Specifications Project 2016-03Ita Qwkra
CALIFORNIA -
BID DOCUMENTS
SPECIFICATIONS
�� � �-� � :zap x� � � t;•�z�� r:��a� i
LA QUINTA LANDSCAPE RENOVATION IMPROVEMENT — CACTUS FLOWER
CITY OF LA QUINTA, CALIFORNIA
PREPARED FOR:
CITY OF LA QUINTA
DEPARTMENT OF DESIGN & DEVELOPMENT
78-495 CALLE TAMPICO
LA QUINTA, CA 92253
(760) 777-7000
APPROVED BY: DATE: November 9, 2023
-6474,ltj�9
BRYAN McKINNEY, -r7-.Lf
PUBLIC WORKS DIRECTOR/ CITY ENGINEER
R.C.E. No. 49418 Exp Date: 09/30/24
November 2023
TABLE OF CONTENTS
DIVISION 1 - BIDDING AND CONTRACT REQUIREMENTS
PAGE
1100
Invitation to Bid
1100-1
1110
Instructions to Bidders
1110-1
1.0 Work to be Done
1110-1
2.0 Examination of Contract Documents
1110-1
3.0 Inspection of Site
1110-1
4.0 Interpretation of Contract Documents
1110-2
5.0 Postponement of Opening
1110-2
6.0 Opening of Bids
1110-2
7.0 Preparation of Bid Forms
1110-3
8.0 Bidder's Signature and Authority
1110-3
9.0 Erasures
1110-4
10.0 Bid Irregularities
1110-4
11.0 Modification of Bid
1110-4
12.0 Withdrawal of Bids
1110-4
13.0 Addenda
1110-4
14.0 Bid Prices
1110-4
15.0 Bid Guaranty
1110-5
16.0 Qualification of Bidder
1110-5
17.0 Subcontractors
1110-5
18.0 Bidders Interested in More Than One Bid
1110-6
19.0 Sheeting, Shoring, and Bracing
1110-6
20.0 Wage Rates
1110-6
21.0 Offer of Assignment of Antitrust Actions
1110-7
22.0 Assignment of Contract
1110-7
23.0 Rejection of Bids
1110-7
24.0 Contract and Bonds
1110-7
25.0 Award of Contract
1110-7
26.0 Execution of Contract
1110-8
27.0 Construction Documents
1110-8
28.0 Bid Protest
1110-8
29.0 Compliance with Iran Contracting Act of 2010
1110-9
30.0 Compliance with California Executive Order N-6-22
1110-9
1200
Bid
1200-1
1210
Bid Schedule
1210-1
1220
Bid Guaranty Bond
1220-1
1230
Certification of Bidder's Experience and Qualifications
1230-1
1240
Proposed Subcontractors
1240-1
1250
Non -Collusion Affidavit
1250-1
1260
DIR Project Vendor Information
1260-1
1270
Iran Contracting Act of 2010 Certification
1270-1
1280
Russian Aggression Against Ukraine Sanctions
1280-1
Certification
1300
Contract
1300-1
1310
Performance Bond
1310-1
1320
Payment Bond
1320-1
1330
Workers' Compensation Insurance Certificate
1330-1
1340
Liability and Insurance Requirements
1340-1
1.0 Indemnification
1340-1
2.0 Insurance Requirements
1340-2
2.1 General
1340-2
2.2 Insurance
1340-3
2.3 Remedies
1340-5
2.4 General Conditions
1340-5
2.5 Change in Terms
1340-8
1400
General Conditions
1400-1
1.0 General
1400-1
1.1 Intent of Contract Documents
1400-1
1.2 Discrepancies and Omissions
1400-1
1.3 Headings
1400-2
1.4 Penalty for Collusion
1400-2
1.5 Successors and Assigns
1400-2
1.6 Assignment to City
1400-2
1.7 Rights and Remedies
1400-2
1.8 Definitions
1400-2
2.0 Administration
1400-7
2.1 Administration of the Contract
1400-7
2.2 City Engineer
1400-8
2.3 Consultants
1400-8
3.0 City
1400-8
3.1 General
1400-8
3.2 Attention to Work
1400-8
3.3 Inspection
1400-9
3.4 City's Right to Carry Out the Work
1400-9
3.5 City's Right to Perform Work and to
1400-9
Award Separate Contracts
4.0 Contractor 1400-10
4.1 Office 1400-10
4.2 Contractor's Representative 1400-10
4.3 Construction Procedures 1400-10
4.4
Contractor's Employees
1400-10
4.5
Subcontractors
1400-11
4.6
Contractor's Equipment and Facilities
1400-11
4.7
Public Safety and Convenience
1400-11
4.8
City -Contractor Coordination
1400-11
4.9
Permits
1400-12
4.10
Contractor's Responsibility for the Work and Material
1400-13
4.11
Laws to be Observed
1400-13
4.12
Safety
1400-16
5.0
Control of Work and Material
1400-18
5.1
Means and Method
1400-18
5.2
City -Furnished Materials
1400-18
5.3
Defective and Unauthorized Work
1400-19
5.4
Unnoticed Defects
1400-19
5.5
Right to Retain Imperfect Work
1400-19
6.0
Progress of the Work
1400-19
6.1
Beginning of Work
1400-19
6.2
Time of Completion
1400-20
6.3
Delays
1400-20
6.4
Time Extensions
1400-21
6.5
Temporary Suspension of Work
1400-23
6.6
Termination of Contract
1400-23
7.0
Changes in Scope of Work
1400-24
7.1
Change Orders
1400-24
7.2
Differing Site Conditions
1400-25
7.3
Resolution of Disputes
1400-26
8.0
Project Modifications Procedures
1400-29
8.1
Changes in Contract Price
1400-29
8.2
Negotiated Change Orders
1400-30
8.3
Force Account Payment
1400-31
8.4
Time Extensions for Change Orders
1400-34
9.0
Payment
1400-34
9.1
Scope of Payment
1400-34
9.2
Partial Payments
1400-35
9.3
Partial Payments - Inclusion of Material on Hand
1400-35
9.4
Right to Withhold Amounts
1400-36
9.5
Substantial Completion
1400-37
9.6
Final Inspection and Payment
1400-38
9.7
Warranty of Title
1400-39
1500 Supplemental General Conditions 1500-1
1.0 City Engineer 1500-1
2.0 Consultants 1500-1
2.1 Design Engineer 1500-1
2.2 Materials Testing 1500-1
2.3 Survey 1500-1
3.0 Liquidated Damages 1500-1
4.0 Submittals 1500-2
DIVISION 2 - GENERAL PROJECT REQUIREMENTS
2000 General 2000-1
1.0 Standard Specifications 2000-1
1.1 Alternative Specifications 2000-1
2.0 Standard Plans 2000-1
2.1 Alternative Guidance 2000-1
3.0 Preconstruction Conference 2000-2
3.1 Attendees 2000-2
3.2 Agenda 2000-2
4.0
Progress Schedules
2000-2
4.1
General
2000-2
4.2
Construction Schedule
2000-2
4.3
Time Impact Analysis
2000-4
4.4
Weekly Activities Plan
2000-4
4.5
Cash Flow Projection
2000-4
4.6
Lump Sum Price Breakdown
2000-4
5.0
Special Controls
2000-4
5.1
Dust Control
2000-4
5.2
Noise Abatement
2000-5
5.3
Working Hours
2000-5
5.4
Drainage Control
2000-5
5.5
Construction Cleaning
2000-5
5.6
Disposal of Material
2000-6
5.7
Parking and Storage Areas
2000-6
6.0 Protection and Restoration of
Existing Improvements 2000-6
7.0
Existing Utilities
2000-6
7.1
General
2000-6
7.2
Notification and Location
2000-7
7.3
Damage and Protection
2000-7
7.4
Utility Relocation and Rearrangement
2000-7
7.5
Underground Facilities
2000-8
DIVISION 3 - SPECIAL PROVISIONS
SECTION 3000
1.0
General
3000-1
1.1
Scope of Services
3000-1
1.2
Project Description
3000-1
1.3
Project Plans
3000-1
1.4
Drawings of Record
3000-1
1.5
Cooperation with other Contractors
3000-1
1.6
Time Allowed for Construction
3000-2
2.0 Bid Items 3000-2
3.0
Materials
3000-3
3.1
General
3000-3
3.2
Substitutions
3000-3
3.3
Storage
3000-3
4.0
Work Details
3000-3
4.1
Traffic Control
3000-3
4.2
Dust Control
3000-7
4.3
Water
3000-7
4.4
Permits, Licenses, and Inspection Fees
3000-7
4.5
Air Contaminants
3000-7
4.6
Notification
3000-7
DIVISION 4 - TECHNICAL SPECIFICATIONS
SECTION 4000
1.0 General Requirements 4000-1
2.0 Mobilization 4000-1
3.0 Traffic Control 4000-1
4.0 Dust Control 4000-1
5.0 Clearing and Grubbing 4000-2
6.0 Unclassified Excavation
4000-3
7.0 Demolition and Disposal
4000-4
8.0 Grading and Subgrade Preparation
4000-5
9.0 Asphalt Concrete
4000-5
10.0 Modify, Relocate and Repair Existing Lighting/Electrical
4000-8
11.0 Concrete and Masonry Construction
4000-11
12.0 Provide New Sleeving per City Standard 600
4000-12
13.0 Wall Cleaning
4000-13
14.0 Keystone Concrete Retaining Block Walls
4000-13
15.0 Interlocking Concrete Pavers — Installation Only
4000-16
16.0 Pickleball Court Synthetic Surfacing
4000-22
17.0 Site Amenities
4000-22
18.0 Landscape and Irrigation
4000-26
Appendix A: Escrow Agreement for Security Deposits In lieu of Retention
Appendix B: Standard Plans
SECTION 1100
INVITATION TO BID
PROJECT NO. 2016-031
LA QUINTA LANDSCAPE RENOVATION IMPROVEMENT — CACTUS FLOWER
SEALED BIDS will be received by the City of La Quinta (City) at the Office of the City Clerk
located at 78-495 Calle Tampico, La Quinta, California, 92253, until 11:00 AM on Monday,
December 4, 2023 at which time they will be publicly opened and read for performing work
as follows:
The project consists of removing designated turf and plant material and
sidewalk reconstruction along the parkway and street entrances at the
Cactus Flower Development along the southside of Fred Waring Drive
generally from Dune Palms Road to Monticello Avenue and on the east
side of Dune Palms from Star Flower Trail to Fred Waring Drive. Work
will also take place at the three retention basins within the
Development. Additionally, on the east side of Jefferson Street south of
Avenue 50 to 665 feet south of Avenue 50. Turf will be replaced with
drought -tolerant landscaping and irrigation. The plant palette shall
include Cresta rubble, multi -colored crushed rock, and Baja Cresta'
boulders of varying sizes with minimal use of drought -tolerant plants
and re -use of designated existing plant material. In addition, the
existing perimeter wall shall be cleaned, and construction of keystone
block wall at various locations. Existing lighting and electrical shall be
modified and new lighting shall be furnished and installed. An additive
alternate includes the construction of pickleball courts with site
amenities. All project work and incidental items to complete the project
shall be performed in accordance with the plans, specifications, and
other provisions of the contract. All the above improvements are to be
constructed in a workmanlike manner, leaving the entire project in a
neat and presentable condition. Refer to Sections 3000 and 4000 for
more information.
This project shall be completed within 60 working days from the date specified in the
Notice to Proceed. Time for the commencement and completion of the work is important
and is to be of the essence of the Contract. The successful bidder should plan to order any
long lead time equipment items immediately following "Notice of Award".
A pre-bid conference is scheduled for 2:00 PM, Tuesday, November 28, 2023 in the
Public Works conference room at City of La Quinta, City Hall located at 78-495 Calle
Tampico, La Quinta, California 92253.
Complete sets of the bidding documents may be purchased online at:
www.planitplanroom.com
Invitation to Bid
1100-1
IMPORTANT: If you are not on the plan holders list through Planit Planroom you will not
receive addendums. It is the responsibility of the bidder to ensure that they are placed on
the plan holders list.
Bidding procedures are prescribed in the Project Specifications. Bids shall be executed
upon the forms bound and made a part of said Specifications.
Bid security in an amount not less than ten percent (10%) of the total bid dollar amount and
conforming to the prescribed bidding procedures is required to be submitted with each bid,
as a guaranty to be forfeited should the bidder, if awarded the contract, fail to enter into the
same, or fails to furnish in a timely manner the bonds and/or proof of insurance. The City
reserves the right to reject any or all bids, and to waive any irregularities in the bids. Bid
log sheets can be found at http://www.laguintaca.gov/business/design-and-
development/bid-on-mobs.
Pursuant to the provisions of California Labor Code Section 6707, each bid submitted in
response to this Invitation to Bid shall contain, as a bid item, adequate sheeting, shoring,
and bracing, or equivalent method, for the protection of life and limb in trenches and open
excavation, which shall conform to applicable safety orders. By listing this sum, the bidder
warrants that its action does not convey tort liability to the City, its consultants, and their
employees, agents, and sub -consultants.
Pursuant to Section 1770, et. seq., of the California Labor Code, the successful bidder shall
pay not less than the prevailing rate of per diem wages as determined by the Director of the
California Department of Industrial Relations. These wage rates are available from the
California Department of Industrial Relations' Internet website at http://www.dir.ca.gov.
Pursuant to Section 1725.5 of the California Labor Code, no contractor or subcontractor
may be awarded a contract for public work on a public works project unless registered with
the Department of Industrial Relations at the time the contract is awarded. Contractors and
subcontractors may find additional information for registering at the Department of Industrial
Relations website at http://www.dir.ca.gov/Public-Works/PublicWorks.html .
Pursuant to Labor Code section 1771.1, no contractor or subcontractor may be listed on a
bid proposal for a public works project submitted on or after March 1, 2015 unless
registered with the Department of Industrial Relations. Furthermore, all bidders and
contractors are hereby notified that no contractor or subcontractor may be awarded, on or
after April 1, 2015, a contract for public work on a public works project unless registered
with the Department of Industrial Relations.
Pursuant to Labor Code section 1771.4, all bidders are hereby notified that this project is
subject to compliance monitoring and enforcement by the Department of Industrial
Relations.
Pursuant to SB854, all contractors and subcontractors must furnish electronic
certified payroll records directly to the Labor Commissioner (aka Division of Labor
Standards Enforcement). All contractors and subcontractors must also provide a
copy and proof to the City of online submittal within 2 days of online submission.
Invitation to Bid
"IIID:
Pursuant to Public Contract Code Section 22300, for monies earned by the Contractor and
withheld by the City to ensure the performance of the Contract, the Contractor may, at its
option, choose to substitute securities meeting the requirements of said Public Contract
Code Section 22300.
All bidders shall be licensed under the provisions of Chapter 9, Division 3 of the Business
and Professions Code of the State of California to do the type of work contemplated in the
project. In accordance with provisions of California Public Contract Code Section 3300, the
City has determined that the General Contractor shall possess a valid Class A (General
Contractor) and/or C12 (Earthwork and Paving Contractor), at the time that the bid is
submitted. Subcontractors shall possess valid, suitable licenses for the work they will
perform. Failure to possess the specified license(s) shall render the bid as non-responsive.
The successful bidder will be required to furnish a Labor and Materials bond in the amount
equal to one hundred percent (100%) of the Contract price, as well as a Faithful
Performance Bond, in the amount equal to one hundred percent (100%) of the Contract
price.
Each bidder shall submit with its bid a statement setting forth its experience on the forms
included in the Bid Proposal.
Telephones will not be available to bidders. Bid forms received after the designated time
will not be accepted. Bidders and their authorized agents are invited to attend.
No bidder may withdraw its bid for a period of sixty (60) days after the date set for the
opening of bids.
Approved
Published
Invitation to Bid
By:
Bryan WKinney, P.
Public Works Director/pity En ineer
By:
Monika Radeva
City Clerk
**END OF SECTION**
Date: November 9, 2023
Date: November 9, 2023
SECTION 1110
INSTRUCTIONS TO BIDDERS
1.0 WORK TO BE DONE
It is the intention of the City to construct improvements as shown and set forth on the plans
and detailed drawings, and in the particular locations shown on the drawings. All of the
work is particularly set forth in the plans and specifications, and all of said work, together
with all other work incidental thereto, is included.
The work includes the furnishing of all labor, materials, incidentals and equipment
necessary for Project No. 2016-031, La Quinta Landscape Renovation Improvement —
Cactus Flower
and all appurtenant incidental items. The Contractor shall be required to provide, at its own
cost and expense, all necessary insurance, as required by law or these specifications, and
shall pay the cost and expense of any and all incidental matters herein required.
2.0 EXAMINATION OF CONTRACT DOCUMENTS
Each bidder shall thoroughly examine and be familiar with those Contract documents
contained in the Project Manual, drawings and addenda, if any. The submission of a bid
shall constitute an acknowledgment upon which the City may rely that the bidder has
thoroughly examined and is familiar with the Contract documents. The failure or neglect of
a bidder to receive or examine any of the Contract documents shall in no way relieve him
from any obligation with respect to its proposal or to the Contract. No claim for additional
compensation will be allowed which is based upon a lack of knowledge of any Contract
documents.
3.0 INSPECTION OF SITE
Bidders are required to inspect the site of the work to satisfy themselves by personal
examination or by such other means as they may prefer, of the location of the proposed
work, and of the actual conditions of and at the site of work. If, during the course of its
examination, a bidder finds facts or conditions which appear to be in conflict with the letter
or spirit of the bidding documents, the Bidder may apply to the City, in writing, for additional
information and explanation before submitting its bid.
Submission of a bid by the bidder shall constitute acknowledgment that, if awarded the
Contract, it has relied and is relying on its own examination of (1) the site of the work, (2)
access to the site, and (3) all other data and matters requisite to the fulfillment of the work
and on its own knowledge of existing facilities on and in the vicinity of the site of the work to
be constructed under the Contract.
The information provided by the City is not intended to be a substitute for, or a supplement
to the independent verification by the bidder to the extent such independent investigation of
site conditions is deemed necessary or desirable by the bidder.
Instruction to Bidders 1110-1
4.0 INTERPRETATION OF CONTRACT DOCUMENTS
No oral representations or interpretations will be made to any bidder as to the meaning of
the Contract documents. Requests for an interpretation shall be made in writing and
delivered at least five (5) days before the time announced for opening the bids to:
Ubaldo Ayon, Assistant Construction Manager
City of La Quinta
78-495 Calle Tampico
La Quinta, CA 92253
(760) 777-7096 — Phone
uayon(a-laquintaca.gov — Email
Requests to clarify the source of materials, equipment, suppliers or any other such matter
which does not modify, change, increase, or decrease the scope of work requires no action
by the City other than a response to the bidder requesting the clarification. Requests to
clarify possible ambiguous or incomplete statements or designs, or any other such
clarification which modifies, changes, increases or decreases the scope of work, requires
issuance of an addendum by the City for the interpretation to become effective.
5.0 POSTPONEMENT OF OPENING
The City reserves the right to postpone the date and time for receiving and/or opening of
bids at any time prior to the date and time established in the Invitation to Bid.
Postponement notices shall be mailed to plan holders of record in the form of addenda.
6.0 OPENING OF BIDS
All bids, irrespective of any irregularities or informalities, if received on time, will be opened
and publicly read aloud at the time and place set forth in the Invitation to Bid. Bidders, their
representatives and other interested persons may be present at the opening and reading of
bids.
Any bids received after the time for receiving and opening bids as set forth in the Invitation
to Bid or as postponed by addenda will be considered nonresponsive and will not be
opened. Any such bids will be returned unopened to the Bidder.
The public reading of each bid will include at least the following:
A. Name and address of bidder.
B. The total amount of bid.
C. The nature and amount of the security furnished with the bid.
Instruction to Bidders 1110-2
7.0 PREPARATION OF BID FORMS
Bids shall be made on the blank forms in this manual and must be submitted at the time
and place stated in the Invitation to Bid. All blanks in the bid forms must be appropriately
filled in and all prices must be stated in figures. Unit prices in each and every case shall
represent a true unit price used in preparing the bid schedule totals (Bid Form). Unit prices
listed herein shall include material, installation and appurtenant work as is necessary to have
the item complete and in place meeting the full intent of the plans and specifications.
Unbalanced unit prices shall be sufficient cause for rejection of the bid. The purpose of the
unit pricing is for bid evaluation and changes in the work during construction. The basis for
award shall be the lowest combined price of the Base Bid Area plus all Additive
Alternates. All bids must be submitted in a sealed envelope, addressed to the City Clerk,
with the following annotation:
BIDDER
ADDRESS
This envelope contains a SEALED BID for:
Project No. 2016-031, La Quinta Landscape
Renovation Improvement — Cactus Flower
CITY OF LA QUINTA, CALIFORNIA
Envelope to be opened on:
December 4, 2023 @ 11:OOAM
Unless revised by Addendum.
It is the sole responsibility of the bidder to see that its bid is received in proper time. Any bid
received after the scheduled closing time for receipt of bids will be returned to the bidder
unopened. City shall not be responsible for errors or omissions in the bid. Bidders shall
write their names on each bid form at the space provided.
8.0 BIDDER'S SIGNATURE AND AUTHORITY
If the bid is made by an individual, his/her name, signature, and post office address must
be shown; if made by a firm or partnership, the name and post office address of the firm or
partnership, a list of the partners, and the signature of at least one of the general partners
must be shown; if made by a corporation, the bid shall show the name of the state under
the laws of which the corporation is chartered, the name and post office address of the
corporation, and the title of the person who signs on behalf of the corporation. If the bid is
made by the corporation, a certified copy of the bylaws or resolution of the Board of
Directors of the corporation shall be furnished, upon request of the City Engineer or
designee, showing the authority of the officer signing the bid to execute Contracts on behalf
of the corporation. If the bid is made by a joint venture, the bid shall be signed by a
representative of one of the joint venture firms. Additionally, the bid shall include a copy of
the resolution or contract empowering the representative to execute the bid and bind the
joint venture.
Instruction to Bidders 1110-3
9.0 ERASURES
The bid submitted must not contain any erasure, interlineations, or other corrections unless
each such correction is suitably authenticated by affixing in the margin immediately
opposite the correction the signature or signatures of the person or persons submitting the
bid.
10.0 BID IRREGULARITIES
Changes in or additions to the bid form, recapitulations of the work bid upon,
alternative bids, or any other modifications of the bid form which are not specifically
called for in the Contract Documents may result in rejection of the bid by the City, as
not being responsive to the Invitation to Bid. No oral or telephonic modification of any
bid submitted will be considered.
11.0 MODIFICATION OF BID
Modification of a bid already received will be considered only if the modification is received
prior to the time established for receiving bids. Modifications shall be made in writing,
executed, and submitted in the same form and manner as the original bid.
12.0 WITHDRAWAL OF BIDS
In accordance with Public Contract Code 5103, within five days after the opening of bids, a
bidder may withdraw its bid providing the bidder can establish to the City's satisfaction that
a mistake was made in preparing the bid. A bidder desiring to withdraw shall give written
notice to the City, specifying, in detail, how the mistake occurred and how the mistake
made the bid materially different than it was intended to be. Withdrawal will not be
permitted for mistakes resulting from errors in judgment or carelessness in inspecting the
site of the work or in reading the Project Documents.
13.0 ADDENDA
Addenda issued during the time of bidding shall become a part of the documents furnished
bidders for the preparation of bids, shall be covered in the bids, and shall be made a part of
the Contract. Each bid shall include specific acknowledgment in the space provided of
receipt of all Addenda issued during the bidding period. Failure to so acknowledge may
result in the bid being rejected as not responsive. Failure of any bidder to receive such
Addenda shall not be grounds for non-compliance with the terms of the instructions. You
must be on the plan holders list through Planit Planroom Enterprises or Plan Manager Pro
in order to receive Addenda.
14.0 BID PRICES
Bid prices shall include everything necessary for the completion of the work including but
not limited to providing the materials, equipment, tools, plant and other facilities, and the
management, superintendence, labor and services. Bid prices shall include allowance for
all federal, state and local taxes.
In the event of a difference between a price quoted in words and a price quoted in figures
for the same quotation, the words shall be the amount bid. In the event that the product of a
Instruction to Bidders 1110-4
unit price and an estimated quantity does not equal the extended amount quoted, the unit
price shall govern, and the correct product of the unit price and the estimated quantity shall
be deemed to be the amount bid. If the sum of two or more items in a bidding schedule
does not equal the total amount quoted, the individual item amounts shall govern and the
correct total shall be deemed to be the amount bid.
15.0 BID GUARANITY
The bid form shall be accompanied by a bid guaranty bond provided by a guaranty
company authorized to carry on business in the State of California for payment to the City
in the sum of at least ten (10) percent of the total amount of the bid price, or, alternatively,
by a certified or cashier's check, payable to the City in the sum of at least ten (10) percent
of the total amount of the bid price. The bid guarantee bond shall be provided on the form
included in Section 1220, BID GUARANTY BOND, of this Project Document. The amount
payable to the City under the bid guaranty bond, or the certified or cashier's check and the
amount thereof, as the case may be, shall be forfeited to the City as liquidated damages in
case of a failure or neglect of the bidder to furnish, execute, and deliver to the City the
required performance and payment bonds evidences of insurance; and to enter into,
execute, and deliver to the City the Contract on the form provided herewith, within ten (10)
calendar days after receiving written notice from the City that the award has been made
and the Contract is ready for execution.
The City shall retain all bid security until a contract has been executed or until the City
Council rejects all bids at which time all bid security not forfeited shall be returned to the
appropriate bidders.
16.0 QUALIFICATION OF BIDDER
Each bidder shall complete and submit with their bid Section 1230, CERTIFICATION OF
BIDDER'S EXPERIENCE AND QUALIFICATIONS.
Upon the request of City, any bidder whose bid is under consideration for the award of the
Contract shall promptly submit satisfactory evidence showing the bidder's financial
resources, its construction experience, and its organization's availability for the
performance of the Contract.
The bidder may be required to establish to the satisfaction of the City the reliability and
responsibility of the persons or entities proposed to furnish and perform the work described
in the Documents.
17.0 SUBCONTRACTORS
In accordance with California Public Contracting Code Section 4100, et. seq., each bid
shall have listed in Section 1240, PROPOSED SUBCONTRACTORS, the name, portion of
work to be performed, and location of the place of business of each subcontractor who will
perform work or labor or render service to the bidder in or about the construction of the
work or improvement, or of any subcontractor licensed by the State of California who, under
subcontract to the bidder, will specially fabricate and install a portion of the work or
improvement according to detailed drawings contained in the plans and specifications, in
an amount in excess of one-half of one percent of the bidder's total bid, or, in the case of
Instruction to Bidders 1110-5
bids or offers for the construction of streets or highways, including bridges, in excess of
one-half of one percent of the bidder's total bid or Ten Thousand Dollars ($10,000.00),
whichever is greater.
The Contractor shall perform, with its own organization, Contract work amounting to at least
50 percent of the Contract Price except that any designated "Specialty Items" may be
performed by subcontract and the amount of any such "Specialty Items" so performed will
be deducted from the Contract Price before computing the amount required to be
performed by the Contractor with its own organization. "Specialty Items" will be identified by
the Agency in the Bid or in the Special Provisions. Where an entire item is subcontracted,
the value of work subcontracted will be based on the Contract Unit Price. When a portion of
an item is subcontracted, the value of work subcontracted will be based on the estimated
percentage of the Contract Unit Price. This will be determined from the information
submitted by the Contractor, and subject to approval of the Engineer.
Failure to list subcontractors may render the bid non-responsive and may be grounds for
rejection of the bid. Failure to comply with the provisions of the California "Subletting and
Subcontracting Fair Practices Act" shall make the Contractor subject to the sanctions as set
forth in the Act.
18.0 BIDDERS INTERESTED IN MORE THAN ONE BID
No person, firm, or corporation, under the same or different name, shall make, file, or be
interested in more than one bid for the same work unless alternate bids are called for. A
person, firm, or corporation may, however, submit sub -proposals or quote prices on
materials to more than one bidder.
The City may reject the bids of the known participants in such collusion. Pursuant to Public
Contract Code Section 7106, bidders shall execute and furnish with their bids Section
1250, NON -COLLUSION AFFIDAVIT.
19.0 SHEETING, SHORING AND BRACING
Pursuant to the provisions of California Labor Code Section 6707, each bid submitted shall
contain, in the bid item indicated, the amount included in its bid for adequate sheeting,
shoring, and bracing, or equivalent method, for the protection of life and limb in trenches
and open excavation, which shall conform to applicable safety orders. By listing this sum,
the bidder warrants that its action does not convey tort liability to the City, its consultants,
and their employees, agents, and sub -consultants.
20.0 WAGE RATES
Pursuant to provisions of the Labor Code Section 1770, et. seq., of the State of California,
the Director of the Department of Industrial Relations has ascertained the prevailing rate of
per diem wages of the locality in which the Work is to be performed and applicable to the
work to be done. These wage rates are available from the California Department of
Industrial Relations' Internet web site at: www.dir.ca.gov
Bidders shall promptly notify the City, in writing, about all the classifications of labor not
listed in the prevailing wage determinations but necessary for the performance of the Work
before bids are submitted.
Instruction to Bidders 1110-6
21.0 OFFER OF ASSIGNMENT OF ANTITRUST ACTIONS
As provided by Sections 4551 and 4552 of the California Government Code, in submitting a
bid to the City, the bidder offers and agrees that if the bid is accepted, it will assign to the
City all rights, title, and interest in and to all causes of action it may have under Section 4 of
the Clayton Act (15 U.S.C. Section 15) or under the Cartwright Act (Chapter 2 [commencing
with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising
from purchases of goods, materials, or services by the bidder for sale to the City pursuant
to the bid. Such assignment shall be made and become effective at the time the City
tenders final payment to the bidder.
22.0 ASSIGNMENT OF CONTRACT
No assignment by the Contractor of any contract to be entered into hereunder, or any part
thereof, or of funds to be received thereunder by the Contractor, will be recognized by City
unless such assignment has had prior approval of City and the Surety has been given due
notice of such assignment in writing and has consented thereto in writing.
23.0 REJECTION OF BIDS
The City reserves the right to reject all bids for any reason. The City further reserves the
right to reject any bid: which is non-responsive, incomplete, obscure, or irregular; which
omits a bid on any one or more of the required bid items; which does not contain
satisfactory documentation of the bidder's qualifications as required by Section 1110-16.0,
QUALIFICATION OF BIDDER; which, in the City's opinion, the unit prices are unbalanced;
which is accompanied by insufficient or irregular bid security; or, which is from a bidder who
has previously failed, on a contract of any nature, to perform properly or to complete it on
time. The City reserves the right to waive irregularities.
24.0 CONTRACT AND BONDS
The successful bidder, simultaneously with the execution of the Contract, will be required to
furnish a Payment Bond on forms provided by the City in an amount equal to one hundred
percent (100%) of the Contract Price, a Faithful Performance Bond in an amount equal to
one hundred (100%) of the Contract Price, and the WORKER'S COMPENSATION
INSURANCE CERTIFICATE in Section 1330. Said bonds shall be secured from a surety
company satisfactory to City.
The form of Contract, as provided in Section 1300, which the successful bidder as
Contractor will be required to execute, and the forms of bonds as provided in Sections 1310
and 1320, which it will be required to furnish, shall be carefully examined by the bidder.
25.0 AWARD OF CONTRACT
Within sixty (60) days after the time of opening of the bids, the City will act either to accept
a bid, to reject all bids or with the consent of the bidders and their sureties to extend the
time in which the City may act. The acceptance of a bid will be evidenced by a notice of
award of Contract in writing, delivered in person or by certified mail to the bidder whose bid
is accepted. No other act of City will constitute acceptance of a bid. The award of Contract
shall obligate the bidder whose bid is accepted to furnish performance and payment bonds
Instruction to Bidders 1110-7
and evidences of insurance, and to execute the Contract in the form set forth in the
Contract documents.
26.0 EXECUTION OF CONTRACT
The Contract Agreement shall be executed by the successful bidder and returned,
together with the Contract bonds and evidences of insurance, within ten (10) days
after receiving written notice of the award of the Contract. Time is of the essence in
this regard. After execution by City, one copy shall be returned to Contractor.
27.0 CONSTRUCTION DOCUMENTS
The City will furnish the Contractor five copies of the Specifications after the execution of
the Contract. The Contractor may request up to three additional copies at no cost, for a
total of eight (8) no cost copies.
28.0 BID PROTEST
Any bid protest must be in writing and received by City at the Office of the City Clerk
located at 78-495 Calle Tampico, La Quinta, California, 92253, before 5:00p.m., no later
than two working days following bid opening (the "Bid Protest Deadline") and must comply
with the following requirements:
28.1 General. Only a bidder who has actually submitted a Bid Proposal is eligible to
submit a bid protest against another bidder. Subcontractors are not eligible to
submit bid protests. A bidder may not rely on the bid protest submitted by
another bidder but must timely pursue its own protest. The protesting bidder
must submit a non-refundable fee in the amount of $824.00, based upon City's
reasonable costs to administer the bid protest. Any such fee must be
submitted to City no later than the Bid Protest Deadline, unless otherwise
specified. For purposes of this Section 28, a "working day" means a day that
City is open for normal business, and excludes weekends and holidays
observed by City.
28.2 Protest Contents. The bid protest must contain a complete statement of the basis
for the protest and all supporting documentation. Material submitted after the Bid
Protest Deadline will not be considered. The protest must refer to the specific
portion or portions of the Contract Documents upon which the protest is based. The
protest must include the name, address, email address, and telephone number of
the person representing the protesting bidder if different from the protesting bidder.
28.3 Copy to Protested Bidder. A copy of the protest and all supporting documents
must be concurrently transmitted by fax or by email, by or before the Bid Protest
Deadline, to the protested bidder and any other bidder who has a reasonable
prospect of receiving an award depending upon the outcome of the protest.
28.4 Response to Protest. The protested bidder may submit a written response to
the protest provided the response is received by City before 5:00p.m., within
two working days after the Bid Protest Deadline or after actual receipt of the
bid protest, whichever is sooner (the "Response Deadline"). The response must
include all supporting documentation. Material submitted after the Response
Instruction to Bidders 1110-8
Deadline will not be considered. The response must include the name, address,
email address, and telephone number of the person representing the protested
bidder if different from the protested bidder.
28.5 Copy to Protesting Bidder. A copy of the response and all supporting
documents must be concurrently transmitted by fax or by email, by or before
the Bid Protest Deadline, to the protesting bidder and any other bidder who
has a reasonable prospect of receiving an award depending upon the outcome
of the protest.
28.6 Exclusive Remedy. The procedure and time limits set forth in this section are
mandatory and are the bidder's sole and exclusive remedy in the event of bid
protest. A bidder's failure to comply with these procedures will constitute a waiver of
any right to further pursue a bid protest, including filing a Government Code Claim or
initiation of legal proceedings.
28.7 Right to Award. The City Council reserves the right to award the Contract to the
bidder it has determined to be the responsible bidder submitting the lowest
responsive bid, and to issue a notice to proceed with the Work notwithstanding any
pending or continuing challenge to its determination.
29.0 COMPLIANCE WITH IRAN CONTRACTING ACT OF 2010. Pursuant to the Iran
Contracting Act of 2010 (Pub. Contract Code, § 2200 et seq.),
(a) Contractor shall be ineligible to bid on or submit a proposal for any contract for One
Million Dollars ($1,000,000) or more if Contractor engages in investment activities in
Iran as defined in Public Contract Code Section 2202.5, and/or if Contractor is
identified on the list of persons engaging in investment activities in Iran prepared by
the State of California pursuant to Public Contract Code Section 2203 subdivision
(b).
(b) For bids of One Million Dollars ($1,000,000) or more, Contractor must certify that it is
not on the list of ineligible vendors prohibited from doing business with the State of
California and shall complete the Iran Contracting Act Certification and submit with
their proposal at the time of bid. Contractor shall obtain the Iran Contracting Act
Certification in the form approved by the State of California, or upon written request
to the City Clerk's Office, a copy of the form will be provided to Contractor. Failure
by Contractor to provide the certification required by this Section may deem
Contractor's bid non-responsive.
Nothing in this Section is intended to prevent the City from exercising its rights
pursuant to Public Contract Code section 2203, subdivision (c) or (d), or both, on a
case-by-case basis.
30.0 COMPLIANCE WITH CALIFORNIA EXECUTIVE ORDER N-6-22. Russian
aggression against Ukraine.
(a) Contractor shall comply with California Governor Executive Order N-6-22 regarding
sanctions in response to Russian aggression in the Country of Ukraine, and any
implementing guidelines and/or economic sanctions imposed by the United States
government in response to Russian actions in Ukraine, as well as any sanctions
Instruction to Bidders 1110-9
imposed under California law (collectively "economic sanctions"). Contractor shall
comply with all such economic sanctions. By submitting a bid to the City, Contractor
agrees to take any and all actions to support the Ukrainian government and people
as required by law, including by refraining from new investments in, and financial
transactions with, Russian institutions or companies that are headquartered or have
their principal place of business in Russia (Russian entities), not transferring
technology to Russia or Russian entities, and directly providing support to the
government and people of Ukraine.
(b) If bidding on a contract for Five Million Dollars ($5,000,000) or more, Contractor
shall submit a written report to the City on Contractor's compliance with the
economic sanctions, and the steps Contractor has taken in response to Russia's
actions in Ukraine, including, but not limited to, desisting from making new
investments in, or engaging in financial transactions with, Russian entities, not
transferring technology to Russia or Russian entities, and directly providing support
to the government and people of Ukraine as required by law. Failure to submit the
report required by this Section may deem Contractor's bid non-responsive.
**END OF SECTION**
Instruction to Bidders 1110-10
SECTION 1200
BID
MAN 9: I
The undersigned, as bidder, declares it has received and examined the Contract
Document entitled Project No. 2016-031, La Quinta Landscape Renovation
Improvement — Cactus Flower and will contract with the City, on the form of Contract
provided herewith, to do everything required for the fulfillment of the contract for said work
at the prices and on the terms and conditions herein contained.
We have included the following items and agree that they shall form a part of this bid:
SECTION TITLE
1200
Bid
1210
Bid Schedule
1220
Bid Guaranty Bond
1230
Certification of Bidder's Experience and Qualifications
1240
Proposed Subcontractors
1250
Non -Collusion Affidavit
1260
DIR Project Vendor Information
1270
Iran Contracting Act of 2010
1280
Russian Aggression Against Ukraine Sanctions
We acknowledge that the following addenda have been received and have been
examined as part of the Contract Documents. Bidders must be on the Plan Holders List
with the City of La Quinta in order to receive addenda.
Addendum #
Date Received
Initials
Attached is a bid guaranty bond as required by Paragraph 1110-15.0, BID GUARANTY.
Name of Bidder
Bidder's Telephone Number
Bid 1200-1
If our bid is accepted, we agree to sign the contract without qualifications and to furnish
the performance and payment bonds and the required evidence of insurance within 10
calendar days after receiving written notice of the award of the contract.
We further agree, if our bid is accepted and a Contract for performance of the work is
entered into with the City, to so plan work and to prosecute it with such diligence that the
work shall be completed within the time stipulated.
Name of Bidder
Bidder's Address
Contractor's License No.
State of Incorporation
Signature of Bidder
Printed Name of Signatory
Title of Signatory
Bidder's Telephone Number
Bidder's Email Address
Contractor's Expiration Date
Witness
Title of Witness
Bid 1200-2
SECTION 1210
BID SCHEDULE
PROJECT NO. 2016-031
LA QUINTA LANDSCAPE RENOVATION IMPROVEMENT — CACTUS FLOWER
City of La Quinta
78-495 Calle Tampico
La Quinta, CA 92253
To Whom It May Concern:
Pursuant to the Invitation to Bid, and in accordance with the provisions therein stated, the
undersigned hereby proposes and agrees that on award by the City under this Bid, to
execute a Contract, with necessary bonds, to furnish and install any and all labor,
materials, transportation and services for Project No. 2016-031, La Quinta Landscape
Renovation Improvement — Cactus Flower
in accordance with the plans and specifications therefore adopted and on file with the City
within the time hereinafter set forth and at the prices named in this Bid. It is understood
that the basis of award shall be the lowest total price of the Base Bid Area plus all
Additive Alternates.
Unit prices in each and every case represent the true unit price used in preparing the bid
schedule totals (Bid Form). Unit prices listed herein include material, installation and
appurtenant work as is necessary to have the item complete and in place meeting the full
intent of the plans and specifications. We acknowledge that unbalanced unit prices shall
be sufficient cause for the rejection of our bid.
BASE BID —
Item
No.
Item Description
Est.
Qty.
Unit
Unit Price
(in figures)
Dollars
Item Total
(in figures)
Dollars
OVERALL PROJECT
1
Mobilization
1
LS
$
2
Traffic Control (Includes Traffic
Control Plans and Engineering)
1
LS
$
$
3
Dust Control
1
LS
$
4
Clearing and Grubbing
1
LS
$
CACTUS FLOWER PLAN IMPROVEMENTS
Bid Schedule 1210-1
Item
Item Description
Est.
Unit
Unit Price
Item Total
No.
Qty.
(in figures)
(in figures)
Dollars
Dollars
5
Demolition and Disposal
1
LS
$
6
Soil Preparation and Fine Grading
1
LS
$
Modify, Relocate, and Repair
7
Existing Lighting Electrical System
1
LS
$
w/ New Fixtures
8
Install New Sleeving per City
1
LS
$
Standard
9
Sidewalk Replacement per City
280
SF
$
$
Code and Concrete Pads
10
Wall Cleaning
1
LS
$
11
Keystone Block — 2 Course Stack
1,084
SF
$
$
12
Keystone Block — 3 Course Stack
1,542
SF
$
$
13
Keystone Block — 4 Course Stack
1,360
SF
$
$
14
Keystone Block — 5 Course Stack
1,100
SF
$
$
15
Furnish and Install - Landscape
111
EA
$
$
Boulders
Furnish and Install - 3/8" Minus
16
w/20% Fines — Decomposed
1,295
SF
$
$
Granite — Desert Gold
17
Furnish and Install - 3/8" Crushed
1,835
SF
$
$
Rock — Apache Brown
18
Furnish and Install — 3/4" Crushed
88,675
SF
$
$
Rock — Desert Gold
19
Furnish and Install - 12"-18" Sierra
1,045
SF
$
$
Cobble
20
Furnish and Install - 6" Minus
7,455
SF
$
$
Crushed — Baja Cresta Rubble
21
Furnish and Install - 6" Minus
3,680
SF
$
$
Crushed — Cresta Rubble
22
Furnish and Install PermaLoc
1 730
LF
$
$
Header — Asphalt Edge
23
Furnish and Install Landscaping
1
LS
$
$
per Plan
24
Furnish and Install Irrigation per
1
LS
$
$
Plan
Bid Schedule 1210-2
Item
Item Description
Est.
Unit
Unit Price
Item Total
No.
Qty.
(in figures)
(in figures)
Dollars
Dollars
25
90 — Day Maintenance Period
1
LS
$
$
JEFFERSON PARKWAY PLAN IMPROVEMENTS
26
Demolition and Disposal
1
LS
$
$
27
Soil Preparation and Fine Grading
1
LS
$
$
28
Keystone Block — 2 Course Stack
20
SF
$
$
29
Furnish and Install - Landscape
4
EA
$
$
Boulders
30
Furnish and Install - 3/8" Crushed
3,556
SF
$
$
Rock — Apache Brown
31
Furnish and Install - 6" Minus
164
SF
$
$
Crushed — Baja Cresta Rubble
32
Furnish and Install PermaLoc
25
LF
$
$
Header — Asphalt Edge
33
Boring for Lateral Line
60
LF
$
$
34
Furnish and Install Landscaping
1
LS
$
$
per Plan
35
Furnish and Install Irrigation per
1
LS
$
$
Plan
36
90 — Day Maintenance Period
1
LS
$
$
Total Amount of Bid Items 1 — 36
$
Bid Schedule 1210-3
ADDITIVE ALTERNATE 01— CACTUS FLOWER MINI SPORTS PARK
Item
Item Description
Est.
Unit
Unit Price
Item Total
No.
Qty.
(in figures)
(in figures)
Dollars
Dollars
AA1-1
Site Control
1
LS
$
$
AA1-2
Dust Control
1
LS
$
$
AA1-3
Clearing and Grubbing
1
LS
$
$
AA1-4
Demolition and Disposal
1
LS
$
AA1-5
Fine Grading
1
LS
$
3" Asphalt Concrete Over 4"
AA1-6
Aggregate Base Over 12"
700
SF
$
$
Scarified and Compacted Native
AA1-7
Asphalt Crack Fill
3,340
SF
$
$
AA1-8
Interlocking Concrete Pavers
740
SF
$
$
(Installation Only)
AA1-9
Concrete Banding — 2' Wide, 6"
72
LF
$
$
Thick
AA1-10
Pickleball Court Synthetic
3,100
SF
$
$
Surfacing
AA1-11
Pickleball Fence and Gates per
1
LS
$
$
Plan
AA1-12
Pickleball Net and Posts
1
LS
$
$
AA1-13
Benches — 6' Length
2
EA
$
$
AA1-14
Drinking Fountain and 1" Water
1
EA
$
$
Service Line
Total Amount of Bid Items AA1- 1 — 14
$
Bid Schedule 1210-4
GRAND TOTAL BASE BID PLUS ALL ADDITIVE ALTERNATES (Figures):
Eli
GRAND TOTAL BASE BID PLUS ALL ADDITIVE ALTERNATES (Words):
Bid Amount of each of the above Bid Items must be filled in and completed. It is
understood that the quantities shown hereon are but estimates and the bidder is
responsible to verify quantities prior to submitting a bid. Final payment will be based
upon actual work performed, subject to such adjustments and alterations as elsewhere
provided herein.
Signature of Bidder (Ink)
Name of Bidder (Printed or Typed)
Bidder Telephone Number
Bidder Email Address
Bid Schedule 1210-5
SECTION 1220
BID GUARANTY BOND
PRINCIPAL, and , as SURETY, are held and firmly bound
unto the City in the penal sum of TEN (10) PERCENT OF THE TOTAL AMOUNT OF
THE BID of the Principal above named, submitted by said Principal to the City for the
work described below, for the payment of which sum in lawful money of the United
States, well and truly to be made to the City to which said bid was submitted, we bind
ourselves, our heirs, executors, administrators, and successors, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT WHEREAS, the Principal
has submitted the above-mentioned bid to the City, for certain construction specifically
described as follows, for which bids are to be opened at La Quinta, California.
PROJECT NO. 2016-031
LA QUINTA LANDSCAPE RENOVATION IMPROVEMENT — CACTUS FLOWER
NOW, THEREFORE, if the aforesaid Principal is awarded the contract and, within the
time and manner required under the specifications, after the prescribed forms are
presented to him/her for signature enters into a written contract in the prescribed form, in
accordance with the bid, and files two bonds with the City, one to guarantee faithful
performance, and the other to guarantee payment for labor and materials as required by
law, and provide certificate of insurance coverage required by the Contract Documents,
then this obligation shall be null and void; otherwise, it shall be and remain in full force
and virtue.
IN WITNESS WHEREOF, we have hereunto set our hands on this day of
.2023.
Title of Signatory
Signature of Principal
Address
Title of Signatory
Signature of Surety
Address
Note: Signatures of those executing for the surety must be properly acknowledged.
Bid Guaranty Bond 1220-1
SECTION 1230
CERTIFICATION OF BIDDER'S EXPERIENCE AND QUALIFICATIONS
The undersigned Bidder certifies that he is, at the time of bidding, and shall be,
throughout the period of the contract, licensed under the provisions of Chapter 9, Division
3, of the Business and Professions Code of the State of California, to do the type of work
contemplated in the Contract Documents. Bidder shall further certify that it is skilled and
regularly engaged in the general class and type of work called for in the Contract
Documents.
The Bidder represents that it is competent, knowledgeable, and has special skills on the
nature, extent, and inherent conditions of the work to be performed. Bidder further
acknowledges that there are certain peculiar and inherent conditions existent in the
construction of the particular facilities, which may create, during the construction program,
unusual or peculiar unsafe conditions hazardous to persons and property. Bidder
expressly acknowledges that it is aware of such peculiar risks and that it has the skill and
experience to foresee and to adopt protective measures to adequately and safely perform
the construction work with respect to such hazards.
The Bidder shall list below four (4) projects completed in the last seven (7) years of
similar size and complexity that indicate the Bidder's experience as a General Contractor.
1. Project Name:
Owner:
Construction Cost: $
Construction Time:
Owner's Representative:
Owner's Telephone No.:
Date of Substantial Completion:
2. Project Name:
Owner:
Construction Cost: $
Construction Time:
Owner's Representative:
Owner's Telephone No.:
Date of Substantial Completion:
Calendar Days
Calendar Days
Bidders Experience & Qualifications 1230-1
KI
9
Project Name:
Owner:
Construction Cost: $
Construction Time:
Owner's Representative:
Owner's Telephone No.:
Date of Substantial Completion:
Project Name:
Owner:
Construction Cost: $
Construction Time:
Owner's Representative:
Owner's Telephone No.:
Date of Substantial Completion:
Signed this
Name of Bidder
Signature of Bidder
day of
Printed Name of Bidder
Calendar Days
Calendar Days
2023.
Contractor's License No. DIR Reg No.
Expiration Date
Title of Signatory
Bidders Experience & Qualifications 1230-2
SECTION 1240
PROPOSED SUBCONTRACTORS
Pursuant to California Public Contracting Code, Section 4100 et. seq., the following list
gives the name, business address, and portion of work (description of work to be done)
for each subcontractor that will be used in the work if the bidder is awarded the Contract.
(Additional supporting data may be attached to this page. Each page shall be sequentially
numbered and headed "Proposed Subcontractors" and shall be signed.)
The Contractor shall perform, with its own organization, Contract work amounting to at
least 50 percent of the Contract Price except that any designated "Specialty Items" may
be performed by subcontract and the amount of any such "Specialty Items" so
performed will be deducted from the Contract Price before computing the amount
required to be performed by the Contractor with its own organization. "Specialty Items"
will be identified by the Agency in the Bid or in the Special Provisions. Where an entire
item is subcontracted, the value of work subcontracted will be based on the Contract
Unit Price.
Subcontractor/Business Address/Description of Work/% of Work/License No./DIR Reg No.
Signature of Bidder
Name of Bidder
Proposed Subcontractors 1240-1
SECTION 1250
NON -COLLUSION AFFIDAVIT TO BE EXECUTED BY BIDDER AND SUBMITTED
WITH BID
State of California )
ss.
County of )
being first duly sworn, deposes and say that he
or she is of , the
party making the foregoing bid that the bid is not made in the interest of, or on behalf of,
any undisclosed person, partnership, company, association, organization, or corporation;
that the bid is genuine and not collusive or sham; that the bidder has not directly or
indirectly induced or solicited any other bidder to put in a false or sham bid, and has not
directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone
else to put in a sham bid, or that anyone shall refrain from bidding; that the bidder has not
in any manner, directly or indirectly sought by contract, agreement, communication, or
conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any
overhead, profit, or cost element of the bid price, or of that of any other bidder, or to
secure any advantage against the public body awarding the contract of anyone interested
in the proposed contract; that all statements contained in the bid are true; and, further,
that the bidder has not, directly or indirectly, submitted his or her bid price or any
breakdown thereof, or the contents thereof, or divulged information or data relative
thereto, or paid, and will not pay, any fee to any corporation, partnership, company
association, organization, bid depository, or to any member or agent thereof to effectuate
a collusive or sham bid.
Signature
Name of Bidder
Title
Date
Non -Collusion Affidavit 1250-1
SECTION 1260
DIR Project Vendor Information
Vendor Information:
Name:
Address:
Project Manager:
Phone:
Public Works Registration No.:
Classification:
City:
Email:
ST: Zip:
CSLB/Certification Number:
Asbestos Boilermaker Bricklayers Carpenter Carpet/Linoleum_
Cement Masons Drywall Finisher Drywall/Lathers Electricians
Elevator Mechanic Glaziers Iron Workers Laborers Millwrights
Operating Eng Painters Pile Drivers Pipe Trades Plasterers
Roofer SheetMetal Sound/Com Surveyor Teamster Tile Worker.
Prevailing Wages and Payroll:
The project is subject to prevailing wage rates and enforcement by the Department of
Industrial Relations (DIR). Prevailing wage rates can be obtained at:
http://www.dir.ca.gov/Public-Works/Prevailing-Wage.html.
Contractors and subcontractors on most public Works projects are required to submit
certified payroll records to the Labor Commissioner using DIR's electronic certified
payroll reporting system. For your convenience, the link for reporting certified payroll is:
httD://www.dir.ca.aov/Public-Works/Certified-Pavroll-ReDortina.html.
A copy of certified payroll, including the names and addresses of employees
and/or subcontractors working on the job must be included with invoices
submitted to the City of La Quinta.
DIR Project Vendor Information 1260-1
SECTION 1270
COMPLIANCE WITH IRAN CONTRACTING ACT OF 2010
Pursuant to the Iran Contracting Act of 2010 (Pub. Contract Code, § 2200 et seq.),
(a) Contractor shall be ineligible to bid on or submit a proposal for any contract for
One Million Dollars ($1,000,000) or more if Contractor engages in investment
activities in Iran as defined in Public Contract Code Section 2202.5, and/or if
Contractor is identified on the list of persons engaging in investment activities
in Iran prepared by the State of California pursuant to Public Contract Code
Section 2203 subdivision (b).
(b) For bids of One Million Dollars ($1,000,000) or more, Contractor must certify
that it is not on the list of ineligible vendors prohibited from doing business with
the State of California and shall complete the Iran Contracting Act Certification
and submit with their proposal at the time of bid. Contractor shall obtain the
Iran Contracting Act Certification in the form approved by the State of California,
or upon written request to the City Clerk's Office, a copy of the form will be
provided to Contractor. Failure by Contractor to provide the certification
required by this Section may deem Contractor's bid non-responsive.
(c) Nothing in this Section is intended to prevent the City from exercising its rights
pursuant to Public Contract Code section 2203, subdivision (c) or (d), or both,
on a case-by-case basis.
IRAN CONTRACTING ACT CERTIFICATION
Pursuant to the Iran Contract Act of 2010 (Public Contract Code 2200-2208), Vendors/Bidders
are ineligible to bid on or submit a proposal for any contract with a public entity for goods or
services of one million dollars ($1,000,000) or more if the Vendor/Bidder engages in
investment activities in Iran.
MUST BE SUBMITTED WITH BID PROPOSAL IF BID AMOUNT IS $1,000,000 OR MORE
Prior to bidding on, submitting a proposal, or executing a contract or renewal for a public entity
contract for goods or services of $1,000,000 or more, a vendor must either: a) certify it is not
on the current list of persons engaged in investment activities in Iran created by the California
Department of General Services ("DGS") pursuant to Public Contract Code section 2203(b) and
is not a financial institution extending $20,000,000 or more in credit to another person, for 45
days or more, if that other person will use the credit to provide goods or services in the energy
sector in Iran and is identified on the current list of persons engaged in investment activities in
Iran created by DGS; or b) demonstrate it has been exempted from the certification
requirement for that solicitation or contract pursuant to Public Contract Code section 2203(c)
or (d).
To comply with this requirement, please insert your vendor or financial institution name and
Federal ID Number (if available) and complete one of the options below. Please note: California
law establishes penalties for providing false certifications, including civil penalties equal to the
greater of $250,000 or twice the amount of the contract for which the false certification was
made, contract termination, and three-year ineligibility to bid on contracts. (Pub. Cont. Code §
2205.)
OPTION #1- CERTIFICATION
I, the official named below, certify I am duly authorized to execute this certification on behalf of
the vendor/financial institution identified below, and the vendor/financial institution identified
below is not on the current list of persons engaged in investment activities in Iran created by
DGS and is not a financial institution extending twenty million dollars ($20,000,000) or more in
credit to another person/vendor, for 45 days or more, if that other person/vendor will use the
credit to provide goods or services in the energy sector in Iran and is identified on the current
list of persons engaged in investment activities in Iran created by DGS.
I certify (or declare) under penalty of perjury under the laws of the State of California that the
foregoing is true and correct.
„ Vendor Name/Financial Institution (Printed) Federal ID Number (or n/a)
By (Authorized Signature)
Printed Name and Title of Person Signing
Iran Contracting Act Certification
Date Executed
1270-2
OPTION #2 — EXEMPTION
Pursuant to Public Contract Code sections 2203(c) and (d), a public entity may permit a
vendor/financial institution engaged in investment activities in Iran, on a case-by-case basis, to
be eligible for, or to bid on, submit a proposal for, or enters into or renews, a contract for goods
and services.
If you have obtained an exemption from the certification requirement under the Iran
Contracting Act, please fill out the information below, and attach documentation
demonstrating the exemption approval.
Vendor Name/Financial Institution (Printed)
By (Authorized Signature)
Printed Name and Title of Person Signing
Federal ID Number (or n/a)
Date Executed
Iran Contracting Act Certification 1270-3
SECTION 1280
COMPLIANCE WITH CALIFORNIA EXECUTIVE ORDER N-6-22
RUSSIAN AGGRESSION AGAINST UKRAINE
(a) Contractor shall comply with California Governor Executive Order N-6-22
regarding sanctions in response to Russian aggression in the Country of Ukraine,
and any implementing guidelines and/or economic sanctions imposed by the
United States government in response to Russian actions in Ukraine, as well as
any sanctions imposed under California law (collectively "economic
sanctions"). Contractor shall comply with all such economic sanctions. By
submitting a bid to the City, Contractor agrees to take any and all actions to
support the Ukrainian government and people as required by law, including by
refraining from new investments in, and financial transactions with, Russian
institutions or companies that are headquartered or have their principal place of
business in Russia (Russian entities), not transferring technology to Russia or
Russian entities, and directly providing support to the government and people
of Ukraine.
(b) If bidding on a contract for Five Million Dollars ($5,000,000) or more, Contractor
shall submit a written report to the City on Contractor's compliance with the
economic sanctions, and the steps Contractor has taken in response to Russia's
actions in Ukraine, including, but not limited to, desisting from making new
investments in, or engaging in financial transactions with, Russian entities, not
transferring technology to Russia or Russian entities, and directly providing
support to the government and people of Ukraine as required by law. Failure to
submit the report required by this Section may deem Contractor's bid non-
responsive.
Please include a written report to the City if this section is applicable.
SECTION 1300
CONTRACT
THIS CONTRACT, by and between the CITY OF LA QUINTA, a municipal
corporation, herein referred to as "City," and ,
herein referred to as, "Contractor."
WITNESSETH:
In consideration of their mutual covenants, the parties hereto agree as follows:
1. Contractor shall furnish all necessary labor, material, equipment, transportation
and services for Project No. 2016-031, La Quinta Landscape Renovation
Improvement — Cactus Flower in the City of La Quinta, California pursuant to the
Invitation to Bid, dated November 2023, the project Specifications, and Contractor's
Bid, all of which documents shall be considered a part hereof as though fully set herein.
Should any provisions of Contractor's Bid be in conflict with the Notice Inviting
Bids, Specifications, or this Contract, then the provisions of said Contract,
Specifications, and Invitation to Bid shall be controlling, in that order of precedence.
The time frame for construction work shall be in accordance with that specified in the
Invitation to Bid.
2. Contractor will comply with all Federal, State, County, and La Quinta Municipal
Code, which are, as amended from time to time, incorporated herein by reference.
3. All work shall be done in a manner satisfactory to the City Engineer.
4. Contractor shall commence work after the issuance of a written Notice to
Proceed and agrees to have all work completed within 60 working days from the date
of Notification to Proceed.
5. In consideration of said work, City agrees to pay Contractor such sums as shall
be approved by the City Engineer at lump sums and/or unit prices stated in the
Contractor's Bid, the base consideration (Type in correct dollar amount using
currency format)
($ .00). All payments shall be subject to approval by the City Engineer and
shall be in accordance with the terms, conditions, and procedures provided in the
Specifications.
6. The Contractor shall not knowingly pay less than the general prevailing rate for
per diem wages, as determined by the State of California Department of Industrial
Relations and referred to in the Invitation to Bid, to any workman employed for the work
to be performed under this contract; and the Contractor shall forfeit as a penalty to the
City the sum of Twenty -Five Dollars ($25.00) for each calendar day, or fraction thereof,
for such workman paid by him or by any subcontractor under him in violation of this
provision (Sections 1770-1777, Labor Code of California).
Contract 1300-1
Pursuant to Section 1770, et. seq., of the California Labor Code, the successful bidder
shall pay not less than the prevailing rate of per diem wages as determined by the
Director of the California Department of Industrial Relations. These wage rates are
available from the California Department of Industrial Relations' Internet website at
http://www.dir.ca.gov.
Pursuant to Section 1725.5 of the California Labor Code, no contractor or subcontractor
may be awarded a contract for public work on a public works project unless registered
with the Department of Industrial Relations at the time the contract is awarded.
Contractors and subcontractors may find additional information for registering at the
Department of Industrial Relations website at http://www.dir.ca.gov/Public-
Works/PublicWorks.html.
Pursuant to Labor Code section 1771.1, no contractor or subcontractor may be listed on
a bid proposal for a public works project submitted on or after March 1, 2015 unless
registered with the Department of Industrial Relations. Furthermore, all bidders and
contractors are hereby notified that no contractor or subcontractor may be awarded, on
or after April 1, 2015, a contract for public work on a public works project unless
registered with the Department of Industrial Relations.
Pursuant to Labor Code section 1771.4, all bidders are hereby notified that this project
is subject to compliance monitoring and enforcement by the Department of Industrial
Relations.
7. Concurrently with the execution of this Contract, Contractor shall furnish bonds of
a surety satisfactory to City, as provided in said Specifications or Invitation to Bid, the
cost of which shall be paid by Contractor.
8. Except for the gross negligence or willful misconduct of an Indemnified Party (as
hereinafter defined), the Contractor hereby assumes liability for and agrees to defend
(at Indemnified Parties' option), indemnify, protect and hold harmless City and its
Project Consultants, and Engineers, officers, agents, and employees ("Indemnified
Parties") from and against any and all claims, charges, damages, demands, actions,
proceedings, losses, stop notices, costs, expenses (including counsel fees), judgments,
civil fines and penalties, liabilities of any kind or nature whatsoever, which may be
sustained or suffered by or secured against the Indemnified Parties arising out of or
encountered in connection with this Contract or the performance of the Work including,
but not limited to, death of or bodily or personal injury to persons or damage to property,
including property owned by or under the care and custody of City, and for civil fines
and penalties, that may arise from or be caused, in whole or in part, by any negligent or
other act or omission of Contractor, its officers, agents, employees or Subcontractors
including, but not limited to, liability arising from:
1. Any dangerous, hazardous, unsafe or defective condition of, in or on the
premises, of any nature whatsoever, which may exist by reason of any act,
omission, neglect, or any use or occupation of the premises by Contractor, its
officers, agents, employees, or subcontractors;
2. Any operation conducted upon or any use or occupation of the premises by
Contractor, its officers, agents, employees, or subcontractors under or
Contract 1300-2
pursuant to the provisions of this contract or otherwise;
3. Any act, omission or negligence of Contractor, its officers, agents,
employees, or Subcontractors;
4. Any failure of Contractor, its officers, agents or employees to comply with any
of the terms or conditions of this Contract or any applicable federal, state,
regional, or municipal law, ordinance, rule or regulation; and
5. The conditions, operations, uses, occupations, acts, omissions or negligence
referred to in Sub -subsections (1), (2), (3), and (4), existing or conducted
upon or arising from the use or occupation by Contractor on any other
premises in the care, custody and control of City.
The Contractor also agrees to indemnify City and pay for all damages or loss suffered
by City including but not limited to damage to or loss of City property, to the extent not
insured by City and loss of City revenue from any source, caused by or arising out of
the conditions, operations, uses, occupations, acts, omissions or negligence referred to
in Sub -subsections (1), (2), (3), (4) and (5).
Contractor's obligations under this Section apply regardless of whether or not such
claim, charge, damage, demand, action, proceeding, loss, stop notice, cost expense,
judgment, civil fine or penalty, or liability was caused in part or contributed to by an
Indemnified Party. However, without affecting the rights of City under any provision of
this contract, Contractor shall not be required to indemnify and hold harmless City for
liability attributable to the active negligence of City, provided such active negligence is
determined by agreement between the parties or by the findings of a court of competent
jurisdiction. In instances where City is shown to have been actively negligent and
where City's active negligence accounts for only a percentage of the liability involved,
the obligation of Contractor will be for that entire portion or percentage of liability not
attributable to the active negligence of City.
Contractor agrees to obtain executed indemnity agreements with provisions identical to
those set forth here in this section from each and every subcontractor or any other
person or entity involved by, for, with or on behalf of Contractor in the performance of
this contract. In the event Contractor fails to obtain such indemnity obligations from
others as required here, Contractor agrees to be fully responsible according to the
terms of this section.
Failure of City to monitor compliance with these requirements imposes no additional
obligations on City and will in no way act as a waiver of any rights hereunder. This
obligation to indemnify and defend City as set forth here is binding on the successors,
assigns or heirs of Contractor and shall survive the termination of this contract or this
section.
This indemnity shall survive termination of the Contract or Final Payment hereunder.
This Indemnity is in addition to any other rights or remedies that the Indemnified Parties
may have under the law or under any other Contract Documents or Agreements. In the
event of any claim or demand made against any party which is entitled to be
indemnified hereunder, City may, in its sole discretion, reserve, retain or apply any
monies to the Contractor under this Contract for the purpose of resolving such claims;
Contract 1300-3
provided, however, City may release such funds if the Contractor provides City with
reasonable assurance of protection of the Indemnified Parties' interests. City shall, in its
sole discretion, determine whether such assurances are reasonable.
Approval of any insurance contracts by the City does not relieve the Contractor or
subcontractors from liability under Section 1340-1.0, Indemnification of the
Specifications. The City will not be liable for any accident, loss, or damage to the work
prior to its completion and acceptance.
9. Except as otherwise required, Contractor shall concurrently with the execution of
this contract, furnish the City satisfactory evidence of insurance of the kinds and in the
amounts provided in said Specifications, Section 1340-2.0, Insurance Requirements.
This insurance shall be kept in full force and effect by Contractor during this entire
contract and all premiums thereon shall be promptly paid by it. Each policy shall further
state that it cannot be canceled without written notice to the City and shall name the City
as an additional insured on the Commercial General Liability policy only. Contractor
shall furnish evidence of having in effect, and shall maintain, Workers Compensation
Insurance coverage of not less than the statutory amount or otherwise show a certificate
of self-insurance, in accordance with the Workers Compensation laws of the State of
California. Failure to maintain the required amounts and types of coverage throughout
the duration of this Contract shall constitute a material breach of this Contract.
10. Except as otherwise required, Contractor shall concurrently with the execution of
this contract, furnish the City a Milestone Schedule with a beginning date of 15 days
after the Notice of Award as provided in said Specifications, Section 4.2, Construction
Schedule. Contractor shall pay to City $500.00 liquidated damages per calendar day
that the Milestone Schedule is not provided.
11. Contractor shall forfeit as a penalty to City $25.00 for each laborer, workman, or
mechanic employed in the execution of this Contract by said Contractor, or any
subcontractor under it, upon any of the work herein mentioned, for each calendar day
during which such laborer, workman, or mechanic is required or permitted to work at
other than a rate of pay provided by law for more than 8 hours in any one calendar day
and 40 hours in any one calendar week, in violation of the provisions of Sections 1810-
1815 of the Labor Code of the State of California.
12. In accepting this Contract, Contractor certifies that in the conduct of its business
it does not deny the right of any individual to seek, obtain and hold employment without
discrimination because of race, religious creed, color, national origin, ancestry, physical
handicap, medical condition, marital status, sex or age as provided in the California Fair
Employment Practice Act (Government Code Sections 12900, et seq.). Contractor
agrees that a finding by the State Fair Employment Practices Commission that
Contractor has engaged during the term of this Contract in any unlawful employment
practice shall be deemed a breach of this Contract and Contractor shall pay to City
$1,607.00 liquidated damages for each such breach committed under this contract.
Contract 1300-4
13. Contractor also agrees that for contracts in excess of $30,000.00 and more
than 20 calendar days duration, that apprentices will be employed without
discrimination in an approved program in a ratio established in the
apprenticeship standards of the craft involved (Sections 1777.5 and 1777.6, Labor
Code of California). Contractors who willfully fail to comply will be denied the
right to bid on public projects for a period of six months in addition to other
penalties provided by law.
14. This Contract shall not be assignable by Contractor without the written consent of
City.
15. Contractor shall notify the City Engineer (in writing) forthwith when the Contract is
deemed completed.
16. In accepting this Contract, Contractor certifies that no member or officer of the
firm or corporation is an officer or employee of the City except to the extent permitted by
law.
17. Contractor certifies that it is the holder of any necessary California State
Contractor's License and authorized to undertake the above work.
18. The City, or its authorized auditors or representatives, shall have access to and
the right to audit and reproduce any of the Contractor records to the extent the City
deems necessary to insure it is receiving all money to which it is entitled under the
contract and/or is paying only the amounts to which Contractor is properly entitled under
the Contract or for other purposes relating to the Contract.
19. The Contractor shall maintain and preserve all such records for a period of at
least three years after termination of the contract.
20. The Contractor shall maintain all such records in the City of La Quinta. If not, the
Contractor shall, upon request, promptly deliver the records to the City or reimburse the
City for all reasonable and extra costs incurred in conducting the audit at a location
other than at City offices including, but not limited to, such additional (out of the City)
expenses for personnel, salaries, private auditors, travel, lodging, meals and overhead.
21. The further terms, conditions, and covenants of the Contract are set forth in the
Contract Documents, each of which is by this reference made a part hereof.
Contract 1300-5
IN WITNESS WHEREOF, the parties have executed this Contract as of the
dates stated below.
"CITY"
CITY OF LA QUINTA
a California municipal corporation
Dated:
ATTEST:
Monika Radeva, City Clerk
APPROVED AS TO FORM:
City Attorney
Dated:
Name:
Print Name
Address:
Street Address
Dated:
Name:
Print Name
Address:
Street Address
By:
Jon McMillen, City Manager
Dated:
Dated:
"CONTRACTOR"
(If corporation, affix seal)
By:
Signature
Title:
City
By:
Signature
Title:
City
State Zip Code
State Zip Code
Contract 1300-6
SECTION 1310
FAITHFUL PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS:
THAT the City of La Quinta, a municipal corporation, hereinafter designated the
City, has on , 2023, awarded to
, hereinafter designated as the Principal, a Contract for Project No. 2016-
031, La Quinta Landscape Renovation Improvement — Cactus Flower and:
WHEREAS, said Principal is required under the terms of said Contract to furnish
a bond for the faithful performance of said Contract:
NOW, THEREFORE, we, the Principal, and , as
Surety, are held and firmly bound unto the City in the just and full amount of
DOLLARS ($ ) lawful money of
the United States, for the payment of which sum well and truly to be made, we bind
ourselves, our heirs, executors, administrators, and successors, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that if said Principal, his or
its heirs, executors, administrators, successors, or assigns, shall in all things stand to
and abide by, and well and truly keep and faithfully perform the covenants, conditions,
and agreements in the said contract and any alterations made as therein provided, on
his or their part to be kept and performed, at the time and in the manner therein
specified, and in all respects according to their true intent and meaning, and shall
indemnify and save harmless, the City, its officers and agents as therein stipulated, then
this obligation shall become null and void; otherwise it shall be and remain in full force
and virtue.
It is acknowledged that the Contract provides for one-year guarantee period,
during which time this bond remains in full force and effort.
And the said Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration, or addition to the terms of the Contract or to the
work to be performed thereunder or the specifications accompanying the same shall, in
any way, affect its obligations on this bond, and it does hereby waive notice of any such
change, extension of time, alteration, or addition to the terms of the Contract or to the
work or to the specifications. Said Surety hereby waives the provisions of Sections 2819
and 2845 of the Civil Code of the State of California.
Faithful Performance Bond 1310-1
IN WITNESS WHEREOF, the Principal and Surety have executed this instrument
under their seals this
day of 2023, the name and corporate seal of each
corporate party being hereto affixed and these presents duly signed by its undersigned
representative, pursuant to authority of its governing body.
Principal
Signature for Principal
Title of Signatory
Surety
Signature for Surety
Title of Signatory
Address of Surety
Phone # of Surety
Contact Person for Surety
(Seal)
(Seal)
Faithful Performance Bond 1310-2
SECTION 1320
PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS:
THAT the City of La Quinta, a municipal corporation, hereinafter designated the
City, has on , 2023, awarded to
hereinafter designated as the Principal, a Contract for Project No.
2016-031, La Quints Landscape Renovation Improvement — Cactus Flower
WHEREAS, said Principal is required to furnish a bond in connection and with
said Contract, providing that if said Principal, or any of it or its subcontractors shall fail to
pay for any materials, provisions, or other supplies used in, upon, for, or about the
performance of the work contracted to be done, or for any work or labor done thereon of
any kind, the Surety of this bond will pay the same to the extent hereinafter set forth:
NOW, THEREFORE, we, the Principal, and as
Surety, are held and firmly bound unto the City in the just and full amount of
DOLLARS ($ ) lawful money of
the United States, for the payment of which sum well and truly to be made, we bind
ourselves, our heirs, executors, administrators, and successors, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that if said Principal, it or its
heirs, executors, administrators, successors, or assigns, shall fail to pay for any
materials, provisions, or other supplies used in, upon, for, or about the performance of
the work contracted to be done, or for any work or labor thereon of any kind or for
amount due under the Unemployment Insurance Act with respect to such work or labor,
or for any amounts due, or to be withheld pursuant to Sections 18806 of the Revenue
and Taxation Code of the State of California with respect to such work or labor, then
said surety will pay the same in or to an amount not exceeding the amount hereinabove
set forth, and also will pay in case suit is brought upon this bond, such reasonable
attorney's fees to the City as shall be fixed by the court.
This bond shall insure to the benefit of any and all persons, companies, and
corporations named in Section 3181 of the Civil Code of the State of California so as to
give a right of action to them or their assigns in any suit brought upon this bond.
And the said Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration, or addition of the terms of the Contract or to the
work to be performed thereunder or the specifications accompanying the same shall, in
any way, affect its obligations of this bond, and it does hereby waive notice of any
change, extension of time, alteration, or addition to the terms of the contract or to the
work or to the specifications. Said Surety hereby waives the provisions of Sections
2819 and 2845 of the Civil Code of the State of California.
Payment Bond 1320-1
IN WITNESS WHEREOF, the Principal and Surety have executed this instrument
under their seals this
day of 2023, the name and corporate seal of each
corporate party being hereto affixed and these presents duly signed by its undersigned
representative, pursuant to authority of its governing body.
Principal
(Seal)
Signature for Principal
Title of Signatory
Surety
(Seal)
Signature for Surety
Title of Signatory
Address of Surety
Phone # of Surety
Contact Person for Surety
Payment Bond 1320-2
SECTION 1330
WORKERS' COMPENSATION INSURANCE CERTIFICATE
In accordance with California Labor Code Section 1861, prior to commencement of
work on the Contract, the Contractor shall sign and file with the City the following
certification:
"I am aware of the provisions of Section 3700 of the Labor Code which require
every employer to be insured against liability for workers' compensation or to
undertake self-insurance in accordance with the provisions of that code, and I will
comply with such provisions before commencing the performance of the work of
this contract."
Signature
Title
Date
Workers Compensation Insurance Certificate 1330-1
SECTION 1340
LIABILITY AND INSURANCE REQUIREMENTS
1.0 INDEMNIFICATION
Except for the gross negligence or willful misconduct of an Indemnified Party (as
hereinafter defined), the Contractor hereby assumes liability for and agrees to
defend (at Indemnified Parties' option), indemnify, protect and hold harmless City
and its Project Consultants, and Engineers, officers, agents, and employees
("Indemnified Parties") from and against any and all claims, charges, damages,
demands, actions, proceedings, losses, stop notices, costs, expenses (including
counsel fees), judgments, civil fines and penalties, liabilities of any kind or nature
whatsoever, which may be sustained or suffered by or secured against the
Indemnified Parties arising out of or encountered in connection with this Contract
or the performance of the Work including, but not limited to, death of or bodily or
personal injury to persons or damage to property, including property owned by or
under the care and custody of City, and for civil fines and penalties, that may arise
from or be caused, in whole or in part, by any negligent or other act or omission of
Contractor, its officers, agents, employees or Subcontractors including, but not
limited to, liability arising from:
1. Any dangerous, hazardous, unsafe or defective condition of, in or on the
premises, of any nature whatsoever, which may exist by reason of any act,
omission, neglect, or any use or occupation of the premises by Contractor,
its officers, agents, employees, or subcontractors;
2. Any operation conducted upon or any use or occupation of the premises by
Contractor, its officers, agents, employees, or subcontractors under or
pursuant to the provisions of this contract or otherwise;
3. Any act, omission or negligence of Contractor, its officers, agents,
employees, or Subcontractors;
4. Any failure of Contractor, its officers, agents or employees to comply with
any of the terms or conditions of this Contract or any applicable federal,
state, regional, or municipal law, ordinance, rule or regulation; and
5. The conditions, operations, uses, occupations, acts, omissions or
negligence referred to in Sub -subsections (1), (2), (3), and (4), existing or
conducted upon or arising from the use or occupation by Contractor on any
other premises in the care, custody and control of City.
The Contractor also agrees to indemnify City and pay for all damages or loss
suffered by City including but not limited to damage to or loss of City property, to
the extent not insured by City and loss of City revenue from any source, caused
by or arising out of the conditions, operations, uses, occupations, acts, omissions
or negligence referred to in Sub -subsections (1), (2), (3), (4) and (5).
Contractor's obligations under this Section apply regardless of whether or not such
claim, charge, damage, demand, action, proceeding, loss, stop notice, cost
Liability and Insurance Requirements 1340-1
expense, judgment, civil fine or penalty, or liability was caused in part or
contributed to by an Indemnified Party.
However, without affecting the rights of City under any provision of this Contract,
Contractor shall not be required to indemnify and hold harmless City for liability
attributable to the active negligence of City, provided such active negligence is
determined by Contract between the parties or by the findings of a court of
competent jurisdiction. In instances where City is shown to have been actively
negligent and where City's active negligence accounts for only a percentage of the
liability involved, the obligation of Contractor will be for that entire portion or
percentage of liability not attributable to the active negligence of City.
Contractor agrees to obtain executed indemnity agreements with provisions
identical to those set forth here in this section from each and every subcontractor
or any other person or entity involved by, for, with or on behalf of Contractor in the
performance of this Contract. In the event Contractor fails to obtain such indemnity
obligations from others as required here, Contractor agrees to be fully responsible
according to the terms of this section.
Failure of City to monitor compliance with these requirements imposes no
additional obligations on City and will in no way act as a waiver of any rights
hereunder. This obligation to indemnify and defend City as set forth here is binding
on the successors, assigns or heirs of Contractor and shall survive the termination
of this Contract or this section.
This indemnity shall survive termination of the Contract or Final Payment
hereunder. This Indemnity is in addition to any other rights or remedies that the
Indemnified Parties may have under the law or under any other Contract
Documents or Agreements. In the event of any claim or demand made against any
party which is entitled to be indemnified hereunder, City may, in its sole discretion,
reserve, retain or apply any monies to the Contractor under this Contract for the
purpose of resolving such claims; provided, however, City may release such funds
if the Contractor provides City with reasonable assurance of protection of the
Indemnified Parties' interests. City shall, in its sole discretion, determine whether
such assurances are reasonable.
Approval of any insurance contracts by the City does not relieve the Contractor or
subcontractors from liability under Section 1340-1.0, Indemnification. The City will
not be liable for any accident, loss, or damage to the work prior to its completion
and acceptance.
2.0 INSURANCE REQUIREMENTS
2.1 General
Prior to the beginning of and throughout the duration of the Work, Contractor will
maintain insurance in conformance with the requirements set forth below.
Contractor will use existing coverage to comply with these requirements. If that
existing coverage does not meet the requirements set forth here, it will be
Liability and Insurance Requirements 1340-2
2.2
amended to do so. Contractor acknowledges that the insurance coverage and
policy limits set forth in this section constitute the minimum amount of coverage
required. Any insurance proceeds available to City in excess of the limits and
coverage required in this Contract and which is applicable to a given loss, will be
available to City.
Contractor shall submit coverage verification for review and approval by the City
upon execution of the Contract.
The Notice to Proceed with the Work under this Contract will not be issued, and
the Contractor shall not commence work, until such insurance has been approved
by the City. The Contractor shall not allow any subcontractors to commence work
on its subcontract until all similar insurance required of the subcontractor has been
obtained and verified by Contractor. Such insurance shall remain in full force and
effect at all times during the prosecution of the Work and until the final completion
and acceptance thereof.
The Notice to Proceed does not relieve the Contractor of the duty to obtain such
insurance as required by Paragraph 1340-2.0 INSURANCE REQUIREMENTS.
Contractor shall provide the following types and amounts of insurance:
Insurance
Prior to the beginning of and throughout the duration of this Agreement, the
following policies shall be maintained and kept in full force and effect providing
insurance with minimum limits as indicated below and issued by insurers with A.M.
Best ratings of no less than A -VI:
Commercial General Liability (at least as broad as ISO CG 0001)
$5,000,000 (per occurrence)
$5,000,000 (general aggregate)
Must include the following endorsements:
General Liability Additional Insured
General Liability Primary and Noncontributory
Commercial Auto Liability (at least as broad as ISO CA 0001)
$1,000,000 (per accident)
Personal Auto Declaration Page if applicable
Workers' Compensation
(per statutory requirements)
Must include the following endorsements:
Workers Compensation Waiver of Subrogation
Workers Compensation Declaration of Sole Proprietor if applicable
Contracting Party shall procure and maintain, at its cost, and submit concurrently
with its execution of this Agreement, Commercial General Liability insurance
against all claims for injuries against persons or damages to property resulting from
Contracting Party's acts or omissions rising out of or related to Contracting Party's
performance under this Agreement. The insurance policy shall contain a
severability of interest clause providing that the coverage shall be primary for
Liability and Insurance Requirements 1340-3
losses arising out of Contracting Party's performance hereunder and neither City
nor its insurers shall be required to contribute to any such loss. An endorsement
evidencing the foregoing and naming the City and its officers and employees as
additional insured (on the Commercial General Liability policy only) must be
submitted concurrently with the execution of this Agreement and approved by City
prior to commencement of the services hereunder.
Contracting Party shall carry automobile liability insurance of $1,000,000 per
accident against all claims for injuries against persons or damages to property
arising out of the use of any automobile by Contracting Party, its officers, any
person directly or indirectly employed by Contracting Party, any subcontractor or
agent, or anyone for whose acts any of them may be liable, arising directly or
indirectly out of or related to Contracting Party's performance under this
Agreement. If Contracting Party or Contracting Party's employees will use personal
autos in any way on this project, Contracting Party shall provide evidence of
personal auto liability coverage for each such person. The term "automobile"
includes, but is not limited to, a land motor vehicle, trailer or semi -trailer designed
for travel on public roads. The automobile insurance policy shall contain a
severability of interest clause providing that coverage shall be primary for losses
arising out of Contracting Party's performance hereunder and neither City nor its
insurers shall be required to contribute to such loss.
Professional Liability or Errors and Omissions Insurance as appropriate shall be
written on a policy form coverage specifically designed to protect against acts,
errors or omissions of the Contracting Party and "Covered Professional Services"
as designated in the policy must specifically include work performed under this
agreement. The policy limit shall be no less than $1,000,000 per claim and in the
aggregate. The policy must "pay on behalf of the insured and must include a
provision establishing the insurer's duty to defend. The policy retroactive date shall
be on or before the effective date of this agreement.
Contracting Party shall carry Workers' Compensation Insurance in accordance
with State Worker's Compensation laws with employer's liability limits no less than
$1,000,000 per accident or disease.
If coverage is maintained on a claims -made basis, Contracting Party shall maintain
such coverage for an additional period of three (3) years following termination of
the contract.
Contracting Party shall provide written notice to City within ten (10) working days
if: (1) any of the required insurance policies is terminated; (2) the limits of any of
the required polices are reduced; or (3) the deductible or self-insured retention is
increased. In the event any of said policies of insurance are cancelled, Contracting
Party shall, prior to the cancellation date, submit new evidence of insurance in
conformance with this Exhibit to the Contract Officer.
The procuring of such insurance or the delivery of policies or certificates
evidencing the same shall not be construed as a limitation of Contracting Party's
obligation to indemnify City, its officers, employees, contractors, subcontractors,
or agents.
Liability and Insurance Requirements 1340-4
2.3 Remedies
In addition to any other remedies City may have if Contracting Party fails to provide
or maintain any insurance policies or policy endorsements to the extent and within
the time herein required, City may, at its sole option:
a. Obtain such insurance and deduct and retain the amount of the premiums
for such insurance from any sums due under this Agreement.
b. Order Contracting Party to stop work under this Agreement and/or withhold
any payment(s) which become due to Contracting Party hereunder until
Contracting Party demonstrates compliance with the requirements hereof.
c. Terminate this Agreement.
Exercise of any of the above remedies, however, is an alternative to any other
remedies City may have. The above remedies are not the exclusive remedies for
Contracting Party's failure to maintain or secure appropriate policies or
endorsements. Nothing herein contained shall be construed as limiting in any way
the extent to which Contracting Party may be held responsible for payments of
damages to persons or property resulting from Contracting Party's or its
subcontractors' performance of work under this Agreement.
2.4 General Conditions Pertaining to Provisions of Insurance Coverage by
Contracting Party. Contracting Party and City agree to the following with
respect to insurance provided by Contracting Party:
Contracting Party agrees to have its insurer endorse the third -party general liability
coverage required herein to include as additional insureds City, its officials,
employees, and agents, using standard ISO endorsement No. CG 2010 with an
edition prior to 1992. Contracting Party also agrees to require all contractors, and
subcontractors to do likewise.
2. No liability insurance coverage provided to comply with this Agreement shall
prohibit Contracting Party, or Contracting Party's employees, or agents, from
waiving the right of subrogation prior to a loss. Contracting Party agrees to waive
subrogation rights against City regardless of the applicability of any insurance
proceeds, and to require all contractors and subcontractors to do likewise.
3. All insurance coverage and limits provided by Contracting Party and available or
applicable to this Agreement are intended to apply to the full extent of the policies.
Nothing contained in this Agreement or any other agreement relating to City or its
operations limits the application of such insurance coverage.
4. None of the coverages required herein will be in compliance with these
requirements if they include any limiting endorsement of any kind that has not been
first submitted to City and approved of in writing.
5. No liability policy shall contain any provision or definition that would serve to
eliminate so-called "third party action over" claims, including any exclusion for
bodily injury to an employee of the insured or of any contractor or subcontractor.
Liability and Insurance Requirements 1340-5
6. All coverage types and limits required are subject to approval, modification and
additional requirements by the City, as the need arises.
7. Contracting Party shall not make any reductions in scope of coverage (e.g.
elimination of contractual liability or reduction of discovery period) that may affect
City's protection without City's prior written consent.
8. Proof of compliance with these insurance requirements, consisting of certificates
of insurance evidencing all of the coverages required and an additional insured
endorsement to Contracting Party's general liability policy, shall be delivered to
City at or prior to the execution of this Agreement. In the event such proof of any
insurance is not delivered as required, or in the event such insurance is canceled
at any time and no replacement coverage is provided, City has the right, but not
the duty, to obtain any insurance it deems necessary to protect its interests under
this or any other agreement and to pay the premium. Any premium so paid by City
shall be charged to and promptly paid by Contracting Party or deducted from sums
due Contracting Party, at City option.
9. It is acknowledged by the parties of this agreement that all insurance coverage
required to be provided by Contracting Party or any subcontractor, is intended to
apply first and on a primary, non-contributing basis in relation to any other
insurance or self-insurance available to City.
10. Contracting Party agrees to ensure that subcontractors, and any other party
involved with the project that is brought onto or involved in the project by
Contracting Party, provide the same minimum insurance coverage required of
Contracting Party. Contracting Party agrees to monitor and review all such
coverage and assumes all responsibility for ensuring that such coverage is
provided in conformity with the requirements of this section. Contracting Party
agrees that upon request, all agreements with subcontractors and others engaged
in the project will be submitted to City for review.
11. Contracting Party agrees not to self -insure or to use any self-insured retentions or
deductibles on any portion of the insurance required herein (with the exception of
professional liability coverage, if required) and further agrees that it will not allow
any contractor, subcontractor, Architect, Engineer or other entity or person in any
way involved in the performance of work on the project contemplated by this
agreement to self -insure its obligations to City. If Contracting Party's existing
coverage includes a deductible or self-insured retention, the deductible or self-
insured retention must be declared to the City. At that time the City shall review
options with the Contracting Party, which may include reduction or elimination of
the deductible or self-insured retention, substitution of other coverage, or other
solutions.
12. The City reserves the right at any time during the term of this Agreement to change
the amounts and types of insurance required by giving the Contracting Party ninety
(90) days advance written notice of such change. If such change results in
substantial additional cost to the Contracting Party, the City will negotiate
additional compensation proportional to the increased benefit to City.
Liability and Insurance Requirements 1340-6
13. For purposes of applying insurance coverage only, this Agreement will be deemed
to have been executed immediately upon any party hereto taking any steps that
can be deemed to be in furtherance of or towards performance of this Agreement.
14. Contracting Party acknowledges and agrees that any actual or alleged failure on
the part of City to inform Contracting Party of non-compliance with any insurance
requirement in no way imposes any additional obligations on City nor does it waive
any rights hereunder in this or any other regard.
15. Contracting Party will renew the required coverage annually as long as City, or its
employees or agents face an exposure from operations of any type pursuant to
this agreement. This obligation applies whether or not the agreement is canceled
or terminated for any reason. Termination of this obligation is not effective until
City executes a written statement to that effect.
16. Contracting Party shall provide proof that policies of insurance required herein
expiring during the term of this Agreement have been renewed or replaced with
other policies providing at least the same coverage. Proof that such coverage has
been ordered shall be submitted prior to expiration. A coverage binder or letter
from Contracting Party's insurance agent to this effect is acceptable. A certificate
of insurance and/or additional insured endorsement as required in these
specifications applicable to the renewing or new coverage must be provided to City
within five (5) days of the expiration of coverages.
17. The provisions of any workers' compensation or similar act will not limit the
obligations of Contracting Party under this agreement. Contracting Party expressly
agrees not to use any statutory immunity defenses under such laws with respect
to City, its employees, officials, and agents.
18. Requirements of specific coverage features, or limits contained in this section are
not intended as limitations on coverage, limits or other requirements nor as a
waiver of any coverage normally provided by any given policy. Specific reference
to a given coverage feature is for purposes of clarification only as it pertains to a
given issue, and is not intended by any party or insured to be limiting or all-
inclusive.
19. These insurance requirements are intended to be separate and distinct from any
other provision in this Agreement and are intended by the parties here to be
interpreted as such.
20. The requirements in this Exhibit supersede all other sections and provisions of this
Agreement to the extent that any other section or provision conflicts with or impairs
the provisions of this Exhibit.
21. Contracting Party agrees to be responsible for ensuring that no contract used by
any party involved in any way with the project reserves the right to charge City or
Contracting Party for the cost of additional insurance coverage required by this
agreement. Any such provisions are to be deleted with reference to City. It is not
the intent of City to reimburse any third party for the cost of complying with these
requirements. There shall be no recourse against City for payment of premiums
or other amounts with respect thereto.
Liability and Insurance Requirements 1340-7
22. Contracting Party agrees to provide immediate notice to City of any claim or loss
against Contracting Party arising out of the work performed under this agreement.
City assumes no obligation or liability by such notice, but has the right (but not the
duty) to monitor the handling of any such claim or claims if they are likely to involve
City.
2.5 Change in Terms
The Contractor shall provide immediate written notice to the City of any change in
terms and conditions and/or reduction in the coverage of any nature to the
insurance policies. The notice shall be sent to:
Jon McMillen, City Manager
City of La Quinta
78-495 Calle Tampico
La Quinta, CA 92253
Liability and Insurance Requirements 1340-8
SECTION 1400
GENERAL CONDITIONS
1.0 GENERAL
1.1 Intent of Contract Documents
Where the Plans or Specifications describe portions of the Work in general terms
but not in complete detail, it is understood that only the best general practice is to
prevail and that only materials and workmanship of the first quality are to be used.
Unless otherwise specified, the Contractor shall furnish tools, equipment, and
incidentals, and do all the work involved in executing the Contract in a satisfactory
and workmanlike manner.
Unless specifically noted otherwise, all sections of the Specifications and the Plans
shall be complimentary and applicable to each other.
In the event the materials and/or equipment are to be furnished by the City, as
designated in the Specific Project Requirements or as agreed on, this shall not
relieve the Contractor of the above requirements to furnish all other labor, materials,
and equipment to complete the Contract.
Words and abbreviations which have well known technical or trade meaning are
used in the Contract Documents in accordance with such recognized meanings.
1.2 Discrepancies and Omissions
Any discrepancies or omissions found in the Contract Documents shall be
immediately reported to the City Engineer who will clarify discrepancies or
omissions, in writing, within a reasonable time.
In resolving inconsistencies among two or more sections of the Contract
Documents, precedence shall be given in the following order:
1. Contract
a. Agreement
b. Permits
c. Change Orders
2. Instruction to Bidders
3. Permits issued by other agencies
4. Specific Project Requirements
5. General Project Requirements
6. Supplementary Conditions
7. General Conditions
8. Technical Specifications
9. Standard Specifications
10. Reference Specifications
11. Plans
12. Standard Plans
General Conditions 1400-1
1.3 Headings
Headings to parts, divisions, sections, articles, paragraphs, subparagraphs, and forms
are inserted for convenience of reference only and shall not affect the interpretation of
the Contract Documents.
1.4 Penalty for Collusion
If, at any time, it is found that the person, firm, or corporation to whom the Contract
has been awarded has, in presenting any bid or bids, colluded with any other party
or parties, then the Contract shall be null and void, and the Contractor and its
sureties shall be liable for loss or damage which the City may suffer thereby, and
the City may advertise for new bids for said Work.
1.5 Successors and Assigns
The City and the Contractor, respectively, bind themselves, their partners,
successors, assigns, and legal representatives to the other party hereto and to the
partners, successors, assigns, and legal representatives of such other party with
respect to all covenants, contracts, agreements, and obligation contained in the
Contract Documents. Neither party to the Contract shall assign the Contract or
sublet it as a whole without the written consent of the other.
1.6 Assignment to the City
Pursuant to Public Contract Code 4551, in entering into the Contract and all
subcontracts, to supply goods, services, or materials pursuant to the Contract, the
Contractor and its subcontractors offer and agree to assign to the City all rights, title,
and interest in and to all causes of action it may have under Section 4 of the Clayton
Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 (commencing with
section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising
from purchases of goods, services, or materials pursuant to the Contract and
subcontracts. This assignment shall be made and become effective at the time the
City tenders final payment to the Contractor, without further acknowledgment by the
parties.
1.7 Rights and Remedies
The duties and obligations imposed by the Contract Documents and the rights and
remedies available thereunder shall be in addition to, and not a limitation of, any
duties, obligations, rights, and remedies otherwise imposed or available by law.
No action or failure to act by the City and its representatives or the consultants, shall
constitute a waiver of any right or duty afforded any of them under the Contract, nor
shall any such action or failure to act constitute an approval of or acquiescence in
any breach thereunder, except as may be specifically agreed in writing.
1.8 Definitions
Unless otherwise stated, the words directed, required, permitted, ordered,
instructed, designated, applicable, appropriate, sufficient, proper, desirable,
General Conditions 1400-2
necessary, prescribed, approved, acceptable, satisfactory or words of like import,
refer to actions, expressions, and prerogatives of the City, the City Engineer.
Masculine gender words include the feminine. References to gender, such as
"workman" and "flagman" and the pronouns "he" or "his" referring to such titles, are
abstract in the specifications, used for the sake of brevity are intended to refer to
persons of either sex.
Singular words include the plural and "person" includes firms, companies, and
corporations.
Where used in the Contract Documents, the following words and terms shall have
the meanings indicated. The meanings shall be applicable to the singular, plural,
masculine, and feminine of the words and terms.
Acceptance - The formal written acceptance by the City of an entire Contract which
has been completed in all respects in accordance with the Contract Documents and
any modifications thereof previously approved.
Act of God - An earthquake, flood, cyclone, or other cataclysmic phenomenon of
nature. A rain, windstorm, high water, or other natural phenomenon, which might
reasonably have been anticipated from historical records of the general locality of
the work, shall not be construed as an Act of God.
Addenda - Written or graphic instruments issued prior to the bid which modify or
interpret the Contract Documents, drawings, and specifications, by additions,
deletions, clarifications, or corrections.
Architect - The Architect responsible for the preparation of plans and specifications
for the City of La Quinta
Bid - The offer or proposal of the Bidder submitted on the prescribed form setting
forth the price for the work to be performed.
Bond(s) - Bid, Performance, or Payment Bonds and other instruments of surety,
furnished by the Contractor and Contractor's surety in accordance with the Contract
Documents.
Bidder - Any properly licensed and qualified individual, firm, partnership,
corporation, joint venture, or combination thereof, submitting a proposal for the work
contemplated, acting directly or through a duly authorized representative.
Calendar Day - Any day including legal holidays, Saturdays, and Sundays.
City - The City of La Quinta, a Municipal Corporation in the State of California.
City Engineer - The person designated, in writing, by the City to act as its
representative at the construction site and to perform construction inspection
services and administrative functions relating to this Contract. Initial contact by the
Contractor with the City shall be through the City Engineer.
City Representative - The person designated in writing by the City to act as its
agent on specified matters relating to this Contract. The City's Representative is not
General Conditions 1400-3
the City Engineer but is another individual who has been designated to represent
the City.
Contract - The written document covering the performance of the Work as more
fully described in, but not limited to, the plans, standard specifications, special and
technical provisions, Contract bonds, proposal, addenda, and Contract Change
Orders.
Contract Change Order - A written order to the Contractor, covering changes in the
plans or quantities, or both, and establishing the basis of payment and time
adjustments for the work affected by the changes. Also referred to as a Change
Order.
Contract Documents - The words "Contract Documents" shall mean any or all of,
but not limited to, the following items, as applicable:
Invitation to Bid
Instructions to Bidders
Bid Documents
Designation of Subcontractors
Bid Guaranty Bond
Contract
Acknowledgments
Performance Bond
Payment Bond
General Conditions
Supplementary General Conditions
General Project Requirements
Specific Project Requirements
Standard Specifications
State Standard Specifications
Project Plans
Standard Drawings
Addenda, if any
Executed Change Orders, if any Notice of Award
Notice to Proceed
Permits from other agencies
Each of these items is to be considered by reference as part of the Contract
Documents, also referred to as Contract.
Contract Price - The amount payable to the Contractor under the terms and
conditions of the Contract based on the price given on the bidding schedule, with
adjustments made in accordance with the Contract. The base amount given in the
bidding schedule shall be either a lump sum bid or the summation of the unit price
bids multiplied by the estimated quantities set forth in the bid form. Also referred to
as Contract Amount or Contract Sum.
Contract Time - Number of calendar days stated in the Contract for the completion
of the Work.
General Conditions 1400-4
Contract Completion Date - The date on which the City accepts the work as being
complete.
Contractor - The person or persons, firms, partnership, corporation, or combination
thereof, who have entered with the City, as party or parties of the second part of his
or their legal representatives.
Contractor's Plant and Equipment - Equipment, material, supplies, and all other
items, except labor, brought onto the site by the Contractor to carry out the Work,
but not to be incorporated in the Work.
Consultant - Individuals and/or companies retained by the City to provide specific
professional services.
Day(s) - Calendar Day(s); unless contract time is indicated in working days.
Direct - Action of the City or City Engineer by which the Contractor is ordered to
perform or refrain from performing work under the Contract.
Field Directive - Written documentation of the actions of the City or City Engineer
in directing the Contractor. Also referred to as a Directive.
Field Order - A written instruction given to the Contractor authorizing work that is a
change to the scope of work carried out on a time and material basis.
Furnish - To deliver to the job site or other specified location any item, equipment,
or material.
General Conditions - Part of the Contract Documents representing the general
clauses that establishes how the project is to be administered.
General Project Requirements - Part of the Contract Documents establishing
general conditions or requirements peculiar to the way public works projects are
performed in the City of La Quinta.
Herein - Refers to information presented in the Project Manual.
Holidays - Legal holidays designated by the City or specifically identified in the
Contract.
Install - Placing, erecting, or constructing any item, equipment, or material.
Laboratory - The designated materials testing laboratory authorized by the City to
test materials and work involved in the Contract.
Liquidated Damages - A fixed amount as prescribed in Paragraph 1500-3.0, to be
paid to the City or to be deducted from any payments due, or to become due, to the
Contractor as a result of the Contractor not completing the work in the time allowed
in the specifications.
Notice of Award - A written notice by the City to the Bidder informing him that the
Contract has been awarded to him.
Notice to Proceed - The written notice by the City to the Contractor authorizing him
to proceed with the Work and establishing the date of commencement of the Work.
General Conditions 1400-5
Paragraph - For references or citation purposes, refers to the paragraph(s) in these
Specifications, called out by paragraph number and alphanumeric designator.
Person - Includes firms, companies, corporations, partnerships, and joint ventures.
Plans - Refers to the project plans drawings, profiles, cross sections, elevations,
details, and other working drawings and supplementary drawings, or reproductions
thereof, approved by the City, and are referred to in the Contract Documents, which
show the location, character, dimensions, and details of the work to be performed.
The terms drawing, plan and plans have the same meaning as the term drawings
unless otherwise stated or specified.
Project - The undertaking to be performed under the provisions of the Contract.
Project Manual - Those Contract Documents which are bound into one or more
volumes prior to bidding.
Provide - Furnish and install, complete in place.
Punch List - List of incomplete items of work and of items of work which are not in
conformance with the Contract.
Shall - Refers to actions by either the Contractor or the City and means the
Contractor or City has entered into a covenant with the other party to do or perform
the action.
Shown - Refers to information presented on the Drawings, with or without reference
to the Drawings.
Site - The property as described in the General Conditions or as shown on the
Drawings.
Specific Project Requirements - Part of the Contract Documents establishing
specific conditions or requirements peculiar to the work.
Specifications - That part of the Contract Documents consisting of the General
Conditions, Supplementary General Conditions, General Project Requirements,
Specific Project Requirements, applicable portions of the Standard Specifications
and State Standard Specifications, and Technical Specifications.
Specify - Refers to information described, shown, noted or presented in any manner
in any part of the Contract.
Standard Specifications - Standard Specifications for Public Works Construction,
latest edition, including all supplements, as written by the Joint Cooperative
Committee of the Southern California Chapter of the American Public Works
Association and the Southern California District of the Associated General
Contractors of California.
State Standard Specifications - The State of California, Department of
Transportation Agency's Standard Specifications in effect at the time of advertising
the Work. Also referred to as State Standard Specifications and Caltrans Standard
Specifications.
General Conditions 1400-6
Subcontractor - A subcontractor is a person or entity who has a direct contract with
the Contractor to perform any of the Work at the Site. The term subcontractor means
a subcontractor or subcontractor's authorized representative. The term
subcontractor does not include any separate contractor or any separate contractor's
subcontractors.
Submittals - The information which is specified for submission to the City Engineer
in accordance with the Project Manual.
Substantial Completion - Substantial Completion is the stage in the progress of
the Work when the Work is sufficiently complete in accordance with the Contract
Documents so the City can occupy or utilize the Work for its intended use.
Sub -subcontractor - A sub -subcontractor is a person or entity who has a direct or
indirect contract with a subcontractor to perform any of the Work at the Site. The
term sub -subcontractor means a sub -subcontractor or an authorized representative
thereof.
Supplier - Any person, firm, corporation, or organization who supplies materials or
equipment for the Work, including that fabricated to a special design, and may also
be a Subcontractor or a Sub -subcontractor.
Surety - The person, firm, corporation, or organization that joins with the Contractor
in assuming the liability for the faithful performance of the Work and for the payment
of all obligations pertaining to the Work in accordance with the Contract Documents
by issuing the Bonds required by the Contract Documents or by law.
Will - Actions entered into by the Contractor or the City as a covenant with the other
party to do or to perform the action.
Work - The labor, materials, equipment, supplies, and other items necessary for the
execution, completion, and fulfillment of the Contract.
Working Day - Any day, other than a holiday, Saturday or Sunday, on which the
Contractor may proceed with regular work on the current controlling operation as
determined by the City Engineer toward the completion of the Contract. A working
day is equivalent to 1.45 calendar days.
2.0 ADMINISTRATION
2.1 Administration of the Contract
The City Engineer will provide administration of the Contract as hereinafter
discussed. The duties, responsibilities and limitations of authority of City retained
consultants and the City Engineer during the construction, as set forth in the Contract
Documents, will not be modified or extended without written consent of the City.
In case of the termination of the employment of a consultant or the City Engineer,
the City will appoint a consultant or a City Engineer whose status under the Contract
Documents shall be that of the former consultant or City Engineer, respectively.
General Conditions 1400-7
2.2 City Engineer
2.2.1 General - The City Engineer has the authority to act on behalf of the City on
change orders, progress payments, Contract decisions, acceptability of the
Contractor's work, and early possession.
2.2.2 Change Orders - The City Engineer has the authority to accept or reject
change orders and cost proposals submitted by the Contractor or as
recommended by the City Engineer.
2.2.3 Progress Payments - The City Engineer has the authority to accept or reject
requests for progress payments which have been submitted by the
Contractor.
2.2.4 Contract Decisions - Should the Contractor disagree with decisions
rendered under this Contract; the Contractor may appeal to the City Engineer
in accordance with the provisions of the Contract.
2.2.5 Acceptability of Work - The City Engineer has the authority to make the final
determination of the acceptability of the Work.
2.2.6 Construction Schedule - The City Engineer has the authority to review and
recommend acceptance of the progress schedule submitted by the
Contractor at the start of the Work and subsequent significant revisions for
conformance to the specified sequence of work and logic.
2.2.7 Inspection - The City Engineer with the assistance of inspectors will observe
the progress, quality, and quantity of the Work to determine, in general, if the
Work is proceeding in accordance with the intent of the Contract Documents.
The City Engineer shall not be responsible for construction means, methods,
techniques, sequences, or procedures, or for safety precautions and
programs in connection with the Work.
In accordance with the provisions detailed elsewhere in these General Conditions,
the City Engineer will make decisions relative to all matters of interpretation or
execution of the Contract Documents.
2.3 Consultants
2.3.1 General - Consultants will have the authority to act on behalf of the City only
to the extent provided in the Supplemental General Conditions.
3.0 City
3.1 General
The City, acting through the City Engineer, shall have the authority to act as the sole
judge of the Work and materials with respect to both quantity and quality as set forth
in the Contract.
3.2 Attention to Work
The City shall notify the Contractor in writing of the name of individuals designated
as representatives of the City Engineer. The representative will normally be at the
General Conditions 1400-8
Site of the Work. During the representative's absences, the Contractor may contact
the City Engineer or a previously designated representative.
3.3 Inspection
The City will employ one or more inspectors to observe the Work and to act in
matters of construction under this Contract. An inspector is not authorized to revoke,
alter, or waive any requirements of the specifications. The inspector is authorized to
call the attention of the Contractor to any failure of the Work or materials to conform
to the Contract Documents. The inspector shall have the authority to reject material
or, in any emergency, suspend the Work. The Contractor may appeal any such issue
which it disagrees with to the City Engineer.
Contractor shall call in daily for inspections, unless otherwise approved by
the City, at Public Works Inspection Hotline 760-777-7097. Concrete
inspections will be required separately for all stages of the work: subgrade;
forming; and pouring.
Separate and independent from the inspection above, the project may be inspected
by Building Officials for code compliance. Such inspectors shall have the authority
provided to them by local jurisdiction.
3.4 City's Right to Carry Out the Work
If the Contractor defaults or neglects to carry out the Work in accordance with the
Contract Documents and fails within seven (7) days after receipt of written notice
from the City to commence and continue correction of such default or neglect with
diligence and promptness, the City may, after seven (7) days following receipt by
the Contractor of an additional written notice and without prejudice to any other
remedy make good such deficiencies.
The City also reserves the right to perform any portion of the work due to an
emergency threatening the safety of the Work, public, City, and any property or
equipment.
In either case an appropriate Change Order shall be issued unilaterally deducting
from the payments then or thereafter due the Contractor the cost of correcting such
deficiencies and/or for performing such work, including compensation for
consultants and City's additional services made necessary by such default, neglect,
failure, or emergency.
3.5 City's Right to Perform Work and to Award Separate Contracts
The City reserves the right to perform the work related to the Project with the City's
own forces, and to award separate Contracts in connection with other portions of the
Project or other work on the Site under these or similar Conditions of the Contract.
If the Contractor claims that delay, damage, or additional cost is involved because
of such action by the City, the Contractor shall make such claim as provided
elsewhere in the Contract Documents.
When separate Contracts are awarded for different portions of the Project or other
work on the Site, the term "Contractor" in the Contract Documents in each case shall
mean the Contractor who executes each separate Contract.
General Conditions 1400-9
The City will provide for the coordination of the work of the City's own forces and of
each separate Contractor with the Work of the Contractor, who shall cooperate
therewith as provided in Paragraph 1400-4.8.3, Cooperation.
4.0 CONTRACTOR
4.1 Office
The Contractor's address stated in the Bid is hereby designated as the legal address
of the Contractor for the receipt of documents, samples, notices, letters, and other
Articles of communication.
4.2 Contractor's Representative
The Contractor shall notify the City in writing of the name of the person who will act
as the Contractor's representative and shall have the authority to act in matters
relating to this Contract. The Contractor, acting through its representative, shall give
personal attention to, and shall manage the Work, so that it shall be prosecuted
faithfully. The Contractor's representative shall be an employee of the Contractor.
Upon written request of the Contractor, this requirement may be waived by the City.
The City's waiver, if granted will be in writing. There is no obligation by the City to
waive this provision regardless of the effect on the Contractor's operations.
At all times during the progress of the Work, the Contractor's representative shall be
personally present at the Project site, or a designated alternate shall be available
who has the authority to act in matters relating to the Contract. The Contractor's
representative or designated alternate shall have the authority to carry out the
provisions of the Contract and to supply materials, equipment, tools, and labor
without delay for the performance of the Work.
Before initial work is begun on the Contract, the Contractor shall file with the City
Engineer addresses and telephone numbers where the Contractor's and all
subcontractors' representatives can be reached during all hours, including nights
and weekends when work is not in progress.
4.3 Construction Procedures
The Contractor will supervise and direct the work. The Contractor has the authority
to determine the means, methods, techniques, sequences, and procedures of
construction, except in those instances where the City, to define the quality of an
item of work, specifies in the Contract, a means, method, technique, sequence, or
procedure for construction of that item of Work.
4.4 Contractor's Employees
The Contractor shall be responsible for the adequacy, efficiency, and sufficiency of
its employees. Workers shall have sufficient knowledge, skill, and experience to
perform properly the work assigned to them.
The Contractor shall employ only competent, skillful workers to perform the Work. If
any subcontractor or person employed by the Contractor or its subcontractors,
appear to the City Engineer to be incompetent or act in a disorderly or improper
manner, such person or subcontractor shall be discharged from the site immediately
General Conditions 1400-10
by the Contractor upon written direction of the City Engineer, and such person shall
not again be employed on the Project.
4.5 Subcontractors
Subcontractors will not be recognized as having a direct relationship with the City.
The persons engaged in the Work, including employees of subcontractors and
suppliers, will be considered employees of the Contractor. The Contractor will be
responsible for their work and their work shall be subject to the provisions of the
Contract. The Contractor is as fully responsible to the City for the acts and omissions
of its subcontractors and of persons either directly or indirectly employed by them
as the Contractor is for the acts and omissions of persons directly employed by the
Contractor. Nothing contained in the Contract Documents shall create any
contractual relation between any subcontractor and the City. References in the
Contract Document to actions required of subcontractors, manufacturers, suppliers,
or any party other than the Contractor, the City, the City Engineer, its consultants
shall be interpreted as requiring that the Contractor shall require such subcontractor,
manufacturer, supplier, utility company, or party to perform the specified action,
unless the Contract Documents specifically state that the Work is not included in the
Contract.
The Contractor shall not employ any subcontractors that are not properly licensed
in accordance with State law. Prior to commencement of any work by a
subcontractor, the Contractor shall submit verification to the City Engineer that the
subcontractor is properly licensed for the work it will perform. Changes to
subcontractors listed in the Bid in accordance with Public Contract Code 4100 et.
seq., shall be made only with the approval of the City.
4.6 Contractor's Equipment and Facilities
The Contractor shall furnish and maintain in good condition all equipment and
facilities as required for the proper execution and inspection of the Work. Such
equipment and facilities shall meet all requirements of applicable ordinances and
laws.
4.7 Public Safety and Convenience
The Contractor shall conduct its work so as to insure the least possible obstruction
to traffic and inconvenience to the general public and the residents in the vicinity of
the Work and to insure the protection of persons and property at no extra cost to the
City. The Contractor shall have under construction no greater length or amount of
work than he can prosecute properly with due regard to the rights of the public.
4.8 City -Contractor Coordination
4.8.1 Service of Notice - Notice, order, direction, request, or other communication
given by the City or the City Engineer to the Contractor shall be deemed to
be well and sufficiently given to the Contractor if delivered to the Contractor's
Representative designated in Paragraph 1400-4.2, Contractor's
Representative, to the Contractor's office designated in Paragraph 1400-4.1,
Office, or to the Contractor's address provided in the Bid Proposal.
General Conditions 1400-11
4.8.2 Suggestions to Contractor - Plans or methods of work suggested by the
City, City Engineer or authorized representatives to the Contractor, but not
specified or required, if adopted or followed by the Contractor in whole or in
part, shall be used at the risk and responsibility of the Contractor. The City,
City Engineer, or authorized representatives assume no responsibility
therefor, and in no way will be held liable for any defects in the Work which
may result from or be caused by use of such plan or method of work.
4.8.3 Cooperation - The Contractor shall afford the City, the City Engineer and
separate Contractors reasonable opportunity for the introduction and storage
of their materials and equipment and the execution of their work and shall
coordinate the Work with theirs as required by the Contract Documents.
If any part of the Contractor's Work depends for proper execution or results upon the
work of the City or any separate Contractor, the Contractor shall, prior to proceeding
with the Work, promptly report to the City Engineer any apparent discrepancies or
defects in such other work that render it unsuitable for such proper execution and
results. Failure of the Contractor to so report shall constitute an acceptance of the
City's or separate Contractor's work as fit and proper to receive the Work, except as
to defects which may subsequently become apparent in such work by others.
If requested by the Contractor, the City shall arrange meetings with other contractors
performing work on behalf of the City to plan coordination of construction activities.
The City shall keep the Contractor informed of the planned activities of other
contractors.
Any costs caused by defective or ill-timed work shall be borne by the responsible
party.
Differences and conflicts arising between the Contractor and other contractors
employed by the City or between the Contractor and the workers of the City with
regard to their work, shall be submitted to the City for its decision in the matter. If
such separate contractor sues the City on account of any delay or damage alleged
to have been caused by the Contractor, the City shall notify the Contractor who shall,
at the City's election, defend such proceedings at the Contractor's expense.
If any judgement or award against the City arises from any such litigation whether
defended by City or by Contractor, the Contractor shall pay or satisfy said judgement
or award and shall reimburse the City for all attorney's fees and court costs which
the City has incurred or for which it is liable.
4.9 Permits
Unless specifically stated to be provided by the City, Contractor shall apply for,
obtain, and comply with all the terms, conditions and requirements attached to all
permits, bonds and licenses required by local, state, or federal agencies to perform
work, construct, erect, test and startup of any equipment or facility for this Contract.
Where operating permits are required, the Contractor shall apply for and obtain such
operating permits in the name of the City and provide the permit in an appropriate
frame or file holder when the City accepts substantial completion of the equipment
General Conditions 1400-12
or facility. The Contractor shall give all notices necessary or incidental to the due
and lawful prosecution of the work.
Any permits, bonds, licenses and fees therefore required for the performance of work
under this Contract and not specifically mentioned herein as having been obtained
and paid by the City shall be included in the Contractor's bid price.
The Contractor shall apply for and obtain in its name the necessary building,
plumbing and electrical permits and shall be responsible for satisfying all code
requirements, calling for inspections, and obtaining final approvals. Code
inspections will be coordinated by the City Engineer. The Contractor shall comply
with all construction conditions stipulated in the permits. The Contractor shall
include in its bid the fees for any permits required.
The Contractor shall apply for and obtain all safety permits for excavations,
tunneling, trenches, construction (building structure, scaffolding, or falsework) and
demolition required by CAL/OSHA including but not limited to, the permits required
by Labor Code Section 6500.
4.10 Contractor's Responsibility for the Work and Materials
Until acceptance of the Work, the Contractor shall have the charge and care of the
Work and of the materials to be used therein and shall bear the risk of injury, loss,
or damage, to any part thereof (regardless of whether partial payments have been
made on such damaged portions of the Work) by the action of the elements or from
any other cause, whether arising from the non -execution of the Work. The Contractor
shall rebuild, repair, restore, and make good all injuries, losses, or damages to any
portion of the Work or the materials occasioned by any cause before its completion
and acceptance and shall bear the expense thereof, except for such injuries, losses,
or damages as are directly and approximately caused by acts of the City.
4.11 Laws to be Observed
The Contractor shall keep himself fully informed of all existing and future County,
State, and National laws and regulations and all municipal ordinances and
regulations of the City which in any manner affect those engaged or employed in the
Work and of all such orders and decrees of bodies having any jurisdiction or authority
over the same; and shall protect and indemnify the City and all of its officers, agents,
and servants against any claim or liability arising from or based on the violation of
any such laws, ordinances, regulations, orders, or decrees whether by himself or its
employees. If any discrepancy or inconsistency is discovered in the plans, drawings,
specifications, or Contract for the Work in relation to any such law, ordinance,
regulations, order or decree, the Contractor shall immediately report the same to the
City Engineer in writing.
4.11.1 Construction Registration with California Department of Industrial
Relations - A contractor or subcontractor shall not be qualified to bid on, be
listed in a bid proposal, subject to the requirements of Section 4104 of the
Public Contract Code, or engage in the performance of any contract for public
works, as defined in Chapter 1 (commencing with Section 1720) of Part 7 of
Division 2 the Labor Code, unless currently registered and qualified to
General Conditions 1400-13
perform public works pursuant to Section 1725.5 of the Labor Code. Prior to
March 1, 2015, it is not a violation of this section for an unregistered contractor
to submit a bid that is authorized by Section 7029.1 of the Business and
Professions Code or by Section 10164 or 20103.5 of the Public Contract
Code, provided the contractor is registered to perform public works pursuant
to Section 1725.5 of the Labor Code prior to April 1, 2015. Effective March
1, 2015, only contractors and subcontractors that are registered to perform
public works pursuant to Section 1725.5 of the Labor Code may submit a bid
for a public works project. Effective April 1, 2015, contractors and
subcontractors not registered to perform public works pursuant to Section
1725.5 of the Labor Code may not engage in the performance of a public
works project awarded after April 1, 2015.
4.11.2 Prevailing Wage - In accordance with Section 1770 of the Labor Code, the
City has ascertained and does hereby specify that the prevailing wage rates
shall be those provided in Article 1110-20.0, WAGE RATES. The said rates
shall include all employer payments that are required by Section 1773.1 of
the Labor Code. The City will furnish to the Contractor, upon request, a copy
of such prevailing rates. It shall be the duty of the Contractor to post a copy
of such prevailing wages at the job site.
For each worker paid less than the stipulated rate in the execution of the
Contract by the Contractor, or any subcontractor under him, in violation of the
provisions of the Labor Code, and in particular, Section 1770 to Section 1780,
inclusive, the Contractor shall be subject to the provisions and penalties of
Section 1775 of the Labor Code. In addition to said penalty, and pursuant to
said Section 1775, the difference between such stipulated prevailing wage
rates and the amounts paid to each worker for each calendar day, or portion
thereof, for which each worker was paid less than the stipulated prevailing
rate shall be paid to each worker by the Contractor.
The wage rates set forth are the minimum that may be paid by the Contractor.
Nothing herein contained shall be construed as preventing the Contractor
from paying more than the minimum set forth.
No extra compensation whatever shall be allowed by the City due to the
inability of the Contractor to hire labor at the minimum rate nor for any
necessity for payment by the Contractor for subsistence, travel time,
overtime, or other added compensation, all of which possibilities are elements
to be considered and ascertained to the Contractor's own satisfaction in
preparing the bid.
If it becomes necessary to employ a craft other than those listed, the
Contractor shall notify the City immediately and the City will determine the
additional prevailing rate from the Director of the Department of Industrial
Relations and the rate thus determined shall be applicable as a minimum at
the time of initial employment.
The Contractor shall pay travel and subsistence payments to workers needed
to execute the work as such travel and subsistence payments are defined in
General Conditions 1400-14
the applicable collective bargaining agreement filed with the Department of
Industrial Relations pursuant to Labor Code Section 1773.8.
Pursuant to Labor Code section 1771.1, no contractor or subcontractor may
be listed on a bid proposal for a public works project submitted on or after
March 1, 2015 unless registered with the California Department of Industrial
Relations. Furthermore, all bidders and contractors are hereby notified that
no contractor or subcontractor may be awarded, on or after April 1, 2015, a
contract for public work on a public works project unless registered with the
Department of Industrial Relations.
Pursuant to Labor Code section 1771.4, all bidders and contractors are
hereby notified that this project is subject to compliance monitoring and
enforcement by the California Department of Industrial Relations.
4.11.3 Certified Payrolls - In accordance with Section 1776 of the Labor Code,
each Contractor and subcontractor shall keep an accurate payroll record,
showing the name, address, social security number, work classification,
straight time, and overtime hours worked each day and week, and the actual
per diem wages paid to each journeyman, apprentice, worker, or other
employee employed by him or her in connection with the project.
The payroll records shall be certified and shall be available for inspection at
all reasonable hours at the principal office of the Contractor on the following
basis:
a. Pursuant to S113854, all contractors and subcontractors must furnish
electronic certified payroll records directly to the Labor
Commissioner (aka Division of Labor Standards Enforcement). All
contractors and subcontractors must also provide a copy and proof
to the City of online submittal within 2 days of online submission.
b. A certified copy of an employee's payroll record shall be made available
for inspection or furnished to the employee or his or her authorized
representative on request.
c. A certified copy of all payroll records shall be made available for inspection
or furnished upon request to a representative of the City, the Division of
Labor Standards Enforcement, and the Division of Apprenticeship
Standards of the Department of Industrial Relations.
d. A certified copy of all payroll records shall be made available upon request
by the public in accordance with Section 1776 of the Labor Code.
The Contractor is responsible for its and its subcontractor's compliance with
the provisions of Section 1776 of the Labor Code.
4.11.4 Overtime Requirements - The Contractor shall forfeit, as a penalty to the
City, the penalty as provided in Section 1813 of the Labor Code for each
worker employed in the execution of the Contract by the Contractor, or any
subcontractor under the Contractor, for each day during which such worker
is required or permitted to work more than eight (8) hours in any one day and
forty (40) hours in any one week, in violation of the provisions of the Labor
General Conditions 1400-15
Code, and in particular, Section 1810 to Section 1815 thereof, inclusive,
except that work performed by employees of Contractors in excess of eight
(8) hours a day and forty (40) hours during one week, shall be permitted upon
compensation for all hours worked in excess of eight (8) hours per day, at not
less than one and a half (1'/2) times the basic rate of pay as provided for in
Section 1815 of the Labor Code.4.11.5 Apprentice and Trainee -
Attention is directed to the provisions in Section 1777.5 of the Labor Code
and in accordance with the regulations of the California Apprenticeship
Council concerning the employment of apprentices by the Contractor or any
subcontractor under the Contractor.
Section 1777.5 requires the Contractor or subcontractors employing
tradespersons in any apprenticeable occupation to apply to the joint
apprenticeship committee nearest the site of the project and which
administers the apprenticeship program in that trade for a certificate of
approval. The Contractor and subcontractors are required to submit contract
award information to the applicable joint apprenticeship committee. As
provided for in Section 1777.5 of the Labor Code, the Contractor is
required to make contributions to funds established for the
administration of apprenticeship programs.
It shall be the responsibility of the Contractor to abide by the provisions of
Section 1777.5 (except 1777.5(b)) of the Labor Code and to require all
subcontractors employed by or contracting with the Contractor to abide by
said provisions. The Contractor shall furnish the City any and all evidence of
compliance with this code section when requested by the City.
For failure to comply with Section 1777.5 (except 1777.5(b)) of the Labor
Code, the Contractor shall be subject to the penalties in Section 1777.7 of the
Labor Code.
4.11.6 Workers' Compensation Insurance - The Contractor is required to secure
the payment of compensation to its employees in accordance with the
provisions of Sections 1860 and 3700 of the Labor Code and Paragraph
1340-2.4 Workers' Compensation Insurance
4.12 Safety
The Contractor shall be solely and completely responsible for conditions of the job
site, including safety of all persons and property during performance of the work.
This requirement shall apply continuously and not be limited to normal working
hours. Safety provisions shall conform to U.S. Department of Labor (OSHA), the
California Occupational Safety and Health Act, and all other applicable Federal,
State, County, and local laws, ordinances, codes, the requirements set forth below,
and any regulations that may be detailed in other parts of these Documents. Where
any of these are in conflict, the more stringent requirement shall be followed.
The completed Work shall include all necessary permanent safety devices, such as
machinery guards and similar ordinary safety items, required by the State and
General Conditions 1400-16
Federal (OSHA) industrial authorities and applicable local and national codes.
Further, any features of the Work, including City -selected equipment, subject to such
safety regulations shall be fabricated, furnished, and installed in compliance with
these requirements. All equipment furnished shall be grounded and provided with
guards and protection as required by safety codes.
Where vapor -tight or explosion -proof electrical installation is required by safety
codes, this shall be provided. Contractors and manufacturers of equipment shall be
held responsible for compliance with the requirements included herein. The
Contractor shall notify all equipment suppliers and subcontractors of the provisions
of this paragraph.
Before proceeding with any construction work, the Contractor shall take the
necessary action to comply with all provisions for safety and accident prevention.
The Contractor shall develop and maintain for the duration of this Contract, a safety
program that will effectively incorporate and implement all required safety provisions.
The Contractor shall appoint an employee as safety supervisor who is qualified and
authorized to supervise and enforce compliance with the safety program.
The Contractor, as a part of his safety program, shall maintain at his office or other
well-known place at the Site, safety equipment applicable to the Work as prescribed
by the aforementioned authorities, all items necessary for giving first aid to the
injured, and shall establish the procedure for the immediate removal to a hospital or
a doctor's care of persons who may be injured on the job site.
In accordance with the provisions of Section 6705 of the Labor Code, the Contractor
shall submit, in advance of excavation 5 feet or more in depth, detailed plans
showing the design of shoring, bracing, sloping, or other provisions to be made for
worker protection from hazard of caving ground during such excavation. If such
Plans vary from the shoring system standards set forth in the Construction Safety
Orders in Title 8, California Code of Regulations, Article 6, the Plans shall be
prepared and signed by a registered civil or structural engineer. Shoring, bracing,
sloping, or other protective system shall not be less effective than required by the
California Construction Safety orders.
If death or serious injuries or serious damages are caused, the accident shall be
reported immediately by telephone or messenger to the City. In addition, the
Contractor must promptly report in writing to the City Engineer all accidents
whatsoever arising out of, or in connection with, the performance of the Work
whether on, or adjacent to, the Site, giving full details and statements of witnesses.
The Contractor shall make all reports as are, or may be, required by any authority
having jurisdiction, and permit all safety inspections of the work being performed
under this Contract. If a claim is made by anyone against the Contractor or any
subcontractor on account of any accident, the Contractor shall promptly report the
facts in writing to the City Engineer, giving full details of the claim.
General Conditions 1400-17
5.0 CONTROL OF WORK AND MATERIALS
5.1 Means and Methods
It is expressly stipulated that the drawings, specifications and other Contract
Documents set forth the requirements as to the nature of the completed Work and
do not purport to control the method of performing work except in those instances
where the nature of the completed Work is dependent on the method of
performance.
Except as provided elsewhere in the Contract Documents, neither the City, its
consultants, or the City Engineer will be responsible for or have control or charge of
construction means, methods, techniques, sequences or procedures, or for safety
precautions and programs in connection with the Work. Except as provided
elsewhere in the Contract Documents, neither the City, its consultants, or the City
Engineer will be responsible for or have control or charge over the acts or omissions
of the Contractor, or any of their subcontractors, agents or employees, or any other
persons performing any of the Work. Any general control of the Work exercised by
the City or its authorized representatives shall not make the Contractor an agent of
the City, and the liability of the Contractor for all damages to persons and/or to public
or private property arising from the Contractor's execution of the Work shall not be
lessened because of such general control.
Neither the inspection by the City, its consultants, or the City Engineer, nor any
order, measurement, approved modification, or payment of monies, nor acceptance
of any part or whole of the Work by the City, the City Engineer or the consultant, or
their agents, shall operate as a waiver of any provision of the Contract.
Acceptance by the City, it consultants, or the City Engineer of any drawings,
methods of work, or any information regarding materials and equipment the
Contractor proposes to furnish in the Work shall not be regarded as an assumption
of risks or liability by the City, its consultants, or the City Engineer, or any officer or
employee thereof, and the Contractor shall have no claim under the Contract on
account of the failure or partial failure or inefficiency or insufficiency of any plan or
method of work or material and equipment so accepted. Such acceptance shall be
considered to mean merely that the City, its consultants, or the City Engineer has
no objection to the Contractor using, upon its own full responsibility, the plan or
method of work proposed, or furnishing the materials and equipment proposed.
5.2 City -Furnished Materials
Materials, if furnished by the City, will be made available as designated in the
Specific Project Requirements. The cost of loading, unloading, hauling and handling,
and placing City -furnished materials shall be considered as included in the price bid
for the Contract item involving such City -furnished material.
Contractor shall inspect and assure himself of the amount and soundness of such
materials.
The Contractor will be held responsible for all materials furnished to it and shall pay
all demurrage and storage charges. City -furnished materials lost or damaged from
any cause whatsoever shall be replaced by the Contractor. The Contractor will be
General Conditions 1400-18
liable to the City for the cost of replacing City -furnished material and such costs may
be deducted from any monies due or to become due the Contractor.
5.3 Defective and Unauthorized Work
Materials and workmanship not conforming to the requirements of the Contract
Documents shall be considered defective and will be subject to rejection. Defective
work or material, whether in place or not, shall be removed immediately from the
Site by the Contractor, at its expense, when so directed by the City Engineer.
Any work done beyond the limits of work, lines, and grades shown on any approved
plans or established by the City Engineer, or any extra work done without written
authority, will be considered as unauthorized and will not be paid for.
Upon failure on the part of the Contractor to comply with any order of the City
Engineer made under the provisions of this section, the City Engineer shall have
authority to cause defective work to be remedied, or removed and replaced, and
unauthorized work to be removed, and to deduct the costs thereof from any monies
due or to become due the Contractor. The time, cost and compliance requirements
stipulated in Paragraph 1400-3.4, City's Right to Carry Out the Work, shall apply
for this paragraph also.
5.4 Unnoticed Defects
Any defective work or material that may be discovered by the City, its consultants,
or the City Engineer before the final acceptance of the Work, or before final payment
has been made, or during the warranty period, shall be removed and replaced by
work and materials which shall conform to the provisions of the Contract Documents.
Failure on the part of the City, its consultants, or the City Engineer to condemn or
reject bad or inferior work or materials shall not be construed to imply acceptance of
such work or materials.
5.5 Right to Retain Imperfect Work
If any part or portion of the work performed or material furnished under this Contract
shall prove defective and not in accordance with the Drawings and Specifications,
and if the imperfection in the same shall not be of sufficient magnitude or importance
as to make the work dangerous or unsuitable, or if the removal of such work will
create conditions which are dangerous or undesirable, the City shall have the right
and authority to retain such work but shall make such deductions in the final
payment therefor as may be just and reasonable.
6.0 PROGRESS OF THE WORK
6.1 Beginning of Work
The Contractor shall begin work within ten (10) days after receiving Notice to
Proceed and shall diligently prosecute the same to completion within the time limit.
Should the Contractor begin work in advance of receiving Notice to Proceed, any
work performed in advance of the said date of approval shall be considered as
having been done by the Contractor at its own risk and as a volunteer.
General Conditions 1400-19
6.2 Time of Completion
Time shall be of the essence of the Contract. The Contractor shall prosecute the
work so that the various portions of the project shall be complete and ready for use
within the time specified in Paragraph 3000-1.6 TIME ALLOWED FOR
COMPLETION. It is expressly understood and agreed by and between the
Contractor and the City that the Contract time for completion of the work described
herein is a reasonable time taking into consideration the average climatic and
economic conditions and other factors prevailing in the locality and the nature of the
work.
6.3 Delays
6.3.1 Notice of Delays - When the Contractor foresees a delay in the prosecution
of the Work and, in any event, immediately upon the occurrence of a delay,
the Contractor shall notify the City Engineer in writing of the probability of the
occurrence and the estimated extent of the delay, and its cause. The
Contractor shall take immediate steps to prevent, if possible the occurrence
or continuance of the delay. The Contractor agrees that no claim shall be
made for delays which are not called to the attention of the City Engineer at
the time of their occurrence.
6.3.2 Avoidable Delays - Avoidable delays in the prosecution of the Work shall
include delays which could have been avoided by the exercise of care,
prudence, foresight, and diligence on the part of the Contractor or its
subcontractors, at any tier level, or suppliers.
6.3.3 Unavoidable Delays - Unavoidable delays in the prosecution or completion
of the Work shall include delays which result from causes beyond the control
of the Contractor, and which could not have been avoided by the exercise of
care, prudence, foresight, and diligence on the part of the Contractor or his
subcontractors, at any tier level, or suppliers. Delays in completion of the
Work of other Contractors employed by the City will be considered
unavoidable delays insofar as they interfere with the Contractor's completion
of the current critical activity item of the Work.
6.3.3.1 Abnormal Delays - Delays caused by acts of God, fire, unusual storms,
floods, tidal waves, earthquakes, strikes, labor disputes, freight embargoes,
and shortages of materials shall be considered as unavoidable delays insofar
as they prevent the Contractor from proceeding with at least seventy-five (75)
percent of the normal labor and equipment force for at least five (5) hours per
day toward completion of the current critical activity item on the favorably
reviewed progress schedule.
6.3.3.2 Material Shortages - Upon the submission of satisfactory proof to the City
Engineer by the Contractor, shortages of material will be acceptable as
grounds for granting a time extension. In order that such proof may be
satisfactory and acceptable to the City Engineer, it must be demonstrated by
the Contractor that the Contractor has made every effort to obtain such
General Conditions 1400-20
materials from all known sources within reasonable reach of the proposed
Work.
Only the physical shortage of material, caused by unusual circumstances, will
be considered under these provisions as a cause for extension of time, and
no consideration will be given to any claim that material could not be obtained
at a reasonable, practical, or economical cost or price, unless it is shown to
the satisfaction of the City Engineer that such material could have been
obtained only at exorbitant prices entirely out of line with current rates, taking
into account the quantities involved and usual practices in obtaining such
quantities. A time extension for shortage of material will not be considered for
material ordered or delivered late or whose availability is affected by virtue of
the mishandling of procurement. The above provisions apply equally to
equipment to be installed in the work.
6.4 Time Extensions
6.4.1 Avoidable Delay - The City may grant an extension of time for avoidable
delays if the City deems it is in its best interest. If the City grants an extension
of time for avoidable delays, the Contractor agrees to pay the City's actual
costs, including charges for engineering, inspection and administration
incurred during the extension.
6.4.2 Unavoidable Delay - If the Contractor is delayed in the performance of its
work by an act of the City or if the Contractor is delayed in the performance
of its work by an unavoidable delay, then the Contract completion date may
be extended by the City for such time that, in the City's and City Engineer's
opinion, the Contractor's completion date will be unavoidably delayed,
provided that the Contractor strictly fulfills the following:
a. The Contractor shall provide notification, in accordance with Paragraph
1400-6.3.1, Notice of Delays and submit in writing a request for an
extension of time to the City Engineer stating at a minimum the probable
cause of the delay and the number of days being requested. The time
extension request shall be submitted in accordance with the requirements
of Paragraph 2000-4.3, TIME IMPACT ANALYSIS.
b. If requested by the City Engineer, the Contractor shall promptly provide
sufficient information to the City Engineer to assess the cause or effect of
the alleged delay, or to determine if other concurrent delays affected the
work.
c. Weather Delays. The Contractor will be granted a non -compensable time
extension for weather caused delays.
Should the Contractor fail to fulfill any of the foregoing, which are considered
conditions precedent to the right to receive a time extension, the Contractor
waives the right to receive a time extension.
Should the Contractor fail to complete the work within the time specified in
the contract, as extended in accordance with this clause if appropriate, the
General Conditions 1400-21
Contractor shall pay to the City liquidated damages in accordance with
Section 1500, Paragraph 1500- 2.1, Liquidated Damages.
During such extension of time, neither extra compensation for engineering,
inspection, and administration nor damages for delay will be charged to the
Contractor. It is understood and agreed by the Contractor and City that time
extensions due to unavoidable delays will be granted only if such unavoidable
delays involve controlling operations which would prevent completion of the
whole Work within the specified Contract time.
6.4.3 Indirect Overhead - The Contractor shall be reimbursed for indirect
overhead expenses for periods of time when the Work is stopped due to
delays as defined in Paragraph 1400-6.3.3, Unavoidable Delay. However,
no reimbursement for indirect overhead shall be made for delays as defined
in Paragraphs 1400-6.3.3.1, Abnormal Delays; 1400-6.4.2c, Weather Delays;
or 1400-6.3.3.3, Material Shortages.
As a condition precedent to any reimbursement, the Contractor must fulfill all
conditions as provided in Paragraph 1400-6.4.2, Unavoidable Delay.
The reimbursement of indirect overhead is limited to those delay conditions
defined above when the Contractor is prevented from proceeding with
seventy-five (75) percent of the normal labor and equipment force for at least
five (5) hours per day toward completion of the current critical activity item(s)
on the current favorably reviewed progress schedule.
6.4.3.1 Indirect Field Overhead - For those allowable delay periods as defined in
Paragraph 1400-6.4.3, Indirect Overhead, the Contractor shall be
reimbursed for its indirect field overhead based on:
a. Invoices for all field office equipment.
b. Actual salary for field office staff.
c. Fair rental values acceptable to the City Engineer as described in
Paragraph 1400-8.3, Force Account Payment for construction
equipment idled due to the delay.
6.4.3.2 Home Office Overhead - For those allowable delay periods as defined in
Paragraph 1400-6.4.3, Indirect Overhead, the Contractor shall be
reimbursed for its home office overhead based on the following formula:
Contract Bid Price divided by Contract Period Days x $0.03 = Daily Home
Office Overhead ($/Day)
Such reimbursement shall be mutually agreed between the City and
Contractor to encompass full payment for any home office overhead
expenses for such periods of time for the Contractor and all subcontractors.
The Contractor agrees to hold the City harmless for any indirect overhead
claims from its subcontractors.
General Conditions 1400-22
6.5 Temporary Suspension of Work
6.5.1 If the Contractor fails to correct defective work as required by Paragraph
1400-5.3, Defective and Unauthorized Work, or fails to carry out the Work
in accordance with the Contract Documents or any other applicable rules and
regulations, the City, by a written order of the City Engineer or a
representative specifically empowered to do so, may order the Contractor to
stop the work, or any portion thereof, until the cause for such order has been
eliminated; however, this right of the City to stop the Work shall not give rise
to any duty on the part of the City to exercise this right for the benefit of the
Contractor or any other person or entity. All delays in the Work occasioned
by such stoppage shall not relieve the Contractor of any duty to perform the
Work or serve to extend the time for its completion. Any and all necessary
corrective work done in order to comply with the Contract Documents shall
be performed at no cost to the City.
6.5.2 In the event that a suspension of Work is ordered, as provided in this
paragraph, the Contractor, at its expense, shall perform all work necessary to
provide a safe, smooth, and unobstructed passageway through construction
for use by public, pedestrian, and vehicular traffic, during the period of such
use by suspension. Should the Contractor fail to perform the Work as
specified, the City may perform such work and the cost thereof may be
deducted from monies due the Contractor under the Contract.
6.5.3 The City shall also have authority to suspend the Work wholly or in part, for
such period as the City may deem necessary, due to unsuitable weather, or
to such other conditions as are considered unfavorable for the suitable
prosecution of the Work. Such temporary suspension of the Work will be
considered justification for time extensions to the Contract in an amount equal
to the period of such suspension.
The Contractor as directed by the City shall provide the provisions as
stipulated in Paragraph 1400-6.6.2 above. Such additional work shall be
compensated as provided for in Paragraph 1400-7.0, CHANGES IN SCOPE
OF WORK.
6.6 Termination of Contract
If at any time the Contractor is determined to be in material breach of the Contract,
notice thereof in writing will be served upon the Contractor and its sureties, and
should the Contractor neglect or refuse to provide means for a satisfactory
compliance with the Contract, as directed by the City Engineer, within the time
specified in such notice, the City shall have the authority to terminate the operation
of the Contract.
Upon such termination, the Contractor shall discontinue the Work, or such parts of
it as the City may designate. Upon such termination, the Contractor's control shall
terminate and thereupon the City or its fully authorized representative may take
possession of all or any part of the Contractor's materials, tools, equipment, and
appliances upon the premises and use the same for the purposes of completing the
General Conditions 1400-23
Work and hire such force and buy or rent such additional machinery, tools,
appliances, and equipment, and buy such additional materials and supplies at the
Contractor's expense as may be necessary for the proper conduct of the Work and
for the completion thereof; or the City may employ other parties to carry the Contract
to completion, employ the necessary workers, substitute other machinery or
materials and purchase the materials contracted for, in such manner as the City may
deem proper; or the City may annul and cancel the Contract and relet the Work or
any part thereof. Any excess of cost arising there from over and above the Contract
price will be charged against the Contractor and its sureties, who will be liable
therefore.
In the event of such termination, all monies due the Contractor or retained under the
terms of this Contract shall be held by the City in an escrow account; however, such
holdings will not release the Contractor or its sureties from liability for failure to fulfill
the Contract. Any excess cost over and above the Contract Amount incurred by the
City arising from the termination of the operations of the Contract and the completion
of the Work by the City as above provided shall be paid for by any available funds
in the escrow account. The Contractor will be so credited with any surplus remaining
after all just claims for such completion have been paid.
7.0 CHANGES IN THE SCOPE OF WORK
7.1 Change Orders
7.1.1 Without invalidating the Contract and without notice to sureties or insurers,
the City, through the City Engineer, may at any time or from time to time,
order additions, deletions, or revisions in the Work; these will be authorized
by Field Directive, Field Order, or Change Order. A Change Order will not be
issued for a Field Directive unless the City Engineer concurs with an appeal
by the Contractor that such Field Directive is a change in the scope of the
Contract. The Contractor shall comply promptly with the requirements for all
Change Orders, Field Orders, or Field Directives. The work involved in
Change Orders shall be executed under the applicable conditions and
requirements of the Contract Documents. If any Field Order causes an
increase or decrease in the Contract Amount or an extension or shortening
of the Contract Time, an equitable adjustment will be made by issuing a
Change Order. If the Contractor accepts a Change Order that does not
include a time extension, the Contractor waives any claim for additional time
for the work covered by that Change Order.
Additional or extra work performed by the Contractor without written
authorization of a Field Order or Change Order will not entitle the Contractor
to an increase in the Contract Amount or an extension of the Contract Time.
7.1.2 Extra work shall be that work not shown or detailed on the Contract Drawings
and not specified. Such work shall be governed by all applicable provisions
of the Contract Documents. In giving instructions, the City Engineer shall
have authority to make minor changes in the work, not involving extra cost,
and not inconsistent with the purposes of the work; but otherwise, except in
General Conditions 1400-24
an emergency endangering life or property, no extra work or change shall be
made unless in pursuance of a written order by the City through the City
Engineer, and no claim for an addition to the total amount of the Contract
shall be valid unless so ordered.
7.1.3 In case any change increases or decreases the work shown, the Contractor
shall be paid for the work actually done at a mutually agreed upon adjustment
to the Contract price, based upon the provisions of Paragraph 1400-8.0
PROJECT MODIFICATION PROCEDURES
7.1.4 If the Contractor refuses to accept a Change Order, the City may issue it
unilaterally. The Contractor shall comply with the requirements of the Change
Order. The City shall provide for an equitable adjustment to the Contract and
compensate the Contractor accordingly. If the Contractor does not agree that
the adjustment is equitable, it may submit a claim in accordance with
Paragraph 1400-7.3.2, Claims.
7.2 Differing Site Conditions
Pursuant to Public Contract Code Section 7104, the Contractor shall promptly, and
before such conditions are disturbed, notify the City Engineer in writing, of any:
a. Material that the Contractor believes may be material that is hazardous waste,
as defined in Section 25117 of the Health and Safety Code that is required to be
removed to a Class I, Class II, or Class III disposal site in accordance with
provisions of existing law.
b. Subsurface or latent physical conditions at the site differing from those indicated.
c. Unknown physical conditions at the site of any unusual nature, differing
materially from those ordinarily encountered and generally recognized as
inherent in work of the character provided for in the Contract.
The City shall promptly, investigate the conditions, and if it finds that the conditions
do materially differ, or do involve hazardous waste, and cause a decrease or
increase in the Contractor's cost of, or the time required for, performance of any part
of the work the City shall cause to be issued a change order under the procedures
provided in Paragraph 1400-7.1, Change Orders.
In the event that a dispute arises between the City and the Contractor whether the
conditions materially differ, or involve hazardous waste, or cause a decrease or
increase in the Contractor's cost of, or time required for, performance of any part of
the work, the Contractor shall not be excused from any scheduled completion date
provided for by the Contract, but shall proceed with all work to be performed under
the Contract. The Contractor shall retain any and all rights provided either by
Contract or by law which pertain to the resolution of disputes and protests between
the contracting parties, Paragraph 1400-7.3, Resolution of Disputes.
No claim of the Contractor under this clause shall be allowed unless the Contractor
has given the notice required.
General Conditions 1400-25
7.3 Resolution of Disputes
7.3.1 Contract Interpretation by the City Engineer - Questions regarding the
meaning and intent of the Contract Documents shall be referred in writing by
the Contractor to the City Engineer. The City Engineer shall respond to the
Contractor in writing with a decision.
7.3.2 Claims - Submission of a claim, properly certified, with all required supporting
documentation, and written rejection or denial of all or part of the claim by the
City, is a condition precedent to any action, proceeding, litigation, suit or
demand for arbitration by the Contractor.
7.3.2.1 Notice - If the Contractor disagrees with the City Engineer's decision in
Paragraph 1400-7.3.1, Contract Interpretation by the City Engineer, or in
any case where the Contractor deems additional compensation or a time
extension to the Contract period is due him for work or materials not covered
in the Contract or which the City Engineer has not recognized as extra work,
the Contractor shall notify the City Engineer, in writing, of his intention to make
claim. Claims pertaining to decisions provided in Paragraph 1400-7.3.1 shall
be filed in writing to the City Engineer within five (5) days of receipt of such
decision. All other claims notices for extra work shall be filed in writing to the
City Engineer prior to the commencement of such work. Written notice shall
use the words "Notice of Potential Claim". Such Notice of Potential Claim shall
state the circumstances and the reasons for the claim but need not state the
amount. Additionally, no claim for additional compensation or extension of
time for a delay will be considered unless the provisions of Paragraphs 1400-
6.3, Delays, and 6.4, Time Extensions, are complied with. No claim filed
after the date of final payment will be considered.
It is agreed that unless notice is properly given, the Contractor shall not
recover costs incurred by him as a result of the alleged extra work, changed
work or other situation which had proper notice been given would have given
rise to a right for additional compensation.
The Contractor should understand that timely notice of potential claim is of
great importance to the City and is not merely a formality. Such notice allows
the City to consider preventative action, to monitor the Contractor's increased
costs resulting from the situation, to marshal facts, and to plan its affairs.
Such notice by the Contractor, and the fact that the City Engineer has kept
account of the cost as aforesaid, shall not in any way be construed as proving
the validity of the claim.
7.3.2.2 Submission of claim costs - Within 30 days after the last cost of work for
which the Contractor contends additional compensation is due, but if costs
are incurred over a span of more than 30 days, then within 15 days after the
thirtieth day and every month thereafter, the Contractor shall submit to the
City Engineer the costs incurred for the claimed matter. Claims shall be made
in itemized detail satisfactory to the City Engineer in content, detail and format
of presentation. If the additional costs are in any respect not knowable with
certainty, they shall be estimated. If the claim is found to be just, it shall be
General Conditions 1400-26
allowed and paid for as provided in Section 1400-8.0, PROJECT
MODIFICATION PROCEDURES.
7.3.2.3 Affidavit required - All claims submitted to the City shall be accompanied
with a type written affidavit containing the following language: it must be
signed, dated, and notarized on the Contractor's letterhead:
I, (must be an officer) , being the title of (contractor's name,) ,
declare under penalty of perjury under the laws of the state of California,
and do personally certify and attest that: I have thoroughly reviewed the
attached claim for additional compensation and/or extension of time, and
know its contents, and said claim is made in good faith; the supporting
data is truthful and accurate; the amount requested accurately reflects
the contract adjustment for which the contractor believes the City of La
Quinta is liable; and further, that I am familiar with California Penal Code
Section 72 and California Government Code Section 12560, Et Seq,
pertaining to false claims, and further know and understand that
submission or certification of a false claim may lead to fines,
imprisonment and/or other severe legal consequences.
7.3.2.4 Claim meetings - From time to time the City Engineer may call special
meetings to discuss outstanding claims. The Contractor shall cooperate and
attend, prepared to discuss outstanding claims, making available the
personnel necessary for claim resolution, and providing documents
reasonably requested by the City Engineer.
7.3.3 Resolution of Claims - For all contracts awarded during the effective dates
of Public Contract Code Section 20104, where claims cannot be resolved
between the parties, claims for three hundred and seventy-five thousand
dollars ($375,000) or less shall be resolved pursuant to the provisions of that
code section, which is summarized in Paragraphs 1400-7.3.3.1 to 1400-
7.3.3.5. For claims greater than three hundred and seventy-five thousand
dollars ($375,000) Paragraphs 1400-7.3.3.2 to 1400-7.3.3.4 are applicable;
however, Paragraph 1400-7.3.3.5, Civil Actions for claims less than
$375,000, is not applicable.
7.3.3.1 Claims Less Than $50,000
a. For claims of less than fifty thousand dollars ($50,000), the City Engineer
shall respond in writing to written claims within 45 days of receipt of the
claim in Paragraph 1400-7.3.2, Claims, or may request, in writing, within
30 days of receipt of the claim, any additional documentation supporting
the claim or relating to defenses or claims the City may have against the
Contractor.
b. If additional information is thereafter required, it shall be requested and
provided pursuant to this section, upon mutual agreement of the City and
the Contractor.
c. The City Engineer's written response to the claim, as further documented,
shall be submitted to the Contractor within 15 days after receipt of the
General Conditions 1400-27
further documentation or within a period of time no greater than that taken
by the Contractor in producing the additional information, whichever is
greater.
7.3.3.2 Claims Greater Than $50,000
a. For claims of over fifty thousand dollars ($50,000), the City Engineer shall
respond in writing to all written claims within 60 days of receipt of the claim
in Paragraph 1400-7.3.2, Claims, or may request, in writing, within 30
days of receipt of the claim, any additional documentation supporting the
claim or relating to defenses or claims the City may have against the
Contractor.
b. If additional information is thereafter required, it shall be requested and
provided pursuant to this paragraph, upon mutual agreement of the City
and the Contractor.
c. The City Engineer's written response to the claim, as further documented,
shall be submitted to the Contractor within 30 days after receipt of the
further documentation, or within a period of time no greater than that taken
by the Contractor in producing the additional information or requested
documentation, whichever is greater.
7.3.3.3 Claim Conference - If the Contractor disputes the City Engineer's written
response, or if the City Engineer fails to respond within the time prescribed,
the Contractor may so notify the City, in writing, either within 15 days of
receipt of the City Engineer's response or within 15 days of the City
Engineer's failure to respond within the time prescribed, respectively, and
demand an informal conference to meet and confer for settlement of the
issues in dispute. Upon a demand, the City shall schedule a meet and
conference within 30 days for settlement of the dispute.
7.3.3.4 Claim Filing - If the claim or any portion remains in dispute after the claim
conference noted in Paragraph 1400-7.3.3.4, Claim Conference, the
Contractor may file a claim pursuant to Chapter 1 (commencing with Section
900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6
of Title 1 of the Government Code. For purposes of those provisions, the
running of the period of time within which a claim must be filed shall be tolled
from the time the Contractor submits his or her written claim pursuant to
Paragraph 1400-7.3.2, Claims, until the time the claim is denied, including
any period of time utilized in the meet and confer process.
7.3.3.5 Civil Actions for Claims Less Than $375,000 - The following procedures
are established for all civil actions filed to resolve claims for less than three
hundred seventy-five thousand dollars ($375,000):
a. Within 60 days, but no earlier than 30 days, following the filing or
responsive pleading, the court shall submit the matter to non-binding
mediation unless waived by mutual stipulation of both parties. The
mediation process shall provide for the selection within 15 days by both
parties of a disinterested third person as mediator, shall be commenced
General Conditions 1400-28
within 30 days of the submittal, and shall be concluded within 15 days
from the commencement of the mediation unless a time requirement is
extended upon a good cause showing to the court.
b. If the matter remains in dispute, the case shall be submitted to judicial
arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of
Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section
1141.11 of that Code. The Civil Discovery Act of 1986 (Article 3
(commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the
Code of Civil Procedure) shall apply to any proceeding brought under this
subdivision consistent with the rules pertaining to judicial arbitration.
c. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of
Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible,
be experienced in construction law, and (B) any party appealing an
arbitration award who does not obtain a more favorable judgement shall,
in addition to payment of costs and fees under the chapter, also pay the
attorney's fees on appeal of the other party.
7.3.3.6 Unresolved Issues - Unless this Contract provides otherwise, all claims,
counterclaims, disputes, and other matters in question between the City and
the Contractor that are not resolved between the City and the Contractor and
are not governed by Public Contract Code 20104 shall be decided by a court
of competent jurisdiction. Arbitration shall not be used for resolution of these
disputes.
Should either party to this Contract bring legal action against the other, the
case shall be handled in the California county where the work is being
performed.
7.3.4 Records of Disputed Work - In proceeding with a disputed portion of the
Work, the Contractor shall keep accurate records of its costs and shall make
available, to the City Engineer, a daily summary of the hours and
classification of equipment and labor utilized on the disputed work, as well as
a summary of any materials or any specialized services which are used.
Such information shall be submitted to the City Engineer on a monthly basis,
receipt of which shall not be construed as an authorization for or acceptance
of the disputed work.
8.0 PROJECT MODIFICATION PROCEDURES
8.1 Changes in Contract Price
Whenever corrections, alterations, or modifications of the work under this Contract
are ordered by the City Engineer and approved by the City and increase the amount
of work to be done, such added work shall be known as extra work; and when such
corrections, alterations, or modifications decrease the amount of work to be done,
such subtracted work shall be known as work omitted.
The difference in cost of the work affected by such change will be added to or
deducted from the amount of said Contract price, as the case may be, by a fair and
General Conditions 1400-29
reasonable valuation, which shall be determined in one or more of the following ways
as directed by the City Engineer:
a. By unit prices subsequently fixed by agreement between the parties;
b. By an acceptable lump sum proposal from the Contractor; or
c. By Force Account (as described in Paragraph 1400-8.3, Force Account
Payment), when directed in writing and administered by the City through its
agents.
When required by the City Engineer, the Contractor shall submit, in the form
prescribed by the City Engineer, an itemized breakdown with supporting data of the
quantities and prices used in computing the value of any change that may be
ordered.
The City Engineer will review the Contractor's proposal for the change and negotiate
an equitable adjustment with the Contractor. After there is an agreement the City
Engineer will prepare and process the Change Order and make a recommendation
for action by the City. All Change Orders must be approved by the City in writing
before the work can be authorized and the Change Order executed.
The prices agreed upon and any agreed upon adjustment in Contract Time shall be
incorporated in the written order issued by the City, which shall be written so as to
indicate an acceptance on the part of the Contractor as evidenced by its signature.
By signature of the Change Order, the Contractor acknowledges that the
adjustments to cost and time contained in the Change Order are in full satisfaction
and accord, payment in full, and so waives any right to claim further cost and time
impacts at any time during and after completion of the Contract for the changes
encompassed by the Change Order.
8.2 Negotiated Change Orders
Under the methods described in Paragraph 1400-8.1b and 8.1c above, the
Contractor shall submit substantiating documentation with an itemized breakdown
of Contractor and subcontractor direct costs, including labor, material, equipment
rentals, and approved services, pertaining to such ordered work in the form and
detail acceptable to the City Engineer. The direct costs shall include only the payroll
cost for workers and foremen, including wages, fringe benefits as established by
negotiated labor agreements or state prevailing wages, workers' compensation and
labor insurance, and labor taxes as established by law. No other fixed labor burdens
will be considered, unless approved in writing by the City Engineer; the cost of
materials used and equipment delivered and installed in such work as substantiated
by appropriate documents; the cost of construction machinery and equipment based
on fair rental or ownership values acceptable to the City Engineer as described in
Paragraph 1400-8.3, Force Account Payment; and the cost of incidentals directly
related to such work. The direct costs shall not include any labor or office costs
pertaining to the Contractor's managers or superintendents, his office and
engineering staff and office facilities, or anyone not directly employed on such work,
nor the cost of rental of small tools as all such indirect costs form a part of the
Contractor's overhead expense.
General Conditions 1400-30
Under the method described in Paragraph 1400-8.1b and 8.1c the maximum
percentage which will be allowed for the Contractor's combined overhead and profit
will be:
a. For work by its own organization, the Contractor may add the following
percentages:
Direct Labor 25 percent
Materials 15 percent
Equipment (owned or rented) 15 percent
b. For all such work done by subcontractors, such subcontractor may add the same
percentages as the Contractor as listed in (1) above to its actual net increase in
costs for combined overhead and profit and the Contractor may add up to ten
(10) percent of the subcontractor's total for its combined overhead and profit.
c. For all such work done by subtier-subcontractors, such sub -subcontractors may
add the same percentages as the Contractor as listed in (1) above to its actual
net increase in costs for combined overhead and profit and the subcontractor
may add up to ten (10) percent of the sub -subcontractor's total for his combined
overhead and profit. The Contractor may add up to five (5) percent of the
subcontractor's total for its combined overhead and profit.
d. To the total of the actual costs and fees allowed hereinunder, not more than two
(2) percent shall be added for additional bond and insurance other than labor
insurance.
The above fees represent the maximum limits which will be allowed, and they include
the Contractor's and all subcontractors' indirect home office expenses and all costs
for cost proposal preparation.
When both additions and credits are involved in any one change, the combined
overhead and profit shall be figured on the basis of the net increase, if any, for each
area of work, i.e. direct labor, materials, equipment, and subcontractors. The amount
of credit to be allowed by the Contractor to the City for any such change which results
in a net decrease in cost will be the amount of the actual net decrease and a credit
in accordance with the markups allowed under the use of the method described in
Paragraph 1400-8.3, Force Account Payment. The Contractor shall not claim for
anticipated profits on work that may be omitted.
8.3 Force Account Payment
If either the amount of work or payment for a Change Order cannot be determined
or agreed upon beforehand, the City may direct by written Change Order or Field
Order that the work be done on a force account basis. The term "force account" shall
be understood to mean that payment for the work will be done on a time and expense
basis, that is, on an accounting of the Contractor's forces, materials, equipment, and
other items of cost as required and used to do the work. For the work performed,
payment will be made for the documented actual cost of the following:
a. Direct labor cost for workers, including foremen, who are directly assigned to the
force account work: Direct labor cost is the actual payroll cost, including wages,
General Conditions 1400-31
fringe benefits as established by negotiated labor agreements or state prevailing
wages, workers' compensation and labor insurance, and labor taxes as
established by law. No other fixed labor burdens will be considered, unless
approved in writing by the City.
b. Material delivered and used on the designated work, including sales tax, if paid
for by the Contractor or its subcontractor.
c. Equipment rental, including necessary transportation for items having a value in
excess of One Thousand Dollars ($1,000.00).
d. Additional bond.
e. Additional insurance, other than labor insurance.
To the preceding costs, there shall be added the following fees for the Contractor,
subcontractor, or sub -subcontractor actually performing the work:
• A fixed fee not to exceed fifteen (15) percent of the costs of Items a, b, and c
above.
To the total of the actual costs and fees allowed hereunder, not more than two
(2) percent shall be added for additional bond and insurance as the cost of Items
d and a above.
For work performed by an approved subcontractor, the Contractor may add to the
total of the actual costs and fixed fees allowed under the preceding paragraph an
additional fixed fee of five (5) percent of said total. No further compensation will be
allowed for the Contractor's administration of the work performed by the
subcontractor.
For work performed by a sub tier -subcontractor, the subcontractor may add to the
total of the actual costs and fixed fees allowed under the preceding paragraph an
additional fixed fee of five (5) percent of said total. No further compensation will be
allowed for the subcontractor's administration of the work performed by the sub tier -
subcontractor. The Contractor may add to the total of the actual costs and fixed fees
allowed under this paragraph an additional fixed fee of five (5) percent of said total.
No further compensation will be allowed for the Contractor's administration of the
work performed by the subcontractor.
The added fixed fees shall be considered to be full compensation, covering the cost
of general supervision, overhead, profit, and any other general expense. The above
fixed fees represent the maximum limits which will be allowed, and they include the
Contractor's and all subcontractors' indirect home office expenses and all costs for
cost proposal preparation and record keeping.
The City reserves the right to furnish such materials and equipment as it deems
expedient, and the Contractor shall have no claim for profit or added fees on the cost
of such materials and equipment.
For equipment under Item c above, rental or equivalent rental cost will be allowed
for only those days or hours during which the equipment is in actual use. Payment
shall be based on actual rental and transportation invoices but shall not exceed the
General Conditions 1400-32
monthly rate in the Rental Rate Blue Book. Owner -operated equipment rates shall
not exceed the monthly rate in the Rental Rate Blue Book plus the labor costs as
provided in Item a. above. The rental cost allowed for equipment will, in all cases,
be understood to cover all fuel, supplies, repairs, ownership, and incidental costs
and no further allowances will be made for those items, unless specific agreement
to that effect is made. For Contractor owned equipment, the rental rate shall be as
listed for such equipment in the California Department of Transportation publication
entitled "Labor Surcharge and Equipment Rental Rates", which is in effect on the
date the work is accomplished. When equipment is not listed in said publication, a
suitable rental rate for such equipment will be established by the City Engineer.
Prior to the commencement of force account work, the Contractor shall notify the
City Engineer of its intent to begin work. Labor, equipment and materials furnished
on force account work shall be recorded daily by the Contractor upon report sheets
furnished by the City Engineer to the Contractor. The reports, if found to be correct,
shall be signed by both the Contractor and City Engineer, or inspector, and a copy
of which shall be furnished to the City Engineer no later than the working day
following the performance of said work. The daily report sheet shall thereafter be
considered the true record of force account work provided.
The Contractor shall maintain its records in such a manner as to provide a clear
distinction between the direct costs of work paid for on a force account basis and
the costs of other operations.
To receive partial payments and final payment for force account work, the Contractor
shall submit, in a manner approved by the City Engineer, detailed and complete
documented verification of the Contractor's and any of its subcontractor's actual
costs involved in the force account pursuant to the pertinent Change Order or Field
Order. Such costs shall be submitted within thirty (30) days after said work has been
performed. No payments will be made for work billed and submitted to the City
Engineer after the thirty (30) day period has expired.
The force account invoice shall itemize the materials used and shall cover the direct
costs of labor and the charges for equipment rental, whether furnished by the
Contractor, subcontractor, or other forces. The invoice shall be in a form acceptable
to the City Engineer and shall provide names or identifications and classifications of
workers, the hourly rate of pay and hours worked, and also the size, type, and
identification number of equipment and hours operated. Material charges shall be
substantiated by valid copies of vendor's invoices.
When both additions and credits are involved in any one change, the combined
overhead and profit shall be figured on the basis of the net increase, if any. The
amount of credit to be allowed by the Contractor to the City for any such change
which results in a net decrease in cost will be the amount of the actual net decrease
and a credit in accordance with the markups allowed under the use of the method
described in this Paragraph. The Contractor shall not claim for anticipated profits on
work that may be omitted.
General Conditions 1400-33
8.4 Time Extensions for Change Orders
If the Contractor requests a time extension for the extra work necessitated by a
proposed Change Order, the request must comply with the applicable requirements
within Section 2000, Special Provisions, Paragraph 4.3 Time Impact Analysis.
9.0 PAYMENT
9.1 Scope of Payment
9.1.1 General - The Contractor shall accept the compensation, as herein provided,
as full payment for furnishing all labor, materials, tools, equipment, and
incidentals necessary for completing the Work according to the Contract
Documents, and no additional compensation will be allowed therefor. Neither
the payment of any partial payment estimate nor of any retained percentage
shall relieve the Contractor of any obligation to make good any defective work
or material.
9.1.2 Payment for Patents and Patent Infringement - All fees or claims for any
patented invention, article, or arrangement that may be used upon, or in, any
manner connected with the performance of the work or any part thereof shall
be included in the price bid for doing the work, and the Contractor and its
sureties shall defend, protect, and hold the City, its consultants, the City
Engineer, together with all their officers, agents, and employees harmless
against liability of any nature or kind for any and all costs, legal expenses,
and damages made for such fees or claims and against any and all suits and
claims brought or made by the holder of any invention or patent, or on account
of any patented or unpatented invention, process, article, or appliance
manufactured for or used in the performance of the Contract, including its use
by the City, unless otherwise specifically stipulated in the Contract. Before
final payment is made on the Contract, the Contractor shall furnish an affidavit
to the City regarding patent rights for the project. The affidavit shall state that
all fees and payments due as a result of the work incorporated into the project
or methods utilized during construction have been paid in full. The Contractor
shall certify in the affidavit that no other fees or claims exist for work in this
project.
9.1.3 Payment of Taxes - The Contractor shall pay and shall assume exclusive
liability for all taxes levied or assessed on or in connection with the
Contractor's performance of this Contract, including, but not limited to, State
and local sales and use taxes, Federal and State payroll taxes or
assessments, and excise taxes, and no separate allowance will be made
therefor, and all costs in connection therewith shall be included in the total
amount of the Contract price.
9.1.4 Payment for Labor and Materials - The Contractor shall pay and require its
subcontractors to pay any and all accounts for labor including worker's
compensation premiums, state unemployment and federal social security
payments and other wage and salary deductions required by law. The
Contractor also shall pay and cause its subcontractors to pay any and all
General Conditions 1400-34
accounts for services, equipment, and materials used by the Contractor and
its subcontractors during the performance of work under this Contract. Such
accounts shall be paid as they become due and payable. If requested by the
City, the Contractor shall furnish proof of payment of such accounts to the
City.
9.2 Partial Payments
In consideration of the faithful performance of the work prosecuted in accordance
with the provisions of these Specifications and the Contract, the City will pay the
Contractor for all such work installed on the basis of percentage completion.
Payments will be made by the City to the Contractor on estimates duly certified and
approved by the City Engineer, based on the value of equipment installed and
tested, labor and materials incorporated into said permanent work by the Contractor
during the preceding month. Payments will not be made for temporary construction
unless specifically provided for in the Contract Documents.
Partial payments will be made monthly based on work accomplished as of a day
mutually agreed to by the City and the Contractor.
The Contractor shall submit his estimate of the work completed during the prior
month and the work completed to date in a format corresponding to the accepted
cost breakdown. The City Engineer shall review the submitted estimate, and upon
approval, the Contractor may submit a detailed invoice for those amounts approved
by the City Engineer.
If requested, the Contractor shall provide such additional data as may be reasonably
required to support the partial payment request. If the City Engineer does not agree
with the Contractor's estimate of amount earned, the partial payment request will be
returned for revision. The City Engineer will be available to meet to discuss the
partial payment request prior to its re -submittal. When the Contractor's estimate of
amount earned conforms with the City Engineer's evaluation, the City Engineer will
calculate the amount due the Contractor, prepare the progress payment request for
signature by the Contractor, and submit the recommended progress payment
request for the City's approval and processing.
Payment will be made by the City to the Contractor in accordance with City's normal
accounts payable procedures; the City shall retain amounts in accordance with
Paragraph 1400-9.4, Right to Withhold Amounts.
No such estimate or payment shall be required to be made, when in the judgement
of the City Engineer, the Work is not proceeding in accordance with the provisions
of the Contract, or when in the City Engineer's judgement, the total value of the Work
done since the last estimate amounts to less than One Thousand Dollars
($1,000.00).
9.3 Partial Payments - Inclusion of Materials on Hand
No payment will be made for materials delivered to the site that are not yet
incorporated into the work.
General Conditions 1400-35
9.4 Right to Withhold Amounts
9.4.1 Retention - The City will deduct from each partial payment and retain as part
security, five (5) percent of the amount earned until the final payment.
Pursuant to Public Contract Code Section 22300, for monies earned by the
Contractor and withheld by the City to ensure the performance of the
Contract, the Contractor, may, at his or her option, choose to substitute
securities meeting the requirements of said Section 22300. In the event the
Contractor desires to choose this option, the Contractor shall enter into an
escrow agreement with the City, and the escrow agent, a qualified bank to be
chosen by City, in the form of the contract included in the project
specifications. The costs of such escrow shall be paid by the Contractor. The
securities to be deposited in said escrow account shall be equivalent, in fair
market value, to the amount to be withheld as performance retention. The
securities shall be held in accordance with the provisions of Public Contract
Code Section 22300, and the implementing contract.
Contractor shall have the obligation of ensuring that such securities deposited
are sufficient so as to maintain, in total fair market value, an amount equal to
the cash amount of the sums to be withheld under the Contract. If, upon
written notice from the City, or from the appropriate escrow agent, indicating
that the fair market value of the securities has dropped below the dollar
amount of monies to be withheld by the City to ensure performance,
Contractor shall, within five days of the date of such notice, post additional
securities as necessary to ensure that the total fair market value of all such
securities held by the City, or in escrow, is equivalent to the amount of money
to be withheld by the City under the Contract.
Any Contractor that desires to exercise this option shall give notice in writing
to City and shall thereafter execute the escrow agreement form provided in
Appendix A of these Specifications.
9.4.2 Other Withholds - In addition to the amount which the City may otherwise
retain under the Contract, the City may withhold a sufficient amount or
amounts of any payment or payments otherwise due the Contractor, as in its
judgement may be necessary to cover:
a. Payments which maybe past due and payable for just claims against the
Contractor or any subcontractor for labor or materials furnished for the
performance of this Contract.
b. For defective work not remedied.
c. For failure of the Contractor to make proper payments to its
subcontractors or suppliers.
d. A reasonable doubt that the Contract can be completed for the balance
then unpaid.
e. Damage to another Contractor or third party, or to property.
General Conditions 1400-36
Failure of the Contractor to keep its work progressing in accordance with
its progress schedule or maintaining current "As -Built" record drawings.
g. The City's costs for the Contractor's failure to complete within the allowed
time.
h. Cost of insurance arranged by the City due to cancellation or reduction of
the Contractor's insurance.
Failure of the Contractor to make proper submissions, as herein specified.
Failure to submit, revise, resubmit, or otherwise conform to the
requirements herein for preparing and maintaining a construction
schedule.
k. Payments due the City from the Contractor.
Reduction of Contract Amount because of modifications.
m. The Contractor's neglect or unsatisfactory prosecution of the work
including failure to clean up.
n. Provisions of law that enable or require the City to withhold such payments
in whole or in part.
When the above reasons for withhold amounts are removed, payment may
be made to the Contractor for amounts withheld. The City in its discretion may
apply any withheld amount or amounts to the payment of valid claims. In so
doing, the City shall be deemed the agent of the Contractor, and any payment
so made by the City shall be considered as a payment made under the
Contract by the City to the Contractor, and the City shall not be liable to the
Contractor for such payment made in good faith. Such payments may be
made without prior judicial determination of the claim or claims. The City will
render to the Contractor a proper accounting of such funds disbursed in
behalf of the Contractor.
9.5 Substantial Completion
When the Contractor considers that the Work is substantially complete, the
Contractor shall notify the City Engineer in writing. Upon receipt of the notification,
the City and/or its authorized representatives will make inspection, to determine if
the Work is sufficiently complete in accordance with the Contract Documents so the
City can occupy or utilize the Work for its intended use. If items are found which
prevent such use or occupancy, the City Engineer shall notify the Contractor in
writing of such items.
Upon the completion of such corrective work, the Contractor shall so notify the City
Engineer in writing. The City Engineer shall inspect the Work to determine its
acceptability for Substantial Completion and for determination of other items which
do not meet the terms of the Contract. Upon verification that the project is
substantially complete the City Engineer shall prepare a Certificate of Substantial
Completion. The Certificate shall establish the date of Substantial Completion and
the responsibilities of the City and Contractor for security, maintenance, heat,
General Conditions 1400-37
utilities, damage to the Work and insurance, and shall fix the time, not to exceed 60
days, within which the Contractor shall finish all items on the punch list
accompanying the Certificate. When the preceding provisions have been approved
by both the City and the Contractor, they shall sign the Certificate to acknowledge
their written acceptance of the responsibilities assigned to them in such Certificate.
By such acknowledgment, the Contractor agrees to pay the City's actual costs
including, but not limited to, charges for engineering, inspection and administration
incurred due to the failure to complete the punch list within the time period provided
in the Certificate of Substantial Completion.
9.6 Final Inspection and Payment
Upon completion of the Work, and upon completion of final cleaning, the Contractor
shall so notify the City Engineer in writing. Upon receipt of the notification, the City
and/or its authorized representatives, will make the final inspection, to determine the
actual status of the Work in accordance with the terms of the Contract. If materials,
equipment, or workmanship are found which do not meet the terms of the Contract,
the City Engineer shall prepare a punch list of such items and submit it to the
Contractor.
Following completion of the corrective work by the Contractor, the City Engineer
shall notify the City that the Work has been completed in accordance with the
Contract. Final determination of the acceptability of the Work shall be made by the
City. After completion of the work, but prior to its acceptance by the City, the last
partial payment will be made to the Contractor in accordance with Paragraph
1400-9.2, Partial Payments.
After receipt of the last partial payment, but prior to acceptance of the Work by the
City, the Contractor shall send a letter to the City Engineer. The letter, pursuant to
California Public Contract Code Section 7100, shall state that acceptance of the final
payment described below shall operate as and shall be, a release to the City, its
consultants, the City Engineer, and their duly authorized agents, from all claim of
and/or liability to the Contract arising by virtue of the Contract related to those
amounts. Disputed Contract claims in stated amounts previously filed as provided in
Paragraph 1400-7.3.2, Claims, may be specifically excluded by the Contractor from
the operation of the release. Following receipt of all required Submittals and the City
Engineer's written statement that construction is complete and recommendation that
the City accept the project, the City will take formal action on acceptance.
Within ten (10) days of the acceptance by the City of the completed work embraced
in the Contract, the City will cause to be recorded in the office of the County Recorder
a Notice of Completion.
After thirty-five (35) days after recording Notice of Completion of the work involved
in the Contract, the City will pay the Contractor in lawful money such sums of money
as may be due the Contractor including all sums retained but excluding such sums
as have previously been paid the Contractor. This payment will constitute the final
payment to the Contractor under this Contract.
General Conditions 1400-38
9.7 Warranty of Title
No material, supplies, or equipment for the work under this Contract shall be
purchased subject to any chattel mortgage, security agreement, or under a
conditional sale or other agreement by which an interest therein or any part thereof
is retained by the seller or supplier. The Contractor warrants good title to all material,
supplies, and equipment installed or incorporated in the work and agrees upon
completion of all work to deliver the premises, together with all improvements and
appurtenances constructed or placed thereon by the Contractor, free from any claim,
liens, security interest, or charges, and further agrees that neither the Contractor nor
any person, firm, or corporation furnishing any materials or labor for any work
covered by this Contract shall have any right to a lien upon the premises or any
improvement or appurtenances thereon.
**END OF SECTION**
General Conditions 1400-39
SECTION 1500
SUPPLEMENTAL GENERAL CONDITIONS
1.0 CITY ENGINEER
The City Engineer for the City of La Quinta is:
Bryan McKinney, P.E.
Public Works Director/City Engineer
78-495 Calle Tampico
La Quinta, CA 92253
Phone: (760) 777-7045
2.0 CONSULTANTS
2.1 Design Engineer
Chris Hermann, R.L.A
Chris Hermann Design Group, Inc.
77-899 Wolf Road, Suite 102
Palm Desert, CA 92211
Phone: (760) 777-9131
Fax: (760) 777-9132
Email: chris(a)hdg-inc.com
2.2 Materials Testing
Materials testing for this project will be provided by the City. The City inspector will notify
the Contractor when materials will be tested. However, testing may be random as
determined by City.
2.3 Survey
Not applicable. If survey is needed for this project it will be provided by the City.
The Contractor's requests for surveying shall be made to the Engineer a minimum of forty-
eight (48) hours prior to the time requested for said work. All requests for survey work shall
be approved by the City prior to issue of survey request.
If construction staking is provided and subsequently removed whether accidentally or
otherwise, or the contractor desires additional staking from the above sets, the Contractor
will be charged for re -staking at a fee of $245.00 per hour (4 -hour minimum).
3.0 LIQUIDATED DAMAGES
It is agreed by the parties to the Contract that time is of the essence; and that in the case
all work is not completed before or upon the expiration of the time limit set forth within
Section 1300 Contract; Subsection 4, damage will be sustained by the City and it is,
therefore, agreed that the Contractor will pay to the City an amount of $2,000 per calendar
day minimum. The damages described above will be deducted from any money due the
Contractor under this Contract; the Contractor and his sureties shall be liable for any such
excess cost.
Supplemental General Conditions 1500-1
The Contractor shall not be deemed in breach of its Contract and no forfeiture due to delay
shall be made because of any delays in the completion of the work due to unforeseeable
causes beyond the control and without the fault or negligence of the Contractor, provided
the Contractor requests an extension of time in accordance with the procedures set forth in
Section 3 of the Standard Specifications. Unforeseeable causes of delay beyond the
control of the Contractor shall include acts of God, acts of a public enemy, acts of the
government, or acts of another contractor in the performance of a contract with the City,
fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, weather, or
delays caused by failure of the City or the owner of a utility to provide for removal or
relocation of existing utility facilities. Delays caused by actions or neglect of the Contractor,
its agents, employees, officers, subcontractors, or suppliers shall not be excusable.
Excusable delays (those beyond Contractor's control) shall not entitle the Contractor to any
additional compensation. The sole remedy of the Contractor shall be to seek an extension
of contract time.
4.0 SUBMITTALS
Definitions
A. Shop Drawings, Product Data and Samples: Instruments prepared and
submitted by Contractor, for Contractor's benefit, to communicate to
Engineer the Contractor's understanding of the design intent, for review
and comment by Engineer on the conformance of the submitted
information to the general intent of the design. Shop drawings, product
data and samples are not Contract Documents.
B. Shop Drawings: Drawings, diagrams, schedules and illustrations, with
related notes, specially prepared for the Work of the Contract, to
illustrate a portion of the Work.
C. Product Data: Standard published information ("catalog cuts") and
specially prepared data for the Work of the Contract, including standard
illustrations, schedules, brochures, diagrams, performance charts,
instructions and other information to illustrate a portion of the Work.
D. Samples: Physical examples that demonstrate the materials, finishes,
features, workmanship and other characteristics of a portion of the
Work. Accepted samples shall serve as quality basis for evaluating the
Work.
E. Other Submittals: Technical data, test reports, calculations, surveys,
certifications, special warranties and guarantees, operation and
maintenance data, extra stock and other submitted information and
products shall also not be considered to Contract Documents but shall
be information from Contractor to Engineer to illustrate a potion of the
Work for confirmation of understanding of design intent.
Supplemental General Conditions 1500-2
2. Review of Submittals
A. Submittals shall be a communication aid between Contractor and the
Engineer by which interpretation of Contract Documents requirements
may be confirmed in advance of construction.
1. Reviews by Engineer and other design professionals shall be
only for general conformance with the design concept of the
Project and general compliance with the Drawings and
Specifications.
2. Engineer will review submittals as originally submitted and the
first resubmission. Costs for additional reviews shall be
reimbursed by Contractor to Owner by deductive Change Order.
3. All submittals shall be approved by the Engineer and/or City
prior to installation
3. Required Submittals (May include but are not limited to):
A. Milestone Schedule
B. Traffic Control
C. CPM Schedule
D. Boulder, Cobble, Decomposed Granite
E. Plants, Shrub, and Tree nursery visit for approval by the City per
Sub -Section 800 of Section 4000. If the City is unable to attend a
nursery visit, the Contractor shall submit plant photos.
F. Irrigation Components
G. Soil Samples
H. Concrete
I. Court Surfacing
J. Keystone Block
K. Header -board
L. Lights
M. Electrical Components
**END OF SECTION**
Supplemental General Conditions 1500-3
SECTION 2000
DIVISION 2 - GENERAL PROJECT REQUIREMENTS
1.0 STANDARD SPECIFICATIONS
The "Standard Specifications" of the City of La Quinta are contained in the latest edition
of the Standard Specifications for Public Works Construction, including all supplements,
popularly known as the Green Book, as written and promulgated by the Joint Cooperative
Committee of the Southern California Chapter of the American Public Works Association
and the Southern California District of the Associated General Contractors of California.
Copies of the Standard Specifications are available from the publisher, Building News Inc.,
as follows:
Bookstore Locations: see website for Southern California locations
Website: www.bnibooks.com
The Standard Specifications shall prevail in all cases except where a Contract Document of
a higher order, as defined in Section 1400-1.2 Discrepancies and Omissions, provides a
different requirement on a given topic or topic aspect. All language in the Standard
Specifications that is not in conflict with the language in the prevailing Contract Documents
on a given topic or topic aspect shall remain in full force and effect, unless the language in
the prevailing Contract Document specifically cites the section number in the Standard
Specification and says said provision is in lieu that Standard Specification section.
1.1 Alternative Specifications — The Standard Specifications shall apply to this project
unless specifically referenced otherwise in the Contract Documents. Wherever
"State Standard Specifications" are referenced, it shall mean the Standard
Specifications, 2018, edition, published by the State of California Department of
Transportation, and wherever the "State Standard Plans" are referenced in the
Contract Documents, it shall mean the Standard Plans, 2018, edition, published by the
State of California Department of Transportation.
The Contractor may request bound copies of these documents from Caltrans at:
California Department of Transportation
Publication Distribution Unit
1900 Royal Oaks Drive
Sacramento, CA 95815-3800
(916) 263-0822, (916) 263-0865
Or, download these documents at no cost from the Caltrans website:
https:Hdot.ca.gov/programs/design/ccs-standard-plans-and-standard-specifications
Wherever the State Standard Specifications reference, Section 4-1.03d "Extra
Work," it shall mean Paragraph 1400-7.0 Changes in the Scope of Work of
these project Specifications.
2.0 STANDARD PLANS
The Standard Plans of the City of La Quinta adopted by the City Council on August 21,
General Project Requirements 2000-1
2001, shall apply to this project unless specifically stated otherwise in the Contract
Documents.
2.1 Alternative Guidance
2.1.1 California Manual on Uniform Traffic Control Devices (CA MUTCD)
The Standard Plans shall apply to this project unless specifically referenced
otherwise in the Contract Documents. Wherever "CA MUTCD" is referenced, it shall
mean the 2014 edition of the California Manual on Uniform Traffic Control Devices,
published by the State of California.
The Contractor may download these documents at no cost from the Caltrans
website:
https://dot.ca.gov/programs/safety-programs/camutcd
2.1.2 California Building Code, Part 2 (CBC)
The Contractor may download these documents at no cost from the California
Building Standards Commission website:
https://www.dgs.ca.gov/BSC/Codes
2.1.3 California Electrical Code, Part 3 (CBC)
The Contractor may download these documents at no cost from the California
Building Standards Commission website:
https://www.dgs.ca.gov/BSC/Codes
3.0 PRE -CONSTRUCTION CONFERENCE
3.1 Attendees
The City and its consultants, and the Contractor and its superintendent, invited
subcontractors, and other concerned parties shall each be represented at the
conference by persons familiar with and authorized to conclude matters relating to
the work.
3.2 Agenda
The City Engineer will prepare an agenda for discussion of significant items relative
to contract requirements, procedures, coordination and construction.
4.0 PROGRESS SCHEDULES
4.1 General
Prior to commencing work, the Contractor shall provide a Construction Schedule
and Cash Flow Projection. During the course of construction, the Contractor shall
provide a Weekly Activities Plan.
4.2 Construction Schedule
4.2.1 A milestone schedule shall be submitted concurrently with the execution of the
Contract in Section 1300. Contractor shall pay to City $500.00 liquidated damages
General Project Requirements 2000-2
per calendar day that the Milestone Schedule is not provided.
4.2.2 The Contractor shall submit the milestone schedule based on major orders of work
and how they relate to traffic control and lane closures. The schedule shall be time
scaled and shall be drafted to show a continuous flow from left to right. The milestone
schedule shall clearly show the sequence of construction operations and specifically
list:
a. The start and completion dates of all major phases of work.
b. The dates of submittals, procurement, delivery, installation and completion of
each major equipment and material requirement.
C. Progress milestone events or other significant stages of completion.
d. The lead time required for starting construction.
e. The major impacts to traffic flow.
The detailed construction schedule shall be submitted within five (5) days of Notice
to Proceed and accepted by the City Engineer before the first partial payment can
be made.
4.2.2.1 The Contractor shall submit the detailed construction schedule based on the Critical
Path Method (CPM). The schedule shall indicate preceding activity relationships
and/or restraints where applicable and a controlling path shall be indicated. The
schedule shall be time scaled and shall be drafted to show a continuous flow from
left to right. The construction schedule shall clearly show the sequence of
construction operations and specifically list:
a. The start and completion dates of all work items.
b. The dates of submittals, procurement, delivery, installation and completion of
each major equipment and material requirement.
C. Progress milestone events or other significant stages of completion.
d. The lead time required for testing, inspection and other procedures required
prior to acceptance of the work.
Activities shall be no longer than 10 workdays, except for submittals and delivery
items. If an activity takes longer, it shall be broken into appropriate segments of
work for measurement of progress. This limitation may be waived, upon approval of
the City Engineer, for repetitious activities of longer durations for which progress
can be easily monitored.
4.2.2.2 Any activity that cannot be completed by its original completion date shall be
considered to be "behind schedule."
4.2.2.3 At not less than monthly intervals and when requested by the City Engineer, the
Contractor shall submit a revised schedule for all work remaining. If, at any time,
the City Engineer considers the project completion date to be in jeopardy because
of activities "behind schedule," the Contractor shall submit additional schedules and
diagrams indicating how the Contractor intends to accomplish the remaining work
to meet the Contract completion date.
General Project Requirements 2000-3
4.2.2.4 All change orders, regardless of origin, shall be reflected in the schedule.
4.3 Time Impact Analysis
4.3.1 When change orders are initiated, delays are experienced, or the Contractor desires
to revise the schedule logic, the Contractor shall submit to the City Engineer a written
Time Impact Analysis illustrating the influence of each change, delay, or Contractor
request on the current contract schedule completion date.
4.4 Weekly Activities Plan
On the last working day of every week the Contractor shall submit to the City
Engineer the Contractor's Plan of Activities for the following two weeks. The Plan of
Activities shall describe the activity and location of the activity.
4.5 Cash Flow Prosection
A cash flow projection shall be submitted with the Construction Schedule. This cash
flow projection shall be revised and resubmitted when revisions of the Construction
Schedule will result in changes to the projected cash flow.
4.6 Lump Sum Price Breakdown
For work to be performed for a lump sum price, the Contractor shall submit a price
breakdown to the City Engineer prior to the first payment and within twenty (20)
calendar days after award of the Contract. The price breakdown, as agreed upon by
the Contractor and the City Engineer, shall be used for preparing future estimates
for partial payments to the Contractor, and shall list the major items of work with a
price fairly apportioned to each item.
Mobilization, overhead, bond, insurance, other general costs and profit shall be
prorated to each item so that the total of the prices for all items equal the lump sum
price. At the discretion of the City Engineer, mobilization, bond and insurance costs
may be provided for separately if accompanied by invoices to verify actual
expenses.
The price breakdown will be subject to the approval of the City Engineer, and upon
request, the Contractor shall substantiate the price for any or all items and provide
additional level of detail, including quantities of work. The price breakdown shall be
sufficiently detailed to permit its use by the City Engineer as one of the bases for
evaluating requests for payments. The City Engineer shall be the sole judge of the
adequacy of the price breakdown.
5.0 SPECIAL CONTROLS
The Contractor shall take all reasonable means to minimize inconvenience and injury to the
public by dust, noise, diversion of storm water, or other operations under its control.
5.1 Dust Control
The Contractor at its expense shall take whatever steps, procedures, or means as
are required to comply with Section 3000-4.2 and prevent abnormal dust conditions
being caused by its operations in connection with the execution of the Work.
General Project Requirements 2000-4
5.2 Noise Abatement
Operations shall be performed so as to minimize unnecessary noise. Special
measures shall be taken to suppress noise during night hours. Noise levels due to
construction activity shall not exceed the levels specified by local ordinance.
Internal combustion engines used on the Work shall be equipped with a muffler of a
type recommended by the manufacturer. No internal combustion engine shall be
operated without said muffler.
5.3 Working Hours
Construction operations and maintenance of equipment within one half mile of
human occupancy shall be performed only during the time periods as follows, unless
otherwise approved by the City:
Monday - Friday 8:00 AM to 5:30 P.M.
The Contractor shall be responsible for any inspection and additional administration
costs incurred by the City for work by the Contractor after the hours defined above
on weekdays, or any work on weekends or holidays recognized by the City. Such
costs shall be withheld from the succeeding monthly progress payment. Any work in
Section 3000, SPECIFIC PROJECT REQUIREMENTS, specifically required to be
performed outside the normal working hours are excluded from the provisions of this
paragraph.
5.4 Drainage Control
In all construction operations, care shall be taken not to disturb the existing drainage
pattern whenever possible. Particular care shall be taken not to direct drainage
water onto private property. Drainage water shall not be diverted to streets or
drainage ways inadequate for the increased flow. Drainage means shall be provided
to protect the Work and adjacent facilities from damage to water from the site or due
to altered drainage patterns from construction operations.
Contractor shall provide, 48 hours in advance of a significant forecast of any likely
precipitation rainfall event of 0.5 inches or more, a Rainfall Event Action Plan
(REAP) specific for that event which, when implemented, is designed to protect all
expose construction portions of the site.
Temporary provisions shall be made by the Contractor to insure the proper
functioning of gutters, storm drain inlets, drainage ditches, culverts, irrigation
ditches, and natural water courses.
5.5 Construction Cleaning
The Contractor shall, at all times, keep property on which work is in progress and
the adjacent property free from accumulations of waste material or rubbish caused
by employees or by the work. All surplus material shall be removed from the site
immediately after completion of the work causing the surplus materials. Upon
completion of the construction, the Contractor shall remove all temporary structures,
rubbish, and waste materials resulting from his operations.
General Project Requirements 2000-5
5.6 Disposal of Material
The Contractor shall make arrangements for disposing of materials outside the right-
of-way and the Contractor shall pay all costs involved. The Contractor shall first
obtain permission from the property owner on whose property the disposal is to be
made and absolve the City from any and all responsibility in connection with the
disposal of material on said property. When material is disposed of as above
provided, the Contractor shall conform to all required codes pertaining to grading,
hauling, and filling of earth.
5.7 Parking and Storage Areas
All stockpiled materials and parked equipment at the job site shall be located to
avoid interference with private property and to prevent hazards to the public.
Locations of stockpiles, parking areas, and equipment storage must be approved by
the City Engineer.
6.0 PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS AND
PUBLIC
The Contractor shall be responsible for the protection of public and private property at and
adjacent to the Work and shall exercise due caution to avoid damage to such property,
persons, or public in general. Contractor shall install fencing, open trench signs, cones, or
other protective devices as directed by the City. Site protection shall be to the satisfaction
of the City Engineer.
The Contractor shall repair or replace all existing improvements within the
right-of-way, which are not designated for removal (e.g., electrical, lighting, curbs,
sidewalks, survey points, fences, walls, signs, utility installations, pavements,
structures, etc.) which are damaged or removed as a result of its operations.
Repairs and replacements shall be at least equal to existing improvements and shall
match them in finish and dimension.
Trees, lawns, and shrubbery that are not to be removed shall be protected from damage or
injury. If damaged or removed because of the Contractor's operations, they shall be
restored or replaced in as nearly the original conditions and location as is reasonably
possible. Lawns shall be covered with sod seeded to the applicable season, to the
satisfaction of City.
The Contractor shall give reasonable notice to occupants or owners of adjacent property to
permit them to salvage or relocate plants, trees, fences, irrigation, sprinklers, and other
improvements within the right-of-way which are designated for removal and would be
destroyed because of the work.
7.0 EXISTING UTILITIES
7.1 General
Some existing utilities are shown on the drawings; however, the Contractor is
responsible to verify exact location of all utilities prior to the start of construction.
Pursuant to Government Code Section 4216, et. seq., the Contractor shall notify the
appropriate required notification center. The notification center for La Quinta can be
General Project Requirements 2000-6
reached by contacting UNDERGROUND SERVICE ALERT (USA) at 1-800-422-
4133 or dial 811. USA member utilities will provide the Contractor with the precise
locations of their substructures in the construction area when the Contractor gives at
least 48 hours of notice.
7.2 Notification and Location
At least two (2) working days before performing any excavation work, the Contractor
shall request the utility owners to mark or otherwise indicate the location of their
service.
It shall be the Contractor's responsibility to determine the exact location and depth of
all utilities, including service connections, which have been marked by the
respective owners and which he believes may affect or be affected by his
operations. If no pay item is provided in the Contract for this work, full compensation
for such work shall be considered as included in the prices bid for other items of
work.
The Contractor shall notify the following agencies at least 48 hours in advance of
excavating around any of their structures. The following utility companies provide
service to the La Quinta area and can be contacted via the USA telephone number
or the number list below.
1. Southern California Gas Company, (909) 335-7851
2. Imperial Irrigation District, (760) 398-5823
3. Frontier Communications, (760) 778-3621
4. Coachella Valley Water District, (760) 398-2651
5. Spectrum, (760) 674-5451
7.3 Damage and Protection
The Contractor shall immediately notify the City Engineer and utility owner of any
damage to a utility.
7.4 Utility Relocation and Rearrangement
The right is reserved to the City and the owners of utilities or their authorized agents
to enter upon the Work area for the purpose of making such changes as are
necessary for the rearrangement of their facilities or for making necessary
connections or repairs to their properties. The Contractor shall cooperate with forces
engaged in such work and shall conduct his operations in such a manner as to avoid
any unnecessary delay or hindrance to the work being performed by such forces
and shall allow the respective utilities time to relocate their facility.
The Contractor assumes responsibility for the removal, relocation, or protection of
existing facilities wherein said facilities are identified by the Plans, field located by a
utility company, or as provided for in the General Requirements. The Contractor
shall coordinate with the owner of utility facilities for the rearrangement of said
facilities.
In the event that underground utilities are found that are not shown in the Contract
Documents or are found to exist in a different location than shown in the Contract
Documents, the Contractor shall: (1) notify the City Engineer of the existence of said
General Project Requirements 2000-7
facilities immediately; and (2) take steps to ascertain the exact location of all
underground facilities prior to doing work that may damage such facilities.
Requests for extensions of time arising out of utility rearrangement delays shall be
determined by City Engineer. In accordance with Government Code Section 4215
the Contractor shall not be assessed liquidated damages for delay in completion of
the project, when such delay is caused by the failure of the City or utility company to
provide for the removal or relocation of facilities for which they are the responsible
party as defined in Paragraph 2000-7.3, Damage and Protection.
Where it is determined by the City Engineer that the rearrangement of an
underground main, the existence of which is not shown on the Plans, Specifications,
or in the General Requirements, is essential in order to accommodate the
contemplated improvement, the City Engineer will provide for the rearrangement of
such facility by other forces or by the Contractor in accordance with the provisions of
Paragraph 1400-7.1, Change Orders.
When the General Requirements, Specifications, or Plans indicate that a utility is to
be relocated, altered or constructed by others, the City will conduct all negotiations
with the utility company and the work will be done at no cost to the Contractor.
Temporary or permanent relocation or alteration of utilities desired by the Contractor
for its own convenience shall be the Contractor's responsibility and it shall make
arrangements and bear all costs.
7.5 Underground Facilities
The Contractor is responsible for coordinating all project documentation, including
but not necessarily limited to, the Contract Documents and existing record drawings
for the determination of the location of all underground facilities.
The Contractor shall exercise care in all excavations to avoid damage to existing
underground facilities. This shall include potholing or hand digging in those areas
where underground facilities are known to exist until they have been sufficiently
located to avoid damage to the facilities.
Prior to fabrication, the Contractor shall verify the location and elevations of existing
underground facilities, which the Contractor is connecting to.
No additional compensation shall be provided the Contractor for compliance with the
provisions of this section or for the damage and repair of facilities due to the lack of
such care.
The California Public Utilities Commission mandates that, in the interest of public
safety, main line gas valves be maintained in a manner to be readily accessible and
in good operating condition. The Contractor shall notify The Gas Company's
Headquarters Planning Office at least 2 working days prior to the start of
construction.
**END OF SECTION**
General Project Requirements 2000-8
SECTION 3000
DIVISION 3 SPECIAL PROVISIONS
1.0 GENERAL
1.1 Scope of Services
It shall be the contractor's responsibility to provide and furnish all materials, tools,
labor and incidentals to complete the work as outlined in the Project Description and
as shown in the Project Specifications and Contract Bid Documents for 2016-031, La
Quinta Landscape Renovation Improvement — Cactus Flower.
It shall be the Contractor's responsibility to thoroughly review the project area,
familiarize himself with the scope of proposed work and submit the proposal for the
work accordingly.
1.2 Project Description
The project consists of removing designated turf and plant material and
sidewalk reconstruction along the parkway and street entrances at the Cactus
Flower Development along the southside of Fred Waring Drive generally from
Dune Palms Road to Monticello Avenue and on the east side of Dune Palms from
Star Flower Trail to Fred Waring Drive. Work will also take place at the three
retention basins within the Development. Additionally, on the east side of
Jefferson Street south of Avenue 50 to 665 feet south of Avenue 50. Turf will be
replaced with drought -tolerant landscaping and irrigation. The plant palette shall
include Cresta rubble, multi -colored crushed rock, and Baja Cresta' boulders of
varying sizes with minimal use of drought -tolerant plants and re -use of
designated existing plant material. In addition, the existing perimeter wall shall
be cleaned, and construction of keystone block wall at various locations. Existing
lighting and electrical shall be modified and new lighting shall be furnished and
installed. An additive alternate includes the construction of pickleball courts with
site amenities. All project work and incidental items to complete the project
shall be performed in accordance with the plans, specifications, and other
provisions of the contract. All the above improvements are to be constructed in
a workmanlike manner, leaving the entire project in a neat and presentable
condition. Refer to Section 4000 for more information.
1.3 Project Plans
The area of work is shown on the attached plans titled "Project No. 2016-031, La
Quinta Landscape Renovation Improvement — Cactus Flower". The plan set
consists of 35 sheets.
Contractor shall examine all maps, lists and these specifications, in a manner to be
fully cognizant of all work required, and all existing conditions. Bidders are required
to visit the site and verify existing conditions. Make adjustments and allowances for
all necessary equipment to complete all parts of the required work.
Special Provisions 3000-1
1.4 Drawings of Record
Provide and keep up-to-date, a complete record set of blue line prints. Correct
these prints daily and show every change from the original drawings. Keep this set
of prints on the job site and use only as a record set.
Do not construe this as authorization to make changes in the layout without definite
instruction in each case. Incorporate all changes as noted on the record set of prints
thereon with black ink in a neat, legible, understandable and professional manner.
Deliver this set to the City upon completion and acceptance of work.
1.5 Cooperation with Other Contractors
Section 7-7 of the Standard Specifications is amended by the addition of the
following provisions:
Should the Contractor foresee any interference or believe project delays or
problems might occur due to any action of any other contractor, or if the Contractor
determines his own work may cause a delay to the work of the other contractors, the
Contractor shall bring this to the attention of the Engineer as soon as possible so
that the potential problems or delays may be worked out before problems arise. It is
the intention of these Specifications that the Contractor shall cooperate as needed
to affect this purpose, and shall be prepared to make short delays, to redeploy its
work force to other parts of the work or project, to temporarily reschedule work, and
take other reasonable actions to minimize interference and maximize cooperation
with all other parties working within the project area.
If the Contractor maintains that he is unable to reasonably cooperate with others,
then the Contractor shall be prepared to verify to the satisfaction of the Engineer
that there are no reasonable actions which he could take to cooperate with others,
and that if he did, such actions would cause serious financial harm or unreasonable
delay to the Contractor. If the Engineer finds that such evidence is unsatisfactory,
the Engineer may order the Contractor to take whatever reasonable actions the
Engineer determines are necessary to provide the needed cooperation in order to
meet the intent of these Specifications.
The contractor shall have no claim for extra compensation for any delay or costs if
his work is held up, delayed or interrupted by the City's having to order cooperative
work measures or schedule priorities as outlined above. An extension of contract
time shall be the only compensation granted.
1.6 Time Allowed for Construction
In accordance with the provisions of Paragraph 1400-6.2, Time of Completion, this
project shall be completed within 60 working days from the date specified in the
Notice to Proceed.
2.0 BID ITEMS
The bid items presented in the bidders schedule are intended to indicate major
categories of the work for purposes of comparative bid analysis and payment
breakdown for monthly progress payments. Bid items are not intended to be
Special Provisions 3000-2
exclusive descriptions of work categories. The Contractor shall determine and
include in its pricing, all materials, labor, and equipment necessary to complete each
bid item associated appurtenant work.
Those items for which there is no estimated quantity and/or specific pay item shall
be completed in workmanship like manner to the satisfaction of the City Engineer.
Work that is specified for which there is no bid item shall be considered incidental to
work associated with bid items; therefore, the payment for these items shall be
considered included in the various items of work for which a specific bid item has
been provided.
The bid items shown in the bidder's schedule with "F" designates a final pay
quantity. Quantity of any bid item in excess of the final pay quantity shown on the
bidder's schedule estimated by the City Engineer will not be paid for. The final pay
quantity can only be adjusted to reflect any change orders, extra work, or additional
work authorized by the City Engineer.
3.0 MATERIALS
3.1 General
Whenever a material, article or piece of equipment is identified on the drawings or
specified by reference to brand name or catalog number, it shall be understood that
this is referenced for the purpose of defining the performance or other salient
requirements and that other products of equal capacities, quality and function shall
be considered.
3.2 Substitutions
The Contractor may recommend the substitution of a material, article, or piece of
equipment of equal substance and function for those referred to in the Contract
Documents by reference to the brand name or catalog number and, if in the opinion
of the City Engineer, such material, article, or piece of equipment is of equal
substance and function to that specified, the City Engineer may approve its
substitution and use by the Contractor. Any cost differential shall be deductible from
the Contract Price and the Contract Documents shall be appropriately modified by
Change Order. The Contractor warrants that if substitutes are approved, no major
changes in the function or general design of the project will result. Incidental
changes or extra component parts required to accommodate substitute will be made
by the Contractor without a change in the Contract Price or Contract time.
3.3 Storage
Materials and equipment shall be so stored as not to create a public nuisance and to
insure the preservation of their quality and fitness for the work.
4.0 WORK DETAILS
4.1 Traffic Control
The Contractor shall provide a traffic control plan, signed by a PE or TE, for
acceptance by the City no later than five (5) working days after issuance of the
Special Provisions 3000-3
Notice of Award. Subsequently, comments and corrections shall be returned to the
Contractor within ten (10) working days. The traffic control plan shall conform to the
following requirements listed in this section:
Traffic controls, including but not limited to, vehicular and pedestrian traffic controls,
maintenance of vehicular and pedestrian access, detours, and street closures shall
be in accordance with Subsection 7-10 of the latest edition of the "Standard
Specifications for Public Works Construction," including all its subsequent
amendments and the latest edition of the "Work Area Traffic Control Handbook."
In the event of conflict, the Special Provisions shall take precedence over the 2014
CAMUTCD. The 2014 CAMUTCD shall take precedence over the plans, and the
plans shall take precedence over the "Standard Specifications."
Traffic control and the traffic plan shall conform to the following:
a. The traffic control plan shall indicate the traffic control requirements
for the different types of work to be performed. The Contractor shall
be responsible for the preparation of plans as necessary for specific
items of work. These plans shall be approved by the City Engineer
prior to the Contractor commencing any work.
b. All traffic controls and safety devices, equipment and materials,
including but not limited to, cones, delineators, flashing warning lights,
barricades, high level warning devices (flag trees), flags, signs,
makers, portable barriers, flashing arrow signs, electronic changeable
message signs and markings shall be provided and maintained in "like
new" condition.
C. The Contractor shall furnish and properly install, construct, erect, use,
and continuously inspect and maintain, twenty-four (24) hours per
day, seven (7) days a week, all said devices, equipment and materials
and all temporary and permanent pedestrian and driving surfaces as
necessary to provide for the safety and convenience of, and to
properly warn, guide, control, regulate, channelize, and protect the
vehicular traffic, pedestrian traffic, project workers, and the public
throughout the entire limits of the work activity and beyond said limits
as necessary to include area affecting or affected by the work, from
the start of work to the completion of the work.
d. High-level warning devices (flag trees) are required at all times for any
work being performed within the roadway unless otherwise specifically
authorized by the City Engineer.
e. All barricades shall be equipped with flashing warning lights, and all
traffic cones shall be no less than twenty-eight (28) inches in height,
except that shorter cones, twelve (12) inches high or higher, may be
used during striping maintenance operations where the only function
of the cones is to protect the wet paint from the traffic.
Special Provisions 3000-4
f. Portable Changeable Message Signs (PCMS) are required for this
project. A minimum of one (1) PCMS is required in each direction
in advance of each work area as identified by the City. They shall
be placed two (2) weeks in advance of the start of work and
maintained throughout the construction window. Total count is
dependent on Contractor's proposed staging plan. A PCMS can
be reused at a different location once the work is complete in
that stage.
g. Except as otherwise directed, as shown in the approved traffic control
plan, and/or authorized by the City Engineer, two-way vehicular traffic
shall be maintained at all times within a minimum of two, 12 -foot -wide
lanes. At no time shall the Contractor be allowed to reduce the
traveled way to one-way vehicular traffic.
No reduction of the traveled way width shall be permitted between the
hours of 8:30 a.m. and 3:30 p.m., unless otherwise shown in the
approved traffic control plans, or prior authorization to do so is granted
by the City Engineer. No lane closures shall be permitted or allowed
on any City street before 8:30 a.m. and after 3:30 p.m., unless
otherwise shown in the approved traffic control plans, or unless
authorization to do so is granted by the City Engineer. No reduction of
traveled way width shall be permitted on any City street before 8:30
a.m. or after 3:30 p.m., on weekends or holidays, or when active work
is not being done, unless otherwise shown in the approved traffic
control plans, or unless prior authorization to do so is granted by the
City Engineer.
Except as shown in the approved traffic control plans, if traffic lanes
are not kept open for public use on the days, at the times, and in the
manner specified, damage will be sustained by the City and its
residents. Since it is and will be impracticable to determine the
actual damage which the City and its residents will sustain by
reason of Contractor's failure to comply with the special
provisions outlined herein, the City and Contractor agree that
Contractor will pay to the City the sum of $200 per hour for each
and every hour that any traffic lane is not kept open for public
use as required by these special provisions, not as a penalty, but
as predetermined liquidated damages. The Contractor agrees to
pay such liquidated damages as are provided for in this paragraph,
and in case the same are not paid, Contractor agrees that City may
deduct the amount of such liquidated damages from any money that is
due or that may be due the Contractor under the contract.
h. Access to vacant unused property may be restricted at the Engineer's
discretion. Both vehicular and pedestrian access shall be maintained
at all times to all other property except as otherwise specifically
authorized in writing by the City Engineer.
Special Provisions 3000-5
Any traffic control and safety devices and equipment being used
which becomes damaged, destroyed, faded, soiled, misplaced, worn
out, inoperative, lost, or stolen shall be promptly repaired, refurbished
and/or replaced, and any traffic control and safety devices and
equipment being used which are displaced or not in an upright
position from any cause, shall be properly returned or restored to their
proper position.
Any obstructed view of all signs and warning devices including but not
limited to stop signs, stop ahead signs, street name signs, and other
regulatory, warning and construction signs, markers, and warning
devices shall be maintained at all times. No trucks or other equipment
or materials shall be stopped, parked, or otherwise placed so as to
obscure said signs, markers and devices from the view of vehicular
and/or pedestrian traffic to which it applies.
k. When entering or leaving roadways carrying public traffic, the
Contractor's equipment, whether empty or loaded, shall yield to said
public traffic at all times, except where the traffic is being controlled by
police officers, fire officers or traffic signalized intersections.
Stockpiling and/or storage of materials on any public right-of-way or
parking areas will not be allowed without specific permission of the
City Engineer. Materials spilled on or along said right-of-way or
parking areas shall be kept in a safe, neat, clean, and orderly fashion,
and shall be restored to equal or better than original condition upon
completion of the work.
m. When work has been completed on a particular street or has been
suspended or rescheduled, and said street is to be opened to
vehicular traffic, all equipment, "NO PARKING" signs, other
obstruction, and necessary traffic control devices and equipment shall
be promptly removed from that street except as otherwise authorized
or directed by the City Engineer.
n. Should the Contractor be neglectful, negligent, or refuse, fail, or
otherwise be unavailable to promptly, satisfactorily, and fully comply
with the provisions specified and referred to herein above, the City
reserves the right to correct and/or mitigate any situation, which in the
sole opinion of the City's Engineer constitutes a serious deficiency
and/or serious case of noncompliance, by any means at its disposal at
the Contractor's and/or permittee's expense, and will deduct the cost
therefore from the Contractor's progress and/or final payments. Such
corrective action taken by the City shall not reduce or abrogate the
Contractor's legal obligations and liability for proper traffic control and
safety measures and shall not serve to transfer said obligations and
liabilities from the Contractor to the City or the City's agents.
Special Provisions 3000-6
o. Violations of any of the above provisions and/or provisions of the
referenced publications, unless promptly and completely corrected to
the satisfaction of the City Engineer, shall, at the sole discretion of the
City, be grounds for termination of the Contract, or shutdown or partial
shutdown of the work, without compensation to the Contractor and/or
permittee, or liability to the City, all as prescribed by contractual
obligation or State law, whichever is applicable.
P. The Contract item "Traffic Control" shall include labor lights,
barricades, signs, materials, fencing, and equipment necessary to
ensure that the vehicular traffic conforms to requirements as set forth
in this section and as shown on the drawings.
q. The compensation for furnishing, placing, maintaining and removing
traffic cones, telescoping tree flags, advance warning signs, electronic
changeable message signs, barricades, temporary striping, and other
safety devices as required for public safety or as directed by the City
Engineer, shall be considered full compensation for all labor and
materials for complying with these requirements, and no additional
compensation will be made therefore.
4.2 Dust Control
The Contractor must comply with the City of La Quinta's Municipal Code, Chapter
6.16, "Fugitive Dust Control" Ordinance. Dust generated by traffic, Contractor's
operations, or wind are all included in the definition of dust. The Contractor will be
responsible for watering the work area where dust is generated from traffic,
contractor's operations and wind. Contractor's area of operations includes areas
outside of roadbed or trench limits where excavation, fill, or stockpiling of dirt or
debris has taken place. The Contractor is responsible for monitoring all of the
above-described areas in the project area during the life of the project, including
holidays and weekends.
The Contractor shall prepare for review and approval by the City, the required
PM -10 plan. The plan shall be prepared in accordance with South Coast Air Quality
Management District guidelines. The Contractor shall have a designated person
Certified by the SCAQMD to prepare the PM -10 plan and oversee the approved
dust control measures. Dust control shall include, but is not limited to the
following:
1) Maintain dust control at all times by watering, including developing a
water supply, and furnishing and placing all water required for work done
in the contract.
2) Provide means to prevent track out onto public streets.
3) Provide street sweeping of material tracked onto public streets.
Special Provisions 3000-7
4.3 Water
The Contractor shall make arrangements with the Coachella Valley Water District to
obtain water from designated fire hydrants at or near the project for use in dust
control. It shall be the responsibility of the contractor to pay for the water and any
deposits required. The cost to furnish and apply water shall be included in the unit
prices for the various items bid and no additional payment will be allowed therefore.
4.4 Permits, Licenses and Inspection Fees
The Contractor shall obtain and pay for all costs incurred for permits, licenses and
inspection fees required by other agencies because his operations. Prior to starting
any work, the Contractor shall be required to have a City of La Quinta Business
License for the life of the contract; his subcontractors shall also have Business
Licenses for the time they are engaged in work. The Contractor will also be
required to obtain a no -cost encroachment permit from the City of La Quinta.
4.5 Air Contaminants
The Contractor shall not discharge smoke, dust or any other air contaminants into
the atmosphere in such quantity as will violate the regulations of any legally
constituted authority.
4.6 Notification
The Contractor shall notify the City, local authorities, and utility companies, of his
intent to begin work at least five days before work is to begin. The Contractor shall
cooperate with local authorities relative to handling traffic through the area including
coordinating with trash collection, school bus schedules, public transportation and
emergency activities.
Three days before work is to begin, the Contractor shall provide written notice
of intent to begin work to all adjacent properties, per Section 4000. The written
notice will be approved by the City prior to issuance and shall include at least
the following information: brief description of the improvements, the name,
address and phone number of the Contractor, and the date and time work is to
begin and finish. Contractor shall update and repost the information in the
event the work is rescheduled.
**END OF SECTION**
Special Provisions 3000-8
SECTION 4000
DIVISION 4 - TECHNICAL SPECIFICATIONS
1.0 GENERAL REQUIREMENTS
The Standard Specifications as defined in Section 2000 shall govern the work for this
project. All language in the Standard Specifications shall remain in full force and effect,
unless the language in the prevailing Contract Document specifically cites the section
number in the Standard Specification and says said provision is in lieu of that Standard
Specification section.
The project drawings and details are considered as part of these specifications, and any
work or materials shown on the drawings and not mentioned in the specifications, or vice
versa, are executed as if specifically mentioned in both.
2.0 MOBILIZATION (BID ITEM No. 1)
Mobilization shall conform to the provisions in Section 7-3.4, "Mobilization" of the
Standard Specifications. Mobilization includes expenditures for all preparatory work and
operations, including but not limited to, those costs necessary for the movement of
personnel, equipment, supplies, and incidental to the project site; for the establishment
of all facilities necessary for work on the project; and for all other work and operations
which must be performed or costs incurred prior to beginning work on the various contract
items on the project site as well as the related demobilization costs anticipated at the
completion of the project.
MOBILIZATION shall be paid for at the Contract Lump Sum Price as shown on the Bid
Schedule. Fifty percent (50%) of the lump sum price will be paid upon successful move
in and completion of mobilization. The remaining fifty percent (50%) shall be paid after
the contractor is completely demobilized and all project sites have satisfactorily been
restored and the project cleanup is completed.
3.0 TRAFFIC CONTROL (BID ITEM No. 2 and AA1-1)
Traffic Control shall comply with Standard Specifications Section 600 and modified by
Section 3000-4.1 and these special provisions.
TRAFFIC CONTROL shall be paid for at the Contract Lump Sum Price as shown on the
Bid Schedule. Monthly payments will be made on a pro -rata basis.
4.0 DUST CONTROL (BID ITEM No. 3 and AA1-2)
Dust Control shall comply with Section 3000-4.2.
DUST CONTROL shall be paid for at the Contract Lump Sum Price as shown on the bid
schedule. Monthly payments will be made on a pro -rata basis.
Technical Specifications 4000-1
4.1 Water Quality Management Plan (No Bid Item)
4.1.1 Water Quality Management Plan
Contractors shall comply with the 2014 Whitewater Region Water Quality
Management Plan (WQMP)
Contractor shall be responsible for installing post -construction BMPs as specified
per the approved site specific WQMP.
4.1.2 Payment
Payment for compliance with the WATER QUALITY MANAGEMENT PLAN
shall be considered as included in other items of work and no additional
compensation will be allowed therefore.
5.0 CLEARING AND GRUBBING (BID ITEM No. 4 and AA1-3)
Clearing and Grubbing shall conform to the provisions in Section 300-1, "Clearing and
Grubbing", of the Standard Specifications and these Special Provisions:
Contractor shall field verify existing grades and shall accept site as is, for no other
grading shall be performed by the City.
300-1.1.1 Removal and Disposal of Materials
300-1.1.1.1 General [Add the following]:
All materials removed shall be disposed of in a legal manner at an appropriate Disposal
Site.
300-1.1.1.2 Requirements. [Add the following]:
(a) Excess soil, turfgrass, trees, stumps, and plant material to be removed as
indicated in the project documents.
(d) Miscellaneous
In addition to the work outlined in Subsection 300-1 of the Standard Specifications, the
following items of work are included under Clearing and Grubbing unless otherwise
covered by a specific bid item.
(1) Provide all necessary water for construction activities. The contractor shall make
arrangements with CVWD to obtain construction water meter(s), if required. The cost of
the water meters shall be included in the cost of related items.
(2) Removal of structures, as directed by Engineer to be removed or abandoned.
(3) Protection of lights, utilities, trees, fences, gates, walls, greens and other facilities
within the construction zone, except those shown on the plans and those specifically
directed by the Engineer to be removed or relocated.
Technical Specifications 4000-2
(4) Clearing and removal of debris from the site of work. This includes removal and
legal disposal of structural items, non-structural items, existing fences, gates, signs, and
posts including the associated footings/foundations.
(5) Verification of existing locations and elevations as shown on the plans or directed
by the Engineer.
(6) Provide for the replacement of lighting, conduit, wire, trees, plants, and
hardscape of the same kind, to the satisfaction of the City whether indicated on the
plans or not.
(7) Provide saw cutting of asphalt paving and installation of sleeving per City of La
Quinta Detail 600 where existing sleeving for irrigation and wiring cannot be located.
(8) This item shall also be interpreted to include the removal or relocation of any
additional items in conflict with the proposed work not specifically mentioned herein or
covered by specific bid item as directed in the field by the Engineer, which may be
found within the work limits whether shown or not shown on the plans to be removed or
relocated.
300-1.4 Payment. [Add the following]:
Clearing and Grubbing shall be paid for at the lump sum (LS) contract price and no
additional compensation will be allowed. Payment shall include full compensation for
furnishing all labor, materials, tools, equipment, and doing all work involved in clearing
and grubbing as specified and no additional compensation will be allowed therefore.
No payment will be made to the Contractor for Clearing and Grubbing outside the stated
limits unless such work is authorized in writing by the City.
6.0 UNCLASSIFIED EXCAVATION (NO BID ITEM)
Unclassified Excavation shall conform to the provisions in Section 300-2, "Unclassified
Excavation," Section 401, "Removal," of the Standard Specifications and these Special
Provisions:
300-2.1 General. [Add the following]
Unclassified Excavation shall include excavating, loading, stockpiling, hauling, and
disposing of surplus material and or aggregate base to the subgrade depth indicated on
the plans or as directed by the Engineer. Saw cutting and removal of existing asphalt
concrete pavement, excavation, fills, and compaction, to complete the roadway section,
shall be included in this item of work.
The areas and quantities shown on the plans or specifications are given only for the
Contractor's aid in planning the work and/or preparing bids. The Engineer shall designate
the limits to be removed and these designated areas shall be considered to take
precedence over the areas shown on the plans. No guarantee is made that areas or
quantities shown will equal the areas or quantities designated by the Engineer.
Technical Specifications 4000-3
300-2.6 Surplus Material. [Add the following]:
All surplus materials shall be disposed of in a legal manner at the Contractor's expense.
300-2.9 Payment. [Replace with the following]:
Unclassified Excavation shall be incidental to other removal and construction activities
included with the project and no additional compensation will be allowed therefore.
7.0 DEMOLITION AND DISPOSAL (BID ITEMS 5, 26, and AA14)
This Section shall conform to Sub -Section 6, "Clearing and Grubbing" of these technical
provisions and the following:
Existing Bituminous Pavement Removal shall conform to the provisions in Section 401
"Removal", of the Standard Specifications and these Special Provisions:
Existing bituminous pavement removal shall include sawcutting, excavating, loading,
stockpiling, hauling, and disposing of existing bituminous pavement material and/or
aggregate base to the subgrade depth indicated on the plans or as directed by the
Engineer. Sawcutting and removal of existing bituminous concrete pavement shall be
included in this item of work.
300-1.3.2 (a) "Bituminous Pavement" shall be amend as follows:
Removal of bituminous pavement shall be made to a sawcut at the designated lines of
removal shown on the Plans or as designated by the Engineer. Location of sawcut and
width of existing pavement to be removed shall be as shown on the plans or as
determined by the Engineer in the field. Payment for sawcutting shall be included in the
compensation paid for the pavement removal and no additional compensation will be
allowed. Minimum laying depth of new pavement material shall be 0.10 foot at join lines.
The areas and quantities shown on the plans or specifications are given only for the
Contractor's aid in planning the work and/or preparing bids. The Engineer shall designate
the limits to be removed and these designated areas shall be considered to take
precedence over the areas shown on the plans. No guarantee is made that areas or
quantities shown will equal the areas or quantities designated by the Engineer. Spalled
or loose blocks of pavement and pavement cracks wider than 3/8 inch will be deemed
justification for extending or adding to the removal and replacement of asphalt concrete
pavement.
The areas indicated for removal and replacement shall be excavated to the full
depth of the proposed pavement section (asphalt), regardless of thickness. The
City does not have boring data. No warranty is given or implied as to the thickness, or to
the amount of material which may result from the removal of the street pavement. If the
Contractor wishes to personally check the existing pavement thickness, the City
Engineer's office will cooperate by issuing the necessary encroachment permit upon
application by the Contractor.
Existing Concrete Pavement Removal shall conform to the provisions in Section 401,
Technical Specifications 4000-4
"Removal," of the Standard Specifications and these Special Provisions:
Existing concrete pavement removal shall include sawcutting, excavating, loading,
stockpiling, hauling, and disposing of existing concrete sidewalks and driveways as
indicated on the plans or as directed by the Engineer. Sawcutting and removal of existing
concrete pavement shall be included in this item of work. Removals shall be to the nearest
joint as shown on the plans or as directed by the Engineer.
Demolition and Disposal shall be paid for on a lump sum (LS) basis and shall include
full compensation in furnishing all labor, materials, tools and equipment as specified in
the SSPWC and the Special Provisions, including loading, hauling, stockpiling and legal
disposal, shall be included in this item of work for which removal and disposal of materials
are required per approved design plan, as directed by the Engineer, equipment, as
defined in the SSPWC and the Special Provisions. No further compensation will be
allowed therefore.
8.0 GRADING AND SUBGRADE PREPARATION (NO BID ITEM)
Preparation of the pavement subgrade shall conform to the provisions of Section 301-1
of the Standard Specifications and these Special Provisions.
301-1.3 Relative Compaction. [Replace with the following]:
Relative compaction shall be modified to require 95% relative compaction of the top 12"
of the subgrade in lieu of the 90% allowed under base material, including removal of
aggregate base or subgrade to required depth.
301-1.7 Payment. [Replace with the following]:
Compensation for subgrade preparation shall be deemed to be included in the bid price
of other items, and no additional compensation will be allowed.
9.0 ASPHALT CONCRETE (BID ITEM No. AA1-6 and AA1-7)
301-2 UNTREATED BASE
301-2.1 General. [Replace with the following]:
Untreated base shall be Class II Aggregate Base or Crushed Aggregate Base and shall
conform to the Provisions of the Section 200-2 "Untreated Base Materials" of the Standard
Specifications.
301-2.4 Measurement and Payment. [Add the following]:
The contract Unit price paid per Square Foot of 3" Asphalt Concrete Over 4"
Aggregate Base Over 12" Scarified and Compacted Native includes full compensation
for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the
work involved in constructing and placing Aggregate Base, complete in place, including
hauling, grading, shaping, watering and compacting the Aggregate Base, as shown on
the plans, as specified in the Standard Specifications and these special provisions, and
as directed by the engineer, and no additional compensation will be allowed therefore.
Technical Specifications 4000-5
203-6 ASPHALT CONCRETE
203-6.1 General. [Add the following to the end of the subsection]:
Asphalt concrete shall conform to the provisions of Subsection 200-1.2, "Rock Products,"
and Subsection 302-5, "Asphalt Concrete Pavement".
The viscosity grade of paving asphalt shall be PG 70-10. The following aggregate
size shall be used.
Asphalt Base Course III -C2 -PG 70-10 1/2" Max. Medium — 1.5" Total Thickness
Finish Course III -C2 -PG 70-10 1/2" Max. Medium — 1.5" Total Thickness
The Contractor shall submit final asphalt mix designs to the Agency for review prior to
paving.
Asphalt Concrete Pavement
1. Asphalt concrete material shall conform to PG 70-10, as specified in Section 203-
6, "Asphalt Concrete", of the Standard Specifications.
2. Distribution, spreading, rolling, and compaction of asphalt concrete pavement shall
conform to requirements as specified in Section 302-5, "Asphalt Concrete
Pavement", of the Standard Specifications.
3. Diesel fuel shall not be used to coat the beds of delivery trucks. If diesel fuel is
detected on any load the entire load will be rejected.
4. Asphalt concrete surface course shall be placed in two (2) lifts, and compacted to
the thickness shown in the Plans.
5. No roller shall be permitted to stand motionless on any portion of the work before
it has been properly compacted. Upon completion, the pavement shall be true to
grade and cross-section. When a 10 -foot straightedge is laid on the finished
surface, the surface shall not vary from the edge of the straightedge more than 1/4-
inch.
302-5.5 Distribution and Spreading. [Add the following, including new Subsection
302-5.4.1.]:
A minimum of two courses shall be laid for all asphalt concrete pavements of three inches
or thicker. Both the base and finish course shall be machine placed.
9.3 Saw cutting
Existing asphalt concrete pavement that is to match proposed asphalt concrete
surfacing shall be sawcut to a neat vertical face. A minimum two feet (2') sawcut
shall be provided along all existing pavement edges. Existing asphalt concrete
pavement that is unsound, as determined by the City Inspector or City Engineer
shall be removed to limits as required.
Payment for saw cutting is included in the cost of associated items and no
additional payment will be made therefore.
Technical Specifications 4000-6
9.4 Asphalt Tack Coat
302-5.4 Tack Coat (replace with the following)
Prior to paving over against asphalt concrete, the surface shall be cleaned,
cracks shall be sealed as shown below, and the surface shall have a tack coat
of SS -1 h emulsion at a rate of 0.10 gallon per square yard applied. The surface
shall be free of water, foreign material, or dust, when the tact coat is applied. To
minimize public inconvenience, no greater area shall be treated in any one day
than is planned to be covered by asphalt concrete during the same day unless
otherwise authorized by the Engineer.
A similar tack coat shall be applied to the surface of any course, if the surface is
such that a satisfactory bond cannot be obtained between it and a succeeding
course.
The contact surfaces of all cold pavement joints, curbs, gutters, manholes, shall
be painted with grade SS -1 h emulsified asphalt immediately before the adjoining
asphalt concrete is placed.
9.5 Patching and Repair
1. Damaged, faulty, or nonconforming asphalt concrete pavement surfaces shall be
completely removed New asphalt concrete pavement surfacing shall be placed
and compacted to the minimum thickness required, and to smoothly join the
adjacent finished surfaces.
2. Patching with thin overlays will not be permitted unless authorized by the CITY
3. Prior to placing the Court Surfacing, any cracks greater than 1/8" shall be cleaned
and treated with weed killer and filled with crack filler (GuardTop or approved
equal). Cracks are to be filled to match existing surface.
a. Cracks 1 inch in width and wider shall be filled with compacted pea -gravel
and SS grade asphaltic emulsion or hot mix asphalt concrete as directed
by the Engineer so that the sealant does not exceed 1 inch in depth.
9.6 Maintenance and Protection
1. After an area has been released to the Contractor he shall assume complete
responsibility for maintenance and protection responsibilities without the written
authorization of the CITY
2. All surfaces, structures, manholes, gratings, etc., damaged after the areas have
been released to Contractor, whether such damage was caused by the
Contractor or other contractors working on the site, shall be repaired by the
Contractor at no additional cost to the City, unless the maintenance and
protection responsibilities of the Contractor has been waived in writing by the
CITY.
3. Damaged areas of pavement shall immediately be repaired to protect the
subgrade from surface waters.
4. The pavement thickness specified will not support repeated loading from heavy
construction equipment.
Technical Specifications 4000-7
9.7 Warranty
The Contractor shall furnish an unqualified warrantee stating, in writing, that he
will, at no additional cost to the City, repair or replace all bituminous pavement
and aggregate base in any areas that become defective within a period of one
year after completion and acceptance of the work by the City.
9.8 Measurement and Payment. [Add the following]:
The contract Unit price paid per Square Foot for 3" Asphalt Concrete Over 4"
Aggregate Base Over 12" Scarified and Compacted Native includes full
compensation for furnishing all labor, materials, tools, equipment, and
incidentals, and for doing all the work involved in constructing and placing
Asphalt Concrete Pavement, complete in place, including hauling, as shown on
the plans, as specified in the Standard Specifications and these special
provisions, and as directed by the engineer, and no additional compensation will
be allowed therefore.
The contract Unit price paid per Square Foot for Asphalt Crack Fill includes full
compensation for furnishing all labor, materials, tools, equipment, and
incidentals, and for doing all the work involved in Asphalt Crack Fill prior to Court
Surfacing, complete in place, including hauling, as shown on the plans, as
specified in the Standard Specifications and these special provisions, and as
directed by the engineer, and no additional compensation will be allowed
therefore.
10.0 MODIFY, RELOCATE AND REPAIR EXISTING LIGHTING/ELECTRICAL (BID
ITEM 7)
The contractor shall test all existing electrical systems and report to the City what is in
need of repair before starting demolition.
The contractor shall furnish and install all electrical equipment and materials required for
a complete electrical system after all landscape modifications.
All equipment and materials shall comply with the requirements of the governing code
and the serving utility and shall be approved and identified by Underwriters Laboratories,
Inc. (UL).
Work includes, but is not necessarily limited to, the following.
Modifying the existing electrical system to remove existing lights.
2. Installation of new light fixtures and cutting and capping broken or non-functioning
lights at the direction of the City.
3. Installation of new pull rope and sealant.
4. Protecting lights, wires, and conduit in place it possible.
Technical Specifications 4000-8
At no time shall the placement of equipment or devices create a condition that is not
allowed by the California Electrical Code or local jurisdiction.
In the event changes of locations for equipment or devices are necessary due to field
conditions the change shall be made without cost. This assumes that the change is
ordered before modifications are made and work directly connected to same is modified
and no extra materials are required.
The contractor shall coordinate the location of all pull boxes with the City prior to
construction.
Coordinate and cooperate in every way with other trades in order to avoid interference
and assure a satisfactory job.
Prior to starting any underground work, the contractor shall notify DIGALERT at 811 and
request an underground infrastructure search and identify report.
Perform cutting and patching of the construction work which may be required for the
proper installation of the electrical work. Patching shall be per city of La Quinta Standard
Detail #600. Match the surrounding work to the satisfaction of the City. Trenches shall be
in accordance with City of La Quinta Std. detail #600.
The following specifications are included in the event modifications are required
to provide a complete operable electrical system:
Conduit
Conduit shall be Polyvinyl chloride, Schedule 40 for all underground applications, or
schedule 80 as required per project requirements.
Conduit Installation:
1. Underground conduits entering pullboxes shall enter from the bottom of the pullbox
unless indicated otherwise. Provide end bell fitting on the end of each conduit 2" or
larger entering the pullbox. Provide waterproof sealant "Duct Seal" after conductors
have been installed.
2. Provide metallic or plastic caps on all conduits during construction until installation of
conductors.
3. Provide all trenching, excavation, shoring and backfilling required for the proper
installation of underground conduits. Make trenches a minimum of 6 inches wider than
the duct bank.
4. Install underground conduit, not less than 18" below finished grade in non -traffic areas
and 24" below finished grade in traffic areas, including roads. Install long radius bends
in all underground conduits in excess of 100 feet long.
Technical Specifications 4000-9
5. Provide a yellow magnetic detector tape over the entire length of all new
underground conduits, if new conduits are required. Place tape in backfill at a
depth not to exceed 12 inches below finish grade or as required by the manufacturer.
Pullboxes
Pullboxes shall be rectangular plastic with locking lid with base. Provide graylid
permanently marked indicating the system installed.
Provide a minimum of 12" deep bedding base of crushed rock 3/4" size in the bottom of
the excavation. Bedding shall be level and well compacted by a minimum of four passes
with a plate type mechanical vibrator.
Entrances of conduits/ducts shall terminate with end -bells inside the pullbox.
Grounding
Grounding shall be executed in accordance with all applicable codes and regulations,
both of the State of California and local authorities having jurisdiction.
Each pull box or any other enclosure in which several ground wires are terminated shall
be equipped with a ground bus secured to the interior of the enclosure. The bus shall
have a separate lug for each ground conductor. No more than one conductor shall be
installed per lug.
The maximum resistance to ground shall not exceed 5 ohms.
Wire and Cable
Branch circuit and fixture joints for #10 AWG and smaller wire shall be made with UL -
approved connectors listed for 600 volts, approved for use with copper and/or aluminum
wire. Connector to consist of a cone-shaped, expandable coil spring insert, insulated with
a nylon shell and 2 wings placed opposite each other to serve as a built-in wrench or shall
be molded one-piece as manufactured by "Scotchlok."
Branch circuit joints of #8 AWG and larger shall be made with screw pressure connectors
made of high strength structural aluminum alloy and UL -approved for use with both
copper and/or aluminum wire as manufactured by Thomas & Betts. Joints shall be
insulated with plastic splicing tape, half -lapped and at least the thickness equivalent to
the conductor insulation. Tapes shall be fresh and of quality equal to Scotch.
Use U.L. listed pulling compound for installation of conductors in conduits.
All splices in exterior pull boxes and landscape light fixtures shall be cast resin
encapsulated. Power conductor splices - 3M Scotchcast Series 82/85/90; Plymouth or
equal. No underground splices shall be made in control or signal circuits.
Technical Specifications 4000-10
Neatly group and lace all wiring in panelboards with plastic ties at 3" on centers. Tag all
spare conductors.
Work includes, but is not limited to, furnishing and installing all electrical components to
modify and repair the existing lighting electrical system per plans, specifications and bid
schedule. This item shall include all labor, materials, tools, equipment, transportation, and
incidentals for performing the work. Full compensation for complying with these
requirements shall be at a unit cost "lump sum" to provide a complete and fully
operational electrical lighting system including pullboxes, etc., as indicated on the plans
and in the specifications.
11.0 CONCRETE AND MASONRY CONSTRUCTION (BID ITEMS No. 9 and
AA1-9)
Concrete construction shall conform to Section 201, "Concrete, Mortar, and Related
Materials," and Section 303, "Concrete and Masonry Construction," of the Standard
Specifications and these Special Provisions.
Curing compound shall be in accordance with the City of La Quinta Standard Plan
Number 200.
Preparation of existing native subgrade in areas where Portland Cement Concrete
improvement will be constructed shall conform with Section 301-1, "Subgrade
Preparation," of the Standard Specifications.
Concrete inspections shall be made with three separate actions per section 1400
unless otherwise waived by the City: subgrade preparation; forming; and pouring.
201-1 PORTLAND CEMENT CONCRETE
201-1.1 Requirements
201-1.1.2 Concrete Specified by Class and Alternate Class (Add the following:)
Construction Class Slump
Sidewalks and concrete bands 560-C-3250 5"
201-1.2 Materials
201-1.2.1 Cement (Delete the first paragraph and add the following:)
The cement to be used or furnished shall be Type V Portland Cement conforming to
ASTM C150, unless otherwise specified.
11.1 Concrete Curbs, Walks, Gutters, Cross Gutters, Access Ramps, &
Driveways
Concrete Curb, Gutter, Curb Transition, Sidewalk, Ribbon Gutter, Curb Ramp, and
Driveway, shall conform to the provisions in Section 303-5, of the Standard Specifications
and these Special Provisions.
Technical Specifications 4000-11
303-5.1.1 General. [Add the following paragraph]:
Concrete curbs, walks, gutters, cross gutters, access ramps, and driveways shall conform
to the Standard Specifications as modified herein.
Immediately after finishing operations are completed, Type II clear concrete curing
compound shall be applied at the rate of one gallon per 150 square feet.
All pull boxes, water meter boxes, valve boxes and other utilities indicated on the plans
shall be adjusted to the proposed finish grade and approved by the City prior to the
placement of concrete.
303-5.5.3 Walk. [Add the following]:
Concrete sidewalk, pads, cross gutters and access ramps shall have a medium broom
finish.
303-5.9 Measurement and Payment. [Add the following to this section]:
Payment for Construct Sidewalk per City of La Quinta STD 240 Mod. shall be at the
contract unit bid price per Square Foot and shall include full compensation for providing
this item of work, complete in place, including required hand work, and no additional
compensation will be allowed.
Sidewalks shall be measured for payment from the back of curb to the back of the
sidewalk. The width of the curb shall not be measure for payment for sidewalks.
Sidewalk shall include the adjustment of any traffic signal pull boxes, including the
replacement of traffic signal pull boxes if necessary.
Payment for Construct Concrete Banding — 2' Wide, 6" Thick shall be at the contract
bid price per Linear Foot and shall include full compensation for providing this item of
work, complete in place, including required hand work, and no additional compensation
will be allowed.
12.0 PROVIDE NEW SLEEVING PER CITY STANDARD 600 (BID ITEM 8)
Sawcut and remove asphalt paving per City Standards. Install new sleeving per plans at
depth of not less than 18 inches except that sleeving placed behind a curb shall not be
less than 18 inches nor more than 36 inches below top of curb. Sleeves under asphalt
shall not be placed less than 24 inches. Sleeves shall be installed behind curb within
City right-of-way in a straight line.
New Sleeving shall be paid for at the lump sum (LS) contract price and no additional
compensation will be allowed. Payment shall include full compensation for furnishing all
labor, materials, tools, equipment, and doing all work involved in as specified for new
sleeving and no additional compensation will be allowed therefore.
Technical Specifications 4000-12
13.0 WALL CLEANING (BID ITEM 10)
Remove all surface contamination by pressure washing with an appropriate
cleaner TO REMOVE CALCIUM BUILD UP FROM WALL, rinse thoroughly and allow
to dry to the satisfaction of City. Remove loose stucco, wires, efflorescence, or
laitance. Make stucco repairs as required by the City. Allow new patches to cure for 30
days, if painting can't wait 30 days, allow surface to dry 5-7 days and prime with Loxon
Concrete and Masonry Primer/Sealer. Repair cracks, voids, and other holes with an
elastomeric patch or sealant to satisfaction of City. Seal stains from water, smoke, ink
pencil, grease, etc. with an appropriate primer/sealer.
Wall Cleaning shall be paid for on a lump sum (LS) basis and shall include furnishing
all labor, equipment, tools and materials necessary for prepping and cleaning walls per
approved plans. The price of this items shall also include any incidentals for doing the
work involved in painting as defined in the SSPWC and the Special Provisions. No further
compensation will be allowed therefore.
14.0 KEYSTONE CONCRETE RETAINING BLOCK WALLS (BID ITEMS 11
THROUGH 14 AND 28)
[Add section]:
900-1 Description
Work shall consist of designing, furnishing and construction of a Keystone Legacy Stone®
Straight Split Retaining Wall System in accordance with these specifications and in
reasonably close conformity with the lines, grades, design, and dimensions shown on the
plans. Approved equal wall systems will be considered.
Work includes preparing foundation soil, furnishing and installing leveling pad, and backfill
as shown on the plans and according to manufacturer's recommendations.
900-2 Related Sections
Earthwork
900-3 Submittals/Certifications
Contractor shall submit a Manufacturer's certification, prior to start of work, that the
retaining wall system components meet the requirements of this specification and the
structure design.
900-4 Delivery, Storage and Handling
Contractor shall check all materials upon delivery to assure that the proper type, grade,
color, and certification have been received.
Technical Specifications 4000-13
Contractor shall protect all materials from damage due to jobsite conditions and in
accordance with manufacturer's recommendations. Damaged materials shall not be
incorporated into the work.
900-5 Products
900-5.1 Definitions
Keystone Legacy Stone® Straight split cored unit - a concrete retaining wall element
machine made from Portland cement, water, and aggregates.
900-5.2 Keystone Concrete Retaining Wall Units
Keystone concrete units shall conform to the following architectural requirements:
Face color - tan, unless otherwise specified. Face finish —straight face configuration. 6"
height cored block with 3" height Keystone cap, installed with exterior construction grade
adhesive. Bond configuration - running with bonds nominally located at midpoint vertically
adjacent units, in both straight and curved alignments.
Exposed surfaces of units shall be free of chips, cracks or other imperfections when
viewed from a distance of 10 feet under diffused lighting.
Keystone concrete materials shall conform to the requirements of ASTM C1372 -
Standard Specifications for Segmental Retaining Wall Units.
Keystone concrete units shall conform to the following structural and geometric
requirements measured in accordance with ASTM C140 Sampling and Testing Concrete
Masonry Units:
• Compressive strength: >_ 3000 psi (21 MPa);
• Absorption: <_ 8 % for standard weight aggregates;
Dimensional tolerances: ± 1/8" (3 mm) from nominal unit dimensions not including rough
split face;
• Unit size: 8" (203 mm) (H) x 18" (457 mm)(W) x 18" (457 mm)(D) minimum;
• Unit weight: 93-lbs/unit (42 kg/unit) minimum for standard weight aggregates.
Keystone concrete units shall conform to the following performance testing:
• Inter -unit shear strength in accordance with ASTM D6916 (NCMA SRWU-2):
• 1500-plf (21 kN/m) minimum at 2 -psi (13 kPa) normal pressure.
Keystone concrete units shall conform to the following constructability requirements:
• Vertical setback: 1/8" (3 mm) ± per course (near vertical) or 1" (25 mm) + per
course per the design;
Technical Specifications 4000-14
• Horizontal gap between erected units shall be <_ 1/2 inch (13 mm).
900-5.3 Base Leveling Pad Material
Material shall consist of a compacted crushed stone base or non -reinforced concrete as
shown on the construction drawings.
900-6 Execution
900-6.1 Excavation
Contractor shall excavate as shown on the construction drawings. City Inspector shall
inspect the excavation and approve prior to placement of leveling material or fill soils.
Proof roll foundation area as directed to determine if remedial work is required.
Over -excavation and replacement of unsuitable foundation soils and replacement with
approved compacted fill will be compensated as agreed upon with the City Inspector.
900-6.2 Base Leveling Pad
Leveling pad material shall be placed as shown on the construction drawings, to a
minimum thickness of 6 inches and extend laterally a minimum of 6" in front and behind
the Keystone wall unit.
Soil leveling pad materials shall be compacted to a minimum of 95% Standard Proctor
density per ASTM D-698 or 92% Modified Proctor Density per ASTM D1557.
Leveling pad shall be prepared to insure full contact to the base surface of the concrete
units.
900-6.3 Keystone Unit Installation
First course of units shall be placed on the leveling pad at the appropriate line and grade.
Alignment and level shall be checked in all directions and ensure that all units are in full
contact with the base and properly seated.
Place the front of units side-by-side. Do not leave gaps between adjacent units. Layout
of corners and curves shall be in accordance with manufacturer's recommendations.
Install shear/connecting devices per manufacturer's recommendations.
Place and compact backfill soil behind wall.
Maximum stacked vertical height of wall units, prior to backfill placement and compaction,
shall not exceed three courses.
900-6.5 As -Built Construction Tolerances
Vertical alignment: ± 1.5" (40 mm) over any 10' (3 m) distance.
Technical Specifications 4000-15
Wall Batter: within 2 degrees of design batter.
Horizontal alignment: ± 1.5" (40 mm) over any 10' (3 m) distance.
Corners, bends & curves: ± 1 foot (300 mm) to theoretical location.
Maximum horizontal gap between erected units shall be 1/2 inch (13 mm).
900-6.6 Field Quality Control
Quality Control testing shall include soil and backfill testing to verify soil types and
compaction and verification that the retaining wall is being constructed in accordance with
the design plans and project specifications.
This item shall be paid for on a square foot (SF) basis and shall include furnishing all
labor, equipment, tools and materials necessary for installation of Keystone concrete
retaining block walls per approved plans. The price of this item shall also include any
incidentals for doing the work involved in constructing the walls as defined in the project
plans and specifications.
15.0 INTERLOCKING CONCRETE PAVERS — INSTALLATION ONLY (BID ITEM
17)
Summary
A. Section Includes: Interlocking concrete pavers including aggregate base course,
mat, and sand laying course.
B. Related Documents: The Conditions of the Contract and Division 1 apply to this
section as fully as if repeated herein.
C. Related Sections:
1. Section 201 of the Standard Specifications
2. Section 200-2 of the Standard Specifications
D. Related Work:
1. Preparation of sub -base.
2. Installation of concrete paving.
3. Installation of Class II Base.
Technical Specifications 4000-16
References
A. The editions of the specifications and standards referenced herein, published by the
following organizations, apply to the concrete pavers only to the extent specified by
the reference. Refer to Section 1 for information concerning availability and use of
references.
B. American Society of Testing and Materials (ASTM)
C. Interlocking Concrete Pavement Institute (ICPI)
D. State of California, Department of Transportation, Standard Specifications
Submittals
A. Quality Assurance:
1. Installer Qualifications: A firm which has specialized in installation of precast
concrete pavers for not less than 3 years and which is acceptable to manufacturer
of pavers. Installer must possess a current ICPI Installation Certificate.
2. Field Constructed Mock -Up:
a) Install a 7'-0" by 7'-0" paver area.
b) Use this area to determine surcharge of the bedding sand layer, joint sizes,
lines, laying pattern(s), color(s), and texture of the job.
c) This area will be used as the standard by which the work will be judged.
d) Subject to Owner/Owner Representative's acceptance of visual qualities of the
mock-up before start of paver work. Sample panels, if approved, may be left
in place as part of the completed construction.
e) If mock-up is not retained, remove and properly dispose of mock-up.
B. Project Conditions
1. Contractor shall acquaint himself with all site conditions. Should utilities or other
work not indicated be found during excavations, notify the Landscape Architect for
instructions as to further action. Failure to do so will make Contractor liable for all
damage thereto arising from his operations subsequent to discovery of such
utilities not indicated.
Technical Specifications 4000-17
Products
A. Pavers:
Interlocking Concrete Pavers: Colors, sizes and patterns shall be as indicated on the
drawings.
Materials:
1. Bedding and Joint Sand: Provide bedding and joint sand as follows:
a) Washed, clean, non -plastic, free of deleterious or foreign matter, symmetrically
shaped, natural or manufactured from crushed rock.
b) Do not use limestone screenings, stone dust, or sand for the bedding sand material
that does not conform to the grading requirements of ASTM C 33.
c) Do not use mason sand or sand conforming to ASTM C 144 for the bedding sand.
d) Where concrete pavers are subject to vehicular traffic, utilize sands that are as
hard as practically available.
e) Sieve according to ASTM C 136.
f) Bedding Sand Material Requirements: Grading requirements for bedding sand per
ASTM C 33. Conform to the grading requirements of ASTM C 33 with
modifications as follows:
Sieve Size Percent Passin
3/8 inch 100
No. 4 95-100
No. 8 80-100
No. 16 50-85
No. 30 25-60
No. 50 5-30
No. 100 0-10
No. 200 0-1
g) Joint Material Requirements: Provide Elastomeric Sand.
Technical Specifications 4000-18
h) Grading requirements for joint sand per ASTM C 144. Conform to the grading
requirements of ASTM C 144 with modifications as follows:
Natural Sand Manufactured Sand
Sieve Size Percent Passing Percent Passing
No. 4 100 100
No.8 95-100 95-100
No. 16 70-100 70-100
No. 30 40-75 40-100
No. 50 10-35 20-40
No. 100 2-15 10-25
No. 200 0-1 0-5
i) Edge Restraints:
Provide steel edge restraints installed around the perimeter of all interlocking
concrete paving unit areas.
Execution
A. Examination:
1. Acceptance of Site Verification of Conditions:
a) Examine related work and surfaces before starting work of this section. Report
to the Landscape Architect, in writing, site conditions which will prevent the
proper completion of this work. Beginning the work of this section without
reporting unsuitable conditions constitutes acceptance of site conditions.
Required removal, repair, or replacement of this work caused by unsuitable
conditions shall be done at no additional cost to Owner.
b) Verify that subgrade preparation, compacted density, and elevations conform
to specified requirements.
c) Verify that geotextiles, if applicable, have been placed according to Drawings
and Specifications.
d) Verify that base materials, thickness, surface tolerances and elevations
conform to specified requirements.
e) Provide written density test results for soil subgrade base materials.
Technical Specifications 4000-19
f) Verify location, type, and elevations of edge restraints, utility structures, and
drainage inlets.
g) Verify that subbase or adjacent concrete paving has been installed to finish
grades indicated less sand leveling course and paver thickness.
2. Preparation:
a) Subgrade: Scarify earth subgrade to a depth of not less than 6 inches and
compact it to 95 percent of maximum density.
b) Edge Restraint: Restrain all edges of paver installation. Where permanent
structures do not provide edge restraint, install concrete toe or other suitable
methods as recommended by the paver manufacturer to prevent movement of
edge pavers.
Install edge restraints as indicated on Drawings.
3. Installation:
Spread bedding sand evenly over the base course and screed to a nominal 1 -inch
thickness, not exceeding 1 -1/2 -inch thickness. Spread bedding sand evenly over
the base course and screed rails, using the rails and/or edge restraints to produce
a nominal 1 -inch thickness allowing the specified variation in the base surface.
a) Do not disturb screeded sand.
b) Screeded area shall not substantially exceed that which is covered by pavers
in one day.
c) Do not use bedding sand to fill depressions in the base surface.
d) Lay pavers in pattern(s) indicated on Drawings. Place units hand tight without
using hammers. Make horizontal adjustments to placement of laid pavers with
rubber hammers and pry bars as required.
e) Provide joints between pavers between 1/16 inch and 3/16 inch wide. No more
than 5% of the joints shall exceed 1/4 -inch -wide to achieve straight bond lines.
f) Joint (bond) lines shall not deviate more than +/- 1/2 inch over 50 feet from
string lines.
g) Fill gaps at the edges of the paved area with cut pavers or edge units.
h) Cut pavers to be placed along with edge with a double blade paver splitter or
masonry saw.
i) Cut pavers as indicated on Drawings. All cut pavers exposed to vehicular tires
shall be no smaller than 1/3 of a whole paver.
Technical Specifications 4000-20
j) Keep skid steer and forklift equipment off newly laid pavers that have not
received initial compaction and joint sand.
k) Use a low amplitude plate compactor capable of at least minimum of 4,000 Ibf
at a frequency of 75 to 100 Hz to vibrate the pavers into the sand. Remove
any cracked or damaged pavers and replace with new units.
1) Simultaneously spread, sweep, and compact dry joint sand into joints
continuously until full. This will require at least 4 to 6 passes with a plate
compactor. Do not compact within 6 feet of unrestrained edges of paving units.
m) All work within 6 feet of the laying face must be fully compacted with sand -filled
joints at the end of each day or compacted upon acceptance of the Work.
Cover the laying face or any incomplete areas with plastic sheets overnight if
not closed with cut and compacted pavers with joint sand to prevent exposed
bedding sand from becoming saturated from rainfall.
n) Allow excess joint sand to remain on surface to protect pavers from damage
from other trades. Remove excess sand when directed by City.
o) Surface shall be broom clean after removal of excess joint sand.
Field Quality Control
A. The final surface tolerance from grade elevations shall not deviate more than +/- 3/8
inch under a 10 -foot straightedge.
B. Check final surface elevations for conformance to Drawings.
C. The surface elevations of pavers shall be 1/8 inch to 1/4 inch above adjacent drainage
inlets, concrete collars or channels.
D. Lippage: No greater than 1/8 -inch difference in height between adjacent pavers.
Clean -Up and Protection
A. Protect finished Work from damage due to subsequent construction activity on the
site.
B. Upon completion of work, remove from the premises all surplus materials, tools,
equipment, rubbish and debris resulting from the work.
Installation of interlocking pavers shall be paid for at the square foot (SF) contract
price and no additional compensation will be allowed. Payment shall include full
compensation for furnishing all labor, materials (except pavers), tools, equipment, and
doing all work involved in interlocking pavers as specified and no additional compensation
will be allowed therefore.
Technical Specifications 4000-21
16.0 PICKLEBALL COURT SYNTHENTIC SURFACING (BID ITEM AA1-10)
[Add Section] Pickleball court sizing, painting, and striping shall be in
conformance with the regulations put forth by the USA Pickleball (USAPA)
regulation size and as per the plan details.
Description: A combination of a two component solid pour urethane with precured
rubber granules, and dehydrating cement powders. Acceptable products or equal:
a) Crossfield Products Corp.; Dex-O-Tex Resilient Athletic Surfacing
b) Sports Technology Group, Inc.; Amerisport Track #1
c) Sportec International, Inc.; Laykold 400
Physical Properties: When properly combined and installed, the base pour material
and texture coat shall meet or exceed the following characteristics:
a) Surface Hardness: Shore A hardness of 60-75 in accordance with ASTM
D2240.
b) Moisture Absorption: 2.5 percent or less in accordance with MIL -D -3134-
c) Abrasion Resistance: 0.270 Wear Index in accordance with FTMS #141,
Method 6192 (CS #17 wheel).
Colors: As indicated on plans.
This item shall be paid for on a square foot (SF) basis and shall include furnishing
all labor, equipment, tools and materials necessary for installation of pickleball
court synthetic surfacing and striping per approved plans. The price of this item
shall also include any incidentals for doing the work involved in as defined in the
project plans and specifications.
17.0 SITE AMENITIES (BID ITEMS AA1-11 THROUGH AA1-14)
Contractor to provide and install the following site amenities as per the project
plans and manufacturer specifications:
a) Pickleball Fence and Gates
Four feet height — chain link sports fence — color: black. Two gates as
indicated at 36" width.
Type A Fencing: Fencing with a fabric height of 48 inches and top rail and
bottom tension wire. Posts shall be fitted with post tops.
Submit shop drawings showing layout with post spacings and details
illustrating fence height, location and sizes of posts, rails, braces, gates,
hardware, anchorage details.
Technical Specifications 4000-22
Provide fences and gates meeting the accessibility requirements of the
2010 California Building Code (CBC) Title 24 Part 2 Chapter 11 -
Accessibility; and ADA Accessibility Guidelines for Buildings and Facilities,
dated June 26, 1991 as amended April 5, 1993 and January 18, 1994, and
July 2004.
Galvanized Steel Finish: ASTM A 392, Class 2, with not less than 2 ounces
zinc per square foot of uncoated wire surface.
b) Pickleball Net and Posts
Net: Douglas PN -30 Pickleball Net SKU 20103 as manufactured by:
Douglas Industries, Inc.
3441 S. 11 th Ave.
Eldridge, IA 52748
Phone: 800-553-8907
Fax: 800-443-8907
www.douglas-sports.com
3.Omm Solid Core Knotted Braided Polyethylene with 285 Ib. Break
Strength
Single Ply Vinyl Coated Polyester Headband 32 oz./sq. yd.
Black Vinyl Side Pockets with Fiberglass Dowels
Net Dimensions: 31" high X 21'9" long
Posts: Douglas SW -36 Deluxe Pickleball Posts 2-7/8" OD — Color:
Black — SKU 63079 as manufactured by:
Douglas Industries, Inc.
3441 S. 11 th Ave.
Eldridge, IA 52748
Phone: 800-553-8907
Fax: 800-443-8907
www.douglas-sports.com
54" in length and sit 36" above court surface
2-7/8" OD posts are constructed from heavy-duty 8 -gauge steel.
Systems are finished with black baked -on polyester powder coat to
resist rust and increase durability.
Gear caps are made from die-cast zinc.
Aluminum reel offers a smooth adjusting operation with a side
mounted removable handle. External gears and handle are finished
in black baked -on polyester powder coat finish to resist rust and
increase durability.
Technical Specifications 4000-23
Warranty: 5 Year Limited
Post Sleeves: Douglas GS-24RD/AL Aluminum Ground Sleeves 24" Long
for 2-7/8" OD Posts — SKU 63171 as manufactured by:
Douglas Industries, Inc.
3441 S. 11 th Ave.
Eldridge, IA 52748
Phone: 800-553-8907
Fax: 800-443-8907
www.douglas-sports.com
c) Benches
Model TF5027 — Color: Buff — Finish: Weatherstone as manufactured by:
Belson Outdoors
627 Amersale Drive
Naperville, IL 60563
(800) 323-5664 1
Fax: (630) 897-0573
www.belson.com
Size: 72" L x 18" W x 16" H
Weight: 900 lbs
Seating Capacity: 5-6 persons.
Material: Reinforced Precast Concrete
Reinforcing: 1/2" Dia. steel rebar
Hardware: (4) - 3/8" Dia. threaded inserts for anchoring
Portland Cement: ASTM C150 specifications for Portland Cement.
Aggregates: All aggregates to meet ASTM C33 specifications, to be
cleaned of foreign matter and properly graded to size.
Coloring: Pigments used shall be inorganic, resistant to alkalinity and
used as per manufacturers recommendations.
d) Drinking Fountain
Model 10155 SM Pet Drinking Fountain — Color Blue - as manufactured by:
Most Dependable Fountains
5705 Commander Drive
Arlington, TN 38002
(901)867-0039
Fax: (901) 867-4008
www.mostdependable.com
Water Quality (Lead Free): Section 9, California Proposition 6 and
the Federal Safe Drinking Water Act.
Standard Pedestal: One piece weld construction with MDF
standard 3/16" wall thickness.
Technical Specifications 4000-24
Receptor Bowl: 18 gauge electro -polished stainless steel bowl.
Bowl overlaps pedestal, preventing buildup of residue in visual
drinking area. Optional stainless steel Bowl Strainer recommended
for areas with sand.
Bottle Filler Spout: Sanitary recessed nozzle.
Bubbler Head: Stainless steel anti -squirt head (weighing a pound
and a half) mounted with a lock nut and washer to prevent
tampering. Lock nut pin holds bubbler in locked position to prevent
twisting or turning. The MDF bubbler head has a unique design
that features a steady stream trajectory and a built in natural shield
from contamination.
Push Bar: 304 stainless steel with circumference exceeding 8.6".
Mushroom style push bar overlaps and prevents sand and other
objects from sticking push bar in the ON position. Stainless steel
bubbler housing standard.
Control Valve: Requires less than 5 lbs to operate. Non -cartridge
O-ring valve delivers steady stream of water through an adjustable
valve. This valve design is to operate and function at 30 to 80 PSI.
Ideal operating pressure is 60 PSI.
Water Supply: Maintenance free reinforced nylobraid tubing - this
tubing is not plastic. It is supplied with a 1/2" MIP threaded inlet
with stainless steel strainer. Union fittings at every connection.
Supply line stops above grade. Water Filter is standard on this
model.
Drain: 1 1/2" schedule 40 PVC pipe. Drain line stops above grade.
Finish: Oven baked powder coat.
Installation: Surface Mount installation, is designed to be anchored
on top of a new or existing surface (concrete,etc.) For a new
surface, a surface mount carrier is recommended. For an existing
surface, anchor bolts are to be used through the attached mounting
plate. Surface Mount Fountains come standard with an access
door with vandal resistant stainless steel screws.
Warranty: One year warranty, labor not included.
Site amenities to be for on a linear foot (LF) basis for the pickleball fencing and
gates, and on a per each (EA) basis for the remaining elements and shall include
furnishing all labor, equipment, tools and materials necessary for installation of the
site amenities per approved plans. The price of this item shall also include any
incidentals for doing the work involved in as defined in the project plans and
specifications.
Technical Specifications 4000-25
18.0 LANDSCAPE AND IRRIGATION (BID ITEMS 6,15 THROUGH 25,27 AND 29
THROUGH 36)
Landscape and irrigation shall conform with Section 800 "Landscape and Irrigation
Materials", and Section 801 "Landscape and Irrigation Installation", of the Standard
Specifications and these Special Provisions.
800-1 LANDSCAPE MATERIALS
Material lists and submittals to be approved by City. Nursery visit for approval by
City.
800-1.2.3 Commercial Fertilizer [Add the following]:
For bidding purposes, commercial fertilizer will bear the manufacturer's
guaranteed statement of analysis and will meet the following minimum
requirements: 16% nitrogen, 20% phosphoric acid, 20% potash, when used from
October to March or, a slow release formulation like 16% nitrogen, 6% phosphoric
acid, 8% potash or 15% nitrogen, 4% phosphoric acid, 6% potash when used from
April to September. Fertilizers will be applied at the rate recommended by the
manufacturer and agronomic soils test recommendations.
800-1.2.4 Organic Soil Amendments
Specified as Type 1.
800-1.2.5 Mulch [Add subsection]:
Type 7 — Decomposed Granite Fines
All planting areas to be covered with 3/8" or 3/4" crushed rock, 3/8" minus
decomposed granite, 6" minus rubble, or 12"-18" cobble as per plan. Color for the
3/4" crushed rock shall be Desert Gold or approved equal; color for the 3/8" crushed
rock shall be Apache Brown or approved equal; color for 3/8" minus decomposed
granite with 20% fines shall be Desert Gold or approved equal; color for 6" minus
cobble shall be Baja Cresta Rubble or approved equal and Cresta Rubble or
approved equal; color for 12"-18" cobble shall be Sierra or approved equal.
Available from Southwest Boulder and Stone, Phone (800) 540-1147 or equal.
Contractor to submit one sample of each type for approval prior to installation.
Technical Specifications 4000-26
800-1.4 Plants
800-1.4.1 General [Add the following]:
All plants will be true to name, trees and plant species will be tagged with the name
and size of plants in accordance with the standards of practice recommended by
the American Association of Nurserymen. The root condition of plants furnished
in containers will be checked. The City's representative will check all plants of
each species or variety from each source. All plants rendered unsuitable will be
rejected and replaced at no additional cost. In case the sample plants are found
to be defective, the entire lot or lots of plants represented by the defective samples
may be rejected.
All trees and shrubs shall be from nurseries in geographical areas with similar
climates and transported covered. The specified standard height and diameter will
be set by the American Standard for Nursery Stock. City will visit local nurseries
or suppliers.
800-1.5.2 Headers and Stakes [delete subsection and add the following]:
Permal-oc landscape edging - 3" height — color: black- AsphaltEdge. Install per
plans and details.
800-1.6 Boulders [Add subsection]:
Size and quantity shall be as shown on the plans. Boulder surface to be free of
cracks, disfragments, and broken or cracked edges. Boulder type shall be granite
"Rustic Brown" as available from Southwest Boulder, Phone (800) 540-1147 or
approved equal. Sample photos shall be submitted to Owner for approval or site
visit will be performed by the City.
800-1.12 Certification and Submittals [Add subsection]:
The following written certifications are required to be submitted to the City upon
delivery of the respective materials to the job site:
a. Total quantity of commercial fertilizers by type
b. Total quantity of inorganic (Crushed Aggregate) and/or organic mulch
C. Total quantity of Decomposed Granite, Crushed Rock, Boulders by
type
d. Total quantity of plants by type
All submitted products may only be used when approved by the City. Substitution
of materials must receive prior, written authorization from the City before delivery
to the site.
800-2 Irrigation System Materials
Technical Specifications 4000-27
800-2.1 Pipe and Fittings
800-2.1.1 General [Add the following]:
Irrigation lateral and pressure lines shall be placed in Schedule 40 PVC pipe sleeve
2 times the pipe size where occurs under streets or paving and as directed by the
City.
800-2.1.3 Plastic Pipe for use with Solvent Weld Socket or Threaded
Fittings [Add the following]:
All pipe 3" and smaller shall be Schedule 40 PVC Type 1, Grade 1 pipe. All plastic
pipes will bear the following markings: the manufacturer's name, nominal pipe size
or schedules.
Main Line Fittings will be solvent welded using pipe primer ASTM F656 and pipe
solvent ASTM D-2564. All other fittings will be solvent welded with pipe solvent
ASTM D-2564, NSF or approved equal.
800-2.4 Sprinkler Equipment
Irrigation heads will be as noted on drawings.
800-3.3 Controller Unit [Add the following]:
The Irrigation Controller shall be of a conventional type that is capable of fully
automatic or manual operation. The controller shall be housed in a strong box
stainless steel enclosure, front entry. The controller shall have the ability to be
programmed and operated in any one of six languages: English, Spanish, French,
German, Italian, & Portuguese. The display shall show programming options and
operating instructions in the chosen language without altering the programming or
operation information.
The controller shall have a maximum station capacity of 48 stations. The controller
shall have a Seasonal Adjustment by program which adjusts the station run time
from 0 to 300% in 1% increments. The controller shall also have a Monthly
Seasonal Adjustment of 0 to 300% by month. Station timing with Seasonal
Adjustment shall be from 1 second to 16 hours.
The controller shall have 4 separate and independent programs which can have
different start times, start day cycles, and station run times. Each program shall
have up to 8 start times per day for a total of 32 possible start times per day. The
4 programs shall be allowed to overlap operation based on user -defined settings
which control the number of simultaneous stations per program and total for the
controller. The controller shall allow up to 8 valves to operate simultaneously per
program and total for the controller including the master valves.
Technical Specifications 4000-28
The controller shall have a 365 -day calendar with Permanent Day Off feature that
allows a day(s) of the week to be turned off on any user selected program day
cycle. (Custom, Even, Odd, Odd31, & Cyclical). Days set to Permanent Day Off
shall override the normal repeating schedule and not water on the specified day(s)
of the week. The controller shall also have a Calendar Day Off feature allowing the
user to select up to 5 dates up to 365 -days in the future when the controller shall
not start programs. The controller shall incorporate a Rain Delay feature allowing
the user to set the number of days the controller should remain off before
automatically returning to the auto mode.
The controller shall have Cycle+Soak water management software which is
capable of operating each station for a maximum cycle time and a minimum soak
time to reduce water run-off. The maximum cycle time shall not extend by
Seasonal Adjustment.
The controller shall incorporate a FloManager feature providing real-time flow,
power, and station management. FloManager shall manage the number of stations
operating at any point in time based on water source capacity, station flow rate,
number of valves per station; user -defined simultaneous stations per program and
for the controller. The controller shall provide station priorities to determine the
order in which stations shall operate. The controller shall ignore the station number
and instead operate the highest priority stations first and the lower priority stations
last.
The controller shall offer Water Windows for each program. This function sets the
allowed start and stop time where watering is allowed. If the watering cannot be
completed by the time the Water Window closes, the stations with remaining run
time are paused and watering automatically resumes when the Water Window
opens the next time.
The controller shall include an integrated Flow Smart Module with flow sensing
functionality. The Flow Smart Module shall accept sensor decoder input from 1 - 5
flow sensors with no flow scaling device required.
A FloWatch Learn Flow Utility which learns the normal flow rate of each station
shall be included. Each time a station runs FloWatch compares the current real-
time flow rate to the learned rate and takes user -defined actions if high flow, low
flow, or no flow is detected. FloWatch shall automatically determine the location of
the flow problem and isolate the problem by turning off the affected station(s) or
master valve(s). FloWatch shall be compatible with both normally closed and open
master valves. A Manual Master Valve Water Window shall be provided to
coordinate daytime manual watering with the flow sensing. This Water Window
shall offer programmable days of the week and manual watering additional flow
rate.
The irrigation controller shall have network communication capability. All network
components shall be noted on plans.
Technical Specifications 4000-29
SECTION 801 LANDSCAPE AND IRRIGATION INSTALLATION
801-1 General [Add the following]:
Landscape and irrigation installation shall conform to the provisions of Section 308
of the Standard Specifications and their provisions.
Contractor shall have appropriate licenses, bonds, insurance and City Business
license.
Contractor to coordinate with other trades.
The CONTRACTOR shall visit the construction site and shall take all
measurements and obtain any other information as may be necessary for a
complete and conclusive bid.
The work required is indicated on the drawings and includes, but is not necessarily
limited to: soil preparation; installing irrigation system; planting and staking trees;
planting shrubs and ground cover, providing and placing decomposed granite,
cobble, weed control and 180 -day plant establishment period including
guaranteeing plants and/or replacing plants (See Section 308-6).
Landscape and irrigation workmanship and materials shall be of the highest
standards and quality.
All landscape materials and installations will be guaranteed against any and all
poor, inadequate or inferior materials and/or workmanship for a period of not less
than 180 days, except all tree species (including palm trees), which shall be
guaranteed for a period of 180 days. During the guarantee period, any material
found to be dead, missing, or in poor condition will be replaced by the Contractor
within five (5) days of written notification. The City's representative will be the sole
judge as to the condition of the material. Replacement will be made in accordance
with these specifications and the plans. Material and labor involved in replacing
plant material will be provided by the Contractor at no expense.
All header board and rock/cobble locations to be laid out for approval prior
to installation of irrigation lines and re -marked prior to placement of rock,
cobble or other material. Layout shall be approved by City and/or Landscape
Architect prior to installation of irrigation and/or material.
801-1.1 Inspections [Add subsection]:
Inspections ensure compliance with the drawings and specifications. The
Contractor will contact the City's representative at least 48 hours (two working
days) in advance of each inspection. An inspection is required at each of the
Technical Specifications 4000-30
following steps including but not limited to:
a) Inspection of rough grade.
b) Acceptance of organic mulch and taking of soil samples.
c) Inspection of soil amendment work.
d) Inspection of plants at nursery and upon delivery to the project site.
e) Layout and acceptance of cobble, crushed rock areas.
f) Irrigation pressure test prior to backfill of trench.
g) Irrigation coverage test.
h) Irrigation main lines, valves, laterals, and wires before backfill or during
irrigation installation.
i) Layout of planting prior to installation.
j) At the start of the establishment period.
k) At the end of the plant establishment period, after final acceptance prior to
maintenance period of the project. Project acceptance will be confirmed in
writing.
1) Completion of hardscape work.
The Contractor is required to notify the City of work activity to be inspected. Give
at least 48 hours' notice for all work. No work will proceed until the City has
inspected and verbally approved the work activity.
801-1.2 Soil Testing — Refer to plans for bidding of soil amendments
[Add subsection]:
Soil testing is required to determine fertility of soil and required nutrient
needs. The Contractor must obtain an agronomic soils test for all planting
areas after soil preparation work but before planting. Tests will be performed
by City approved agronomic soil testing laboratory and will include a fertility
and suitability analysis with written recommendations for soil amendments
including post plant fertilization needs. Results should contain a comparison
between the bid/proposed amendments and the actual amendments
required per the soils test. This comparison will be utilized for the evaluation
of any proposed additional costs between the bid amendments and the
actual amendments required.
EC and SAR ratings shall be included.
The soil report recommendations will take precedence over the minimum
recommended amendment. A copy of the soil's report will be submitted to the City
for approval.
Soil testing will be considered as included in other items of work and no additional
payment will be made therefore.
Technical Specifications 4000-31
801-1.3 Boulders [Add subsection]:
Bury boulders 1/3 of boulder dimension so that they appear in natural state.
Orientation of boulder shall expose most surface area possible set as approved
by Engineer.
801-1.4 Crushed Rock [Add subsection]:
Crushed rock will be an imported material 3/4" in diameter Desert Gold, 3/8" in
diameter for Apache Brown, 6" minus for Baja Cresta Rubble and Cresta Rubble,
12"-18" to be Sierra. Prior to placing crushed rock, fine grade area, removing rocks
greater than 1" diameter, moisture condition, and compact sub -grade material.
Spread crushed rock over the planting area to a 2" depth. Apply moisture after
spreading and raking to compact and remove dust.
801-1.5 3/8" Minus Stabilized Decomposed Granite [Add subsection]:
Decomposed Granite will be an imported material screened to include stone
particle 3/8" minus Stabilizer Solutions Stabilizer Binder for Aggregate Pathways
(or approved equal).
Prior to placing decomposed granite, fine grade area, removing rocks greater than
1" diameter, moisture condition and compact sub -grade material.
Install 3/8" minus with Stabilizer Solutions Stabilizer Binder for Aggregate
Pathways according to manufacturer's recommendations and per plan. Toll Free
Phone number: 800-336-2468.
Stabilizer® shall be thoroughly pre -mixed with aggregate at the rate of 15 -lbs of
Stabilizer® per 1 -ton of aggregate. Verify with manufacturer correct StabilizerC
rate for climate. Drop spreading of Stabilizer over pre -placed aggregate or mixing
by rototilling is not acceptable. Stabilizer shall be mechanically per -mixed per
manufacturer's recommendations using an approved mechanical blending unit to
adequately blend Stabilizer with aggregate (Bucket blending is not and approved
blending apparatus). Always blend Stabilizer and aggregate dry.
After pre -blending, place Stabilized Aggregate directly on prepared sub -grade.
Level to desired grade and cross section.
Water heavily for full depth moisture penetration of profile. Water activates
Stabilizer®. Apply 25 to 45 -gallons of water per 1 -ton to achieve saturation.
Randomly test for depth using a probing device, which reaches full depth.
Contractor shall wait a minimum of 6-72 hours or until such time that the Stabilized
Aggregate is able to accept compaction from a 1 to 5 -ton roller without separation,
plowing or any other physical compromise of the aggregate.
Technical Specifications 4000-32
If surface aggregate dries significantly quicker than subsurface material, lightly
mist surface before compaction.
Compact Stabilized Aggregate to 85% relative compaction by equipment such as;
a 2 to 5 -ton double drum roller making 3 to 4 passes. Do not begin compaction for
6 hours after placement and up to 72 hours. DO NOT use a vibratory plate
compactor or vibration feature on roller, as vibration separates large aggregate
particles. If pumping or pancaking of surface occurs, surface is still too wet to roll.
Take care in compacting surface when adjacent to planting and irrigation systems,
use 8" or 10" hand tamp. Installation of Stabilized Aggregate more than 3" thick
shall be installed in lifts. If 4" thick compacted (2) 2" lifts. If 5" thick compacted (2)
2.5" lifts. If Stabilized Aggregate is pre -moistened before installation entire 4" or 5"
lift may be installed.
Lightly spray surface area following compaction. Do not disturb aggregate surface
with spray action.
Finished surface shall be smooth, uniform and solid with no evidence of chipping
or cracking. Cured and compacted pathway shall be firm throughout profile with no
spongy areas. Loose material shall not be present on surface after installation, but
may appear after use and according to environmental conditions. Pathway shall
remain stable underneath loose granite on top with a "natural" look. Any significant
irregularities in path surface shall be repaired to the uniformity of entire installation.
Contractor shall furnish and install construction fence around new surface to
prevent public access. Fencing shall be maintained in place for a minimum of 12
— 72 hours after completion of installation, or as directed by the City. Drying period
may take longer due to weather conditions.
Contractor shall notify City that landscape irrigation shall be restricted near
Stabilized Aggregate surface until drying period is complete. Standing water on
surface and adjacent to path shall be restricted at all times.
801-2.1 General [Add the following]:
All grading, mounding and all weed control measures shall be completed prior to
irrigation and planting. This work shall not commence until the agronomic soil
test has been completed. Should 30 calendar days elapse between completion
of soil preparation and commencement of planting, all areas will be prepared
again.
Excess soil will be placed on top of exposed wall footings and compacted to 90%
Technical Specifications 4000-33
as required to cover 6" of footing with soil. City will employ Soils Engineer to
provide compaction testing. Contractor shall notify City 48 hours' notice to request
soils testing.
Remove rocks, sticks, grass and other undesirable objects unsuitable to plants.
801-2.2.2 Fertilizers and Conditioning Procedures [Add the following]:
Fertilizers will be applied according to the manufacturer's recommendation.
801-2.3 Finished Grading [Add the following]:
All landscape areas will be graded to finish grades, reestablishing flow lines as
approved prior to amending the soil. Finish grades will be inspected upon
completion. The contractor will not proceed with planting work until finish grades
have been inspected and accepted by the City.
801-2.4 Weed Control Measures [Add the following]:
Apply a translocated herbicide and allow sufficient time to completely kill off all
germinated weeds; herbicide to be reapplied as needed to completely eradicate
all germinated weeds. Weed control shall be to the satisfaction of the City. Refer
to plans.
801-4 PLANTING
801-4.1 General [Add the following]:
All planting holes shall be pre-soaked and backfill shall be as recommended by the
soil test report.
Plant locations with flags labeled with the designated plant/shrub/tree type
are to be approved by the City representative.
Finish grade of crushed rock to be 1" below hardscape.
801-4.5 Tree and Shrub Planting [Add the following]:
The height of the trees will be measured according to ANSI Z60.1 standards.
Grade out planting area prior to planting shrubs. All shrubs will be planted similarly
to the trees, in pre -moistened planting holes, roots loosened and soil gently
compacted around the root ball.
Plant shrubs no closer than outside of the tree's rootball. Immediately after
planting, water plants.
Technical Specifications 4000-34
Trees and shrubs in areas having crushed rock mulch shall be planted two inches
(2") high and decomposed granite will be installed in those areas the same day as
planting. No decomposed granite/crushed rock is to be placed on or in the crown
of trees or shrubs. Rake smooth these plant basins and cover rootballs prior to
final acceptance of 90 -day maintenance period.
801-4.7 Ground Cover and Vine Planting [Add the following]:
Grade out planting area prior to planting shrubs and ground cover. All shrubs and
ground cover will be planted similarly to the trees, in pre -moistened planting holes,
roots loosened and soil gently compacted around the root ball.
Plant shrubs and ground cover no closer than 24 inches to tree trunks and palms.
Immediately after planting, water plants.
801-4.9.5 Watering [Add the following]:
It will be the Contractor's responsibility to maintain a balanced watering program
to ensure all plants receive proper amounts of water, well below the root system
of plants. It is the contractor's responsibility to water (by hand if needed) all plant
material, already planted, and plants still in their containers. Any plant material that
dies as a result of the contractor's neglect shall be replaced by the contractor at
no cost to the City. This includes any equipment needed, labor and materials.
801-5 IRRIGATION SYSTEM INSTALLATION
801-5.1 General [Add the following]:
The drawings are essentially diagrammatic. Minor adjustments may be required
due to differences between the site and drawings.
Dig trenches and support pipe continuously on bottom of the ditch. Lay pipe to a
level grade. Trenching excavation will follow layouts indicated on the drawings to
the depth below finish grades as noted. Provide minimum cover of 24 inches for
main pressure supply lines under pavement, 18 inches of cover if not under
pavement, and 12 inches cover for all lateral lines.
Provide minimum cover of 18 inches, maximum 24 inches for control wires.
Excavation in areas where there are tree roots 2 -inches in diameter and larger will
be tunneled under and will be heavily wrapped with wet burlap to prevent scarring
or dying.
New wiring will occupy the same trench and will be installed along the same route
as the pressure supply lines and will be located below the supply lines wherever
possible. Where more than one wire is placed in a trench, the wiring will be taped
together at Intervals of 12 feet and labeled with numbers at each end of the wire.
Technical Specifications 4000-35
Remote control wire will be direct -burial AWG -UF type, sized according to
manufacturer specifications, and in no case smaller than 14 -gauge. Connections
shall be either epoxy -sealed packet -type or Penn-Tite connectors. Common wires
for valves shall be white in color. Control wires shall be black and numbered. An
extra numbered wire shall be installed from controller to each valve location and it
shall be different (not white) in color.
An extra valve control wire will be installed for every six (6) remote control
valves. Each extra control wire will be of a different color, extended to last valve,
and be looped into each valve box.
801-5.3 Irrigation Pipeline Installation
801-5.3.3 Plastic Pipeline [Add the following]:
All threaded plastic -to -plastic connections will have Teflon tape applied to the male
threads of connection prior to assembly. The number of wraps of Teflon tape shall
be per manufacturer's recommendations or per industry standards.
Connect all metal components to plastic pipe connections with a schedule 80
nipple, threaded one end, and a plastic slip coupling. Use Teflon tape on all male
threads prior to assembly.
801-5.3.5 Sleeving [Add subsection]:
If new sleeving is required, install per plan. Prior to backfilling, attach 1/2" x 2'
long metal pipe at end of pipe for future location assistance.
801-5.5 Sprinkler Head Installation and Adjustment.
801-5.5.2 Location, Elevation, and Spacing. [Add the following]:
Sprinkler heads and drip emitters will be installed as designated on the drawings
and per City Standards. Spacing of the sprinkler heads will not exceed maximum
indicated on the drawings. Drip emitters will be placed 9"-12" up-slope from plants.
801-5.7 Flushing and Testing
801-5.7.1 General [Add the following]:
Irrigation design is based on available water pressure as indicated by CVWD. The
Contractor will verify working water pressure prior to construction. Should a
discrepancy exist, notify the City prior to beginning Construction.
Connections to the installation of the water supply will be at the location shown on
the drawings. Minor changes caused by actual site conditions will be made at no
additional cost to the City. If the water meter and backflow unit is existing refer to
Irrigation plans. Contractor shall run mainline pipe to the as indicated on the plans.
Technical Specifications 4000-36
Prior to installation of irrigation heads, the valves will be opened and full head of
water used to flush out the lines and risers. Sprinkler heads shall not be installed
until flushing the system has been completed.
801-5.7.2 Pipeline Pressure Test [Add the following]:
The main line will be tested for no less than six (6) hours and hold a static pressure
of 125 psi. Lateral lines will be tested for two (2) hours and hold a static pressure
test of 100 psi.
801-6 MAINTENANCE AND PLANT ESTABLISHMENT
801-6.1 General [Add subsection]:
The Contractor shall maintain all landscaped areas for a minimum plant
establishment period of not less than ninety (90) days from the date of
written acceptance of the project. The plant establishment period will not
start until the project receives Final, Formal Acceptance by the City Council.
Projects will not be segmented into phases or accepted in phases. Written
acceptance from the Owner must be obtained to start the plant establishment
period. If the project maintenance fails to continuously meet standards required,
the plant establishment period will be suspended and will not re -commence until
Contractor has corrected all deficiencies.
801-6.2 Maintenance Tasks [Add subsection]:
During the contract period and up to final formal acceptance by the city, the
Contractor shall provide weekly maintenance in the planted areas which are within
the work limits of the contract including, but not limited to: 1) watering; weekly
mowing; weeding; fertilizing and cultivating; and spraying to keep the plants in a
healthy, growing condition and keeping the planted areas neat and attractive; 2)
removing trash a minimum of once a week; 3) checking and repairing irrigation
systems weekly; 4) pruning trees and shrubs planted under the contract only
removing dead, dying or broken branches; 5) removing wilted flowers; 6) pest and
vermin control; and 7) all gravel and non -stabilized decomposed granite areas
shall be raked weekly to the satisfaction of the City. Note: Do not prune trees
or shrubs without first advising the City.
801-6.3 Replacement Plantings [Add subsection]:
After planting and during the plant establishment period in the event any plant
should die, is missing, weak or displays the appearance of necrosis, the plant will
be immediately removed and replaced at the Contractor's expense. All
replacements must occur within five (5) days of notice. At the end of the
establishment period, all plants will be in a healthy, growing condition and located
as indicated on the plan or as approved by the City.
Technical Specifications 4000-37
801-6.4 Fertilizing [Add subsection]:
For non -arid plant material, the Contractor will fertilize the plants one (1) month
prior to the end of the establishment period. Follow manufacturer's application rate
guide and water into planting immediately after applying fertilizers. Arid plant
material will not be fertilized.
801-6.5 Weekly Reports [Add subsection]:
The Contractor, as part of this contract, shall submit reports and schedules as
requested. Failure to submit reports and schedules in the time specified may result
in a Performance Deficiency Deduction. The City will supply the format for these
forms. Such reports must be filled out in detail. The following is a breakdown of
required forms and schedules.
The contractor shall submit these reports as they are completed. Weekly reports
shall be filled out by Friday of every week. Payments due shall not be disbursed
unless all reports have been submitted to the City.
801-6.5.1 Schedule of Weekly Maintenance [Add subsection]:
a) Contractor shall provide a schedule of weekly maintenance identifying
areas to be maintained and a breakdown of when each function shall be
performed.
b) The City will assume that the Contractor will adhere to the schedule. The
City must receive notification of changes at least 12 hours in advance.
801-6.5.2 Weekly Irrigation Inspection Report [Add subsection]:
This will be turned in every Friday.
801-6.5.3 Weekly Activity Report [Add subsection]:
Indicating the following:
a) Litter pickup
b) Weed control
c) Chemical maintenance - herbicides and pesticide applications
d) Incident/Accident
801-6.5.4 Landfill Diversion Report [Add subsection]:
801-6.5.5 Fertilization [Add subsection]:
Technical Specifications 4000-38
801-6.6 Performance Deficiencies and Reduction in Payments Due
[Add subsection]:
The City of La Quinta has set up very specific criteria in which to evaluate the
performance of the Contractor on a weekly basis. If performance by the Contractor
is deficient, the City reserves the right to subtract costs from the monthly billing
and/or hire another contractor to provide the service and deduct the expense from
the contract retention. Since it is difficult to quantify and assess a value to every
aspect of the work, the City shall implement a standard $100 cost per incident.
The following describes deficiencies:
a) Lack of compliance to specifications (i.e., failure to adequately mow, edge,
pick up litter, sweep/rake, weed, prune, remove dead plant material, etc.)
b) Failure to provide specified reports or to falsify reports.
c) Failure to supply adequate equipment, labor or supervision.
d) Failure to repair irrigation deficiencies in the allotted time frame.
e) Failure to comply with schedules. Variances may be approved by request.
Delays in part acquisition or adverse weather conditions will be taken into
consideration.
f) Failure to protect public health and safety.
The City reserves the right to cancel and/or assume maintenance duties and
remaining contract amounts shall be deducted from remaining fiscal
commitment.
801-6.7 End of Establishment Period [Add subsection]:
Approximately one week prior to the end of the establishment period, the City will
conduct a walk-through of the area, noting deficiencies and problems to be
resolved. The Contractor will be required to resolve all noted items. If the items
cannot be resolved within the time remaining, the establishment period will be
extended, without cost to the City, until the items are corrected.
Measurement and Payment:
Bid Items 23, 24, 34, 35 — Construct Landscaping/Irrigation
These items shall be paid for on a lump sum (LS) basis and shall include furnishing all
labor, equipment, tools and materials necessary for construction of landscaping per
approved plans. The price of this item shall also include protecting electrical in place,
exporting soil, grading, providing and installing trees, shrubs, irrigation system, irrigation
controller and any incidentals for doing the work involved in constructing landscaping per
City Standards and project plans and specifications.
Technical Specifications 4000-39
Bid Items 15 and 29 — Furnish and Install Boulders
This item shall be paid for on an each (EA) basis and shall include furnishing all labor,
equipment, tools and materials necessary for construction of boulders per direction of
City, quantity shown in bid schedule. The price of this item shall also include any
incidentals for doing the work involved in placing boulders as defined in the SSPWC and
the Special Provisions. No further compensation will be allowed therefore.
Bid Items 16 through 21 and 30 through 31 - Furnish and Install 3/4" and 3/8" crushed
rock and 3/8" compacted decomposed granite and 6" minus rock and 12"-18" cobble in
accordance to landscaping plans.
These items shall be paid for on a square foot (SF) basis and shall include furnishing all
labor, equipment, tools and materials necessary for placement of decomposed granite
and crushed rock per direction of City, quantity shown in bid schedule. The price of this
item shall also include any incidentals for doing the work involved in placing the rock as
defined in the SSPWC and the Special Provisions. No further compensation will be
allowed therefore.
Bid Items 22 and 32 — Furnish and Install PermaLoc Header — Asphalt Edge
This item shall be paid for on a linear foot (LF) basis and shall include furnishing all labor,
equipment, tools and materials necessary for placement of PermaLoc Asphalt Edge
header per direction of City, quantity shown in bid schedule. The price of this item shall
also include any incidentals for doing the work involved in placing the PermaLoc Asphalt
Edge header as defined in the SSPWC and the Special Provisions. No further
compensation will be allowed therefore.
Bid Item 33 — Boring for Lateral Line
This item shall be paid for on a linear foot (LF) basis and shall include furnishing all labor,
equipment, tools and materials necessary for boring for lateral line per direction of City,
quantity shown in bid schedule. The price of this item shall also include any incidentals
for doing the work involved boring for the lateral line as defined in the SSPWC and the
Special Provisions. No further compensation will be allowed therefore.
Bid Items 25 and 36 — 90 Day Maintenance and Plant Establishment
This item shall be paid for on a lump sum (LS) basis and shall include furnishing all labor,
equipment, tools and materials necessary for maintenance and plant establishment of
constructed landscaping per approved plans. The price of this item shall also include any
incidentals for doing the work involved in maintaining and establishing constructed
landscaping as defined in the project plans and specifications.
END OF SECTION
Technical Specifications 4000-40
APPENDIX A
ESCROW AGREEMENT FOR
SECURITY DEPOSITS IN LIEU OF RETENTION
(3 PAGES)
ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION
This Escrow Agreement is made and entered into by and between the City of La Quinta
whose address is 78-495 Calle Tampico, La Quinta, California, 92253, hereinafter
called City, and hereinafter called
Contractor whose address is , and
hereinafter called Escrow Agent whose address is:
For the consideration hereinafter set forth, the City, Contractor, and Escrow Agent
agree as follows:
1. Pursuant to Section 22300 of the Public Contract Code of the State of California,
Contractor has the option to deposit securities which meet the requirements set
forth in said Section 22300, with Escrow Agent, as a substitute for retention
earnings required to be withheld by City pursuant to the Construction Contract
entered into between City and Contractor for Project No. 2016-031, La Quinta
Landscape Renovation Improvement — Cactus Flower in the amount of
Dollars, dated hereinafter referred to as
the Contract. When Contractor deposits the securities as a substitute for
Contract earnings, the Escrow Agent shall notify the City within 10 days of the
deposit. The market value of the securities at the time of the substitution shall be
at least equal to the cash amount then required to be withheld as retention under
the terms of the Contract between the City and Contractor. Securities shall be
held in the name of City of La Quinta and shall designate the Contractor as the
beneficial owner.
2. City shall make progress payments to Contractor for such funds which otherwise
would be withheld from progress payments pursuant to the Contract provisions,
provided that the Escrow Agent holds securities in the form and amount specified
above.
3. Alternatively, City may make payments directly to Escrow Agent in the amount of
retention for the benefit of the City until such time as the escrow created
hereunder is terminated.
4. Contractor shall be responsible for paying all fees for the expenses incurred by
Escrow Agent in administering the escrow account. These expenses and
payment terms shall be determined by the Contractor and Escrow Agent.
5. The interest earned on the securities or the money market accounts held in
escrow and all interest earned on that interest shall be for the sole account of
Contractor and shall be subject to withdrawal by Contractor at any time and from
time to time without notice to the City.
Appendix A Page 1
6. Contractor shall have the right to withdraw all or any part of the principal in the
Escrow Account only by written notice to Escrow Agent accompanied by written
authorization from City to the Escrow Agent that City consents to the withdrawal
of the amount sought to be withdrawn by Contractor.
7. The City shall have a right to draw upon the securities in the event of default by
the Contractor. Upon seven days' written notice to the Escrow Agent from the
City of the default, the Escrow Agent shall immediately convert the securities to
cash and shall distribute the cash as instructed by the City.
8. Upon receipt of written notification from the City certifying that the Contract is
final and complete, and that the Contractor has complied with all requirements
and procedures applicable to the Contract, Escrow Agent shall release to
Contractor all securities and interest on deposit less escrow fees and charges of
the Escrow Account. The escrow shall be closed immediately upon disbursement
of all moneys and securities on deposit and payments of fees and charges.
9. Escrow Agent shall rely on the written notifications from the City and the
Contractor pursuant to Sections (4) to (6), inclusive, of this Agreement, and City
and Contractor shall hold Escrow Agent harmless from Escrow Agent's release
and disbursement of the securities and interest as set forth above.
10. The names of the persons who are authorized to give written notice or to receive
written notice on behalf of the City and on behalf of Contractor in connection with
the foregoing, and exemplars of their respective signatures are as follows:
On Behalf of City:
Title
Name
Signature
Address
On Behalf of Contractor:
Title
Name
Signature
Address
Appendix A Page 2
On Behalf of Escrow Agent:
Title
Name
Signature
Address
At the time the Escrow Account is opened, City and Contractor shall deliver to the
Escrow Agent a fully executed counterpart of this Agreement.
IN WITNESS WHEREOF, the parties have executed this Agreement by their proper
officers on the date first set forth above.
CITY:
Title
Name
Signature
CONTRACTOR:
Title
Name
Signature
Appendix A Page 3
APPENDIX B
STANDARD PLANS
(8 PAGES)
R -SOD' MIN, 4000' MAX.
T MIM.
5:1 MAX. SLOPE f— !I' TO FL
1d' TO 20' SIS• ..
20' SIDEWALK
EASEMENT
R-600' VA ;b ES 160' TO 220'
R-1000 VARIES 240' TO 280'
3: t MAX. SLOPE
LANDSCAPING IN PARKWAY a SETBACK
TO BE MAINTAINED BY OTHERS, NOT BY CR
(SIDEWALK ONLY, MNNTAINED BYCITY)
-CF
11' TO 12'
PARMAY
z � ap" I
1MN• w 2% �•�
. \ VARIES
6'- 8' r' r MIN.
* SLOPE MAY WCREASE TO 33%
1 BEYOND RIOWT-OF-WAY UNIT
'r WIDTH SHALL BE VON NON4MERIAL STREETSAND
�+ V ON ARTERIAL STREETS OR SHARED GOLF CART USE.
I. RADII FOR CURVED SIDEWALK SK-kLL BE BETWEEN SW AND 400(t
Z ALL RADII SHALL BE STAGGERED,
3. EASEMENT REQUIRED FOR SIDEWALK THAT EXTENDS BEYOND RX3HTOF WAY UNE
4, SDEIAALK SMALL BE A MINIMUM OF & IN WDTH ADJACENT TO CURB
& SDEK'ALK SHALL BE Y AWAY FROM CURB FACE EXCEPT AT CURIB REIURNS AND BUS STOPS.
B. SIDEWALK LAYOUT ON PIANS IS CONCEPTUAL ONLY. APPROVAL OF THE PINAL SIDEWALK
LAYOUT SHALL BE MADE IN THE FIELD AND ADJUSTED AS NECESSARY TO MEET FIELD
CONOITIONS AS APPROVED BY THE INSPECTOR PRIOR TO FINAL CONSTRUCTION.
7. CONCRETE SHALL BE CLASS "C.
REVIM, is DEPAR7IIENT OF pU5UC ",,0"
#b €�AAFL ENONEERM ONISaON
APPROVED SY-
o� a
pure ntr*e c�j p+w
ice mft atn
r 5TA"ARo
4 ft-muo.
245
MEANDERING
SIDEWALK Imo,
I
3
City Street
I
D:
T
"BUTT" JOINT
"GREENBOOK" CLASS B -AR -4000
A.C., 3" LIFT,
OR CITY APPROVED EQUAL
PROPOSED UTILITY
EDGE OF PAVEMENT
A ISEE SECTION A -A BELOW
A ;4
v
EDGE OF PAVEMENT
Less than 12'�--d
SECTION A -A
"BUTT" JOINT
EXISTING BASE
(VARIES IN DEPTH)
EXISTING PAVEMENT
(VARIES IN DEPTH)
"GREENBOOK" CLASS 100-E-100
TRENCH BACKFILL SLURRY, OR
CITY APPROVED CONTROLLED
DENSITY FILL (CDF)
REVISIONS:
08 AP20VOED STANDARD
x
CHRIS A. VOGT hc` °`
CITY ENGINEER TRANSVERSE TRENCH BACKFILL & 600
RCE 44250 PAVING DETAIL # 1 SHEET 1 OF 7
EDGE OF PAVEMENT
SEE SECTION A -A BELOW
City Street A A ;4
—
"GREENBOOK" CLASS B -AR -4000 A.C.,
OR CITY APPROVED EQUAL. 2 LIFTS.
4" MIN.
"BUTT" JOINT �
1'
"GREENBOOK" BASE MATERIAL, DEPTH
VARIES, 434" MIN.
PROPOSED UTILITY -
EDGE OF PAVEMENT
VARIES
(36" — 48")
VARIES
(12" — 24")
SECTION A -A
"BUTT" JOINT
EXISTING BASE
(VARIES IN DEPTH)
EXISTING PAVEMENT
(VARIES IN DEPTH)
TRENCH BACKFILL
REVISIONS:
APPROVED
08/21/01 °` `� � ' ~,�i(/ STANDARD
4 l4P
CHRIS A. VOGT 6 0 0
CITY ENGINEER TRANSVERSE TRENCH BACKFILL & v
RCE 44250
PAVING DETAIL # 2 SHEET 2 OF 7
\
City Street A
I �
�I
t
EDGE OF PAVEMENT
SEE SECTION A -A BELOW
A -4
0.10' DEEP A.C. COLD MILL AND OVERLAY WITH
"GREENBOOK" CLASS C2 -AR -4000 A.C., OR CITY
APPROVED EQUAL
�
"BUTT" JOINT I- 3. VARIES
I� GREATER THAN
EDGE OF PAVEMENT
"GREENBOOK" CLASS B -AR -4000 A.C.,
OR CITY APPROVED EQUAL, 2 LIFTS,
4" MIN.
PROPOSED UTILITY
TRENCH BACKFILL --� VARIES
(GREATER THAN 24")
SECTION A -A
REVISIONS:
APPROVED
08/21/01
CHRIS A. VOGT
CITY ENGINEER
RCE 44250
3' --� /-"BUTT" JOINT
EXISTING BASE
(VARIES IN DEPTH)
EXISTING PAVEMENT
(VARIES IN DEPTH)
"GREENSOOK" BASE MATERIAL, DEPTH
VARIES, 4h" MIN.
(FRSE TRENCH BACK,
PAVING DETAIL # 3
STANDARD
• 1 1
SHEET 3 OF 7
3
City Street
- U DIAN fTYP-)—
LANE LINE (TYP.)
a
La SEE SECTION A -A BELOW
'GREENBOOK' SEALCOAT, OR CITY. -1
APPROVED EQUAL
VARIES
(WIDTH OF PARKING LANE)
IN DEPTH
TRENCH PAVEMENT SECTION
PROPOSED UTILITY—
TRENCH BACKFILL SECTION
NOTE
VARIES
SECTION A -A
EXISTING CURB
AND GUTTER
TRENCH BASE SECTION
*NOTE: FOR SPECIFIC TRENCH
BACKFILL AND INITIAL PAVING
REQUIREMENTS, REFER TO THE
TRANSVERSE TRENCH BACKFILL
AND PAVING DETAILS, AS APPRO-
PRIATE FOR THE TRENCH WIDTH.
REVISIONS:
AQP8P OVE❑D ��� , STANDARD
CHRIS A. VOGT 600
CITY ENGINEER LONGITUDINAL TRENCH BACKFILL
RCE 44250
& PAVING DETAIL # 1 SHEET 4OF 7
City Street
MEDIAN (TYP.)
S SEE SECTION A -A BELOW
LANE LINES (TYP.)
0.10' DEEP A.C. COLD MILL AND OVERLAY WITH
"GREENBOOK" CLASS C2 -AR -4000 A.C., OR CITY
APPROVED EQUAL
VARIES
"BUTT" JOINT (WIDTH OF TRAVEL LANE, 12' TYP.)
::�\ /_ 'BUTT' JOINT
TRENCH PAVEMENT SECTION
PROPOSED UTILITY
TRENCH BACKFILL SECTION -
*SEE NOTE
VARIES
SECTION A -A
L- EXISTING BASE
(VARIES IN DEPTH)
EXISTING PAVEMENT
(VARIES IN DEPTH)
TRENCH BASE SECTION
*NOTE: FOR SPECIFIC TRENCH
BACKFILL AND INITIAL PAVING
REQUIREMENTS, REFER TO THE
TRANSVERSE TRENCH BACKFILL
AND PAVING DETAILS, AS APPRO-
PRIATE FOR THE TRENCH WIDTH.
REVISIONS:
AOgP OVEED a � "° STANDARD
4 CHRIS A. VOGT °""°,m� GOO
CITY ENGINEER LONGITUDINAL TRENCH BACKFILL V
RCE 44250
& PAVING DETAIL # 2 SHEET 5 OF 7
TRENCH BACKFILL AND
PAVEMENT RESTORATION REQUIREMENTS
(Requirements Vary Based on Excavated Width of Trench)
1. Trenches less than 12" wide (See Detail 1)
(Typically excavated with a rock saw or other similar methods.)
• Backfill Requirements:
o CDF, or 1 -sack slurry backfill ONLY
o Backfill up to 3" below finish surface of street
o Testing not required
o Backfill depth independent of street structural section
• Resurfacing Requirements:
0 V -saw cut at trench edge is NOT REQUIRED if trench edges are vertical, straight,
and stable.
o Tack oil coat at edges
o Paving with 3/8" A.C. material
■ In one lift
■ Depth of 3", flush with finish surface of street
■ Compaction via mechanical vibrating hand compactor or other mechanical
means
■ Compaction to 95%
• Testing not required
• No grinding or capping with 1/2" A.C. material required
2. Trenches 12" to 24" Wide (See Detail 2)
(Typically excavated with backhoe bucket or other similar methods.)
• Backfill Requirements:
o CDF or 1 -sack slurry backfill (optional)
■ No testing required
o Native or select material backfill
■ Compaction via special conditions to 90%
■ Backfill depth up to appropriate subgrade elevation
■ Testing required
o Crushed Aggregate or Crushed Miscellaneous Base material backfill
• Compaction to 95%
■ Backfill depth up to appropriate base grade elevation (4'/Z" minimum)
■ Testing required
■ Backfill depths dependent upon street structural section
REVISIONS:
APPROVED T4ht 4,�;�,,,�t�
08/21/01 �ikllA� STANDARD
s
CHRIS A. VOLT G+oo
CITY ENGINEER TRENCH BACKFILL & PAVEMENT V
RCE 44250 RESTORATION REQUIREMENTS
SHEET 6 OF 7
12" to 24" Trench (continued...)
• Resurfacing Requirements:
0 1' -saw cut required at trench edges
o Tack oil coat all saw -cut edges
o Total section 1 " thicker than existing A.C. section (4" minimum)
o Two, or more, lifts
■ Base Course: 3/4" A.C. material
• Compaction via vibroplate, tamper, or other mechanical means
• Compaction to 95%
• Testing required
■ Finish Paving/Cap Course, 1 " Thick: 1/2" A.C. material
• Compaction via roller
• Compaction to 95%
• Testing not required
3. Trenches More Than 24" Wide (See Detail 3)
(Typically excavated with a backhoe bucket or other similar methods.)
• Backfill Requirements:
CDF or 1 -sack slurry backfill (optional)
■ No testing required
Native or select material backfill
■ Compaction via special conditions to 90%
■ Backfill depth up to appropriate sub grade elevation
■ Testing required
Crushed Aggregate or Crushed Miscellaneous Base material backfill
■ Compaction to 95%
■ Backfill depth up to appropriate base grade elevation (4'/z" minimum)
■ Testing required
■ Backfill depths dependent upon street structural section
• Resurfacing Requirements:
0 1' -saw cut required at trench edges
o Tack oil coat at all saw -cut edges Base paving with 3/4" A.C. material
o Total Section 1 " thicker than existing A.C. section (4" minimum)
o Two, or more, lifts
■ Base Course: 3/4" A.C. material
• Compaction via vibroplate, tamper, or other mechanical means
• Compaction to 95%
• Testing required
■ Finish Paving/Cap Course, 0.1' Thick: 112" A.C. material
• Compaction via roller
• Compaction to 95%
• Testing not required
0 3' -grind beyond 1' -saw cut at trench edges
■ Depth of grind to 0.10' below existing finish surface of street
(grind after paving base lift)
REVISIONS:
APPROVED STANDARD
08/21/01 0.1CHRIS A. VOGT C 4 !�
600
CITY ENGINEER TRENCH BACKFILL & PAVEMENT
RCE 44250 RESTORATION REQUIREMENTS
SHEET 7 OF 7