array of community outreach services on large
infrastructure projects. Their team maintains relationships with
community leaders and stakeholders throughout the region and
particularly in the Eastern Coachella Valley. BRC has a positive
track record in working closely with CVAG on CV Link and has
21 1 Anser Advisory 1
SECTION 4 (CONTINUED)
demonstrated to the public that the agency can deliver quality
transportation projects with a community driven approach that
is transparent and timely. The Anser and BRC is able to hit the
ground running in providing timely and efficient outreach and
communication services forthe AML project.
Puhl it i7u{VGar19
BRC is currently provides public outreach and communications
services with Anser on the construction management of the
CV Link project. In this role, BRC closely coordinates with local
agencies that include the AML cities of La Quinta, Indio, and
Coachella. BRC also coordinates with many of these cities
police departments as well as with other stakeholders such as
the Desert Sands Unified School District, Desert Healthcare
District, SunLine, property owners, chambers of commerce,
community -based organizations, and bicycle groups. BRC
proactively coordinates with these stakeholders and the public
to inform and raise awareness regarding project updates. The
BRC team has developed and disseminated bilingual notices,
social media tool kits, and signage. They also regularly maintain
the project website and social media channels. BRC manages
the construction project hotline coordinates with our team
on quickly responding to inquiries. As a local firm, BRC can
connect with residents and businesses on a personal level and
immediately respond in person. All calls and any subsequent
response are logged for the record and maintained.
Construction Communication Plan
As discussed in preconstruction, BRCwill develop a Construction
Communications Plan for the AML that will be a comprehensive
document designed to guide construction communication
and outreach in a timely and easy -to -understand format that
leads to public understanding and support of the project. The
Construction Communications Plan will also address planning
for project -related emergencies, notices, website content,
newsletters, social media, coordination with local agency PIO's
on outreach, coordination with the AML Non -Infrastructure
Program Manager, and presentation materials for various
audiences. BRC provides most of these services now for the CV
Link projectand can streamline these efforts forthe AML project.
Community Meetings and Events
The BRC team will help plan, facilitate, and promote community
meetings and presentations prior to construction and
throughoutthe projectas needed. BRC has extensive experience
leading virtual and in -person meetings for CV Link and many
other projects. BRC worked closely with CVAG staff on the first
CV Link ribbon cuttingceremony in Palm Springs and Cathedral
City as well as the groundbreaking ceremonies in Palm Desert,
La Quinta, and Indio. All of the ceremonies were promoted by
BRC in partnership with CVAG and were very well attended! The
BRC team handed event logistics and marketing that included
rentals, signage, colleterial materials, and photography/video
services. BRC offers full -service in-house event services that
include:
• Event Planning Er Logistics
• Program Development
• Design and Production of all Collateral Fr Marketing Materials
in English and Spanish
• Event Marketing, Advertising and Public Relations
Public Outreach Events and Stakeholder Management
As part of the team that launched the CV Linkproject, BRC helped
lead the unique approach in utilizing the many community
events in the Coachella Valley to help educate, raise awareness,
and receive support about the project. BRC strategically
identified community events throughout the Valley and created
an engaging booth with project
literature and promotional items to iNk vut*
engage visitors. BRC staffed dozens of
events over the years for CV Link and
created a large database of people
interested in the project that were
segmented and contacted for various LINK
communications. The BRC team
includes bilingual speakers
that can help interpret at
events and translate materials.
This experience gives BRC the
ability to fully support the
AML project and the Non -
Infrastructure Program with
any public event. irl*
LINK
COLLATERAL MATERIALS
BRC has an in-house award -winning graphic designer with
extensive experience developing all types of bilingual collateral
materials that can include:
» Project Factsheets, FAQs, and Notices
• Signage and Posters
• Promotional Materials
• Direct mail
PowerPoint presentations
COACHELLA VALLEY ASSOCIATION OFCOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 22 1 Anser Advisory
SECTION 4 (CONTINUED)
Our team can also provide in-house photography as well as
project management on video and drone services.
BRC currently maintains the CV Link project website and can
quickly with the CVAG Public Information Office to create
content for the AML tab on the CVAG site. The BRC team's
experience workingwith CVAG IT and managingthe CV Link and
other program sites will allow work on the AML to be seamless
and consistent.
Permits d : Havingworkedextensively throughout the Coachella
Valley, Anser is well versed in the various permits required to
complete a project such as the AML. We anticipate that there
will be dozens of permits required to complete the project.
Each Citywill require multiple permits to complete work within
their right-of-way; as will CVWD, County of Riverside, and the
Tribes. In addition, there will be environmental permits such
as the stormwater general permit, AQMD permit, as well as
requirements notyet knowwhich will be identified in the NEPA
documents, which our teaming partner, LSA will identify and
ensure compliance with.
While this may be significantly higher than the average number of
permits required for a typical construction project, the Anser team
is managing twice as many on the CV Link project. We have existing
relationships with all of the permitting agencies and have built a level
o f trust with all those which administer these permits.
The Anser team will continue fostering those relationships and
ensure that we are in compliance with all permits throughout
construction. We will continue to reviewall permits at minimum
of a monthly basis to ensure that extensions are filed and
executed well ahead of the expiration date, ensure no lapses in
permits.
Cost and Schedule (6)
S
Cost Control (a): At the beginning of the
project,AnserwiIIsetupamasterspreadsheet
which tracks payment quantities of each bid
item, as well as total payment amounts each
month to the contractor. Change Orders,
Extra Work, and Potential Change Orders will all be tracked in
their own report. Additionally, payment for Owner Furnished
Materials and Materials on Hand will be separately reported
on. A monthly project summary report of all these items will be
providedto CVAG on a monthly basis. Tyson will closely monitor
the project contingency and report on it on a monthly basis.
We will analyze both bid items and CCOs to estimate the total
contingency used. It is imperative to communicate the project's
budget with CVAG so that project mitigation measures can be
made and/or additional contingency funds can be secured.
At the end of each pay period our i nspectors wi I I prepare Quantity
(Q) Sheets that clearly and accurately calculate the quantity of
work completed in the past period. The quantity sheets wiII show
calculations or field measurements to justify proper payment
to the Contractor. Upon completion by the field inspector, the
Office Engineer will check the Q Sheets for accuracy and input
the quantities into the Anser tracking log spreadsheet. Prior to
finalizing the payment and submitting to CVAG each month,
Tyson will perform a final check of complete payment package.
With multiple locations and various site conditions on each
project, it is possible that some items may experience quantity
overruns. The Anser team will closely monitor each item of work
and look for trends early in the operation that could raise red
flags of an overrun. If that does happen, Tyson will immediately
bring it up to CVAG and begin to form mitigation ideas in order
to save project costs.
Tyson has had great past success managing cost overruns. While a
Resident Engineer on the County of San Diego AC Overlay project,
Tyson accurately forecasted that the asphalt concrete (AC) quantity
wasgoing to be severely overrun. Due to this, the design engineer was
able to revise originally proposed treatment types from mill and inlay
to overlay, saving on AC tonnage. Ultimately all planned roadways
were completed with an AC treatment and the project finished sl ightly
under budget.
Schedule Control (b): Minimizing impacts to the traveling public,
local residents, and businesseswiII be critical to the success ofthis
project. There are time sensitive notifications, submittal review
times, and utility notifications that will need to be incorporated
into the project specifications so that the Contractor can list
these critical items into the CPM baseline schedule and tie them
to a specific activity. During each monthly update review, the
engineer and Contractor can look at these items to ensure the
team is making the proper notifications to the utility or turning
in and reviewing submittals.
We ensure that the Contractor is complying with the
requirements of the monthly schedule updates and closely
monitor the critical path to avoid delays and disruptions
whenever possible. Our unique approach involves analysis of the
Contractor's schedules on a weekly basis, using the information
from our inspectors' daily reports, meeting minutes, submittal
logs and other project records. This schedule analysis approach
COACHELLA VALLEY ASSOCIATION OFGOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 23 1 Anser Advisory NN
SECTION 4 (CONTINUED)
is extremely proactive and provides CVAG with notice of any
potential delays. We believe the project schedule isacritical tool
for managing project completion, when fully integrated into the 40
project's requirements. Ourexperience indicates thata proactive
scheduling approach with clear specifications and effective
administration is a proven methodto reduce riskand liabilityon
the successful completion of the project for both CVAG and the -
Contractor. The construction management team enforces the
scheduling requirements in the Contract provisions, which are
key to place the project in a positive position in case of claims.
Our team is versed in Primavera P6, Phoenix, Expedition, Claim
Digger, MS Project and other programs. We have experience
dealing with various schedule types, and specific analytical
approaches, including CPM, fragnets, move in schedules and
contemporaneous period analysis as an effective method of
characterizing and quantifying delays.
Our unique approach involves analysis
of the Contractor's schedules on a
weekly basis, using the information
from our inspectors' daily reports,
meeting minutes, submittal logs,
Weekly Statement of Working Days,
and other project records. This schedule analysis approach
is extremely proactive and provides CVAG with notice of any
potential delays. We believe the project schedule is a critical tool
for managing project completion, when fully integrated into the
project's requirements. Ourexperience indicates thata proactive
scheduling approach with clear specifications and effective
administration is a proven method to reduce risk and liability
on the successful completion of the project for both CVAG
and the Contractor. We have experience dealing with various
schedule types, and specific analytical approaches, including
CPM, fragnets, move in schedules and contemporaneous
period analysis as an effective method of characterizing and
quantifying delays.
CM Staffing Plan (c): During the Baseline review, our Resident
Engineer, Tyson Atwood will sit down with our Project Manager,
Lucas Rathe and CVAG to discuss potential staffing needs. We
will identify key activities in which part-time personnel will be
required. We will also analyze the anticipate location of each
overlapping activity to ensure that we have adequate resources
to ensure Quality Assurance of the project. Anserfield personnel
arewell cross trained and can manytimes fulfill multiple project
roles.Wewill lookforopportunitiesto utilize staff inthis manner,
reducing the total number of hours required on the project. Our
proposed resource plan will be shared with CVAG for additional
input and approval. Should major changes be made to the
project schedule, Tyson will again work with Luke to ensure that
we have the proper amount of resources on the project.
Contract Change Order and Claims (7)
Change Orders(a-d): Whether it be an unknown utility, design
omission, or Owner requested design modification; change is
an inevitable part of construction. Anser will advise CVAG of all
situations when a contract change order should be submitted
to the contractor. Proper backup documentation, emails,
approvals, relevant photographs, and reports are always kept in
the project file to support the terms of the Change Order. Anser's
pri mary mechanism for change managementwil I beanegotiate
lump sum agreement. For these agreements an independent
cost estimate (ICE) will be provided with each change order. If
the scope cannot be clearly defined, or if Tyson cannot agree to a
cost with the Contractor, then a Force Account Contract Change
Order (CCO) will be issued. Tentative agreements will be issued
daily by our inspector to the contractor for all work which is
beingtracked under force account, for any work which may later
be disputed. Anser will write the change order, accompanying
memorandum, and package all backup necessary prior to
submittingto CVAG forfinal approval.
Claims e:Anserbelievesandpracticesproactivecommunication
and proactive management which promotes collaboration on
the job and will make every attempt to resolve issues before
they become disputes. However, we will vigorously defend the
interests ofCVAG and explicitly enforce the contract documents.
Our Team employs claims experts with a proven track record
with Caltrans and other public agencies on projects of all sizes.
The Anser Team brings valuable "lessons -learned" and as -
needed advice on resolving and mitigating potential contractor
claims. The core of the Anser Team Risk Management strategy
is to ensure assembling a well-defined bid document. We will
monitorall site records of events, labor, materials and equipment
for potential claims or delay issues. This contemporaneous
data will be essential when analyzing a contractor's claim and
crucial to refute parts of it. Our team will assemble complete
"issue binders" of every issue that will contain all relevant RFI's,
change orders, correspondence, pictures, inspector's dailies,
cost analysis and schedule analysis. These documents will
be electronically linked in our document control system for
easy retrieval by CVAG staff for review. Our objective will be to
minimize misunderstandings by providing clear and concise
analysis of all the major issues on the project.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 24 1 Anser Advisory
SECTION 4 (CONTINUED)
Safety (8, a-d)
Safety is Anser's number one priority. This
includes the safety of the travelling
public, the contractor, and our team.
We adopt a zero -tolerance culture for
preventable accidents to ensure that
every team member and public drivers
go home atthe endof the day. Every memberofourconstruction
team has an obligation to never walk by an unsafe act. We will
require the contractor to submit an Injury and Illness Protection
Plan (I I PP) for all their operations for the project and make sure
the contractor is held accountable for enforcing their plan. If we
see something that goes against the Contractor's plan, we will
shut down the operation and call a meeting to make sure safety
is the numberone goal of the project. Safety is the responsibility
of everyone on the team and, at minimum, we will perform
document weekly and monthly safety checks which will be sent
to our contractor and filed as part of our construction files.
For the Art and Music Line project a few of the high priority safety
items the Anser team will lookout for are machinery working in
close proximity to each other; traffic control; fatigue due to hot
weather conditions, and slips, trips, and falls.
Additionally, there will be added safety requirements when working
in the La Quinta Evacuation channel. This includes fall protection,
both during and after the CIP retaining wall construction, carbon
monoxide monitoring for equipment uses underneath the bridges, and
low objects as we will be in close proximity to the existing bridge decks
and hanging utilities.
Finally, it's likely that we will need to remove some hazardous
materials/waste as a result of the existing homeless
encampments. The Anser team has experience with this on the
CV Link project and will ensure thatthere is a bid item allowance
for such cleanup at the time of bid to ensure the safety of our
workers.
tl.-
•...
.�- .1V,iJiwwtn
[3w�p�N� �sk�q
YgGwM 9iMm+w
IF11 .'Ya
y�1 �
......-gyp
SharePoint example - Project Closeout
Project Closeout( 6a-h)
Anser believes that punch list items should begin well before
the near completion of a project. Following this logic, Anser
has established an innovated way to streamline this process
utilizing an interactive, "live' and always up-to-date punch list.
This web -based punch list (using a cloud -based software such
as Microsoft SharePoint; please reference the bottom left
example) can be viewed by anyone at any time and is always
current. Anser has even developed an app for easy data entry.
The benefit is that the CM, contactor, and other agencies can
have certain permissions to view, update and status the log. The
CM inputs items on the logwhich the contractorcan view, correct
the items, and update the logonce the item is complete. The CM
will receive notification that punch list items are completed and
can verify completeness in the field and update the list. This log
can be accessed and modified in the field using a smart phone
or other mobile device. This streamlined process eliminates the
needs for meetings, reduces the number of transmittals to/from
the contractor and increases efficiency of the project team.
Anser has had a lot of success using this feature on the Segment i CV
Link project. The punch list has evolved into a project completion list
with several different ways to f 1 ter the data that make management
of long, linear project much more feasible. We would implement a
similar system which would be tailored for the features of the AML
project.
As discussed early, throughout the duration of the project,
our Resident Engineer will keep an electronic set of "as -built"
plans utilizing the Bluebeam software previously described. In
utilizing the Bluebeam software, this ensures that A) our Field
Inspector always has the latest information, and B) as -built
packages are complete and ready to send to the design engineer
for review at the cl ick of a button.
Tyson will complete both a proposed and final payment to the
contractor. Hewill assistCVAGwith filingof all required closeout
documentation, including the "Notice of Completion" He
will supply CVAG and applicable stakeholders with a separate
package containing all manuals, warranties, and other such
guarantee's as they relate to the individual project. As part of the
final deliverable of all project files, a final project report, which
will include lessons learned, will be reviewed with CVAG. Anser
will complete all project closeout activities in accordance with
Caltrans LAPM requirements.
Anser has provided the following Responsibilities Matrix on
the subsequent page.
COACHELLA VALLEY ASSOCIATION OFGOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 25 1 Anser Advisory
The following includes a detailed breakdown of hey responsibilkities by personnel.
Arts & Music Line
Responsibility Matrix
P= Primary Responsibility
=Support Role
R= Review
= Approve
C = Consult if Necessary
a
'''
v
.�
°C
c m
N
a
w e
E.
L o
`u
H a
z
M
v
n
a
LL
°
=
E
u`o
a
\
z
c
W
2
~
,.
Randy
Bowman
Tyson
Atwood
Brandon
McKay
Amelia
Fitchett
Scott
Walker
Kenny
Casados
Var.
Melanie
Lopez
Chia -Chi
Wang
Shawn
Paroline
LSA
MBI
Earth
Systems
RE Weekly Report
C
P
S
S
Weekly Progress Report
R
A
R
S
P
Monthly Report
R
A
P
S
Labor Compliance/EEO Review
C
A
R
S
P
DBE Compliance Review
C
A
P
SNR
5
5
QC Testing Review
C
A
P
SQA
Testing Review
C
A
P
S
Progress Pay Estimate
C
A
P
S
S
5
Weekly Statement of Working Days
C
A
R
P
Change Orders
A
A
P
5
5
S
0
Request for Information (RFI) Review
C
A
P
S
S
Submittal Review
C
C
P
S
S
S
LAPM Document Control
C
A
R
P
R
Construction Staking Request
C
C
A
S
R
P
Material Testing Coordination
C
C
P
5
5
S
R
Utility Procurement
C
C
S
S
P
Bi-WeeklySafety Meeting
C
A
P
S
S
S
S
S
S
S
S
S
S
Schedule Review
C
A
S
5
P
SWPPP Monthly Check List
C
A
R
P
Field Daily Report
C
A
R
S
R
P
P
Construction Staking/Cut Sheets
C
A
R
S
S
P
Safety Review/ReportingReview/Reporting
C
A
R
S
P
S
-p
SWPPP Field Review
C
A
R
S
P
S
N
Labor Compliance Interview
C
A
R
5
P
5
R
R
LL
Environmental Compliance
C
A
R
S
P
Punchlist&Completion List
C
A
R
S
P
S
Non -Conformance Report
C
A
P
S
S
S
s
QA Material Testing
C
C
R
S
S
S
S
P
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 26 1 Anser Advisory
SECTION 4 (CONTINUED)
METHODS FOR QUALITY, BUDGET AND
SCHEDULE CONTROL
Anser prides itself in successfully delivering projects with the
highest quality of work productwhile meeting our clients' needs
and expectations. Our quality procedures encompass all aspects
of our performance. We implement project management
procedures to assure accountability of the team using the
project control methods described below to keep this project
on schedule and within the authorized budget. Additionally,
we have quarterly internal audits that vet the completeness of
daily reports and confirm that only relevant and contractual
information is recorded.
Project Management Plan for Successful Delivery
In accordance with Anser standard procedures, Lucas Rathe, PE,
our Project Manager, develops and issues a Project Management
Plan (PMP). The PMP details our management and technical
plan for successfully delivering your project, including quality
procedures, and details the following subjects:
Project Overview. Describes the overall project, your project
goals, your expectations of Anser, and our scope of work.
Organization/Roles and Responsibilities. Provides for a clear
chain of command, confirms the role and decision -making
authority for team members. This can also be used as our
communication plan.
Deliverables/Schedule. Ties deliverables to the schedule,
details deliverable requirements andstandards, and includes
a copy of the contractor's detailed schedule once it is issued.
Document Control Procedures. Details how we will manage
hard copy and electronic files and provides a quick reference
sheetforthe filingsystem.
Inspection and Sampling/Testing Procedures. Provides a quick
reference sheet for inspection protocols with references to
standards, forms, and requirements.
Standard Forms. Provides easy access to all forms we will use
on this project. All forms will be in accordance to the Caltrans
Manual.
The PMP is issued to every project team member, including
CVAG, andweaskteam members to reviewandsign itto confirm
that they have read and understand our approach to delivering
the project. The PMP is regularly updated to reflect the current
status of the project and any changes that have occurred,
such as changes in standard forms. Using the PMP we align
the entire team around your goals, objectives, standards, and
requirements. This approach enables us to achieve consistent
and predictable results the first time and helps us avoid costly
and time-consuming rework.
In addition to planning for quality, we regularly verify that we
are following the plan and meetingyour expectations. Verifying
compliance is the responsibility of our Resident Engineer, Tyson
Atwood, who performs periodic quality assurance audits to
confirm that procedures we comply with all project standards
and procedures, including:
• Field Safety
» Office Procedures
• Submittal tracking and review
• Timely schedule review and monthly updates
• Project f le organization
• Timely daily reports
• Timely RA review and response
• Timely response to claims notices
• Accurate monthly progress payments with support documents
• Timely meeting minutes
• Material testing requirements and resolution of disputed test
results
• Documentation for project permits
• Timely contract change orders and independent estimates
review
• Current As -built status
• Timely issuance of Relief of Maintenance
Following the audits, improvement notifications are issued for
any deficiencies and Luke will follow up with the CVAG PM to
confirm that appropriate corrective action is taken. To meet or
exceed your expectations, Luke will meet with CVAG every six
months to perform an evaluation of our team where we ask
you about our performance. Following this discussion, Luke
will meet with Tyson to provide feedback and help the team
adjust how we perform our work so that we provide you greater
satisfaction with our services. The end result of our approach is
continuous performance improvement over the duration of the
contract.
In addition, the Anserteam will work closely with CVAG to verify
and monitor contractor's adherence to the contract Special
Provisions, Plans, Standard Plans and Caltrans Manuals as it
pertains to Quality Assurance (QA.) QA testing and inspections
will take place to ensure the accuracy and compliance of the
work. QA sampling and testing will be in accordance with
Caltrans Test Methods (CTMs) per the frequencies dictated in
the Caltrans Construction Manual, Testing Frequency Tables.
Test that are not covered by CTM will be covered by American
Society for Testing and Materials (ASTM) International. A
Caltrans certified laboratory shall always be utilized to perform
soils and material service testing to validate contractor's test
results. The Anser team will ensure that all test machines are
calibrated annually or more frequently using devices of accuracy
traceable to the National Bureau of Standards. Batch plant
and source inspections shall take place by individuals that are
certified forthis type of sampling.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 27 1 Anser Advisory N
SECTION 4 (CONTINUED)
Anser will keep daily reports and logs to track the stages of the
work, progress, and any required Quality assurance testing. The
logs will track test performed and their results, samples taken,
and any test or samples taken by the construction management
team will assure current status of certifications, non-compliance
reports (NCRs), submittals, and any other aspect of quality
assurance and inspection that should be tracked for compliance
and proper record keeping.
Document Control
The Anser team, led by Tyson Atwood, will
establish, manage and coordinate a document
control system to manage and store all project -
related information for the Project. We are well
versedwith the Caltrans uniform filingsystem and intendto use
the same system both electronically and hard copy.
A unique tracking numbersystern will be implemented to provide
control of all documents, records, reviews, and writings, and
to provide for expediting the transmittal of all construction
documents. This tracking system will account for all letters,
memos, submittals, shop drawings, change orders, Requests
for Information, Request for Qualifications, notice of potential
claims, suspended correspondence, and all other pertinent
sources of information. Tyson will also establish and maintain
an issue tracki ng system. Both tracking systems will use a unique
numbering system to ensure document control. The system will
contain all issues requiring the attention of all stakeholders. All
meeting minutes will be recorded sequential ly to ensure that al I
actions items are tracked and completed in a timely manner to
avoid potential project delays.
We will utilize an electronic system to allow complete storage
of all project documents electronically in addition to customary
storage of hardcopy documents in accordance to the Caltrans
uniform filing system. Upon completion of each project, all
hardcopy and electronic documents will be transmitted to
CVAG.
Cost Control
We understand the importance of delivering projects within budget.
We have a history of completing construction projects on time
and within budget. Value engineering is an excellent method to
reduce the project costs.
We constantly look for means and methods to reduce the
project cost while being thoughtful to not create impacts to the
public or the cities. Our team is experienced in identifying and
quantifying items to enhance the quality of the project while
reducing lifecycle costs. Through partnering, the contractor
is encouraged to also find ways and means that benefit both
the contractor and CVAG, providing a win —win situation. Using
experience, the CPM schedule and a five -week look -ahead
schedule, we are proactive in "looking ahead" of the contractor's
operations to identify issues that may impact costs, and we
make every effort to provide solutions and present them to
CVAG. If an extra cost item cannot be completely eliminated,
we evaluate the contractor's change order requests to ascertain
validity, merit and appropriate costs based on an independent
cost estimate. Contractor monthly pay estimates are reviewed
for content and financial accuracy and are certified.
Schedule Control
As discussed in the Cost and Document Control section,
our team will review and provide comments to the baseline
schedule submitted by the contractor. The team will review
and monitor progress on a weekly basis by walking the site and
recording actual status and developments. All inspectors will be
required to note down the accuracy of the milestones, start and
completion dates indicated in the approved baseline schedule.
Anserwill reviewthe monthly updates in a timely manner. These
updates are critical not only to establish exactly how the project
is being built, but also to flag emerging issues and trends. Trend
reporting will be used to track the changes in float for all areas
of the project, flagging those areas where the available float is
indicates lack of progress or exceeding planned progress and to
further identify the specific factors that caused the occurrence
of the change. This method ensures that problem areas are
not overlooked by all stakeholders and are identified prior
to the activity becoming critical. The report also provides the
explanation of the root causes for a delay in the project and
makes it an important defense for future claims.
Any proposed change resulting in altering the critical path or
near critical path or extending the schedule completion date
that was originally identified in the approved baseline, the
contractor will be required to submit a revised schedule and a
time impact analysis (TIA) immediately in accordance to the
special provisions. Anser will immediately analyze the TIA
after an event occurs, and, if possible, prior to the start of the
additional work. We will ensure that the review of the TIA is
completed prior to the start of the additional work in order to
recommend the issuance of the change order to increase the
contract duration and price, prior to performing the additional
work. We will analyze the effects of events and added work in a
timely manner.
1 _ — 4- 1
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 28 1 Anser Advisory
PROPOSED ENHANCEMENTS,
PROCEDURAL OR TECHNICAL
INNOVATIONS (V)
Approach to Civil Integrated Management
Anser effectively leverages tools available today, including
bringing our projects successfully into the future by
implementing Civil Integrated Management (CIM). CIM is
the technology -enabled collection, organization, managed
accessibility, and the use of accurate data and information
throughout the Iifecycle of a project. Our aspirations are to make
incremental improvements to functions in workflow and enable
full digital workflows from project inception to project delivery.
Our team is encouraged to always find cost and time savings
on all projects and CIM is proving to be a true value add to
our clients that brings those benefits. We have and continue
to work with different technologies that best fit our projects
and have identified OpenSpace technology and C-MIS project
management software technology to be two tools that we
believe can bring value to this project.
Openspace.Ai
OpenSpace is a document control that captures 36o degree
images which are then stitched to site plans allowing users to
locate exact locations on the plans via the site plan and givi ngyou
split screen images of current days activities and any other past
day activities in the same exact area. This tool has been proven
invaluable in pre -construction services, claims avoidance or
dispute resolution and being historical record, which provides
information for as -built designs in the future if needed. Anser is
currently using the software on a number of projects including:
CV Link with CVAG, the Landis and Georgia -Meade bikeways
project, and the Bayshore Bikeway Barrio Logan project, both
administered by SAN DAG.
By utilizing this software, Anser was successfully able to defend
SANDAL who was named as part of a larger accident within the City
of San Diego. The claim was made that the George -Meade project had
left uneven sidewalk elevations after the project. Through the use of
OpenSpace, we were quickly able to go to the exact spot of the claim,
pull our pre -construction records, and prove that the uneven sidewalk
was an existing conditions within the City right-of-way and that
SANDAL was not responsible for any of the damages.
CMISATAkiIIESI _(NWNffMM9KAT
CMIS is an online project
management software
that manages all basic _ .._.Y_ .,..,._•
construction management-=ri==~==•==-=-=�.-
services, such as RFIs,
Submittals, Change Orders,
and Progress Payments. In _---
addition, all inspector daily
diaries are entered through
the online system in the field.
The major advantage is in
searchability of information
which is accessed remotely and immediately. For inspectors this
means more field time inspection and less time in the office
doing administrative work. This information is accessed by all
authorized staff which allows expeditious flow of information
thereby expediting responses to questions RFIs and any other
question that may impede real time delays to construction.
With this software, data can be mined in minutes instead
of days, making it much more cost feasible to fight frivolous
claims. In addition to using the software for the CVAG CV Link
program, Anser is currently utilizing this software for a number
of other clients including the County of San Diego and the San
Bernardino County Transportation Authority.
Our commitment to our clients is always being proactive in
seeking solutions that bringourclients value in assuring project
delivery success.
SCHEDULE AND DEADLINES (VI)
As demonstrated throughout various section of this proposal,
theAnserteam is readyto hittheground runningoncewe receive
our NTP There is much work to be done so that the project can
be advertised in January of 2025 so that construction can begin
in Q2 2025. We will immediately begin our constructibility
review of the design drawings and provide comments back to
the designer. In parallel with our constructibility review, we
will also begin our cost estimating services to ensure that costs
are lining up with the engineer's estimate. Because there are
federal funds on the project, prior to advertisement, a complete
package will need to be submitted to Caltrans for review prior
to receiving our E76 for construction. Typically this review takes
a minimum of 8-weeks, so this package must be submitted by
October 2024 to meet the current project schedule.
Below, we have detailed out a preliminary schedule for both
pre -construction and construction services. Once additional
information is known, this schedule can easily be manipulated
and refined for use as we move forward with the project.
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 29 1 Anser Advisory
ID
Task Task Name Duration Start Finish Predecessors Total Slack
e Made
D
Half 1, 2024 Half 2, 2024 Half 1, 2111 Half 2, 2121 HaJ11, 2111 Half 2, 2111 Half 1, 211 Half 2, 202 Half 1, 2021
1 F M A M 1 1 A S O N D 1 F M A M 1 1 A S O N D 1 F M A M 1 1 A S 0 il D 1 F M A M 1 1 S O N D 1 F M
0
Arts and Music 910 days Mon 1/1/24 Fri 6/25/27 0 days
1 Pre -Construction 325 days Mon 1/1/24 Fri 3129/25 0 days
1.11st Round Construcability Review 40 days Mon 1/1/24 Fri 2/23/24 0 days
�+ 1.2 Designer Finalize 100% Drawing Package 60 days Mon 2/26/24 Fri 5/17/24 2 0 days
�+ 1.3 Cost Estimating 25 days Mon 2/26/24 Fri 3/29/24 2 115 days
+ 1.4 ROW Permits (City/CVWD/Tribes) 130 days Mon 1/1/24 Fri 6/28/24 10 days
1.5 Caltrans ROW Certification 40 days Mon 7/1/24 Fri 8/23/24 5 10 days
1.6100% Drawing Package Review 20 days Mon 5/20/24 Fri 6/14/24 3 0 days
1.7 Prepare Final Bid Documents 60 days Mon 6/17/24 Fri 9/6/24 7 0 days
�, 1.8 Caltrans E76 Construction Review 45 days Mon 9/9/24 Fri 11/8/24 8,6,4 0 days
1.9 Advertise/Bid/Award 100 days Mon 11/11/2 Fri 3/28/25 9 0 days
. 2 Construction 525 days Mon 3/31/2! Fri 4/2/27 0 days
M. 2.1 Construction Submittals 45 days Mon 3/31/25 Fri 5/30/25 10 0 days
rre. 2.2 A48 Washington to Jefferson 80 days Mon 6/2/25 Fri 9/19/25 0days
. 2.2.1 Demo 10 days Mon 6/2/25 Fri 6/13/25 12 0 days
. 2.2.2 Bikeway and Corner Improvements 40 days Mon 6/16/25 Fri 8/8/25 14 0 days
. 2.2.3 Dune Palms Intersection 15 days Mon 8/11/25 Fri 8/29/25 15 0 days
M. 2.2.4 Grind and Overlay 5 days Mon 9/1/25 Fri 9/5/25 16 0 days
. 2.2.5 Sign and Stripe 10 days Mon 9/8/25 Fri 9/19/25 17 0 days
. 2.3 A48 Jefferson to Monroe 90 days Mon 9/22/2! Fri 1/23/26 0days
. 2.3.1 Demo 10 days Mon 9/22/25 Fri 10/3/25 18 0 days
. 2.3.2 Bikeway and Corner Improvements 50 days Mon 10/6/25 Fri 12/12/25 20 0 days
. 2.3.3 Monroe Intersection 15 days Mon 12/15/2 Fri 1/2/26 21 0 days
M. 2.3.4 Grind and Overlay 5 days Mon 1/5/26 Fri 1/9/26 22 0 days
M. 2.3.5 Sign and Stripe 30 days Mon 1/12/2E Fri 1/23/26 23 0 days
rre. 2.4 A48 Monroe to Dillon 90 days Mon 1/26/2t Fri 5/29/26 0days
. 2.4.1 Demo 15 days Mon 1/26/2E Fri 2/13/26 24 0 days
. 2.4.2 Bikeway and Corner Improvements 60 days Mon 2/16/2E Fri 5/8/26 26 0 days
. 2.4.3 Grind and Overlay 5 days Mon 5/31/2E Fri 5/15/26 27 0 days
. 2.4.4 Sign and Stripe 10 days Mon 5/18/2E Fri 5/29/26 28 0 days
M. 2.5 Evacuation Channel 225 days Mon 9/22/2! Fri 7/17/26 260 days
M. 2.5.1 Ste 10+59 to 43+00 40 days Mon 9/22/2! Fri 11/14/25 260 days
M. 2.5.1.1 Civil Work 20 days Mon 9/22/25 Fri 10/17/25 18 160 days
. 2.5.1.2 Place Bike Path 15 days Mon 10/20/2 Fri 11/7/25 32 160 days
. 2.5.1.3 Sign and Stripe 5 days Mon 11/10/2 Fri 11/14/25 33 160 days
. 2.5.2 Ste 49+00 to 62+09 40 days Mon 11/17/2 Fri 1/9/26 160 days
M. 2.5.2.1 Civil Work 20 days Mon 11/17/2 Fri 12/12/25 34 160 days
�. 2.5.2.2 Place Bike Path 15 days Mon 12/15/2 Fri 1/2/26 36 320 days
�. 2.5.2.3 Sign and Stripe 5 days Mon 1/5/26 Fri 1/9/26 37 320 days
M. 2.5.3 Ste 43+00 to 49+00 155 days Mon 12/15/2 Fri 7/17/26 160 days
. 2.5.3.1 Civil Work 20 days Mon 12/15/2 Fri 1/9/26 18,36 160 days
. 2.5.3.2 Tie -Back Wall 20 days Mon 1/12/2E Fri 2/6/26 40 160 days
. 2.5.3.3 Excavate for Retaining Wall 5 days Mon 2/9/26 Fri 2/13/26 41 160 days
. 2.5.3.4 Retaining Wall 45 days Mon 2/16/2E Fri 4/17/26 42 160 days
. 2.5.3.5 Cure Retaining Wall 20 days Mon 4/20/2E Fri 5/15/26 43 160 days
. 2.5.3.6 Backfill Retaining Wall 20 days Mon 5/18/2E Fri 6/12/26 44 160 days
M. 2.5.3.7 Subgrade Preparation 10 days Mon 6/15/2E Fri 6/26/26 45 160 days
rre. 2.5.3.8 Place Bike Path 10 days Mon 6/29/2E Fri 7/10/26 46 160 days
rre. 2.5.3.9 Sign and Stripe 5 days Mon 7/13/2E Fri 7/17/26 47 160 days
. 2.6 Hjorth and A49 55 days Mon 6/1/26 Fri 8/14/26 0 days
. 2.6.1 Demo 10 days Mon 6/1/26 Fri 6/12/26 29 0 days
2.6.2 Bikeway and Corner Improvements 30 days Mon 6/15/2E Fri 7/24/26 50 0 days
M. 2.6.3 Grind and Overlay 5 days Mon 7/27/2E Fri 7/31/26 51 0 days
M. 2.6.4 Sign and Stripe 10 days Mon 8/3/26 Fri 8/14/26 52 0 days
M. 2.7 Van Buren 70 days Mon 8/17/2t Fri 11/20/26 0 days
. 2.7.1 Demo 30 days Mon 8/17/2E Fri 8/28/26 53 0 days
. 2.7.2 Bikeway and Corner Improvements 30 days Mon 8/31/2E Fri 30/9/26 55 0 days
M. 2.7.3 Van Buren Intersection 15 days Mon 10/12/2 Fri 10/30/26 56 0 days
�. 2.7.4 Grind and Overlay 5 days Mon 11/2/2E Fri 11/6/26 57 0 days
2.7.5 Sign and Stripe 30 days Mon 11/9/2E Fri 11/20/26 58 0 days
M. 2.8 Dillon 70 days Mon 11/23/2 Fri 2/26/27 0 days
. 2.8.1 Demo 10 days Mon 11/23/2 Fri 12/4/26 59 0 days
. 2.8.2 Bikeway and Corner Improvements 30 days Mon 12/7/2E Fri 1/15/27 61 0 days
. 2.8.3 Dillon Intersection 15 days Mon 1/18/27 Fri 2/5/27 62 0 days
M. 2.8.4 Grind and Overlay 5 days Mon 2/8/27 Fri 2/12/27 63 0 days
M. 2.8.5 Sign and Stripe 10 days Mon 2/15/27 Fri 2/26/27 64 0 days
M. 2.9 Punch List 25 days Mon 3/1/27 Fri 4/2/27 65,48 0 days
. 3 Post Construction 60 days Mon 4/5/27 Fri 6/25/27 0 days
rre. 3.1 Project Cloeout 60 days Mon 4/5/27 Fri 6/25/27 11 0 days
Pre -Construction
1st Round Construcability Review
Designer Finalize 100% Drawing Package
ROW Permit (City/CVWD/Tribes)
Itrans ROW Certification
100% Drawing ackage Review
Prepare Final Bid Documents
Caltrans E76 Construction Review
Advertise/Bid/Award
Construction Submittals
A48 Washington to Jefferson
Demo
Bikeway and Corner Improvements
, Dune Palms Intersection
�. Grind and Overlay
'gn and Stripe
I A48 Jefferson to Monroe
Demo
-Bikeway and Corner Improvements
Monroe Intersection
-.Grind and Overlay
Sign and Stripe
I A48 Monroe to Dillon
Demo
Bikeway and Corner Improvements
Grind and Overlay
T Sign and Stripe
Evacuation Channel
Sta 0+59 to 43+00
Civil Work
Place like Path
Sign and Stripe
Sta 49+00 to 62+09
Civil Work
Place Bike Path
Sign and Stripe
Sta 43+00 to 49+00
-,Civil Work
-Tie -Back Wall
L Excavate for Retainir g Wall
Retaini g Wall
C re Retaining Wall
Backfill Retaining Wall
Subgrade Preparation
Place Bike Path
sign -an
Hjorth and A49
.Demo
.. Bikeway and Corner Improvements
7 Grind and Overlay
Sign and Stripe
Van Buren
Demo
Bikeway and Corner Impin ments
Van Buren Intersection
Grind and Overlay
Sign and Stripe
Dillon
-. Demo
Bik ia, and C
Dillon hire
, Grind anc
�&=i
Construction
Arts and Music
nts
Post Construction
Project Cloeout
1
2
3
4
5
6
7
8
9
10
11
12
inner Improvem
section
Overlay
rd Stripe
Punch list
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
Project : Arts and Music
Date: Tue 8/22/23
Task Milestmmaone ♦ Project Summary �� Inactive Milestone Manual Task Manual SummaryRollup Start -only C External Tasks -' Deadline b Critical 'Pit.......... Manual Progress
Split .......... Sury �1 Inactive Task Inactive Summary o o Duration -only i Manual Summary r -----1 Hnish-only 3 External Milestone O Critical Progress ogre
Page 1
COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS
Professional Engineering Services, Arts and Music Line Project 30 1 Anser Advisory
ANSER
ADVISORY
AML SUMMARY OF COSTS
Company
Pre -Construction &
Bid Services
Anser Advisory
$314,170.00
Labor
$299,170.00
ODC's
$15,000.00
Escalation
Dan ken
$23,061.60
Labor
$23,061.60
ODC's
Escalation
Michael Baker International
$11,400.00
Labor
$11,400.00
ODC's
Escalation
Burke Rix
$32,440.00
Labor
$25,240.00
ODC's
$7,200.00
Escalation
Dynamic Engineering Services, Inc.
$1,482.40
Labor
$1,482.40
ODC's
Escalation
LSA Environmental
$9,540.00
Labor
$9,540.00
ODC's
Escalation
Earth Systems
$0.00
Labor
$0.00
ODC's
Escalation
Magana Consulting
$24,850.00
Labor
$24,850.00
ODC's
Escalation
MLA Consulting Services, Inc.
$7,500.00
Labor
$7,500.00
ODC's
Escalation
TOTALS:
$424,444.00
Contigency (20%): $84,888.80
Total: $509,332.80
Contract No. CVAG-20-018-03
Project: ATP — Arts and Music Line
Attachment A-2
T.Y. Lin International
Technical and Fee Proposal
Arts and Music Line Construction Management Services
Work Plan
PROJECT UNDERSTANDING
The Arts and Music Line (AML) is a multi -benefit project that
will make public safety enhancements for pedestrians and
bicyclists, encourage modes of alternative transportation,
and create connectivity to local and regional bike and
pedestrian infrastructure. When completed, the 10 miles of
protected Class I and Class IV bicycle facilities will connect
services, and amenities in the area and add to the CV
Link's 40-plus mile alternative transportation corridor.
The alignment follows Avenue 48 and Dillon Road through
the Cities of La Quinta, Indio, and Coachella. These are
busy thoroughfares with vehicle speeds in excess of 50
miles per hour. The much -needed project will create safer
routes to schools, promote outdoor recreation, while
improving health and reducing greenhouse gas emissions.
The AML will upgrade the current Class II bike lanes along
Avenue 48 to a fully protected Class IV bike lane; construct
new Class IV lanes along Hjorth Street, Van Buren Avenue,
and Dillon Road; and construct a Class I bike lane along
the La Quinta Evacuation Channel, connecting to the
CV Link at the Whitewater River. The AML will provide a
safe backbone that connects existing Class II bike lanes
to provide safe and efficient alternative transportation
options to schools, residences, shopping, entertainment,
and employment centers. In addition to the transportation
benefits, the AML offers architectural features that
draw attention and interest while promoting safety. The
completed network will be recognized as a nationwide
model of alternative transportation.
The work along Avenue 48 involves removing the existing
bike lane along Avenue 48, constructing the concrete
separation, replacing the road pavement, placing the new
bike lane behind the separation, and completing a full
width grind and overlay along Avenue 48. This work is
Figure 1. Rendering courtesy of CVAG website
performed on both sides of Avenue 48 for about
2 miles and a single side for about 3.5 miles. It will impact
intersections, access to shopping, as well as restrict traffic
with construction activity and extended lane closures.
Work along Hjorth Road and Van Buren Street is similar,
though these roads are not as busy as Avenue 48. Dillon
Road will be reduced from four lanes to two lanes to
accommodate the added bike lane and will likely be the
least impactful construction location for the project. Work
along the La Quinta Channel includes a significant amount
of import material and retaining wall construction prior to
constructing the bike path base and surface.
A dedicated, focused, and proactive CM team will
be needed to smooth the way for the contractor to
successfully construct this project. The project success
will be largely defined by the timely completion of a
quality product and public's perception of the progress
and productivity seen during every week of construction.
'IYI.in
Page 17
40 n! CVAG
The TYLin Team has a proven track record of proactive
Arts and Music Line Construction Management Services
changes to accommodate public traffic, or extreme weather
leadership, foreseeing and addressing potential challenges conditions. Each of these situations can be anticipated and
to allow the contractor to continue their work without delay. a plan can be formulated to specifically mitigate the impact.
Typical delays may include unresolved utility conflicts,
right-of-way encroachments, inaccuracies in the project
plans, alignment issues, unanticipated delays caused by
APPROACH TO COMPLETING THE WORK
PROJECT MANAGEMENT
Strong and proactive project management is needed to
efficiently execute the required scope of services and
successfully construct this project within budget, schedule,
and minimal impact to the public. Project Manager, Joseph
Smith, PE, has a demonstrated record of meeting and
overcoming the issues that will be encountered on this
project. Mr. Smith is an experienced construction manager
and can quickly understand project issues. He also has
personally selected the members of this team, both TYLin
staff and sub -consultant support, to meet the specific
challenges that may be encountered throughout the project
duration.
Mr. Smith, Mr. Nowak, and the team have demonstrated
problem solving skills on these and other similar project
impacts throughout their careers.
As Project Manager, Mr. Smith will have ultimate control
over the TYLin Team budget. He will also have oversight
over Resident Engineer, Thomas Nowak, as he monitors
and manages the construction schedule and construction
budget. In our experience, cost and schedule control
must be exercised every day and be regularly evaluated
to assure the final costs are within the budget and
the schedule is acceptable once all the unforeseen
contingencies are considered. TYLin has maintained
our reputation for smooth and efficient project delivery
throughout Southern California for 50 years by developing,
deploying, and adapting project control tools to monitor
budget, schedule, and documents. Each of these is
discussed below:
` Budget Monitoring & Control I To manage the budget of a given project, TYLin's engineers and
project controls staff use data from TYLin's internal accounting system, Deltek Vision, to evaluate
progress. The information is updated monthly for the overall scope of services.
Schedule Monitoring & Control I On contractor driven projects, TYLin uses scheduling tools,
including Microsoft Project and Primavera P6, for Critical Path Method (CPM) scheduling of the work.
The schedule is used to monitor progress throughout the project and is updated monthly or more
frequently as needed. Various metrics are analyzed to track schedule performance.
Document Control I TYLin implements a uniform filing system for all documents associated with
each task order, including prime agreement; amendments; subconsultant contracts; prevailing wage
documents; timesheets and receipts for ODCs.
,rYUn Page 18
`7i CVAG
Arts and Music Line Construction Management Services
Managing the contractor's schedule is directly related to
managing our level of staffing and the resulting budget.
Mr. Smith and Mr. Nowak will work together to provide an
efficient and effect level of staffing to meet the project
needs.
Mr. Smith will remain in regular and close contact with
Mr. Nowak to provide supervision, consultation, and
staffing support to assure that the TYLin work plan is
effectively implemented to the satisfaction of CVAG and
involved cities. Mr. Smith has worked closely with the
Cities of La Quinta, Coachella, and Indio, as well as RCTD,
and has a proven reputation of partnering with client
agencies to overcome project challenges and deliver
successful projects. With Mr. Smith's oversight, Mr. Nowak
will provide the level of staff needed to effectively manage
the contractor's activities.
Serving as the prime CM firm on more than a dozen
projects within Coachella Valley, TYLin has gained
experience working closely with IID electrical transmission
and distribution divisions; CVWD sewer, irrigation,
and potable water departments; and personnel that
monitor the CVSC. We have gained experience working
in challenging hot -weather and windy conditions, and
understand some materials in the region may not be
suitable for structure foundations or bike and roadway
construction and know when suitable material must be
imported.
Mr. Nowak is currently serving as the Resident Engineer
and Structure Representative on the Dune Palms Road
Bridge project. To allow construction of the bridge within
the alignment of the existing roadway, the project utilizes a
temporary roadway shoo -fly and temporarily relocates IID
distribution to the south within the CVSC. Additionally,
Mr. Nowak is overseeing relocation of both water and
sewer services at each end of the project, as well as
relocation of existing dry utilities in the project footprint.
Figure 2. 1-10/Jefferson Street Interchange
Mr. Smith served as Resident Engineer on the Madison
Street Canal Improvement project in the City of Indio,
responsible for overseeing the construction of a large
double -box channel, extension of the canal to the south,
temporary relocation of the existing channel utilizing
temporary bridges and allowing for upgrades to many of
CVWD's existing utilities.
As Project Manager for the 1-10/Jefferson Street
Interchange (Figure 2), Mr. Smith presented to the
leadership team of Golden Voice, the promoter that
spearheads the Coachella and Stagecoach music festivals,
multiple times over three years to update the group on the
changes to traffic patterns within the interchange and to
obtain feedback on how the CM team could help improve
movement of concertgoers through the interchange over
the multiple weekends that are so vital to the economy of
the Valley.
Through these many projects TYLin has gained experience
with the many stakeholders of the AML and will point this
experience towards establishing the best bid set possible
and constructing the high -quality transportation link the
residents of La Quinta, Indio, and Coachella envision.
'IYI.in
Page 19
CVAG
Arts and Music Line Construction Management Services
BID ADMINISTRATION AND PRE -CONSTRUCTION ASSISTANCE
Immediately following authorization, the TYLin Team contractor problems and solutions. Mr. Nowak and
will begin the duties outlined as "Bid Administration
and Pre -Construction Assistance." Primary duties
include conducting a thorough constructability review
of project plans at the 65%, 90%, and 100% level of
completion, creating a Construction Communication Plan,
and reviewing all environmental permits and required
mitigations. Following advertisement, the team will assist
with contractor bid administration, to assure all funding
requirements are met in accordance with the Caltrans
Local Assistance Manual (LAPM) and the manual of Special
Funded Projects.
Resident Engineer, Mr. Nowak and Scheduling and Claims
expert, Wade Durant, PE will lead the constructability
Mr. Durant are intimately familiar with Caltrans standards
and specifications and the LAPM.
Their reviews will start with a field visit to understand field
conditions and include a complete review of project plans,
looking for conflict in details, or the constructability of the
work within the actual constraints of the site. Additionally,
the plans will be reviewed for "bid -ability" to assure
the contractor can be confident that the work is clearly
defined, the quantities are accurate and all accounted for,
thus reducing risk and yielding a lower bid. At times, if a
contractor finds an error in the plans, instead of asking
for clarification, they will lower a bid, knowing a contract
change order will likely be required from which they will
review effort. Both Mr. Nowak and Mr. Durant have over 30 benefit. TYLin has already flown the alignment of the project
years of road, highway, bridge, and related construction
experience with a diverse range of projects. Every one
of these projects has included constructability reviews,
whether a formal review prior to the start of work, or an
ongoing weekly look -ahead review to anticipate potential
and has captured video and photos of the project footprint
with a drone (Figure 3). This information is always valuable
when reviewing project plans and determining whether the
design intent can be implemented considering actual field
conditions that may have changed during plan development.
Figure 3. Drone images of AML project site.
r Y I, i n Page 20
40 n! CVAG
Arts and Music Line Construction Management Services
Project specifications will be reviewed to assure all project
special situations or conditions are addressed and captured
in bid quantities. This will provide the contractual muscle
to the Resident Engineer to enforce the intentions of
CVAG and the cities. Typical issues may include allowed
hours of work, accommodations for public traffic, or
advance notification requirements. Additionally, material
specifications may need to be amended to account for
extreme desert weather conditions. Examples might
include concrete or hot mix asphalt (HMA) placement,
visibility of traffic cones and other control materials,
limitations to sun exposure of plastic materials such as
drainage pipe or wire, or application temperatures for
pavement striping.
Figure 4. Extreme heat caused thermoplastic melting. To prevent
this, we will assure manufacturers provide necessary details for the
application processes, including minimum and maximum tempera-
ture application, type of application method, thickness tolerances,
and protection time before traffic allowed on the applied markings.
Project quantity estimate will be verified. A savvy
contractor will over -bid items that will likely over -run and
under -bid items that will likely under -run. This practice is
a form of unbalanced bidding and can occur on seemingly
minor items such as temporary pavement striping. It is bad
enough if the final quantity is twice the estimated amount,
but when the contractor has increased his bid, knowing
that the quantity would over -run, the cost impacts are
significant. A confirmation of the estimated quantities will
eliminate this opportunity for the contractor and assure
a balanced and competitive bid from all contractors. As
one of the premier engineering design firms in California,
TYLin has a depth of resources available for analyzing
plans and bid documents. Our CM team enjoys a symbiotic
relationship with TYLin civil and structures designers,
routinely exchanging ideas and seeking solutions to
challenging project issues. In addition, TYLin has a national
cost estimating and risk management group within the CM
sector that will be available to Mr. Nowak and Mr. Durant as
they verify estimates and appropriate bid values.
TYLin has provided support to many agencies through the
advertisement, pre -bid meeting, bidder questions and
addenda, bid opening, bid analysis, and recommendation
for award. The process is well defined in the Caltrans
Local Assistance Procedures Manual (LAPM) (Figure 5).
Additionally, Mr. Magana with Magana Consulting Services
will assist the team with reviewing any specific funding
requirements are implemented to assure all requirements
are met prior to recommendation for award of the
construction contract.
.41
LOCAL ASSISTANCE
PROCEDURES MANUAL
Figure 5. TYLin and its subconsultants are all familiar with the
Caltrans LAPM and processes.
Mr. Smith, Mr. Nowak, and Mr. Durant will work side -by -side
with CVAG and the design engineers as questions come in
during bid time. They will assist in validating questions from
contractors and provide content for appropriate responses
along with recommendations of where plans, specifications,
and bid quantities must be revised. Time is of the essence
when a project is out to bid, and our team will work as
'IYI.in
Page 21
CVAG
Arts and Music Line Construction Management Services
many hours as necessary to allow CVAG to maintain timely plan will inform and excite the public for the upcoming
responses to questions and the overall bid schedule. project and provide a proven framework to communicate
Mr. Smith and Mr. Nowak will conduct the pre -bid meeting
along with CVAG representatives and design personnel.
Exhibits will be created to clearly define the project and an
agenda will be created for review and approval by CVAG
prior to issuance in the meeting invite.
PUBLIC OUTREACH
Public outreach will be a critical component of the pre -
construction activities. An effective project communication
throughout the duration of the project. The TYLin Team
includes Connect and Company (Connect) to develop
and lead an effective outreach plan for the AML. The
plan will follow proven protocol used on the Avenue 66
Grade Separation Project in Mecca; the Herbert Hoover
Pedestrian Improvement Project with a Safe Routes for All
outreach in Indio; and currently on the Dune Palms Bridge
Replacement project with TYLin in La Quinta. The protocol
includes:
Develop a targeted, measurable Construction Communications Plan in coordination with the
client/CVAG.
00o Research key stakeholders and the target audience to develop and maintain a solid
working database.
o°o°o Reach out and host meetings early to inform key contacts (emergency services/key stakeholders) and to
Inl establish communication, address concerns, build trust, and tap into their network.
o Complete boots -on -the -ground outreach to impacted residents and businesses (door-to-door, pop-up events,
n community events/meetings). This may occur in phases based on the construction schedule.
�owl Provide timely, accurate and accessible information for the duration of the project using collateral with clear
711 and concise text and simple graphics.
Respond immediately to questions and concerns; document resolution.
g8Serve as both a community resource and a liaison to the construction team representing public point of view.
We've found that if we do the work to know our audience
and make connections up front —fostering two-way open
communication with the public —our team is able to build
ramp -up outreach efforts for traffic pattern changes, large
paving operations or any outreach needs that come up as
the project continues. When the project nears completion,
trust and troubleshoot small problems before they escalate. Connect will start planning a unique, interesting, and safe
Project Pacing
Following this tested outreach protocol, we typically
spend a large chunk of time completing the first 4 steps
shown above, followed by a groundbreaking event before
construction starts. As the project moves out of the start-
up phase, outreach moves into "maintenance mode" and
our monthly budget reduces. The team remains ready to
ribbon cutting event, coordinating with local organizations
and giving back to the community when possible.
Communications Plan
Connect will draw on the team's years of experience
working with cities, public agencies, non -profits and on
transportation infrastructure projects to design a unique,
measurable and appropriate communications plan for the
'IYI.in AML.
Page 22
`7i CVAG
The plan will follow our protocol and include a
Arts and Music Line Construction Management Services
COLLATERAL
groundbreaking event, collateral development
and project start up; an emergency services and
stakeholder meeting; community meetings and/or pop.
up events; ongoing outreach as the project progresses
to different locations; and ongoing coordination with
emergency services, local cities, public information
officers (PIO) and City Engineers.
Connect will also include a media relations section
to engage local media through photo opportunities,
events or tours; and an emergency communications
plan that will include protocol about notifying and
speaking with the media, working with local PIOs and
internal emergency communications protocol.
Connect recently completed a project in the City
of Indio with the County Health Safe Routes for All
program and is incorporating the program into two
additional projects currently under construction. Our
team will coordinate with CVAG and County Health
to incorporate the non -infrastructure activities and
possible media opportunities.
111 ■
compalienos a una celebraci6n comunitaria en
el nu— puente de la Avenida 66 en Mecca!
sabado 13 de m— 111 am a 1 pm
PrYus
Meco Bays&Girls
e el servitlodevanaponegrn
arms
Club en 9139'166tM1
oamine
onibles dentro del 9ovs
Ave, Mecca, CA9i359
M1aaael bro
and Gins Cl.club.
en el poem¢.
Figure 6. Connect & Co has extensive experience
developing outreach materials in both English
and Spanish.
Connect's public outreach manager and in-house graphic
designer will develop and deliver clean and clear, English
and Spanish collateral materials to meet the unique needs
of the AML project. The Connect team will work closely
with the CM team and CVAG staff with approval processes
in place to assure collateral are accurate and meet
expectations.
Collateral could include a fact sheet, door hangers,
post cards, construction alerts, construction cards,
signs/banners, newsletters, advertisements,
PowerPoint presentations, project boards, etc.
We will also develop and manage a webpage on the
CVAG website to provide the most updated information.
Our team will create unique project social media pages
and create weekly social posts with video photos and
will monitor the comments to respond if necessary.
Connect can also manage social media boosting/
advertising if agreed upon with CVAG.
ADDRESSING ENVIRONMENTAL PERMITS AND
MITIGATION REQUIREMENTS
The TYLin Team includes ECORP to lead in understanding
all environmental restrictions and concerns and enforce
the required mitigation. ECORP has assisted TYLin on
numerous projects in the lower desert over the past 10
years, including 1-10/Jefferson Street Interchange, City of
Indio Retrofits, and Dune Palms Road Bridge.
ECORP routinely assists clients in complying with
environmental conditions stipulated in regulatory
permits and/or agreements for specific projects, plans,
and programs. Their team includes senior and expert
personnel with experience with the federal Clean Water
Act, Porter -Cologne Act, federal and state ESAs, the federal
Migratory Bird Treaty Act, and the California Fish and Game
Code. ECORP's project managers and technical experts
routinely meet with regulatory agency personnel on site
or in meetings to negotiate, review and discuss permit
'IYI.in
conditions and the associated schedules, monitoring, and
Page 23
CVAG
Arts and Music Line Construction Management Services
implementation. ECORP routinely assists with creation of a
permit compliance matrix for clients.
ECORP's compliance specialists prepare and implement
worker education programs in English and Spanish, conduct
comprehensive pre -construction surveys, and monitor
during construction activities, as well as prepare the
associated survey and monitoring reports. The firm works
closely with the client and the construction contractors
to establish the correct timing, schedule, and level of
effort required for both pre -construction surveys and
construction monitoring. ECORP's compliance specialists
and monitors are well-informed about all aspects of the
projects and permit conditions prior to the implementation
of the projects so they can ensure compliance with the
permit conditions. They also prepare the variety of plans
typically required by permit conditions, such as Nesting
Bird Management Plans, Protected Species Plans,
Habitat Restoration Plans, HMMPs, Invasive Plant Species
Management Plans, and Conceptual Mitigation Packages.
ECORP's biological monitors are also experienced in
conducting species relocation, monitoring the installation
Street. Project permits may require a 250-foot buffer
during breeding season and a 160-foot buffer during
non -breeding season (can vary depending on the
permit). CDFW coordination and concurrence to either
passively relocate the owls or negotiate a reduced
buffer may be required for work to occur in these areas
adjacent to occupied owl habitat. Passive relocation
of burrowing owl typically can only occur outside of
their breeding season and requires the creation of a
Burrowing Owl Exclusion Plan for the project.
Nesting birds: Cliff swallows nest at many of the
bridges along the Whitewater River/CVSC. They
typically arrive in March and nest until the end of June/
beginning of July. There could be seasonal restrictions
related to work occurring within a certain distance of
Dillon Road and Jefferson Street/La Quinta Bridges.
With other projects, it has been easier to avoid their
nesting season for those areas rather than implement
abatement measures.
Cultural
Our cultural resources team did a preliminary review and
and maintenance of Best Management Practices (BMP) and did not find any seasonal restrictions related to cultural or
exclusion devices, and completing all reporting prior to the tribal resources other than weather which could affect the
due dates listed in the permit conditions.
A cursory review of the project documents indicates the
following potential environmental restrictions that may
constrain the construction schedule:
Biological
Burrowing owl (Athene cunicularia): a State Species
of Special Concern, breeding season is generally Feb
1 to August 31 (CDFW Staff Report). If burrowing owls
are found within the vicinity during pre -construction
biological surveys, then the project has a limited time
of the year that work could occur within so many feet
of the owls (this would be in the Streambed Alteration
Agreement (1600 permit). From our knowledge of
the area, we do know burrowing owls occupy the
Whitewater River/CVSC at Dillon Road and Jefferson
project schedule overall.
General
From ECORP's knowledge and experience of projects in the
area, the Coachella Valley Music and Arts Festival (typically
in mid -April) can cause schedule delays due to traffic issues
and restrictions upon limiting traffic in the area.
Each environmental permit must be closed to the
satisfaction of the issuing agency prior the completion of
the project. ECORP specialists including biologists and
archaeologists will review all important permits related to
environmental compliance for this project and determine
which requirements need to be met during project close-
out. ECORP will conduct final site inspections and will
provide the necessary final reports and annual reports to
meet close-out conditions as required by project permits.
"IYT,in
Page 24
CVAG
Arts and Music Line Construction Management Services
These reports will first be provided to CVAG for review and
approval, before submission to the appropriate agency.
CONSTRUCTION MANAGEMENT - RESIDENT
ENGINEER
Following the award of the construction contract and prior
to the first working day, Resident Engineer, Mr. Nowak,
PE, will prepare the TYLin Team for the task of providing
professional and consistent construction management.
Processes will be implemented, forms will be created,
recurring tasks will be identified and assigned with defined
deadlines and deliverables. Mr. Nowak is perfectly suited
for this role. As demonstrated by his wide variety of
experience, he has the ability to implement comprehensive
QA, financial management, and communication practices,
Monthly estimate
Coordination meetings
Certified payrolls
SWPPP review
Monthly
Weekly
Monthly
Annual, at events, weekly
Partnering Quarterly
Requests for information (RFI) As needed
Submittals As required
Progress schedules Initial baseline with monthly updates
Record drawings Regularly
Additionally, during this pre -construction period, templates
will be developed, and file folders will be created to
manage the information developed throughout the
duration of the project. Financial oversight and quality
control of materials and workmanship are based upon
monitoring activities every day and having the ability to
access the detailed information and confirm the quality of
workmanship and materials is satisfactory, any errors have
been corrected, and quantities to be paid for the month are
constructed in accordance with the project specifications.
The TYLin Team regularly uses the Caltrans filing system
with 63 different categories to comprehensively track
while at the same time, working closely with the contractor
in partnership to deliver the most practical and effective
solutions to daily project challenges.
Prior to the Notice to Proceed (NTP), Mr. Nowak will
schedule a pre -construction meeting with the contractor
and all stakeholders. Contract expectations will be clearly
laid out during this meeting. Contractor responsibilities will
be identified that conform with the Caltrans Construction
Manual. Practices following a regular monthly schedule
throughout the contract with required deliverables will be
defined and clearly communicated to the contractor, with
defined responsibilities.
Typical recurring tasks throughout the project are listed
below, with frequency, and responsibility identified:
Quantity request
Quantity authorization
Look ahead schedule
Minutes
Payroll records
Review and confirm
Required report
Review and confirm
Project status
Project status
Clear question
Timely and clarifying response
Timely, complete submittal
Timely response
Monthly
15 days following submittals
Maintain current markups
Maintain current markups
the progress of the project and confirm the quality of
construction and the financial accuracy of all payments.
Following the Notice to Proceed (NTP), project pre -planning
and preparation is complete, and it is "Go Time." The
project moves forward per the contractor's approved
baseline CPM schedule and a rhythm of daily, weekly, and
monthly duties begins to develop. Local traffic impacts due
to school schedules and music festivals will be factored into
the contractor's work schedule. As Resident Engineer, Mr.
Nowak will be responsible to confirm and assure that the
contractor is meeting all contractual obligations, QA, and at
the same time eliminating obstructions to project progress,
'IYI.in
partnering contribution.
Page 25
ME CVAG
Arts and Music Line Construction Management Services
QUALITY, SCHEDULE AND BUDGET CONTROL
TYLin implements a quality control plan on all projects
consisting of construction services that follow
recognized procedures including detailed checklists
and documentation that closely follow the Caltrans
project and to assure our client's best interests are being
cared for. Our OAP is separated into three segments to
validate documentation, submittals and the inspection of
field work and materials. The first segment addresses the
Construction Manual. The first page of TYLin's Construction overseeing of the office level documentations, the second
Management Quality Assurance Plan summarizes our plan segment is employed to ensure all submittals are properly
as follows:
TYLin's quality assurance program (OAP) is employed to
ensure a successful and correctly managed construction
4& Documentation \TV
Documentation
reviewed and verified prior to approval. The last segment
is to verify all field work and materials are being approved
and documented.
Submittals(a Contractor Performance and
Incorporated Materials
QA of the CM process ensures all office level
documentations are reviewed and verified by a colleague
for accurateness and completeness. Examples of
documents slated for this level of review are CCOs/RFIs,
monthly billing estimates and quantity sheets. Also periodic
spot checking of daily documentation to ensure that the
record of activities and work completed is well documented
in writing and pictures at the Resident Engineer's
discretion.
Submittals
The second segment of our OAP is the validation of our
submittal review process. TYLin has QA checklists for
various submittals set up to ensure that all aspects of a
submittal have been checked and verified and the review
has been conducted accurately and in its totality. Some
examples of checklists for submittal review are: post -
tensioning shop drawing, falsework submittals, temporary
shoring, MSE walls, pile placement plan, and concrete
mix designs. These QA checklists will be filled out by the
reviewer and placed in the job files. When submittals are
reviewed by a junior engineer, a licensed engineer will spot
check their work and verify any comments.
Contractor Performance and Incorporated Materials
The third segment of our OAP is the inspection and
verification of all materials and work that occurs on the job
site. We have modified our construction procedures manual
to encompass all tasks associated with bridge and roadway
related inspection work. This is the first line of reference
to execute our tasked duties. This manual, coupled with
the contract specifications and the agency's governing
specifications, will ensure all work is inspected and verified
to an acceptable level.
The utilization of our OAP will ensure a successfully
managed project and assure our clients that we are
correctly overseeing and controlling the project.
TYLin team members understand the importance of
delivering quality services and products for our clients.
Our team understands the connection between quality and
cost control on a project, and we believe work must be
performed, inspected, and documented properly the first
time to avoid errors and schedule delays to successfully
deliver a project.
The practice of quality assurance is accomplished by review
of the contractor's submittals and field work to assure
'IYI.in
Page 26
`7i CVAG
the contractor's Quality Control Plan is being followed. A
Arts and Music Line Construction Management Services
challenges to the project. This priority will build trust
sufficient level of qualified staffing needs to be maintained between the contractor and the TYLin Team, resulting
to meet the varying levels of work that is ongoing. A in swift conflict resolution, fewer change orders, and a
proposed staffing plan is included in this proposal to reflect
how CM staffing might be scheduled to meet a proposed
contractor work plan. However, Mr. Nowak will regularly
review the workload facing his team and assign duties to
qualified staff to confirm contractor adherence to project
specifications.
TYLin's workplan to assure compliance to the contract
standards is based on the Caltrans Construction Manual
and recognized professional practices to meet the needs
of CVAG, the Cities of La Quinta, Coachella, Indio, RCTD, as
well as residents and business owners.
Quality oversight duties of the Resident Engineer and CM
team include:
Project Safety
>> Stormwater Compliance
Contract Change Order
Control
Submittal Review
Material Testing
Monthly Progress
Payments
Traffic Control
Environmental Compliance
Payroll and DBE
Compliance
RFI Review and Response
Public Safety
Impacts to Local Schools
Partnering
Whenever unforeseen conditions are discovered that could
possibly impede the contractor's work, it is Mr. Nowak's
project centered priority to help resolve the situation to
eliminate, or minimize additional cost, or project delay.
These conditions are typically documented by a formal RFI
from the contractor, but are initially identified by either
the contractor, or the CM team. Most often these issues
come to the attention of the team following careful review
of project plans in anticipation of the upcoming work
considering potential impediments.
Along with implementing formal partnering in accordance
with the project specifications, Mr. Nowak will demonstrate
his "project first" priority and proactively work to address
collaborative work environment.
As a good project partner, Mr. Nowak will work with the
contractor and other stakeholders to resolve conflicts
and provide the contractor a path to continue his work
without delay or added effort. Some sources of conflict may
include:
Delayed utility relocations
Differing site conditions
Plan changes initiated by the owner
Special public events
Reporting
Mr. Nowak will produce a monthly report to update CVAG
on the project status. The report will include the status
of the project schedule, (days completed versus days
remaining), project budget, (dollars spent, versus dollars
remaining), and percent of work completed to date. There
will be a description of the location and type of work
completed during the past period, and the work expected
to be completed during the upcoming period. The report
will also include a listing and status of all project change
orders and any potential change orders, as well as a
discussion of current or anticipated project issues and any
potential claims.
Construction Management - Construction Inspection
The TYLin team's primary responsibility is to assure project
plans and specifications, including all referenced standards,
are safely performed in the field every day. This and
in -person oversight is performed by our field inspectors.
Typically, our field inspector will meet with the contractor's
field crews at the beginning of each shift and gain a clear
understanding of the work planned for the day including
what items of work are planned to be accomplished.
They will learn the names of the crew that is working, the
'IYU n
Page 27
CVAG
Arts and Music Line Construction Management Services
Figure 7. The planned dramatic outcome for the CV link will be achieved by daily, consistent, and professional over-
sight and construction management. Renderings courtesy of CVAG website.
equipment that is to be used, any traffic control that will be conforming work that was corrected, any discussions with
implemented, any anticipated closures to roads or private
access, what potential critical operations are anticipated,
if specialty subcontractors are anticipated, what material
testing is anticipated, and what full-time inspection will be
required. A field inspector may be covering two or more
different crews and need to alternate attention between
different activities throughout the day. Field Inspectors
will work with assistance of our Resident Engineer and
Office Engineer to ensure approved submittals are being
followed and approved and accepted materials are being
incorporated into the work and plan changes are being
implemented.
Material testing will be scheduled in advance to assure
materials are installed to the proper compaction and
grade, concrete is the approved mix design and within
specification for temperature and age, and HMA is the
approved mix design and placed per project specifications
for temperature and compaction. In the event of full-time
inspection for placement of concrete or HMA paving, the
team will coordinate staffing to meet project requirements
and assure contractor compliance.
The activities of each day of contractor work will be fully
documented on inspector daily diaries. Daily diaries will
include all contractor staff and equipment, the hours
worked, which items of work were performed, and the
limits of work. The quantities of work will be documented
as well as any testing that was performed, any non-
the contractor that were held, and any issues or potential
issues that were encountered or anticipated. These daily
diaries are the foundation of our QA oversight. Based on
the daily activities, summary sheets are built to document
material testing, monthly payments, Q-Sheets, payroll
monitoring, safety compliance, and tracking the beginnings
of contract change orders.
Our Field Inspectors will provide daily photographs that
document the existing status of landscaping, pavement,
concrete, and other facilities prior to construction activities.
If the contractor's work unnecessarily damages existing
facilities, the daily report will prove highly valuable in
resolving any dispute by the contractor. Equally, the
contractor will be protected from false accusations if
existing conditions are sub -standard.
The material testing schedule is typically the responsibility
of the contractor. Tests are required to be scheduled 48
hours in advance to assure that testers can be on site. Our
Field Inspector will work with the contractor to be sure
delays to testing avoid impacting the contractor's schedule.
In the same way, he will also assure the contractor does
not over -schedule testers for his convenience and impact
the tester's (and CVAG's) budget.
All non -conforming work will be immediately
communicated to the contractor and asked to be removed
or corrected. It is typically corrected immediately; however,
'IYI.in
Page 28
40 n! CVAG
Arts and Music Line Construction Management Services
when correction is delayed, our inspector will document
the location and the issue with a non -conformance -report
(NCR), which will require a specific and documented re -
inspection prior to acceptance of the work.
In addition to the daily ongoing items of work, our
inspectors will continually review traffic control, SWPPP
compliance, and safety practices throughout the
project. Depending on the specific issue observed, the
inspector will direct the contractor to correct an infraction
immediately, by the end of the day, or by the end of the
week. These observations will be forwarded to Mr. Nowak
to be noted and addressed at the weekly construction
progress meeting.
SCHEDULE
Our proposed project schedule can be found on the
following page.
ASSUMPTIONS
The contractor will perform work during the Caltrans
Working Day calendar.
The contractor will procure long lead items as early as
possible. (e.g. traffic signals)
City and County Traffic Control Plans will need City and
County approval prior to construction.
All utilities (electrical, irrigation piping) will be installed
after surface removals for the various areas are
complete but prior to construction of roadways.
The grind and overlay work performed near active
roadways, (single lane), will minimally disrupt traffic.
PROJECT CLOSEOUT AND ACCEPTANCE:
As the project approaches completion, Mr. Nowak and
the team will begin the process of project closeout.
Material testing sheets will be reviewed to assure there
are no outstanding NCRs, submittal and RFI logs will be
reviewed for completeness, payroll logs will be reviewed
for completeness, and a proposed final estimate will be
compiled for the contractor's review.
The contractor's acceptance of the final estimate is his
acknowledgement that he agrees to the payment for all the
work performed including all change orders and claims.
Any outstanding payroll records will be submitted, and
potential liens will be released.
All maintenance and operation manuals will be confirmed
to have been submitted. The final project walk will
generate a final punchlist. The Cities of La Quinta,
Coachella, and Indio will have input for their jurisdictions.
Once the work is satisfactorily completed, the project can
be recommended for acceptance to CVAG.
Grind and overlay, construction of the new bike paths,
retaining wall construction, bridge, and traffic signal
work may take place concurrently in different locations.
The NEPA permit will be obtained after 90% design is
reviewed but before 100% design is submitted.
The contractor will have multiple crews available to
work at any given time.
No dewatering is required.
The total duration for construction including closeout
activities will be 21 months, about 420 working days.
TYLin constructability reviews will take place after 65%,
90% and 100% design is submitted.
The contractor will need 2 months for submittals and
City and County Traffic Controls Plan approvals after
contract award and prior to NTP
'IYI.in
Page 29
oil CVAG
Arts and Music Line Construction Management Services
Arts and Music Lime Coachella Valley Association of Governments Proposed Construction Schedule
D 0 Task Name Duration Start Finish 2024 2025 2026
tr3 tr4 tr1 Qtr2 Qtr3 Qtr4 Qtr1 Qtr2 Qtr3 � Qtr4 Qtr1 Qtr2 Qtr3
1 Pre -Construction 291 days Fri 8/18/23 Fri 9/27/24
Period
2 Perform 20 days Fri 8/18/23 Thu 9/14/23
Constructability
Review- 95% PS&E
3 Finalize Plans 120 days Fri 9/15/23 Thu 2/29/24
NEPA, and Permits
4 Advertise for 1 day Fri 3/1/24 Fri 3/1/24
Construction
5 Contract Award 90 days Mon 3/4/24 Fri 7/5/24
6 Submittal Review 60 days Mon 7/8/24 Fri 9/27/24
7 Pre -Construction 1 day Tue 9/10/24 Tue 9/10/24
Meeting
8 Construction 420 days Wed 9/11/2d Tue 4/21/26
9 Area 1- Ave 48/La 195 days Wed Tue 6/10/25
Quiinta 9/11/24
10 Removals 65 days Wed 9/11/24Tue 12/10/2'
11 Construct new 75 days Wed Tue 2/11/25
curbs 10/30/24
12 Conduit and ligh 50 days Wed 1/8/25 Tue 3/18/25
13 Construct 40 days Wed 3/5/25 Tue 4/29/25
Bikelane
14 Overlay Street 30 days Wed 4/23/25Tue 6/3/25
15 Stripe and open 5 days Wed 6/4/25 Tue 6/10/25 ir
16 Area 2- Ave 48/Inc 205 days Wed 12/11/, Tue 9/23/25
17 Removals 130 days Wed 12/11/2Tue 6/10/25
18 Construct new 90 days Wed Tue 7/1/25 —
curbs 2/26/25
19 Conduit and ligh 70 days Wed 4/2/25 Tue 7/8/25
20 Construct 80 days Wed Tue 8/19/25
Bikelane 4/30/25
21 Overlay Street 60 days Wed 6/18/25Tue 9/9/25
22 Stripe and open 10 days Wed 9/10/25Tue 9/23/25
23 Area 3- 145 days Wed Tue
Evacuation 6/11/25 12/30/25
24 Removals 25 days Wed 6/11/25Tue 7/15/25
25 Wall Constructic60 days Wed 7/16/25Tue 10/7/25
26 Pave 30 days Wed 10/8/25Tue 11/18/21
27 Rail, Stripe, and 30 days Wed Tue
open 11/19/25 12/30/25
28 Area 4- Hjorth Stre 100 days Wed 8/13/2! Tue 12/30/2!
35 Area 5- Van Buren 100 days Wed Tue 2/10/26
Street 9/24/25
42 Area 6- Dillon Row 120 days Wed 11/5/2! Tue 4/21/26
43 Removals 30 days Wed 11/5/25Tue 12/16/2!
44 Construct new 25 days Wed Tue 1/20/26
curbs 12/17/25
45 Conduit and ligh 15 days Wed 1/21/2ETue 2/10/26
46 Construct 25 days Wed Tue 3/17/26
Bikelane 2/11/26
47 Overlay Street 20 days Wed 3/18/2ETue 4/14/26
48 Stripe and open 5 days Wed 4/15/2ETue 4/21/26
49 Post Construction 46 days Wed 4/22/2E Wed 6/24/2E
50 Final Estimate 30 days Wed 4/22/2ETue 6/2/26
51 As-Builts 40 days Wed 4/22/2ETue 6/16/26
52 Final Acceptance 5 days Wed 6/17/2ETue 6/23/26
53 Deliver Files 1 day Wed 6/24/2E Wed 6/24/2E
Project: Project1 Task I Summary ii Inactive Milestone Duration -only Start -only C External Milestone ♦ Manual Progress
Date: Fri 8/18/23 Split ............. Project Summary Inactive Summary o o Manual Summary Rollup Finish -only ] Deadline i
Milestone ♦ Inactive Task Manual Task Manual Summary r ........ I External Tasks Progress
TYLin
'IYI/in Page 30
R A
HOURLY RATES
TYLin
Arts and Music Line Construction Management Services
Joseph Smith, PE, CCM
Project Manager
$326.81
$339.88
Thomas Nowak, PE, QSD
Resident Engineer/Structure Rep.
$256.20
$266.45
Abigail Manriquez
Office Engineer
$129.56
$178.00
$134.74
$178.00
Alejandro Armendariz
Structural/Const. Inspector
$149.43
$182.73
$155.41
$182.73
Curis Musashi, EIT
Structural/Const. Inspector
$129.35
$176.70
$134.52
$176.70
AIX
Robert Delgado
Inspector/Safety
$205.70
-
$213.93
-
Frank Duffy
Lead Inspector
$205.70
$178.50
$213.93
$178.50
CONNECT AND CORPORATION
Andrea Suarez
Outreach Director -FT
$170.00
-
$176.80
-
Jessica Sanchez
Outreach Specialist- FT
$90.00
$93.60
Christine Feldman
Creative Director/Graphic Design- PT
$110.00
$114.40
Jenessa Sanchez
Outreach Coodinator- PT
$51.00
-
$53.04
-
DESI
John Kannor
Sr. Electrical Inspector
$162.14
$178.50
$168.63
$175.50
Michael Roush
Electrical Inspector
$162.14
$178.50
$168.63
$175.50
Chia -Chi Wang
Labor Compliance Officer
$185.32
-
$192.73
-
ECORP
Kevin Israel
Environmental Manager
$160.00
$166.40
Wendy Turner
Senior Biologist
$160.00
$166.40
Sonia Sifuentes
Cultural Resources Task Manager
$160.00
$166.40
Jesus "Freddie" Olmos
Principal Environmental Planner
$210.00
$218.40
Seth Myers
Air Quality/Noise Task Manager
$195.00
$202.80
Caroline Garcia
Lead Biological Monitor
$106.74
$111.01
Robert Cunningham
Archaeology Support
$110.50
$114.92
Julian Acuna
Lead Archaeological Monitor
$106.74
$111.01
Scott taylor
Aquatic Resources Specialist
$161.73
$168.20
Samantha Alfaro
CEQA Support
$90.83
$94.46
Marc Guidry
GIS
$158.63
$164.98
Torrey Rotellini
GIS
$96.33
$100.18
Jackie McComas
Admin
$110.56
$114.98
Laura Hesse
Publications
$112.66
$117.17
GEOCON
See attached rate sheet on page 9.
Wl.in
Page 7
E A
MICHAEL BAKER
Arts and Music Line Construction Management Services
Jarrad Truman, PLS
Lead Surveyor
$275.00
$286.00
Christopher Albert, PLS
Lead Surveyor
$300.00
$312.00
Steven Chi, PLS
Field Supervisor
$185.00
$192.40
ZT CONSULTING
Farzad Tabingoo
Principal Engineer
$206.30
$214.55
Derick Hobbs
SMR/ Quality Engineer
$128.36
$133.49
Andrew Soria
Lead Precast QA Inspector
$136.39
$141.85
William Kent
Lead QA Inspector
$173.06
$179.98
Eric Sanabria
QA Inspector
$120.34
$125.15
Nathan Liszewski
QA Inspector
$128.36
$133.49
MAGANA CONSULTING
Martin Magana
President/ Construction Liaison
$175.00
$182.00
'IYI,in
Page 8
Arts and Music Line Construction Management Services
GEOTECHNICAL
0 GE OWN ENVIRONMENTAL
w IRM INC. 2023 Schedule of Fees — RV23 MATERIALS
PROFESSIONAL SERVICES
Word Processor/Non-Technical Assistant/Draftsman..................................................................................................................................................$90/hr.
EngineeringAssistant/Lab Technician..........................................................................................................................................................................
$90/hr.
EngineeringField Technician.......................................................................................................................................................................................
*801hr.
SeniorField Technician................................................................................................................................................................................................
*80/hr.
Special Inspector (Concrete, Rebar, Masonry, Welding, etc.)....................................................................................................................................
*90/hr.
FieldTechnician Supervisor.......................................................................................................................................................................................
*120/hr.
StaffEngineer/Geologist.............................................................................................................................................................................................
*125/hr.
Sr. Staff Engineer/Geologist.......................................................................................................................................................................................
*135/hr.
ProjectEngineer/Geologist.........................................................................................................................................................................................
*145/hr.
SeniorProject Engineer/Geologist.............................................................................................................................................................................
*155/hr.
SeniorEngineer/Geologist..........................................................................................................................................................................................
*165/hr.
AssociateEngineer/Geologist.....................................................................................................................................................................................
*175hr.
Principal Engineer/Geologist/Litigation Support..........................................................................................................................................................400/hr.
AttorneyFees (General).............................................................................................................................................................................................
$500/hr.
Depositionor Court Appearance................................................................................................................................................................................
$550/hr.
Overtime/Saturday Rate/Night Rate (7pm — 6am w/ 8 Hr minimum per call out)......................................................................1.5
X Regular Hourly Rate
Sunday and Holiday Rate................................................................................................................................................................2
X Regular Hourly Rate
Minimum Field Services Fee per call -out, 4 hrs (if 4 hrs or less), 8 hrs (if more than 4 hrs and less than 8 hrs)
Short -Notice Cancellation 4 hrs (if after 4 pm of the day prior to the scheduled inspection time)
Short -Notice Cancellation, 4 hrs (upon or after arrival atjobsite)
*Prevailing Wage (PW) California Labor Code §1720, et. Seq. add $45/hr.
TRAVEL E
Personnel................................................................................................................................................................................................. Regular Hourly Rate
Subsistence (Per Diem)................................................................................................................................................................. Quote Based on Location
VehicleMileage........................................................................................................................................................................................................ 0.751mile
EQUIPMENT & MATERIALS
*Nuclear Density Gauge/Sand Cone Testing Equipment ............. $10/hr
*Vehicle............................................................................................
$10/hr.
*Special Inspection Equipment........................................................
$5/hr.
Coring Machine (concrete, asphalt, masonry) ..........................
$285/day
Generator.....................................................................................
$150/day
Double Ring Infiltrometer...........................................................
$200/day
GPSUnit......................................................................................
$175/day
Pick-up Truck..............................................................................
$150/day
Mobile Laboratory with Lab Technician ..................................
$1,650/day
Drive -Tube Sampler.....................................................................
$60/day
Hand-Auger..................................................................................
$50/day
Dynamic Cone Penetrometer....................................................
$250/day
Manometer.................................................................................
$100/day
Schmidt Hammer.......................................................................
$100/day
Water Buffalo .....................................................................$751ea.
Battery -Powered Pump..............................................................$100/day
Water Level Indicator....................................................................$50/day
Perforated 3" PVC Pipe...............................................................
$45/1 Oft.
Gravel............................................................................................
$30/bag
Sand.............................................................................................$30/bag
AC Cold Patch..............................................................................
$30/bag
Quick Set PCC Patch...................................................................
$30/bag
Temp Marking Paint.....................................................................
$151can
LathBundle..................................................................................$1001ea.
Air Compressor...........................................................................$1501day
Soil Sample Tube..........................................................................$15/ea.
Percussion Hammer Drill...........................................................$125/day
31
78-075 Main Street #G-203 ■ La Quinta, California 92213 ■ Telephone 760.565.2002 ■ Fax 951.304.2392 io'
06:
Y I I i n Page 9
Arts and Music Line Construction Management Services
GEOTECHNICAL
0 GE OWN ENVIRONMENTAL
w IRM INC. 2023 Schedule of Fees — RV23 MATERIALS
LABORATORY TESTS
COMPACTION CURVES
(D698/D1557/T99/T108) 4-inch mold ...............................................
$220
(D698/D1557/T99/T108) 6-inch mold ...............................................
$230
(CT 216) California Impact.................................................................
$230
CheckPoint........................................................................................
$100
(D1632/CT312) Soil Cement Cyl. Fabrication (Set of 3) .................
$150
(D1632/CT312) Soil Cement Cyl. Fabrication (Addtl. Spec.) ............
$50
(D1633/CT312) Soil Cement Comp. Strength (Set of 3) .................
$300
(D1633/CT312) Soil Cement Comp. Strength (Addtl. Spec.) .........
$100
SOIL AND AGGREGATE STABILITY
(D2844/CT301) Resistance Value .................................................... $290
(D2844/CT301) Resistance Value, Treated ...................................... $295
(D1883) California Bearing Ratio ...................................................... $530
(C977) Stabilization Ability of Lime .................................................... $185
(D1883) Calif. Bearing Ratio (Army Corp of Engineers) ................. $105
CHEMICAL ANALYSIS
(G187/CT643/T288) pH and Resistivity ............................................
$135
(D4972/T289) pH Only.........................................................................
$30
(CT417) Sulfate Content....................................................................
$100
(CT422) Chloride Content....................................................................
$55
(D2974) Organic Content.....................................................................
$50
PERMEABILITY, CONSOLIDATION AND EXPANSION
(D5084) Permeability, Flexible Wall ..................................................
$270
(D5856) Permeability, Rigid Wall ......................................................
$260
(D2434) Permeability, Constant Head .............................................
$280
(D2434) Permeability, FHA Slab -on -Grade ......................................
$110
(D2434) Permeability, Hourly..............................................................
$55
(D2435IT216) Consolidation (6 pts. w/ Unload) ...............................
$350
(D2435/T216) Consolidation Additional Point wl Unload ...................
$65
(D4546) Swell/Compression Testing & Density ................................
$120
(D4546) Swell/Settlement Testing & Density (ea. addtl. pt.) .............
$85
(D4546) Swell/Settlement Testing & Density (County) ....................
$100
(D4546) Swell/Settlement Testing & Density (FHA) ..........................
$90
(D4829) Expansion Index of Soils .....................................................
$160
SOIL AND AGGREGATE PROPERTIES
(D422/T88) Particle Size, Hydrometer w/out Sieve ..........................$165
(C136/D6913/T27) Sieve, Coarse to Fine w/ #200 Wash ................$150
(C13606913/T27) Sieve, Coarse or Fine w/ #200 Wash................$115
(C136/D6913/T27) Sieve, Coarse or Fine No #200 Wash...............$100
(Cl 17/D1140/T11) Materials Finer than#200.....................................$90
(D2216/T265/CT226) Moisture Content..............................................$30
(D2487/D2488) Visual Soil Classification............................................$30
(D2937) Density of In -Place Soil, Drive-Cyl. Method ..........................$45
(D4943) Shrinkage Factors of Soils, Wax Method..............................$55
(Cl 31/C535/CT211) L.A. Abrasion Resistance................................$200
(C142/T112) Clay Lumps and Friable Particles................................$170
(Cl 23/T113) Light Weight Particles...................................................$245
(D3744/CT229/T210) Durability Index Fine......................................$190
(D3744/CT229/T210) Durability Index Coarse..................................$225
(CT227) Cleanness Value..................................................................$170
(D4791) Flat & Elongated Particles ...................................................
$165
(D693/CT205) Percent Crushed Particles.........................................$145
(D5821) Percent. of Fractured Particles, Coarse Aggregate ............
$140
(C40/CT213/T21) Organic Impurities..................................................$75
(C235) Soft Hardness (Scratch Hardness)......................................$100
(C88/CT214/T104) Sulfate Soundness.............................................$410
(C1252/T304) Uncompact. Void Content, Fine Aggregate ..............$150
(C127/CT206/T85) Coarse Specific Gravity......................................$125
(C1281CT207/T84) Fine Specific Gravity..........................................$150
(D8541CT209/T100) Specific Gravity of Soil.....................................$150
(C29/CT212/T19) Unit Weight & Percent Voids..................................$90
(D2419/CT217/T176) Sand Equivalent.............................................$110
(D43181CT204/T89/T90) Plastic Index (PlasticlLiq. Limit) ...............$165
(D4318/CT204/T89) Liquid Limit..........................................................$95
(D43181CT204/T90) Plastic Limit.........................................................$95
(C330) Spec. for Lightweight Aggregates, Struc. Concrete ..........
Quote
SHEARSTRENGTH
(D2166) Unconfined Compression....................................................$100
(D3080/T236) Direct Shear (3 points) ..............................................$295
(D3080/T236) Remolded Direct Shear (3 points).............................$300
(D3080/T236) Direct Shear Addtl. Points/ea. residual pass.............$115
(D2850) Unconsolidated-Undrained Triaxial Shear ..........................$160
(D2580) Unconsolidated-Undrained Triaxial Staged ........................$160
(D4767) Consolidated-Undrained Triaxial Shear..............................$265
(D4767) Consolidated-Undrained Triaxial Staged............................$340
(EM1110) Consolidated -Drained Triaxial Shear...............................$375
(EM1110) Consolidated -Drained Triaxial Staged.............................$480
-2- M&A66
'IYUn
Page 10
A
Arts and Music Line Construction Management Services
AillIk
E 000
'EST, a Na
LABORATORY TESTS (CONTINUED)
(A370) Bend Test
2023 Schedule of Fees — RV23
• #11 Bar & Smaller..............................................................................
$50
• #14 & #18 Bar....................................................................................
$70
(A370) Tensile - Mechanically Spliced Bar
• #11 Bar & Smaller............................................................................
$150
• #14 Bar & Larger..............................................................................
$190
(A370) Tensile — Electric Resist. Butt Splice w/ Control ...................
$150
(A370) Straightening of bar (if required) ..............................................
$25
Structural Steel Tests:
• (A370) Machining & Prep of Test Specimen ......................
Cost + 20%
• (A370) Tensile Strength & Elongation
Up to 200,000 Ibs......................................................................
$100
200,000 — 300,000 Ibs..............................................................
$125
300,000 — 400,000 Ibs.............................................................. $150
Pre -stressing Wire & Tendon Tests:
• (A421) Tensile Strength, Single Wire ..............................................
$150
• (A416) Tensile Strength, 7-Wire Strand ..........................................
$175
High Strength Bolt, Nut, & Washer Tests:
• (A325/A490) Tensile Test on Bolts .................................................
$100
• (A563) Proof Load Test on Nuts .....................................................
$100
• (A325/A490) Hardness Test on Bolts ...............................................
$50
• (A536) Hardness Test on Nuts..........................................................
$50
• (F436) Hardness Test on Washers ...................................................
$50
Weld Specimen Tests:
• (E164) Ultrasonic Examination ......................................................Quote
Machining & Prep of Test Specimen ...........................
Cost + 20%
• (E381) Macrotech Test (3 Faces) ..................................................
$355
ASPHALT TESTING
Asphalt Properties:
• (D2726/CT308/T166) Bulk Spec. Gray., Compacted HMA...........
$100
• (D1560/CT366) Stabilometer Value (HVEEM) ..............................
$145
• (D2041) Theoretical Max Specific Gravity ......................................
$145
• (D5444) Sieve Analysis of Extracted Asphalt .................................
$150
• (D6307/CT382) Percent Asphalt, Ignition Method .........................
$150
• (D1188) Unit Weight of Asphalt Core ................................................
$65
MISCELLANEOUS TESTING SERVICES
• Emulsion...........................................................................................
$300
• Wet Track Abrasion.........................................................................
$175
MASONRY**
GEOTECHNICAL
ENVIRONMENTAL
MATERIALS
Concrete Block Test (Sets of 3 Required):
• (C140) Unit Weight Moisture Content & Absorption .......................$195
• (C140) Moisture Content/Absorption (ea. addtl. specimen) ............$65
• (C140) Compression Test................................................................$195
• (C140) Compression Test (ea. addtl. specimen).............................$65
• (C426) Linear Drying Shrinkage......................................................$285
• (C109/UBC 21-16) Mortar Cylinder (2"x4")......................................$30
• (C942) Grout Prism (3"x3"x6"), trimming included ............................$35
Masonry Prism (Assemblage):
• (C1314) 8"x8"x16" — 8"x12"x16......................................................
$200
• (C1314) 8"xl6"xl 6" — 10"ATA6 .. .................................................$225
• (C1314)12"ATA6"-12"x16"x16"...............................................$250
• (C1314) Larger than 12" ITA6.. ................................................
Quote
Brick Test (Set of 5 Specimens):
• (C67) 24-Hour Absorption, Cold Water...........................................$225
• (C67) 5-Hour Absorption, Boiling Water..........................................$225
• (C67) Compression Test or Modulus of Rupture............................$255
• (C67) Each Additional Specimen.......................................................$45
CONCRETE**
Mix Designs:
• (ACI211/ACI214) Concrete Mix Design..........................................$350
• (ACI211/ACI214) Review of Concrete Mix Design .........................$350
• (C192) Concrete Trial Mix (includes equipment & labor) ...............$495
Concrete Properties:
• (C39/CT521/T22) Comp. Strength, Concrete Cyl.............................$30
• (C421CT521/T22) Comp. Strength, Concrete/Gunite Core..............$60
• (C78/CT523) Flex. Strength of 6"x6"x21" Concrete Beam.............$165
• (C174) Length Measuring of Drilled Cores.......................................$75
• (C1140) Shotcrete Panel -Coring & Testing (Set of 3)....................$290
• (C1140) Shotcrete Panel (each addtl. specimen).............................$90
• (C496) Static Modulus of Elasticity ..................................................$200
• (C496) Drying Shrinkage (Set of 3, up to 28 days).........................$395
• (C642) Spec. Gravity, Absorp., Voids in Hardened Concrete ..........
$95
• (F1869) Moisture Vapor Emission Rate, Concrete Subfloor............
$50
Calibration of Hydraulic Ram:
• 100 Ton & Under..............................................................................
$200
• 101 Tons — 200 Tons.......................................................................
$300
Use of Universal Testing Machine:
• UTM with One Operator..................................................................
$320
• Additional Technician ...............................................
Regular Tech Rate
Spray Applied Fireproofing:
*2X Surcharge on rush turn -around for laboratory testing.
• (E605/E736) Fireproofing Oven Dry Density/Thickness...... $90 **Fee applies for sample storage, testing, or disposal.
-3-
'IYI,in Page 11
Arts and Music Line Construction Management Services
GEOTECHNICAL
0 `EOWN ENVIRONMENTAL
w IRM 1W. 2023 Schedule of Fees — RV23 MATERIALS
1. Listed are typical charges for the services most frequently performed by Geocon. Prices for unlisted services as well as special
quotations for programs involving volume work will be provided upon request. Laboratory test prices shown are for laboratory
work only and include reporting of routine results not calling for comments, recommendations or conclusions.
2. Sampling and testing are conducted in substantial conformance with the latest applicable or designated specifications of the
American Society for Testing and Materials, Caltrans, American Association of State Highway and Transportation Officials, or
other pertinent agencies.
3. Saturday, night work, and overtime hours are charged at time and one-half; Sundays and holidays at double time. Per diem is
based on the local costs per day when location of work dictates.
4. Equipment and materials will be billed at cost plus 15%. Outside services including subcontractors and rental of special
equipment are billed at cost plus 15%. Hourly services are billed portal to portal from closest office in accordance with the
stated hourly rates herein.
5. Invoices will be submitted at four -week intervals. Terms of payment are met upon presentation of invoice. Invoices become
delinquent thirty (30) days from invoice date and subject to one and one-half percent (1-1/2%) service charge per month, or
the maximum rate allowed by law, whichever is lower. If Client objects to all or any portion of any invoice, Client will so notify
Geocon in writing within fourteen (14) calendar days of the invoice date, identify the cause of disagreement, and pay that
portion of the invoice not in dispute. The parties will immediately make every effort to settle the disputed portion of the invoice.
Payment on delinquent invoices will first be applied to accrued interest and then to the principal amount. All time spent, and
expenses incurred (including any attorney's fees and costs) in connection with collection of any delinquent amount will be paid
by Client to Geocon per Geocon's current fee schedule.
Client and Geocon shall allocate certain of the risks so that, to the fullest extent permitted by law, Geocon's (the term "Geocon"
includes Geocon's partners, officers, directors, employees, agents, affiliates, subcontractors and subconsultants) total
aggregate liability to Client is limited to the greater of $50,000 or the total compensation received from Client by Geocon for
services rendered on this project, for any and all of Client's injuries, damages, claims, losses, expenses, or claim expenses arising
out of this Agreement from any cause or causes, including attorneys' fees and costs which may be awarded to the prevailing
party, and Client agrees to indemnify and hold harmless Geocon from and against all liabilities in excess of the monetary limit
established above.
7. Client and Geocon shall allocate certain of the other risks so that to the fullest extent permitted by law, Client shall limit
Geocon's total aggregate liability to all third parties, including contractors, subcontractors of all tiers, materialmen, and others
involved in Client's project, as well as persons and other entities not involved in the project, to the greater of $100,000 or the
total compensation received from Client by Geocon for services rendered on this project, for any and all injuries, damages,
cause or causes, including attorneys' fees and costs which may be awarded to the prevailing party, and Client agrees to
indemnify and hold harmless Geocon from and against all liabilities in excess of the monetary limit established above, including
all liability incurred by Geocon for acts, errors, or omissions, pursuant to entering into agreements with third parties on behalf
of Client in order to obtain access or entry onto property not owned by Client. Client agrees to notify all contractors and
subcontractors of any limitation of Geocon's liability to them and require them to abide bysuch limitation for damages suffered
by any contractor or subcontractor arising from Geocon's actions or inactions. Neither the contractor nor any subcontractor
assumes any liability for damages to others which may arise on account of Geocon's actions or inactions.
-4-
IL
'IYI,in
Page 12
Contract No. CVAG-20-018-03
Project: ATP — Arts and Music Line
Attachment A-3
Chen Ryan Associates, Inc.
Technical and Fee Proposal
sone
4. Work Plan
The CVAG Arts & Music Line:
The nexus of transportation
planning and the arts
The approach that informs our vision for the CVAG
Arts and Music Line (AML) Active Transportation
Plan (ATP) Non -Infrastructure Program is the nexus
of active transportation planning and the arts. If
infrastructure is the physical manifestation of the
AML, then the arts, education and encouragement
elements that define the Non -Infrastructure Program
are the cultural manifestation of the AML.
Indio
La I
ella
Coachella Valley has experienced a steady growth
over the last fifteen years that has increased vehicular
traffic, collisions, and air pollution. The AML ATP
Non -Infrastructure Program (AML NI Program)
focuses on moving youth, seniors, and the mobility -
challenged community to parks and activity centers
including recreation centers, schools, and commercial
centers. The AML NI Program also incorporates arts
into the design of the AML and will deploy active
transportation education curriculum and community
encouragement campaigns. The scope, scale, and
holistic approach of the AML has the potential to
be highly transformative for residents, visitors, and
businesses with impacts and effects far reaching
throughout the Coachella Valley.
The CRA team knows the history of the AML; CRA
and Arellano Associates (AA) helped conduct
community engagement and supported the Caltrans
ATP Cycle 6 grant application submittal. The CRA
team recognizes the importance of the AML for
connecting transportation planning and the design
process, as well as changing people's minds and
transportation choices.
The overarching goal of the AML is to improve
health and increase safe mobility for residents,
workers, students and visitors (particularly vulnerable
populations reliant upon walking/biking for
transportation) to jobs, schools, and activity centers
through the AML. The AML will facilitate improved
public health, social equity, and provide other
important community benefits. The AML will be used
to achieve the following objectives:
A. Enhance multimodal neighborhood mobility
by strategically identifying street and sidewalk
connections, crossings, gaps, and identifying
how residents can better access businesses, retail
centers, schools, parks, recreational facilities, and
community services, through a seamless active
transportation network.
B. Improve active transportation safety by
exploring linkages of residences, schools, and
other activity centers via pedestrian and bicycle
corridors and the AML, assessing the conditions
of the streets and sidewalks connecting these
places, and by identifying countermeasures to
target the main causes of bicycle and pedestrian -
involved traffic collisions in the region.
C. Foster equitable, livable and healthy
communities by improving walking and bicycling
access to desired destinations, building upon
existing plans and public health programs that
not only identified destinations to implement
changes for social equity, but also provide the
framework to identify more destinations for future
work in expanding such initiatives. This project
focuses on providing people opportunities to
achieve a healthier lifestyle and create a sense
of community using pedestrian and bicycle
infrastructure with the AML.
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
on
4. Work Plan
The construction of the AML will create a high
quality pedestrian and bicycle corridor through
Coachella, Indio, La Quinta, and unincorporated
Riverside County. The AML will connect to eleven
schools from the Desert Sands Unified and Coachella
Valley Unified School Districts, the Coachella Valley
Link (CV Link, the regional multi -use trail) and Bear
Creek Trail, as well as connections to nine different
neighborhoods and community parks including
Rancho Las Flores Park, Dr. Carreon Park, Hijorth Park,
Saguaro Park, La Quinta Park, De Oro Park, Shields
Park, South Jackson Park, and Civic Center Campus.
CRA will work with staff to determine a clear set of
performance metrics that will be tracked through a
two-year arts, education and awareness program with
the goal of creating a system for measuring mode
shift and active transportation change over time in
the Coachella Valley. At the center of this curriculum
is a community -wide bicyclist and pedestrian safety
and education awareness campaign that will include
instructional activities throughout the community
reaching students, residents, visitors, commuters, and
other community stakeholders. The CRA team will
leverage its relationships it has built with Desert Sands
Unified and Coachella Valley Unified, as well as the 11
schools making up the project area, through outreach
in the community in 2021 and 2022 and through
other CVAG projects.
O DESIRED OUTCOMES OF THE AML
The AMUs origins come from the communities of
Coachella, Indio, and La Quinta, CVAG, area schools,
and other stakeholders. They have expressed the
desired outcomes of the AML, which we understand
to be:
► Access to amenities of daily life through active
transportation (parks, grocery stores, pharmacies,
employment, etc.)
► Active transportation safety and enjoyment
► Community/public health through active
transportation
► Educational and skill development of students
and the broader community about active
transportation and the arts
► Promotion and support for the arts
► Positive experience in communities' relationship
with public agencies through collaboration
► Enhancing the icon of Coachella Valley as an arts
destination
► Improved aesthetic experience of Avenue 48 and
the "spurs" connecting to project area schools
► Reduction of greenhouse gas emissions through
increasing active transportation
The AMUs NI Program will contribute to the identity
of the region as an arts destination and draw
people from all over the world. The AML is a tool
for capitalizing on state, national and international
interest in the Coachella Valley. While there are many
positive economic benefits to hosting the Coachella
and Stagecoach festivals, there are also environmental
impacts to the Valley. CRA will work with CVAG to
collaborate with each festival's organizers to develop
an active transportation plan to improve mobility
options during the periods when festivals are being
held, with materials that will encourage festivalgoers
to use active transportation while attending. As is the
case with cities who have seasonal influxes of visitors
due to regularly scheduled and seasonal events, the
AML is a strategy to address the transportation and
arts needs of communities throughout the year, and
visitors on festival occasions.
Scope of Work
O TASK 1: PROJECT MANAGEMENT
& ADMINISTRATION
PROJECT MANAGEMENT
CRA Project Manager, Jenny An, will organize
and facilitate the AML NI Program project kick-off
meeting. That meeting will establish project
direction, communication protocols, and refine the
project schedule and scope. The kickoff meeting will
introduce the approach and plan for outreach and
engagement, data collection and analysis, as well as
the preparation of associated public facing materials
including the project promotion toolkit, maps, and
visuals. A meeting agenda will be submitted by CRA
in advance of the kickoff meeting and presumably
include a review of the project scope, budget,
schedule, establish a bi-weekly check in meeting, and
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/12
on
4. Work Plan
a preliminary discussion of branding, project look and
feel, and communication protocols. After the kickoff
meeting, CRA will develop and submit minutes within
five business days focusing on key decisions, action
items, and next steps.
Jenny will maintain a detailed project schedule and
budget consistent with this proposal (pending any
changes at the kickoff meeting), with careful attention
to the allocation of resources and control over task
execution. CRA has proposed a schedule (see GANTT
Chart at the end of this section) to establish a logical
task sequencing including outreach activities, which
will be further refined in the opening month of the
project. The CRA team has led many projects of this
scale, vision, and scope, and has the multidisciplinary
staff to deliver.
CRA recognizes the importance of presenting
detailed and technical materials in an intuitive and
aesthetically attractive format to the public. After the
schedule has been confirmed at the kickoff meeting,
CRA will develop a simplified version of the project
schedule for use in the Promotional Toolkit, for the
purpose of public presentation.
CRA and CVAG will hold biweekly, primarily virtual
meetings with partner agencies and stakeholders.
In addition to these regular meetings, CRA will
support and facilitate meetings of the existing
Ad Hoc Committee and other already -committed
stakeholders with the goal of maintaining existing
AML public outreach providing continuity for the
AML NI Program. Additionally, CRA will assemble
and maintain a list of AML stakeholders. This list
begins with the Ad Hoc Committee and currently
active stakeholders and will be further developed
as the AML reaches more people within the project
area communities and people throughout the cities
of the Coachella Valley. The AML NI Program is
ambitious to a degree that knowledge of it could
become a household conversation, and thus we
expect stakeholder interest to increase qualitatively
and quantitatively. AA will recruit participants for the
Stakeholder Advisory Group from the stakeholder
pool, City staff, and potentially from other community -
based organizations in underserved communities. The
CRA team will prepare Stakeholder Advisory Group
meeting invitations and track invitations and RSVPs.
CRA will facilitate 8 meetings with the Ad Hoc
Committee, Transportation, and Executive
Committees. To inform as well as draw upon assets
within CVAG, CRA will make presentations to
CVAG's Transportation Committee meetings and
Executive Committee meetings throughout the
three-year duration of the AML NI Program at key
decision making points. The CRA team will prepare
presentation content related to outreach efforts for
Transportation, Executive, and Ad Hoc Committee,
and other stakeholder meetings.
0-1
4A TASK 1 DELIVERABLES
• Meeting agendas, minutes
• Technical memos
• Staff reports and attachments
• Stakeholder list
• Ad Hoc Committee list
• Grant reporting materials
• Presentation materials
• Biweekly project meetings (in -person or
remote, as approved by CVAG)
• Ad Hoc Committee, stakeholders and
member agencies meetings (8 meetings)
• Transportation Committee (2 meetings)
• Executive Committee (2 meetings)
O TASK 2: COMMUNITY
OUTREACH AND ENGAGEMENT
Prior engagement on the AML has been extensive,
robust, and impressive and this is the foundation of
the AML since 2018. The Ad Hoc Committee and
active stakeholders comprising the Stakeholder
Advisory Group will continue to be engaged and
will include community -based organizations (CBOs),
schools, communities in the project area including
families living in affordable housing. The diversity of
publics engaged in the AML includes generational
diversity, which has been facilitated by intentional
collaboration with institutions and organizations for
the young and elderly. The Stakeholder Advisory
Group is best positioned for understanding how,
when, and where outreach in the project area will be
most effective, and whose networks will be a vital
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/13
on
4. Work Plan
asset for achieving broad -based public engagement.
AA has been our engagement partner on the
AML throughout the earlier phases of the project.
Continuity and a track record of successful
collaboration with CVAG is a major asset that we
bring to the project. We have already achieved
project collaboration efficiencies — relationships,
communication protocols, and unparalleled project
understanding — that allow us to hit the ground
running with CVAG.
TASK 2.1: OUTREACH AND
ENGAGEMENT PLAN
CRA and AA, in collaboration with the stakeholder
group, will launch a new phase of outreach and
community engagement for the AML NI Program,
leading to the creation of an Outreach and
Engagement Plan (CEP) (draft and final). AA, with
input from CVAG, will prepare a detailed OEP that will
include parks' and recreation centers' information as
well as data from the technical team and community
engagement events throughout the development of
the AML NI Program. This OEP will identify outreach
methods and activities, as well as new stakeholders
to engage including students, residents, advocates,
and CBOs not previously involved in the project.
The OEP will consist of a strategy to fully engage
disadvantaged communities, including outreach in
multiple languages and through nontraditional means
to reach groups that may not typically participate
in the urban planning process. The OEP, utilizing
AML branding and visual approved as part of the
Promotional Toolkit (see examples below), will present
engagement dates informed by the Coachella Valley
communities. Schedules will include established
community events as well as potential events at ideal
locations for community engagement. The OEP will
include timeline and strategies for how to integrate
the project promotion and outreach events including
up to 22 pop-up events, 10 community events,
participatory challenges such as Bike to Work Day,
Bike to Work Month, or National Walk and Bike to
School Day. The Project will also work integrate the
SCAG Go Human toolkit for demonstration/safety
education classes/assemblies.
The OEP schedule will also be informed by the
academic calendar as part of the school -based
programs associated with the AML NI Program.
Outreach and engagement events will also be timed
with families' working schedules and availability in
mind. The activities and materials of engagement
will be in formats appealing to the community, and
with an understanding of diverse learning styles for
widespread appeal. The goals for each outreach
activity will be defined by the project leadership,
informed by local communities and stakeholders.
A key piece of the OEP will be ongoing surveying
throughout all engagement activities for the duration
of the project. A paper and online survey tool will
be promoted at events, on the project website,
and distributed via all available electronic means of
communication (email, social media outlets).
The input generated through outreach will be
documented as part of the project process. The
input we hear from community members and other
stakeholders will continually inform the project as
it develops, particularly in terms of the conceptual
development of the educational curricula and
encouragement campaigns, the aesthetic/artistic
development of the AML, and subsequent outreach
opportunities and methods. As part of the initial
review of contacts AA will identify missing key
stakeholders in the communities of the project area
and recommend their inclusion in the project contacts
database. Identified groups will be considered
for specific targeted notification and engagement
during the outreach process. AA will maintain the
database throughout the Project and add contacts
as stakeholders join the project's electronic mailing
list. The totality of the OEP along with the database
of stakeholders and their input will be reported in
an Appendix of Program Evaluation Report. This
information will also inform CVAG and advisory
committees, as appropriate.
TASK 2.2: PROJECT PROMOTION
At the onset of the project, CRA and AA will develop
a branding and style guide for use in the AML
Communications and Promotions Toolkit. This will
include branding and a project logo that refers to
the aesthetics of the natural beauty of the Coachella
Valley as well as the centrality of the arts to the region
and to the AML NI Program. CRAs graphic designer
will produce copy of public facing materials (draft
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/14
on
4. Work Plan
and final) that can be presented in multiple forms (for
screen viewing, physical copies, etc.) and through a
diversity of outlets (traditional media, online/social
media, and local media including school newspapers/
newsletters, etc.). Project promotion is essential
to inform stakeholders about the AML clearly and
coherently. The CRA team are experienced in
developing various strategies and collateral materials
based on and tailored to the needs of the project.
All materials will be translated into Spanish, following
English content approval. The Communications and
Promotions Toolkit will present a plan for the strategic
targeting of audiences, scheduled according to the
timing of engagement events, and according to
project milestones. The following materials will be
developed:
Project Branding: AA will create visually
engaging project branding in alignment to
enhance project recognition and resonance. CRA
and AA will listen closely to the community about
the brand identity of the AML NI Program, such
that it will be context -sensitive and appealing
to residents and visitors alike. The brand will
reference the region as an icon of arts and
music, as a region that supports the arts from
within (uplifting local artists) and from without
(showcasing talent from beyond the Coachella
Valley). Materials utilizing project branding will
include promotional items, tabling materials
including posters, banners, or tablecloths. AA will
work with the Project Team to ensure graphics are
consistent with the CVAG's branding guidelines.
► Communications and Promotional Toolkits:
AA will develop two Communications and
Promotional Toolkits, one for schools and
one for employers. The Toolkits will focus on
encouraging participation and feedback from
program partners and participants. Anticipated
partners include Riverside County Public Health,
Coachella Valley and Desert Sands Unified School
Districts, Cities of Coachella, Indio, La Quinta,
and Riverside County. Public facing materials will
be bilingual (English and Spanish) and include
an 11 x1 7 poster, postcards, online/paper survey,
data gathering tools, and other items.
Social Media: AA will develop, at minimum,
one social media post per month that can be
shared across social media platforms for CVAG
and partner cities' accounts. Posts will be visually
appealing, informational, and provided in both
English and Spanish.
Project Website: AA will develop a project
website for the AML NI Program to promote
outreach and education materials, document
activities, promote community events,
participatory challenges, pop -ups, walk audits,
and to facilitate data gathering for the AML
NI Program. AA will host the website and
post information about the project timeline,
background information, and toolkit resources.
There will also be opportunities to solicit
feedback from visitors on various elements of the
project. The website will also allow stakeholders
to submit feedback without attending outreach
events. It could include a simple online
mapping tool to identify current barriers and
recommendations for suggested improvements
around a given park, school, or community
activity site, and allow the ability to rank
improvements. Other interactive website activities
will be developed in coordination with CVAG and
the technical team.
► Traditional Media: AA will develop promotion for
radio, door to door notification, and telephone
and SMS campaign in coordination with CVAG.
Youth Focused: The project team will work with
schools, recreation centers, public works, and
parks and recreation departments in the partner
cities to promote the project website and AML NI
program. The project website will be promoted
through each of the project schools through
school newsletters.
Employer Focused: The project team will work
with employers, the Greater Coachella Valley
Chamber of Commerce, and local businesses to
promote the project website and AML program.
Additionally, "business cards" which will contain
a high-level summary of the project, the project's
web address and a QR Code will be handed
out at the outreach events. At the conclusion of
the survey period, the Consultant will prepare a
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/15
on
4. Work Plan
memorandum outlining the findings of the virtual
engagement platform.
6 TASK 2 DELIVERABLES
Outreach and Engagement Plan
Project Contact Database
Communications and Promotional Toolkits
and collateral materials
O TASK 3: EDUCATION AND
ENCOURAGEMENT ACTIVITIES
AA will plan and lead engagement events for this
program. This will include pop-up events, community
events, and participatory challenges such as Bike
to Work Day, Bike to Work Month, and National
Walk and Bike to School Day. Outreach at these
events will be conducted to promote the AML NI
Program and gather data from the community about
opportunities and challenges of active transportation
in the Coachella Valley. As part of all outreach events,
active transportation incentives (such as merchandise,
bicycle helmets, lights and bells) will be incorporated
to encourage participation.
TASK 3.1: COMMUNITY PARTNER
COORDINATION
To encourage participation and increase program
awareness, AA will utilize extended outreach
through community partners. AA will collaborate
with CBOs who will be compensated to implement
the notification plan utilizing their local networks
and communication tools. CBO partners will be
confirmed and on -boarded during the development
of the outreach and engagement plan and will
be asked to support outreach notification, host
or support facilitation at community events, and
serve as strategic advisors. AA will identify potential
CBOs based on their proximity and relationship to
stakeholders within the project corridor, their interest
in active transportation projects, and/or their ability
to provide a local event venue to meet people where
they are already going. A potential partner includes
the Coachella Valley Housing Coalition, who can
assist with notifying stakeholders in their communities
via pop-up events or by distributing door -hangers.
ASSUMPTIONS
► All collateral and notification materials will be
translated into Spanish
► CVAG will share branding guidelines
► Technical consultants will contribute to the
content of outreach materials
► Technical consultants will prepare maps and other
technical materials
TASK 3.2: POP-UP EVENTS
The intent of pop-up events is to connect project -
specific engagement with standing community
functions, meetings, and events which have existing
audiences and participants. Pop-up events add great
value to the engagement process because it enables
the project to connect and interface with individuals
who may have meaningful input, but would not
have otherwise been interested in participating in
standalone project events. For this project, pop-up
events may include a safety demonstration events
(e.g., teaching riders how to properly navigate
across streets), bicycle rodeos, bicycle skills classes,
bike safety assemblies, safety events in partnership
with local fire and police departments. All pop -ups
will have raffles and giveaways related to active
transportation to incentivize participation. Outreach
will integrate existing events such as at the Tamale
Festival and Date Festival, as well as coordination
with music and arts festivals (e.g., Coachella and
Stagecoach festivals).
TASK 3.3: COMMUNITY EVENTS
AA will organize and lead ten (10) community events.
This may include bike rides/trains, walking tours or
walking school buses to help educate the community
on roadway safety. The outreach team will engage
with local schools, the YMCA, and Boys and Girls
Clubs to promote safety and awareness to the youth
population. In addition, AA will collaborate with CBO
partners to assist with promoting the community
events to their audiences. The outreach team will
also seek to partner with the American Automobile
Association (AAA) on their bike safety program.
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/16
on
4. Work Plan
Tabling at pop -ups and community events will involve
project materials dissemination, appealing visuals,
snacks and water, shade, and the opportunity to
provide input on the AML NI Program via a survey
or conversations with facilitators present . Promotion
of the AML NI Program and events associated with
the engagement campaign will also occur on public
kiosks and in parking lots associated with community
and arts events, through electronic communications
means (messaging through SMS and robocalls), and
through advertisements on radio stations such as
KCRI, KVRA, KKUU, and KPST.
The AML NI Program collaboration with area music
and arts festivals is a key part of the engagement
plan as it supplies the opportunity to simultaneously
address the needs of festival organizers (with regard
to transportation demand and environmental impact)
as well the needs of local communities and the
project team who are seeking the support of festival
organizers and festivalgoers alike. With AA, CRA will
lead in the planning and operations of bicycle services
at music festivals of Coachella and Stagecoach,
specifically by offering bike valet services as well as
bicycle maintenance services for festivalgoers. As
we elaborate in the Innovations section below, we
foresee student involvement in the festival's bike
elements in the form of assisting with bike valet and
assisting with bicycle maintenance (the skills for which
students will develop as part of the bicycle mechanics
after -school program).
TASK 3.4: COMMUNITY CHALLENGES
The project team will help organize and promote two
community participatory challenge events, such as a
Bike to Work Day, Bike to Work Month, or National
Walk and Bike to School Day. The goal of the these
activities is to ignite a sense of enthusiasm within
the community for walking and biking activities on
one designated day. AA will explore multifaceted
strategies including sustained promotional
efforts, enticing raffles, and thoughtful giveaways.
Collaborations with local businesses will be explored
to provide attractive incentives, while also considering
partnerships with employers to offer participation -
based rewards. AA will prepare a media toolkit for
local news stations to promote the challenges.
TASK 3.5: ARTS PROGRAM AND BIKE
MECHANICS COURSE
CRA will collaborate with school's art programs and
look for opportunities to incorporate art into the
AML project. This will include coordination with
arts instructors, students, administators to secure
and incorporate art work into the project procss for
marketing, visual materials.
The project team will work with CVAG to collaborate
with music festival organizers to incorporate bicycle
services. CRA will coordinate with a volunteer -run
community bike repair shop to teach youth how to
repair bikes and to educate interested community
members on the the fundamentals of establishing
and maintaining a volunteer -run repair shop that
serves as a cooperative community space. To create
efficiencies, the Team recommends collaborating
with organizations with experience to utilize and
build upon existing curriculum and models. This
approach seeks to learn from proven models of
success and is anticipated to help the CVAG region
establish similar sustainable models and programs.
✓4 TASK 3 DELIVERABLES
• Planning and attendance of up to twenty-
two (22) pop-up events, ten (10) community
events, and two (2) community challenges
• Coordination with festival organizers for bike
services
• Public facing materials needed per the
outreach and engagement strategy
including PowerPoint presentations, boards,
posters, and incentives
• Event documentation including photos,
summaries, and feedback received
• CBO partner onboarding and coordination
• Arts program
• Bike mechanics course
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/17
on
4. Work Plan
O TASK 4: EVALUATION AND
ASSESSMENT
TASK 4.1: GIS DATA COLLECTION
CRA -- in coordination with CVAG, the Stakeholder
Advisory Group, school districts and schools, the
County, the Cities of Coachella, Indio, and La
Quinta, and our project partners AA -- will conduct
an inventory of project area physical conditions and
assets of the project area, the neighborhoods of the
project area and proximate neighborhoods, areas
including the 11 schools that are part of the AML NI
Program. The elements of the built environment that
will be studied include sidewalks, street crossings,
bus stops, and bikeways/bicycle infrastructure. Our
analysis will include data on commercial and retail
establishments, community spaces, parks, community
centers, and religious facilities. Data collected will be
relevant to metrics associated with Safe Routes To
School, Safe Routes To Parks, and Safe Routes For
Seniors planning and programs (see Task 5).
CRA will develop GIS maps using available data
sources and some inventory for each of the 11
school's surrounding areas and the Empire Polo Fields
(where both Coachella and Stagecoach festivals are
held), displaying their mobility networks (including
street system, bikeways, sidewalks or missing sidewalk
locations, and bus stops). The maps will highlight key
land uses, destinations, and other points of interest.
Neighborhood boundaries, school enrollment areas,
and/or other potentially informative administrative
boundaries will also be displayed.
The maps will be used in the subsequent technical
tasks and products of this study, including the collision
analysis (Task 4.2), mobility assessments (Task 4.4),
existing conditions (Task 4.6), and recommendations
maps (Task 5).
J . TASK 4.1 DELIVERABLES
Technical memos and reports
GIS mapping with metadata
TASK 4.2: BICYCLE AND PEDESTRIAN
COLLISION ANALYSIS
CRA will analyze a period of five years of recent
pedestrian and bicycle collision history in the cities of
the study area (which include the 11 schools served
by the AML) using the client's preferred source of
data, though if not otherwise specified then SWITRS/
TIMS records. The analysis will help identify trends,
issues, high collision locations, common collision
causes, and help determine which user group(s), if
any, are disproportionately represented among the
collisions. The findings will be presented on collision
maps and supporting tables and summarized in a
technical memo according to Caltrans ATP guidelines.
The following attributes will be summarized by
frequency:
► Intersection and segment locations
► Worst injury outcome
► Party at -fault
► Primary Collision Factors and/or CA Vehicle Code
violations
Findings from collision analysis will be examined in
relationship to other technical analysis performed as
a part of this scope, including the existing conditions,
bike/walk audits, and multimodal and summarized
in a technical memorandum (draft and final). The
project team will determine collision exposure
rates from crash frequencies and AADT (derived
from multimodal counts and "Big Data", see Task
4.3), and assess those local conditions relative to
regional, state, and national rates and benchmarks;
this comparative section of the analysis will be
summarized into a scorecard of roadway health. CRA
can monitor collisions post -project during the lifespan
of the study, with the caveat that making conclusions
about safety effects would require additional years
of collection. One helpful strategy for post -project
monitoring can be for the project team to set up an
online collision GIS map with capabilities to filter,
visualize and summarize the data by key attributes.
CRA can provide guidance to CVAG on how to
maintain this resource and update on an annual basis
with new records to assist with post -project safety
monitoring.
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/18
on
4. Work Plan
TASK 4.2 DELIVERABLES
• Technical memos and reports
• GIS data, documentation, maps, and
summary tables
• Presentation materials
• Online collision GIS map and guidance for
maintenance
TASK 4.3: MULTIMODAL COUNTS
CRA will commission 24-hour multimodal roadway
segment/mid-block active transportation counts at
up to 45 locations. These include the AML "spurs"
leading to the project area schools (11 counts),
Avenue 48 between major intersections (10 counts),
at the 10 highest frequency collision locations (10
counts, Task 4.2), and at each of the two festivals (4
counts). Other locations will be chosen based on
results from Existing Conditions facility locations (z
10 counts, Task 4.6). We will deploy 24-hour counts
because they eliminate the necessity of extrapolation
relative to peak rates. Existing Conditions facility
locations will also influence the number of counts.
CRA will collect mode share data pre- and post-AML
construction. CRA will present our analysis of count
data by mode converted to annual average daily trips
(AADT) for collision analysis, and provided in tabular
and GIS data formats. To help estimate activity rates
in areas where count data is not collected, CRA will
use location -based services data (otherwise known
as "Big Data") to extrapolate pedestrian and bicycle
volumes in other parts of the study area. CRA will use
ReplicaHQ to retrieve pedestrian and bicycling data,
to supplement the counts for the development of
the AADT estimates needed to determine exposure
rates for pedestrian and bicycle collisions. The use
of Big Data can also assist with post -project activity
monitoring.
✓ . TASK 4.3 DELIVERABLES
Technical memos and reports
24-hour counts in 45 locations
• GIS mapping with metadata
• ReplicaHQ Big Data to estimate pedestrian
and bicycle activity throughout the project
area
• Presentation materials
TASK 4.4: MOBILITY ASSESSMENTS
CRA will observe mobility conditions in the field at the
11 schools of the project area and the Empire Polo
Club that hosts the Coachella and Stagecoach music
and arts festivals. Mobility Assessments will include
Pedestrian Environment Quality Evaluation (PEQE)
as part of the analysis of pedestrian conditions, and
Level of Traffic Stress (LTS) as part of the analysis of
bicycling conditions.
During visits to each school, CRA will canvass the
area surrounding the school, documenting the
attributes and deficiencies of transportation assets,
infrastructure, and presence of other support features
(crossing guards, school chaperons, etc.) next to
each school. Trip activity, routines and other travel
behavior which occur during pick-up and drop-off
periods will also be observed. During visits, CRA
will meet with administrators deeply familiar with
the school's transportation issues to supplement our
understanding.
Similar efforts will be undertaken to do mobility
assessments at the Empire Polo Club, and in
coordination with festival organizers. In Year 1, CRA
will canvass the areas surrounding access to the
Empire Polo Club, documenting transportation assets
and infrastructure. Trip activity and festivalgoers'
routines will be observed. In Year 2, CRA, in
coordination with festival organizers, will deploy
a transportation plan and maps to test new active
transportation access to the festivals.
The information gathered to produce brief mobility
assessment reports for each school and the festival
site with issues map and recommendations on how
to improve their walking and bicycling conditions.
These assessments may result in various types of
recommendations such as new or improved crossing
locations, sidewalk repair, new signage, suggested
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/19
on
4. Work Plan
routes to school or festival grounds, new bicycle
parking, and changes in vehicle pick-up/drop-off
routine.
0-1
-- TASK 4.4 DELIVERABLES
• Technical memos and reports
• GIS mapping with metadata
• Presentation materials
TASK 4.5: WALK AUDITS
CRA will conduct Walk Audits as part of the mobility
assessment. School administrators and other
stakeholders at each of the 11 schools, and at the
Empire Polo Club grounds that host Coachella
and Stagecoach will be invited to participate. Walk
Audits serve three functions for the AML NI Program:
They are an engagement activity, particularly of
students, parents, and educators, they are an
educational experience as participants learn how
to make systematic observations of roads and AT
infrastructure, and they contribute vital data for
understanding current AT conditions in the project
area.
Tasks 4.1, 4.4, and 4.5 will be conducted on the
same day.
✓4 TASK 4.5 DELIVERABLES
• Technical memos and reports
• GIS mapping with metadata
TASK 4.6: EXISTING CONDITIONS AND
NEEDS ANALYSIS MEMO
Based on the data collection, evaluations, and
assessments of the physical and built environment
of the project area completed in the preceding
tasks, including bicycle and pedestrian collision
data, multimodal counts, mobility assessments and
bike and walk audits, CRA will prepare an Existing
Conditions and Needs Analysis Memo (draft and
final). Like the data collection process, this Memo
will be prepared in collaboration with CVAG, school
officials, city staff, and other stakeholders, and
culminate in presentations to various stakeholders
and project partners.
JQ- TASK 4.6 DELIVERABLES
• Technical memos and reports
• GIS mapping and metadata
• Presentation materials
O TASKS: ENGINEERING
TASK 5.1: SAFE ROUTES TO SCHOOL,
SAFE ROUTES FOR SENIORS, SAFE
ROUTES TO FESTIVALS MAPS
CRA will develop maps to convey the safe/suggested
route recommendations identified in Task 4.4 for the
11 schools and the festival grounds. The purpose
of these maps is to help guide people, particularly
students, seniors, and visiting festivalgoers, to and
from their respective destinations, along direct
navigational routes from the destination's surrounding
areas, along quality facilities, and which channel
travelers to safe and preferred street crossing
locations. The maps will be graphically appealing,
using intuitive design and symbology, and be public
facing. Formats will be optimized for screens and for
physical copies.
✓EM ve TASK 5.1 DELIVERABLES
• Technical memos and reports
• GIS mapping with metadata
• User maps
• Website mapping
• Presentation materials
TASK 5.2: PROJECT IMPLEMENTATION
STRATEGY RECOMMENDATIONS
Upon completion of all data collection and analysis
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/20
on
4. Work Plan
CRA will develop a Project Implementation Strategy
Recommendations Memorandum (draft and final).
The Memorandum will summarize CRAs analyses of
data collected through our outreach, engagement,
education and encouragement efforts, as well as
our analyses of active transportation conditions and
the broader transportation network in the project
area. Based on those assessments, CRA will make a
prioritized recommendations list for infrastructure as
it relates to school/park access and programmatic
recommendations. This Project Implementation
Strategy Recommendations Memorandum will
be prepared in collaboration with CVAG, school
officials, city staff, and other stakeholders. Near the
conclusion of the project, CRA will develop and lead
the presentation of the Memo to CVAG and project
stakeholders.
TASK 5.2 DELIVERABLES
• Technical memos and reports
• GIS mapping with metadata
• Presentation materials
O TASK 6: PROGRAM EVALUATION
CRA will develop a comprehensive Program
Evaluation Report (draft and final) that will supply
a complete assessment of the effectiveness of the
public engagement activities, before and after
construction of the AML. Metrics for evaluation will
include:
► Stakeholders and project team member
feedback/evaluation
► Outreach results
► Effectiveness of Communications and Promotions
Toolkit
► AML design including arts implementation along
the AML
► Curriculum development at schools and for the
community
► Community challenges results
► Festival active transportation analyses and results
► Summaries of all data collection results,
including safety, multimodal counts, and mobility
assessments
This critical Program Evaluation Report allows for
continued learning of the AML project team and
stakeholders in terms of how the project unfolded,
identifying what was effective and what was
challenging, how challenges were overcome, and
documenting how project outcomes and goals were
met.
0-1
4- TASK 6 DELIVERABLE
• Program Evaluation Report
O METHODS OF BUDGET AND
SCHEDULE CONTROL, AND
QUALITY CONTROL
BUDGET AND SCHEDULE CONTROLS
CRA has a track record of delivering high quality
projects on -schedule and within budget. Our
outstanding organizational skills and technical
capabilities in combination with the strong support
from our experienced and highly -qualified staff —
including our seamless internal team communication
developed over years of working together — will
ensure successful project completion.
9`O ®iudum-yampamo AJERA-
'C
CRA prepares and tracks detailed project schedules for each
task including a customized critical path driven schedule with a
detailed list of subtasks, milestones, deliverables, and completion
dates. Each task and subtask listed match the work outlined in the
Scope of Services.
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/21
on
4. Work Plan
CRA uses an interactive web -based management system to assist our project and task managers to successfully
maintain control of a project budget by providing real-time status reports on performance, variances, forecasts,
and expenditures for all project tasks. We apply earned value management as the primary means of monitoring
project progress and forecasting performance by integrating the three fundamental components of every task order
— scope, schedule, and budget. This allows CRA to evaluate and control project risk by planning and monitoring
project performance.
CRA prepares and tracks detailed project schedules through Microsoft Project. The schedule will typically consist
of a customized critical path method schedule with a detailed list of subtasks, milestones, deliverables, and
completion dates. Each subtask listed would match the work outlined in the Scope of Work.
QUALITY ASSURANCE/QUALITY CONTROL
CRA takes pride in providing quality services and products. Our firm was founded on a commitment to fostering
a workplace culture dedicated to delivering products that are accurate, well -written, based on sound analysis and
industry/city specific design standards, and an assurance that final products have been thoroughly reviewed by our
assigned quality assurance/quality control manager before submission.
Kickoff Discussion
Following contract
authorization, the
project team will
begin with a kickoff
meeting to establish
client expectations,
contract require-
ments, and task
scheduling.
QA/QC Procedures
Work Products Checklist Redlines, Reviews & Notes Quality Close -Out Process
Checklists for each
technical group and
project phase are used
by QC leads to ensure
accuracy and attention
to detail. Edits and notes
are digitally archived for
accessibility.
Task & Review Scheduling
Schedules are designed
to include internal and
external reviews. This allows
the project manager and
QC reviewers to establish
timing and duration for
reviews.
QC leads provide feedback
by "redlining" products
and using review forms.
Revisions are rechecked
to ensure corrections
have been successfully
implemented.
Cross -Discipline & Compliance Reviews
QC leads perform compliance reviews
before submission of deliverables to
ensure regulatory compliance and
alignment with constructability criteria.
Principal verifies QC
process implementation.
Check -ins culminate with a
final meeting to ensure con-
tractual obligations have
been met and expectations
have been exceeded.
Progress Discussions
CRA team meets to review
comments and anticipated
project challenges to ensure
the project can proceed
without hindrance.
C p RESPONSE TO CVAG - AML ATP NI PROGRAM p / 22
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
on
4. Work Plan
We have the policies and procedures in place to
ensure that our team delivers a quality product every
time. We acknowledge that quality and schedule
can compete — and, for us, quality always wins.
As a result, our project schedules consider time for
quality control and document revisions prior to each
submittal.
SPECIAL ISSUES OR PROBLEMS AND
HOW THESE WILL BE ADDRESSED
The challenges we identify with the AML NI
Program are associated with its ambitious scope
and associated numerous elements to manage. It
will take a team of experienced active transportation
professionals spanning multiple disciplines to
successfully manage this project so that it meets its
goals and desired outcomes. With our partners AA,
we present to CVAG a team assembled and equipped
to handle this exciting and ambitious project.
We are inspired by the ways in which public and
community engagement has already developed and
want to contribute our hands to the AML effort. The
complexity of this project is the greatest challenge,
but with our collective resources and assets, those
challenges will not be insurmountable.
ENHANCEMENTS OR PROCEDURAL OR
TECHNICAL INNOVATIONS (OPTIONAL)
CRA professionals express a scientific disposition to
our projects, while also bringing artistic sensibilities
forward as well. The AML project, occupying the
nexus of transportation planning and the arts,
supplies the opportunity for CRA to apply our insights
and perspectives across a broad range of issues that
the AML contains. For this reason, CRA is excited
by the current structure of the AML NI Program as
presented in the RFP. In the process of preparing our
response, CRA developed additional enhancements
and innovations that we present for CVAG's
consideration. They are:
/ AML Promotional materials commissioned from
student artists/musicians/videographers
As the project develops and word of the AML
spreads through our various engagement events,
the AML can become the inspiration for the
creation of artworks. The education program
discussed above could include commissioning
artworks about the AML and AT from local
student artists/musicians.
After -school Bicycle Mechanics course
We see tremendous value and potential
in helping to establish an after -school bike
mechanics course as part of the education and
encourage element of the public engagement
of the AML NI Program. This would also serve
as an opportunity for local professional bicycle
mechanics to collaborate with schools and
educators in developing a bicycle mechanics
curriculum.
► Students working at Bike Valet and Bicycle
Maintenance at Music Festivals
As part of the educational element of the AML
NI Program, students in the bicycle mechanics
course will have the opportunity to apply
what they are learning to serve festivalgoers
with bicycle needs. The reward for taking this
opportunity is free access to the festival.
Cp RESPONSE TO CVAG - AML ATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/23
son
4. Work Plan
Schedule
Task 1 Project Management & Administration
Task 1 Project Kickoff Meeting
Project Kickoff Meeting (including agenda & minutes)
Task 1 Project Meetings
Bi-weekly Project Meetings (including agenda & minutes)
Task 1 Ad -Hoc Committee/Stakeholder Advisory Group Meetings
A-HC/SAG Meetings (and presentation deliverables)
Ad -Hoc Committee and Stakeholder List
Task 1 CVAG Transportation Committee Meetings (4)
Meetings (and presentation deliverables)
Task 1 CVAG Executive Committee Meetings (4)
Meetings (and presentation deliverables)
Task 2 Community Outreach and Engagement
Task 2.1 Community Outreach and Engagement
Outreach Engagement Plan
Project Contact Database
Task 2.2 Project Promotion
Communications and Promotions Toolkits
Task 3 Education and Encouragement Activities
Task 3 Public facing materials and event documentation
Task 3.1 Community Partner Coordination
Task 3.1 Community Partner Coordination
Task 3.2 Pop -Up Events
Task 3.2 Pop -Up Events (22)
Task 3.3 Community Events
Task 3.3 Community Events (10)
Task 3.4 Community Challenges
Task 3.4 Community Challenges (2)
Task 3.5 Festival Bike Services
Task 3.5 Coachella and Stagecoach -- research (Year 1)
Task 3.5 Bicycle planning, maps, valet, and maintenance services
Task 4 Evaluation and Assessment
Task 4.1 GIS Data Collection
Task 4.1 GIS Data Collection (including deliverables)
Task 4.2 Bicycle and Pedestrian Collision Analysis
Collision Analysis (including deliverables)
Task 4.3 Multimodal Counts
24-hour counts in 45 locations
ReplicaHQ Big Data to estimate activity
Task 4.4 Mobility Assessments
Mobility Assessments at 11 schools, Spring 2024
Mobility Assessments at Empire Polo Club, Year 1
Technical Memos/Reports, GIS mapping, and presentations
Task 4.5 Bike/Walk Audits
Bike/Walk Audits at 11 schools, Spring 2024
Bike/Walk Audits at Empire Polo Club, Year 1
Technical Memos/Reports, GIS mapping, and presentations
Task 4.6 Existing Conditions and Needs Analysis Memo
Existing Conditions Needs Analysis Memo
Task 5 Engineering
Task 5.1 Safe Routes Maps
Task 5.1 GIS Mapping with Metadata
Task 5.1 User Maps
Task 5.1 Technical Memos and Reports and Presentation materials
Task 5.2 Project Implementation Strategy Recommendations
Task 5.2 Project Implementation Strategy Recommendations Memo
Task 5.2 GIS Mapping with Metadata, and Presentation Materials
Task 6 Program Evaluation
Task 6 Program Evaluation Report
1/24 2/24 3/24 4/24 5/24
6/24 7/24 8/24 9/24 10/24 11/24 12/24 1/25 2/25 3/25 4/25 5/25 6/25 7/25 8/25 9/25 10/25 11/25 12/25 1/26 2/26
r ^ 1/27 2/27 3/27 4/27 5/27
V
Z
■ .........................I
z I....
��������������������������
w ■����
ts determined by A-HC/SAG
(and presentation deliverables)
Committee���er developed
�����������������r
maintained�and (deliverables)
■����
Q
■
■
■
l/1
w
H
■
����������t��������������1
■����
',y
community,
schools
V
Q
Q
LU
rM
mission
3.1 Community Partner
Coordination
LU
LLI
Z
Q
V
w
C11—
Z
O
H
t/1
Z
Q
V
C
I1�'1�
®.1E].......
1�
---
�It
171
3
I�u
I�
Cp RESPONSE TO CVAG -AMLATP NI PROGRAM
1� PROFESSIONAL ENGINEERING AND PUBLIC OUTREACH SERVICES
p/24
Coachella Valley Association of Governments
Arts & Music Line ATP Non -Infrastructure Program
The CRA Team Fee Proposal
No.
Task Description
CRA
AA
Total by Task
Task 1
Project Management and Administration
$ 85,880
$ 28,859
$ 114,739
Project Kick -Off Meeting
$ 2,400
$ 903
$ 3,303
Bi-weekly Project Management Meetings (up to 70)
$ 32,820
$ 5,729
$ 38,549
Ad Hoc Committee Meetings (up to 8)
$ 9,660
$ 12,201
$ 21,861
Transportation Committee Meetings (up to 2)
$ 2,840
$ -
$ 2,840
Executive Committee Meetings (up to 2)
$ 2,840
$ -
$ 2,840
Project Coordination and Invoicing
$ 35,320
$ 10,026
$ 45,346
Task 2
Community Outreach and Engagement
$ 23,780
$ 57,359
$ 81,139
2.1
Outreach and Engagement Plan
$ 4,120
$ 7,909
$ 12,029
2.2
Project Promotion
$ 19,660
$ 49,450
$ 69,110
Task 3
Education and Encouragement Activities
$ 54,540
$ 181,428
$ 235,968
3.1
Community Partner Coordination
$ -
$ 11,068
$ 11,068
3.2
Pop -Up Events (Up to 22)
$ 10,840
$ 36,955
$ 47,795
3.3
Community Events (Up to 10)
$ 22,000
$ 88,446
$ 110,446
3.4
Community Challenges (Up to 2)
$ 1,720
$ 20,944
$ 22,664
3.5
Arts Program and Festival Coordination
$ 11,040
$ 11,426
$ 22,466
3.6
Bike Mechanics Course
$ 8,940
$ 12,591
$ 21,531
Task 4
Evaluation and Assessment
$ 109,700
$ -
$ 109,700
4.1
GIS Data Collection
$ 26,080
$ -
$ 26,080
4.2
Bicycle and Pedestrian Collision Analysis
$ 15,100
$ -
$ 15,100
4.3
Multimodal Counts
$ 10,630
$ -
$ 10,630
4.4
Mobility Assessments
$ 19,260
$
$ 19,260
4.5
Bike/Walk Audits
$ 19,670
$ -
$ 19,670
4.6
Existing Conditions and Needs Analysis Memo
$ 18,960
$ -
$ 18,960
Task 5
Engineering
$ 47,285
$ -
$ 47,285
5.1
Safe Routes for Youth/Seniors/Festival Maps
$ 19,540
$ -
$ 19,540
5.2
Project Implementation Strategy Recommendations
$ 27,745
$ -
$ 27,745
Task 6
Program Evaluation
$ 57,110
$ -
$ 57,110
Draft Program Evaluation Report
$ 34,240
$
$ 34,240
Revised Program Evaluation Report
$ 16,160
$
$ 16,160
Final Program Evaluation Report
$ 6,710
$
$ 6,710
Labor Subtotal
$ 378,295
$ 267,646
$ 645,941
Direct Cost Subtotal
$ 21,000
$ 112,000
$ 133,000
CRA Total
$ 399,295
$ 379,646
$ 778,941
20% Contingency,
$ 155,788
Grand Total
$ 934,730
Coachella Valley Association of Governments
Arts & Music Line ATP Non -Infrastructure Program
Fee Proposal - CRA
No.
Task Description
Principal -in -Charge
Monique Chen
Project Manager
Jenny An
Deputy Project
Manager
Lars Christiansen
Technical
Advisor
Adam Chase
Senior Trans.
Planner/GIS
Sasha Jovanovic
Trans. Planner/GIS
Eric Sindel
Assistant Trans.
Planner
Annabel Grealish
Lead Engineer
Ross Duenas
Senior Traffic
Engineer
jonaman
Traffic Engineer
Cristian Belmudez
Senior Graphic
Design
Rene Rivas
Senior Project
Accountant
Claudia Joaquin
CRA Labor Cost
$340.00
$260.00
$170.00
$290.00
$210.00
$150.00
$135.00
$305.00
$235.00
$165.00
$170.00
$170.00
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Task 1
Project Management and Administration
25
$ 8,500
170
$ 44,200
134
$ 22,780
$
$ -
24
$ 3,600
$
$
$
$
-
$
40
$ 6,800
393
$ 85,880
Project Kick -Off Meeting
2
$ 680
4
$ 1,040
4
$ 680
$
$
$ -
$
$
$
$
$
$ -
10
$ 2,400
Bi-weekly Project Management Meetings (up to 70)
8
$ 2,720
70
$ 18,200
70
$ 11,900
$
$
$ -
$
$
$
$
$
$
148
$ 32,820
Ad Hoc Committee Meetings (up to 8)
3
$ 1,020
24
$ 6,240
-
$ -
$
$
16
$ 2,400
$
$
$
$
$
$
43
$ 9,660
Transportation Committee Meetings (up to 2)
2
$ 680
6
$ 1,560
$
$
$
4
$ 600
$
$
$
$
$
$
12
$ 2,840
Executive Committee Meetings (up to 2)
2
$ 680
6
$ 1,560
$
$
$
4
$ 600
$
$
$
$
$
$
12
$ 2,840
Project Coordination and Invoicing
8
$ 2,720
60
$ 15,600
60
$ 10,200
$
$
$ -
$
$
$
$
$
40
$ 6,800
168
$ 35,320
Task 2
Community Outreach and Engagement
6
$ 2,040
24
$ 6,240
26
$ 4,420
$
$ -
$
30
$ 4,050
$
$
22
$ 3,630
20
$ 3,400
$ -
128
$ 23,780
2.1
Outreach and Engagement Plan
2
$ 680
8
$ 2,080
8
$ 1,360
$
$
$
$ -
$
$
$ -
$ -
$
18
$ 4,120
2.2
Project Promotion
4
1 $ 1,360
16
$ 4,160
18
$ 3,060
$
$
$
30
$ 4,050
$
$
22
$ 3,630
20
$ 3,400
$
110
$ 19,660
Task 3
Education and Encouragement Activities
$ -
33
$ 8,580
96
$ 16,320
$
-
$
79
$ 11,850
62
$ 8,370
$
$ -
20
$ 3,300
36
$ 6,120
$
326
$ 54,540
3.1
Community Partner Coordination
$
$ -
$ -
$
$
$ -
$ -
$
$
$ -
$ -
$
-
$ -
3.2
Pop -Up Events (Up to 22)
$
8
$ 2,080
12
$ 2,040
$
$
24
$ 3,600
8
$ 1,080
$
$
$
12
$ 2,040
$
64
$ 10,840
3.3
Community Events (Up to 10)
$
16
$ 4,160
40
$ 6,800
$
$
32
$ 4,800
16
$ 2,160
$
$
$
24
1 $ 4,080
$
128
$ 22,000
3.4
Community Challenges (Up to 2)
$
4
$ 1,040
4
$ 680
$
$
$ -
$ -
$
$
$
$ -
$
8
$ 1,720
3.5
Arts Program at Schools
$
3
$ 780
24
$ 4,080
$
$
3
$ 450
18
$ 2,430
$
$
20
$ 3,300
$
$
68
$ 11,040
3.6
Bike Mechanics Course
$
2
$ 520
16
$ 2,720
$
$
20
$ 3,000
20
$ 2,700
$
$
$ -
$
$
58
$ 8,940
Task 4
Evaluation and Assessment
10
1 $ 3,400
34
$ 8,840
1
$ 170
4
$ 1,160
70
$ 14,700
200
$ 30,000
148
$ 19,980
14
$ 4,270
30
$ 7,050
122
$ 20,130
-
$ -
$
633
$ 109,700
4.1
GIS Data Collection
1
$ 340
4
$ 1,040
$ -
2
$ 580
20
$ 4,200
55
$ 8,250
46
$ 6,210
4
$ 1,220
4
$ 940
1 20
$ 3,300
$
$
156
$ 26,080
4.21
Bicycle and Pedestrian Collision Analysis
2
$ 680
2
$ 520
$
$ -
16
$ 3,360
64
$ 9,600
-
$ -
$ -
4
$ 940
-
$ -
$
$
88
$ 15,100
4.3
Multimodal Counts
$ -
2
$ 520
$
$
2
$ 420
4
$ 600
8
$ 1,080
$
6
$ 1,410
40
$ 6,600
$
$
62
$ 10,630
4.4
Mobility Assessments
2
$ 680
6
$ 1,560
$
$
20
$ 4,200
40
$ 6,000
24
$ 3,240
$
4
$ 940
16
$ 2,640
$
$
112
$ 19,260
4.5
Bike/Walk Audits
1
$ 340
8
$ 2,080
1
$ 170
$
4
$ 840
21
$ 3,150
30
$ 4,050
4
$ 1,220
8
$ 1,880
36
$ 5,940
$
$
113
$ 19,670
4.6
Existing Conditions and Needs Analysis Memo
4
$ 1,360
12
$ 3,120
$ -
2
$ 580
8
$ 1,680
16
$ 2,400
40
$ 5,400
6
$ 1,830
4
$ 940
10
$ 1,650
$
$
102
$ 18,960
Task 5
Engineering
4
$ 1,360
20
$ 5,200
6
$ 1,020
8
$ 2,320
40
$ 8,400
88
$ 13,200
$ -
8
$ 2,440
28
$ 6,580
41
$ 6,765
-
$ -
$
243
$ 47,285
5.1
ISafe Routes for Youth/Seniors/Festival Maps
2
$ 680
8
$ 2,080
2
$ 340
$ -
24
$ 5,040
60
$ 9,000
$
2
$ 610
2
$ 470
8
$ 1,320
$
$
108
$ 19,540
5.2
Project Implementation Strategy Recommendations
2
$ 680
12
$ 3,120
4
$ 680
8
$ 2,320
16
$ 3,360
28
$ 4,200
$
6
$ 1,830
26
$ 6,110
33
$ 5,445
$
$
135
$ 27,745
Task 6
Program Evaluation
10
$ 3,400
48
$ 12,480
82
$ 13,940
4
$ 1,160
18
$ 3,780
54
$ 8,100
92
$ 12,420
6
$ 1,830
$ -
$ -
-
$
$
314
$ 57,110
Draft Program Evaluation Report
6
$ 2,040
24
$ 6,240
1 48
$ 8,160
4
$ 1,160
12
$ 2,520
32
$ 4,800
60
$ 8,100
4
$ 1,220
$
$
$
$
190
$ 34,240
Revised Program Evaluation Report
3
$ 1,020
16
$ 4,160
24
$ 4,080
$ -
6
$ 1,260
16
$ 2,400
24
$ 3,240
$ -
$
$
$
$
89
$ 16,160
Final Program Evaluation Report
1
$ 340
8
$ 2,080
10
$ 1,700
$ -
-
$ -
6
$ 900
8
$ 1,080
2
$ 610
$ -
$ -
$
$
35
$ 6,710
Labor Subtotal
55
$ 18,700
329
$ 85,540
345
$ 58,650
16
$ 4,640
128
$ 26,880
445
$ 66,750
332
$ 44,820
28
$ 8,540
58
$ 13,630
205
$ 33,825
56
$ 9,520
40
$ 6,800
2037
$ 378,295
Coachella Valley Association of Governments
Arts & Music Line ATP Non -Infrastructure Program
Fee Proposal - AA
No.
Task Description
Project Manager
Jessica Harleaux
Deputy Project
Manager
Stephanie Espinoza
Senior Project
Coordinator
Jennifer Velazquez
Creative Lead
Kyle Santiago
Project Coordinator/
Tech Coordinator
support staff
AA Labor Cost
$0.00
$179.03
$136.28
$106.88
$146.97
$90.85
Hrs.
cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Hrs.
Cost
Task 1
Project Management and Administration
-
$ -
230
$ 23,274
30
$ 4,088
14
$ 1,496
-
$ -
-
$ -
174
$ 28,859
Project Kick -Off Meeting
-
$ -
2
$ 358
4
$ 545
-
$ -
-
$ -
-
$ -
6
$ 903
Bi-weekly Project Management Meetings (up to 70)
-
$ -
32
$ 5,729
-
$ -
-
$ -
-
$ -
-
$ -
32
$ 5,729
Ad Hoc Committee Meetings (up to 8)
-
$ -
40
$ 7,161
26
$ 3,543
14
$ 1,496
-
$ -
-
$ -
80
$ 12,201
Transportation Committee Meetings (up to 2)
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Executive Committee Meetings (up to 2)
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Project Coordination and Invoicing
-
$ -
56
$ 10,026
-
$ -
-
$ -
-
$ -
-
$ -
56
$ 10,026
Task 2
Community Outreach and Engagement
-
$ -
44
$ 7,877
50
$ 6,814
71
$ 7,588
120
$ 17,636
192
$ 17,443
477
$ 57,359
2.1
Outreach and Engagement Plan
-
$ -
12
$ 2,148
16
$ 2,180
8
$ 855
-
$ -
30
$ 2,726
66
$ 7,909
2.2
Project Promotion
-
$ -
32
$ 5,729
34
$ 4,634
63
$ 6,733
120
$ 17,636
162
$ 14,718
411
$ 49,450
Task 3
Education and Encouragement Activities
-
$ -
204
$ 36,522
258
$ 35,160
398
$ 42,538
32
$ 4,703
688
$ 62,505
1,580
$ 181,428
3.1
Community Partner Coordination
-
$ -
14
$ 2,506
4
$ 545
24
$ 2,565
-
$ -
60
$ 5,451
102
$ 11,068
3.2
Pop -Up Events (Up to 22)
-
$ -
30
$ 5,371
40
$ 5,451
100
$ 10,688
-
$ -
170
$ 15,445
340
$ 36,955
3.3
Community Events (Up to 10)
-
$ -
110
$ 19,693
150
$ 20,442
180
$ 19,238
-
$ -
320
$ 29,072
760
$ 88,446
3.4
Community Challenges (Up to 2)
$ -
18
$ 3,223
32
$ 4,361
40
$ 4,275
-
$ -
100
$ 9,085
190
$ 20,944
3.5
Festival Bike Services
-
$ -
16
$ 2,864
24
$ 3,271
24
$ 2,565
-
$ -
30
$ 2,726
94
$ 11,426
3.6
Bike Mechanics Course
-
$ -
16
$ 2,864
8
$ 1,090
30
$ 3,206
32
$ 4,703
8
$ 727
94
$ 12,591
Task
Evaluation and Assessment
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
4.1
GIS Data Collection
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
4.2
Bicycle and Pedestrian Collision Analysis
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
4.3
Multimodal Counts
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
4.4
Mobility Assessments
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
4.5
Bike/Walk Audits
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
4.6
Existing Conditions and Needs Analysis Memo
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Task5
Engineering
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
5.1
Safe Routes for Youth/Seniors/Festival Maps
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
5.2
Project Implementation Strategy Recommendations
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Task 6
Program Evaluation
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Draft Program Evaluation Report
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Revised Program Evaluation Report
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Final Program Evaluation Report
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$
Labor Subtotal
0
$ -
378
$ 67,673
338
$ 46,063
483
$ 51,623
152
$ 22,339
880
$ 79,948
1.231
$ 267,646
Direct Cost Expenses
Printing
$ 12,000
Outreach Supplies (Merchandise, giveaways, promotional
items, refreshments, branded materials)
$ 36,000
CBO Partnerships
$ 20,000
Travel
$ 18,000
Written Spanish translations
$ 4,000
Bike Repair & Co -Op Repair Shop Course (includes CBO
compensation, venue fees, transportation for field trip to LA,
video production for virtual r
$ 22,000
Direct Cost Subtotal
$ 112,000
AA Total
$ 379,646
City of La Quinta CONSENT CALENDAR ITEM NO. 4
CITY COUNCIL MEETING: January 16, 2024
STAFF REPORT
AGENDP TITLE: APPROVE AMENDMENT NO. 3 TO REIMBURSEMENT
AGREEMENT WITH COACHELLA VALLEY ASSOCIATION OF GOVERNMENTS FOR
AVENUE 48 ARTS AND MUSIC LINE PROJECT NO. 2020-08
RECOMMENDATION
Approve Amendment No. 3 to the Reimbursement Agreement with the Coachella Valley
Association of Governments for the Avenue 48 Arts and Music Line Project No. 2020-08;
and authorize the City Manager to execute the amendment.
EXECUTIVE SUMMARY
• Coachella Valley Association of Governments (CVAG) is the lead agency for the
Avenue 48 Arts and Music Line project improvements and has contracted with
Webb and Associates to design the project (Attachment 1).
• This project will be a community connector to the CV Link located primarily along
Avenue 48 between Highway 86 and Washington Street.
• In March 2020 the City approved a reimbursement agreement with CVAG along
with the Cities of Coachella and Indio. The participating cities' local share of the
design cost is determined by their respective linear mileage of the project.
• CVAG was successful in receiving an Active Transportation Program (ATP) grant
in the amount of $36.483 million for the construction.
• Amendment No. 1 updated the cost share associated with the design, and
Amendment No. 2 added additional design to the agreement.
• Amendment No. 3 will incorporate construction management costs and add the
non -infrastructure services to the agreement (Attachment 2).
FISCAL IMPACT
Amendment No. 3 will revise CVAG's 75% total regional share under the agreement to
$3,964,470, and the 25% local share to $1,321,490. The total project cost is allocated as
follows:
31
Original Contract March 18, 2020
Amendment Number One February 28, 2022
Amendment Number Two ❑ecember 5, 2022
Amendment Number Three ❑ecember 4, 2023
Total Contract not -to -exceed
Amendment Regional Local
Amount Share Share
$2,731,897 $2,048,923 $682,974
No Cast $0 $0
$1,060,000 $795,000 $265,000
$1,494,063 $1,120,547 $373,516
$5,285,960 $3,964,470 $1,321,490
The 25%, or $1,321,490, local share is divided between the Cities of La Quinta, Indio,
and Coachella based on their respective linear mileage of the project; each city's share
is detailed in the table below. The City's total share of the 25% is $330,372, which includes
an additional $93,379. There is sufficient funding in the project budget (401-0000-
60188D) for the additional cost to the City.
Total Local
La Quinta Indio Coachella Share (25%)
S330,372 $885,398 $105,719 $1,321,490
259Io 67 % 811/0 100 %
BACKGROUND/ANALYSIS
CVAG coordinated with the cities of La Quinta, Coachella, Indio, and Riverside County to
develop the 10-mile project. The Arts and Music Line is a community connector to the CV
Link that's located primarily along Avenue 48 between Highway 86 and Washington
Street. The eastern end will extend along Dillon Road to the Spotlight 29 Casino. The
western end will extend southward along Washington Street and then further west and
south along Eisenhower Drive, connecting to the Bear Creek Trailhead at the western
terminus of Calle Tampico.
The project's design will incorporate both light and sound, and provide pedestrians and
cyclists safe access to the music and art festivals at the Empire Polo Grounds.
Partnerships with two school districts and Golden Voice, provides an opportunity to
feature students' art and music along the route.
In March 2020, the City executed a reimbursement agreement with CVAG and the cities
of Indio and Coachella for the design of the project. The Avenue 48 Arts and Music Line
is a priority identified in CVAG's Transportation Project Prioritization Study (TPPS) and
was therefore eligible for regional transportation funding. By designing this project, CVAG
was able to secure a $36.483M ATP grant for construction.
Amendment No. 1, executed February 2022, revised the cost share after a portion of the
La Quinta improvements was removed to improve the chances of receiving ATP grant
funding. Amendment No. 2, executed December 2022, included additional design costs.
32
Proposed Amendment No. 3 extends the term of the agreement through December 31,
2025, incorporates the costs associated with pre -construction and construction
management services per CVAG's agreements with Anser Advisory Management, LLC
and T.Y. Lin International, and adds non -infrastructure services per CVAG's agreement
with Chen Ryan Associates.
ALTERNATIVES
Council may elect not to approve this amendment.
Prepared by: Julie Mignogna, Management Analyst
Approved by: Bryan McKinney, PE, Public Works Director/City Engineer
Attachments: 1. Avenue 48 Arts and Music Line Project Map
2. Amendment No. 3 to Reimbursement Agreement With CVAG
33