BRES2022-0164 Certificate of InstallationSPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-01-E
(Page 1 of 8)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. General Information
01
Dwelling Unit Name
DEH MECHANICAL
02
Climate Zone
15
03
Dwelling Unit Total Conditioned
Floor Area (ft2)
2315
04
Number of Space Conditioning
Systems in this Dwelling Unit.
3
05
Certificate of Compliance Type
p yp
Prescriptive alterations CF1R-ALT
p ( )
06
Method Used to Calculate HVAC
Loads (See Section 150.0(h))
Not applicable - equipment chan eout, like -for -like
ppchangeout,
Calculated Dwelling Unit
Sensible Cooling Load (Btu/h)
n/a
08
Calculated Dwelling Unit Heating
Load (Btu/h)
n/a
09
Dwelling Unit Number of
Bedrooms
3
MCH-Olb - Space Conditioning Systems Ducts and Fans - Prescriptive Alterations
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 2 of 8)
B. Space Conditioning (SC) System Information
01
02
03
04
05
06
07
08
09
10
SC System ID/
Name from
parent CC
SC System
Description of
Area Served
CFA served by this
SC System (ft2)
Is the SC system a
ducted system?
Does work
include installing
a refrigerant
containing
component?
Does work
include installing
new SC system
components?
Does work
include installing
more than 25 feet
of ducts?
Does work
include installing
an "entirely new
duct system"?
Does work
include installing
an "entirely new
SC system"?
Alteration Type
System 1
Kitchen living
room
771
Yes
Yes
Yes
No
No
No
Altered space
conditioning
system
System 2
Master
772
Yes
Yes
Yes
No
No
No
Altered space
conditioning
system
System 3
Casita
772
Yes
Yes
Yes
No
No
No
Altered space
conditioning
system
Notes:
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 3 of 8)
C. Space Conditioning (SC) System Alterations Compliance Information
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
SC System
ID/ Name
from
parent CC
SC System
Description
of Area
Served
Heating
System
Type
Altered
Heating
Componen
t
Heating
Efficiency
Type
Heating
Minimum
Efficiency
Value
Cooling
System
Type
Altered
Cooling
Componen
t
Cooling
Efficiency
Type
Cooling
Minimum
Efficiency
Value
SEER/SEER
2
Cooling
Minimum
Efficiency
Value
EER/EER2/
CEER
Required
Thermostat
Type
Number of
Indoor
Units for
this System
Number of
Ducted
Indoor
Units for
this System
Central Fan
Integrated
(CFI)
Ventilation
System
Status
System 1
Kitchen
living room
Electric
All new
heating
component
s
HSPF
8
Central
split HP
All new
cooling
component
s
EER/SEER
14
11.7
Setback
n/a
1
Not a CFI
system
System 2
Master
Electric
All new
heating
component
s
HSPF
8
Central
split HP
All new
cooling
component
s
EER/SEER
14
11.7
Setback
n/a
1
Not a CFI
system
System 3
Casita
Electric
All new
heating
component
s
HSPF
8
Central
split HP
All new
cooling
component
s
EER/SEER
14
11.7
Setback
n/a
1
Not a CFI
system
Notes:
D. Installed Heating Equipment Information for Gas Furnace
Indoor Unit, or Heat Pump Indoor Unit, or Packaged Unit (Gas Furnace or Heat Pump)
01
02
03
04
05
06
07
08
09
10
SC System ID/
Name from
parent CC
SC System
Description of
Area Served
Heating Efficiency
Type
Heating Efficiency
Value
Indoor Unit or
Packaged Unit
Manufacturer
Indoor Unit or
Packaged Unit
Model Number
Indoor Unit or
Packaged Unit
Serial Number
SC System Rated
Heating Capacity,
Output (Btu/h)
Multi -Split Systems only
Indoor Unit Name
or Description of
Area Served
Indoor Unit Duct
Status
System 1
Kitchen living
room
HSPF
8
AMANA
ASPT49D14AD
2310013748
8
n/a
n/a
System 2
Master
HSPF
8
AMANA
ASPT37C14AC
2204393336
8
n/a
n/a
System 3
Casita
HSPF
8
AMANA
ASPT29B14AB
ASPT29B14AB
8
n/a
n/a
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 4 of 8)
E. Installed Cooling Equipment Information for Outdoor Condenser or Packaged Unit (Air Conditioner or Heat Pump)
01
02
03
04
05
06
07
08
09
10
SC System ID/
Name from
parent CC
SC System
Description of
Area Served
Cooling Efficiency
Type
Cooling Efficiency
Value SEER/SEER2
Cooling Efficiency
Value EER/EER2/CEER
Condenser or Package
Unit Manufacturer
Condenser or Package
Unit Model Number
Condenser or
Package Unit
Serial Number
System Cooling
Capacity at
Design
Conditions
(Btu/h)
Condenser
Nominal
Capacity (tons)
System 1
Kitchen living
room
EER/SEER
14
11.7
AMANA
ASZ160481LB
2206430160
48000
4
System 2
Master
EER/SEER
14
11.7
AMANA
ASZ160361LB
2205076869
36000
3
System 3
Casita
EER/SEER
14
11.7
GOODMAN
GSZH502410AA
2309240920
24000
2
Notes:
F. Altered Space Conditioning System Duct Information (< 75%
of duct system is altered; or duct system is not altered)
01
02
03
04
05
06
07
08
09
10
11
12
SC System ID/
Name from
parent CC
SC System
Description of
Area Served
Indoor Unit
Name or
Description of
Area Served
Was Any New
Ducting
Installed?
Required New
Duct R-Value
Installed New
Supply Duct
Location
Installed New
Supply Duct
R-value
Installed New
Return Duct
Location
Installed New
Return Duct
R-Value
Exception
from Min
R-Value
Can Approved
Airflow
Protocols be
used to test
this System?
Indoor Unit
Nominal
Cooling
capacity (tons)
System 1
Kitchen living
room
Kitchen living
room
Both Supply
and Return
R-6
n/a
R-8
n/a
R-8
No Exception
Yes
n/a
System 2
Master
Master
Both Supply
and Return
R-6
n/a
R-8
n/a
R-8
No Exception
Yes
n/a
System 3
Casita
Casita
Both Supply
and Return
R-6
n/a
R-8
n/a
R-8
No Exception
Yes
n/a
G. Installed New or Complete Replacement Duct System Information
This section does not apply to this project.
H. Installed Air Filter Device Information
This section does not apply to this project.
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 5 of 8)
I. Air Filter Device Requirements
This section does not apply to this project.
J. HERS Verification Requirements for Duct Systems
01
02
03
04
05
06
07
08
09
SC System
Identification or
Name
SC System
Description of Area
Served
Indoor Unit Name
or Description of
Area Served
Exemption From
Duct Leakage
Requirements
MCH-20
Duct Leakage Test
MCH-21
Duct Location
Verification
MCH-22
AHU Fan Efficacy
(W/cfm)
MCH-23
AHU Airflow Rate
(cfm/ton)
MCH-28
Return Duct Design
- Table 160.3-A or B
System 1
Kitchen living room
Kitchen living room
None
Yes
No
No
Yes
No
System 2
Master
Master
None
Yes
No
No
Yes
No
System 3
Casita
Casita
None
Yes
No
No
Yes
No
Notes:
K. HERS Verification Requirements For Space Conditioning Equipment
01
02
03
SC System ID/ Name from parent CC
SC System Description of Area Served
MCH-25
Refrigerant Charge
System 1
Kitchen living room
Yes
System 2
Master
Yes
System 3
Casita
Yes
Notes:
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 6 of 8)
L. Space Conditioning Systems, Ducts and Fans Mandatory Requirements and Additional Measures
Additional mandatory requirements from Section 150.0 that are not listed here may be applicable to some systems. These requirements may be applicable to only newly
installed equipment or portions of the system that are altered. Existing equipment may be exempt from these requirements.
Heating Equipment
01
Equipment Efficiency: All heating equipment must meet the minimum efficiency requirements of Section 110.1 and Section 110.2(a) and the Appliance Efficiency Regulations.
02
Controls: All unitary heating systems, including heat pumps, must be controlled by a setback thermostat. These thermostats must be capable of allowing the occupant to program the
temperature set points for at least four different periods in 24 hours. See Sections 150.0(i), 110.2(b).
03
Sizing: Heating load calculations must be done on portions of the building served by new heating systems to prevent inadvertent undersizing or oversizing. See sections 150.0(h)1 and
2).
04
Furnace Temperature Rise: Central forced -air heating furnace installations must be configured to operate at or below the furnace manufacturer's maximum inlet -to -outlet temperature
rise specification. See Section 150.0(h)4.
05
Standby Losses and Pilot Lights: Fan -type central furnaces may not have a continuously burning pilot light. Section 110.5 and Section 110.2(d).
Cooling Equipment
06
Equipment Efficiency: All cooling equipment must meet the minimum efficiency requirements of Section 110.1 and Section 110.2(a) and the Appliance Efficiency Regulations.
07
Refrigerant Line Insulation: All refrigerant line insulation in split system air conditioners and heat pumps must meet the R-value and protection requirements of Section 150.0(j)2 and 3,
and Section 150.0(m)9.
08
Condensing Unit Location: Condensing units shall not be placed within five (5) feet of a dryer vent outlet. See Section 150.0(h)3A.
09
Liquid Line Filter Drier: A liquid line filter drier shall be installed according to the manufacturer's specifications 150.0(h)3B
10
Sizing: Cooling load calculations must be done on portions of the building served by new cooling systems to prevent inadvertent undersizing or oversizing. See Section 150.0(h)1 and 2.
Air Distribution System Ducts, Plenums and Fans
11
Insulation: The minimum duct insulation value is R-6 or ducts can be uninsulated if the duct system is located entirely in conditioned space. Note that higher values may be required by
the prescriptive or performance requirements. See Section 150.0(m)1B for exceptions.
12
Connections and Closures: All installed air -distribution system ducts and plenums must be, sealed and insulated to meet the requirements of CMC Sections 601.0, 602.0, 603.0, 604.0,
605.0 and ANSI/SMACNA-006-2006.
Heat Pump Thermostat
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 7 of 8)
L. Space Conditioning Systems, Ducts and Fans Mandatory Requirements and Additional Measures
Additional mandatory requirements from Section 150.0 that are not listed here may be applicable to some systems. These requirements may be applicable to only newly
installed equipment or portions of the system that are altered. Existing equipment may be exempt from these requirements.
13
A thermostat shall be installed that meets the requirements of Section 110.2(b) and Section 110.2(c).
14
The thermostat shall be installed in accordance with the
manufacturers published installation specifications
15
First stage of heating shall be assigned to heat pump
heating.
16
Second stage back up heating shall be set to come on
only when the indoor set temperature cannot be met.
The responsible person's signature on this compliance document
affirms that all applicable requirements in this table have been
met.
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
SPACE CONDITIONING SYSTEMS, DUCTS, AND FANS
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-01-E
(Page 8 of 8)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation
niAuthor Signature:
!�'
A A E:I��
Company:
iPermit
SignaturFD ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Installation is true and correct.
2. II am either: a) a responsible person eligible under Division 3 of the Business and Professions Code in the applicable classification to accept responsibility for the
system design, construction, or installation of features, materials, components, or manufactured devices for the scope of work identified on this Certificate of
Installation, and attest to the declarations in this statement, or b) I am an authorized representative of the responsible person and attest to the declarations in this
statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on this Certificate of Installation conforms to all
applicable codes and regulations and the installation conforms to the requirements given on the Certificate of Compliance, plans, and specifications approved by the
enforcement agency.
4. I understand that a registered copy of this Certificate of Installation shall be posted or made available with the building permit(s) issued for the building, and made
available to the enforcement agency for all applicable inspections, and I will take the necessary steps to ensure this requirement is accomplished.
5. I understand that a registered copy of this Certificate of Installation is required to be included with the documentation the builder provides to the building owner at
occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Builder/Installer Siig�nature�
Signature:
ResponssiblePic2 _�gtuc
A v blBuA re -
Company Name: (Installing Subcontractor or General Contractor or Builder/Owner)
DEH Mechanical Company Inc
With
Position Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number: 423-A020204948A-000-001-M01001A-0000 Registration Date/Time: 2023-12-04 08:30:27 HERS Provider: CHEERS
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or related to CHEERS. Therefore, CHEERS is not responsible for,
and cannot guarantee, the accuracy or completeness of the information contained in this document.
CA Building Energy Efficiency Standards - 2022 Residential Compliance Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
Schema Version: rev 20220101
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-20-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
01
Space Conditioning System Identification or Name
System 1
02
Space Conditioning System Location
or Area Served
Kitchen living room
03
Indoor Unit Name or Description
of Area Served
Kitchen living room
04
Building Type from from parent CC
Single family
05
Verified Low Leakage Ducts in Conditioned
from parent CC?
Space (VLLDCS) Credit
No, credit is not taken
06
Verified Low Leakage Air Handling
Unit Credit from parent CC?
No, credit is not taken
07
Duct System Compliance Category
New
08
Portions of Duct Located in Garage?
No
09
Is the system type Small Duct High Velocity (SDHV) ?
No
MCH-20a - Completely New Duct System
Registration Number:
423-A020204948A-000-001-M 20002A-0000
Registration Date/Time: 2023-12-04 08:30:39 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 2 of 4)
B. Duct Leakage Diagnostic Test
01
Air Handling Unit Airflow (AHU Airflow) Determination Method
Cooling system method
02
Condenser Nominal Cooling Capacity (ton)
4
03
Indoor Unit Nominal Cooling Capacity
4
04
Heating Capacity (kBtu/h)
n/a
05
Conditioned Floor Area Served by this HVAC System (ft2)
771
06
Measured AHU Airflow (cfm)
n/a
07
Duct Leakage Test Conditions
Test final
08
Duct Leakage Test Method
Total leakage
09
Leakage Factor
0.05
10
Calculated Target Allowable Duct
Leakage (cfm)
80
11
Actual Duct Leakage Rate from Leakage Test Measurement (cfm)
80
12
Compliance Statement
System passes leakage test
Registration Number:
423-A020204948A-000-001-M 20002A-0000
Registration Date/Time: 2023-12-04 08:30:39 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 3 of 4)
C. Additional Requirements for Compliance
01
System was tested in its normal operation condition. No temporary taping allowed.
02
Outside air (OA) duct connections to the central forced air duct system shall not be sealed/taped off during duct leakage testing. OA
ducts used for Central Fan Integrated (CFI) Indoor Air Quality ventilation systems, or Central Fan Ventilation Cooling Systems, that utilize
dampers that open only when OA is required and automatically close when OA is not required, may configure the OA damper to the
closed position during duct leakage testing.
03
All supply and return register boots were sealed to the drywall.
04
Building cavities were not used as plenums or platform returns in lieu of ducts.
05
If cloth backed tape was used it was covered with Mastic and draw bands.
06
All connection points between the
air handler and the supply and return plenums are completely
sealed.
Visual Inspection at Final Construction
After installing the interior finishing wall
Stage (applicable if system was tested at rough -in).
and verifying that the above rough -in tests was completed, the following procedure must be performed
07
For all supply and return registers,
verify that the spaces between the register boot and the interior
finishing wall are properly sealed.
08
If the house rough -in duct leakage
handler and the supply and return
test was conducted without an air handler installed, inspect the
plenums to verify that the connection points are properly sealed.
connection points between the air
09
Inspect all joints to ensure that no
cloth backed rubber adhesive duct tape is used.
The responsible person's signature on this
compliance document affirms that all applicable requirements
in this table have been met.
Registration Number:
423-A020204948A-000-001-M 20002A-0000
Registration Date/Time: 2023-12-04 08:30:39 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 20002A-0000
Registration Date/Time: 2023-12-04 08:30:39 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CERTIFICATE OF INSTALLATION
CF2R-MCH-23-H
(Page 1 of 3)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. Ducted Cooling System Information
01
Space Conditioning System Identification or Name
System 1
02
Space Conditioning System Description of Area Served
Kitchen living room
03
Indoor Unit Name
Kitchen living room
04
System Installation Type
New
05
Nominal Cooling Capacity (tons)
4
06
Condenser Speed Type
n/a
07
Cooling System Zonal Control Type
n/a
08
Central Fan Integrated (CFI) Ventilation System Status
Not a CFI system
09
System Bypass Duct Status
n/a
10
Date of System Airflow Rate Measurement
2023-12-04
11
Airflow Rate Protocol Utilized
RA3.3 procedures for airflow rate measurement
12
Central Fan Ventilation Cooling System Status
Not a CFVCS
B. Hole for the placement of a Static Pressure Probe (HSPP), and Permanently Installed Static Pressure Probe (PSPP) in the Supply Plenum.
Procedures for installing HSPP or PSPP are specified in RA3.3.1.1.
01
Method Used to Demonstrate Compliance with the HSPP/PSPP
Requirement
HSPP installed and labeled consistent with Figure RA3.3-1
Registration Number:
423-A020204948A-000-001-M 23003A-0000
Registration Date/Time: 2023-12-04 08:31:01 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF2R-MCH-23-H
(Page 2 of 3)
C. Airflow Rate Measurement Apparatus and Procedure Information
Instrument Specifications are given in RA3.3.1.1, and system airflow rate measurement apparatus information is given in RA3.3.2.
01
Airflow Rate Measurement Type used for this airflow rate
verification.
Traditional Flow Capture Hood according to procedure in
RA3.3.3.1.4
02
Manufacturer of Airflow Measurement Apparatus
TESTO
03
Model number of Airflow Measurement Apparatus
420
04
Certification Status of the Airflow Measurement Apparatus
Accuracy
Certified by Manufacturer and listed on CEC Website at
http://www.energy.ca.gov/title24/equipment_cert/ama_fas/index.
html
MCH-23a Forced Air System Airflow Rate Measurement - Newly Installed Non -Zoned Systems or Zoned Multi -Speed Compressor
D. Forced Air System Airflow Rate Measurement
The procedures for System Airflow Rate Verification are specified in Reference Residential Appendix RA3.3.
01
Required Minimum System Airflow Rate (cfm/ton)
350
02
Required Minimum System Airflow Target (cfm)
1400
03
Actual System Airflow Rate Measurement (cfm)
1449
04
Compliance Statement:
System airflow rate complies
E. Additional Requirements
01
Air filters that meet the applicable requirements of Standards Section 150.0(m)12 or 150.0(m)13 were properly installed in the system
during system air flow rate measurement identified on this Certificate of Installation.
02
The airflow rate measurement apparatus used to perform the airflow rate measurement identified on this Certificate of Installation was
calibrated in accordance with the apparatus manufacturer's specifications and conforms to the instrumentation specifications given in
RA3.3.1.
03
A visual inspection shall confirm that bypass ducts that deliver conditioned supply air directly to the space conditioning system return
duct airflow are not used on newly constructed zonally controlled systems unless the Performance Certificate of Compliance indicates an
allowance for use of a bypass duct. When a bypass duct is accounted for on the Performance Certificate of Compliance, the airflow rate
shall conform to the specifications listed on the Certificate of Compliance.
04
All registers were fully open during the diagnostic test.
05
System fan was set at maximum speed during the diagnostic test.
06
If fresh air duct is part of the HVAC system it was not closed during the diagnostic test.
07
Airflow rate and fan watt draw shall be simultaneous measurements when used to calculate the Fan Efficacy tested value.
08
Multi -speed compressor space cooling systems or variable speed compressor systems shall verify air flow (cfm/ton) and fan efficacy
(Watt/cfm) with system operating in cooling mode at the maximum compressor speed and the maximum air handler fan speed.
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met.
Registration Number:
423-A020204948A-000-001-M 23003A-0000
Registration Date/Time: 2023-12-04 08:31:01
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:11:52
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF2R-MCH-23-H
(Page 3 of 3)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 23003A-0000
Registration Date/Time: 2023-12-04 08:31:01 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-25-H
(Page 1 of 5)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
Each system requiring refrigerant charge verification will be documented on a separate certificate.
01
Space Conditioning System Identification or Name
System 1
02
Space Conditioning System Location or Area Served
Kitchen living room
03
Condenser (or package unit) Make or Brand
AMANA
04
Condenser (or package unit) Model Number
ASZ160481LB
05
Nominal Cooling Capacity (tons) of Condenser
4
06
Condenser (or package unit) Serial Number
2206430160
07
Refrigerant Type
R-410A
08
Other Refrigerant Type (if applicable)
n/a
09
Liquid Line Filter Drier Installed According to Manufacturers
Specifications (if applicable)
Yes
10
System Installation Type
New
11
Fault Indicator Display (FID) Status (Note: Even systems with a FID
must have refrigerant charge verified by installer).
This system does not have a FID device installed
12
Is the system of a type that the minimum airflow can be verified for
all indoor units using an approved measurement procedure (RA3.3
or RA3.3.3)?
Yes
13
Is the system of a type that approved refrigerant charge verification
procedures can be used to verify compliance with the refrigerant
charge verification requirements when temperatures are >= 55 °F
(RA3.2.2, or RA1)?
Yes, one of the Refrigerant charge verification procedures from
RA3.2.2 or RA1 is applicable to this system and can be used to
verify compliance
14
Date of Refrigerant Charge Verification for this system
2023-12-04
15
Refrigerant charge verification method used.
Subcooling (outdoor temperature must be equal to or greater than
55 degF)
16
Person who performed the Refrigerant Charge Verification
reported on this Certificate of Installation
HERS rater
17
HERS Verification Compliance Requirement Status
System does not qualify for group sampling
Registration Number:
423-A020204948A-000-001-M 25008A-0000
Registration Date/Time: 2023-12-04 08:36:18
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:11:56
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-25-H
(Page 2 of 5)
MCH-25b - Refrigerant Charge Verification - Subcooling Method
B. Metering Device Verification
Subcooling Method can only be used on systems that have a variable metering device.
01
Refrigerant metering device
Thermostatic Expansion Valve (TXV)
02
Subcooling Method applicability status
Subcooling Method is applicable to this system.
C. Instrument Calibration
Procedures for instrument calibration are given in Reference Residential Appendix RA3.2.2 and RA3.2.2.2
01
Date of Digital Refrigerant Gauge Calibration
2023-11-30
02
Date of Digital Thermocouple Calibration
2023-11-30
03
Digital Refrigerant Gauge Calibration Status
Calibration is current
04
Digital Thermocouple Calibration Status
Calibration is current
D. Measurement Access Hole (MAH) Verification
Procedures for installing MAH are specified in Reference Residential Appendix RA3.2.2.3
01
Method Used to Demonstrate Compliance with the Measurement
Access Hole (MAH) Requirement
MAH installed and labeled consistent with Figure 3.2-1
E. Minimum System Airflow Rate Verification
Procedures for verifying minimum system airflow are specified in Reference Residential Appendix RA3.3.3.
01
02
03
Indoor Unit Name or Description of Area
Served
Minimum Required System Airflow Rate (cfm)
System Airflow Rate Verification Status
Kitchen living room
1400
System complies with minimum airflow rate
requirements
04
SC System complies with Minimum System Airflow Rate Verification
Notes:
Registration Number:
423-A020204948A-000-001-M 25008A-0000
Registration Date/Time: 2023-12-04 08:36:18 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 3 of 5)
F. Data Collection and Calculations
Procedures for determining Refrigerant Charge using the Standard Charge Verification Procedure are given in Reference Residential Appendix
RA3.2.2.
01
Lowest Return Air Dry Bulb Temperature that Occurred During the
Refrigerant Charge Verification Procedure (°F)
85
02
Measured Condenser Air Entering Dry -Bulb Temperature
(Tcondenser,db)
70
03
Outdoor Temperature Qualification Status
Outdoor temperature is within range for using Subcooling
refrigerant charge verification method
04
Measured Liquid Line Temperature (Tiiquid) (°F)
75.0
05
Measured Liquid Line Pressure (Piiquid) (psig)
283.0
06
Condenser Saturation Temperature (Tcondenser, sat) from Digital
Gauge or P-T Table using Line F05 (°F)
80.1
07
Measured Subcooling (Line F06 - Lilne F04 (°F)
5.1
08
Target Subcooling from Manufacturer (°F)
8
09
Compliance Statement:
System complies with Subcooling Method - Must also pass
metering device verification, next section
G. Metering Device Verification
Procedures for the verification of proper metering device operation are specified in RA3.2.2.6.2
01
Measured Suction Line Temperature (Tsuction) (°F)
53.0
02
Measured Suction Line Pressure (Psuction) (psig)
135.9
03
Evaporator Saturation Temperature (Tevaporator, sat) from Digital
Gauge or P-T Table using Line G02 (°F)
43.6
04
Measured Superheat (Line G01- Line G03) (°F)
9.4
05
Measured Superheat (Line G04) is between 4 °F and 25 °F
(inclusive)
Passes CEC requirement
06
Measured Superheat (Line G04) is within Manufacturer's
Specifications ( if known)
Yes, documentation to be provided upon request
07
Compliance Statement
Metering device verification passes
MCH-25d - Refrigeration Charge Verification - Fault Indicator Display (FID)
H. Fault Indicator Display
This section does not apply to this project.
Registration Number:
423-A020204948A-000-001-M 25008A-0000
Registration Date/Time: 2023-12-04 08:36:18
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 4 of 5)
I. Fault Indicator Display Additional Requirements
This section does not apply to this project.
Registration Number:
423-A020204948A-000-001-M 25008A-0000
Registration Date/Time: 2023-12-04 08:36:18 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 5 of 5)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 25008A-0000
Registration Date/Time: 2023-12-04 08:36:18 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-20-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
01
Space Conditioning System Identification or Name
System 2
02
Space Conditioning System Location
or Area Served
Master
03
Indoor Unit Name or Description
of Area Served
Master
04
Building Type from from parent CC
Single family
05
Verified Low Leakage Ducts in Conditioned
from parent CC?
Space (VLLDCS) Credit
No, credit is not taken
06
Verified Low Leakage Air Handling
Unit Credit from parent CC?
No, credit is not taken
07
Duct System Compliance Category
New
08
Portions of Duct Located in Garage?
No
09
Is the system type Small Duct High Velocity (SDHV) ?
No
MCH-20a - Completely New Duct System
Registration Number:
423-A020204948A-000-001-M 20004A-0000
Registration Date/Time: 2023-12-04 08:31:13 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 2 of 4)
B. Duct Leakage Diagnostic Test
01
Air Handling Unit Airflow (AHU Airflow) Determination Method
Cooling system method
02
Condenser Nominal Cooling Capacity (ton)
3
03
Indoor Unit Nominal Cooling Capacity
3
04
Heating Capacity (kBtu/h)
n/a
05
Conditioned Floor Area Served by this HVAC System (ft2)
772
06
Measured AHU Airflow (cfm)
n/a
07
Duct Leakage Test Conditions
Test final
08
Duct Leakage Test Method
Total leakage
09
Leakage Factor
0.05
10
Calculated Target Allowable Duct
Leakage (cfm)
60
11
Actual Duct Leakage Rate from Leakage Test Measurement (cfm)
57
12
Compliance Statement
System passes leakage test
Registration Number:
423-A020204948A-000-001-M 20004A-0000
Registration Date/Time: 2023-12-04 08:31:13 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 3 of 4)
C. Additional Requirements for Compliance
01
System was tested in its normal operation condition. No temporary taping allowed.
02
Outside air (OA) duct connections to the central forced air duct system shall not be sealed/taped off during duct leakage testing. OA
ducts used for Central Fan Integrated (CFI) Indoor Air Quality ventilation systems, or Central Fan Ventilation Cooling Systems, that utilize
dampers that open only when OA is required and automatically close when OA is not required, may configure the OA damper to the
closed position during duct leakage testing.
03
All supply and return register boots were sealed to the drywall.
04
Building cavities were not used as plenums or platform returns in lieu of ducts.
05
If cloth backed tape was used it was covered with Mastic and draw bands.
06
All connection points between the
air handler and the supply and return plenums are completely
sealed.
Visual Inspection at Final Construction
After installing the interior finishing wall
Stage (applicable if system was tested at rough -in).
and verifying that the above rough -in tests was completed, the following procedure must be performed
07
For all supply and return registers,
verify that the spaces between the register boot and the interior
finishing wall are properly sealed.
08
If the house rough -in duct leakage
handler and the supply and return
test was conducted without an air handler installed, inspect the
plenums to verify that the connection points are properly sealed.
connection points between the air
09
Inspect all joints to ensure that no
cloth backed rubber adhesive duct tape is used.
The responsible person's signature on this
compliance document affirms that all applicable requirements
in this table have been met.
Registration Number:
423-A020204948A-000-001-M 20004A-0000
Registration Date/Time: 2023-12-04 08:31:13 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 20004A-0000
Registration Date/Time: 2023-12-04 08:31:13 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CERTIFICATE OF INSTALLATION
CF2R-MCH-23-H
(Page 1 of 3)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. Ducted Cooling System Information
01
Space Conditioning System Identification or Name
System 2
02
Space Conditioning System Description of Area Served
Master
03
Indoor Unit Name
Master
04
System Installation Type
New
05
Nominal Cooling Capacity (tons)
3
06
Condenser Speed Type
n/a
07
Cooling System Zonal Control Type
n/a
08
Central Fan Integrated (CFI) Ventilation System Status
Not a CFI system
09
System Bypass Duct Status
n/a
10
Date of System Airflow Rate Measurement
2023-12-04
11
Airflow Rate Protocol Utilized
RA3.3 procedures for airflow rate measurement
12
Central Fan Ventilation Cooling System Status
Not a CFVCS
B. Hole for the placement of a Static Pressure Probe (HSPP), and Permanently Installed Static Pressure Probe (PSPP) in the Supply Plenum.
Procedures for installing HSPP or PSPP are specified in RA3.3.1.1.
01
Method Used to Demonstrate Compliance with the HSPP/PSPP
Requirement
HSPP installed and labeled consistent with Figure RA3.3-1
Registration Number:
423-A020204948A-000-001-M 23005A-0000
Registration Date/Time: 2023-12-04 08:31:29 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF2R-MCH-23-H
(Page 2 of 3)
C. Airflow Rate Measurement Apparatus and Procedure Information
Instrument Specifications are given in RA3.3.1.1, and system airflow rate measurement apparatus information is given in RA3.3.2.
01
Airflow Rate Measurement Type used for this airflow rate
verification.
Traditional Flow Capture Hood according to procedure in
RA3.3.3.1.4
02
Manufacturer of Airflow Measurement Apparatus
TESTO
03
Model number of Airflow Measurement Apparatus
420
04
Certification Status of the Airflow Measurement Apparatus
Accuracy
Certified by Manufacturer and listed on CEC Website at
http://www.energy.ca.gov/title24/equipment_cert/ama_fas/index.
html
MCH-23a Forced Air System Airflow Rate Measurement - Newly Installed Non -Zoned Systems or Zoned Multi -Speed Compressor
D. Forced Air System Airflow Rate Measurement
The procedures for System Airflow Rate Verification are specified in Reference Residential Appendix RA3.3.
01
Required Minimum System Airflow Rate (cfm/ton)
350
02
Required Minimum System Airflow Target (cfm)
1050
03
Actual System Airflow Rate Measurement (cfm)
1063
04
Compliance Statement:
System airflow rate complies
E. Additional Requirements
01
Air filters that meet the applicable requirements of Standards Section 150.0(m)12 or 150.0(m)13 were properly installed in the system
during system air flow rate measurement identified on this Certificate of Installation.
02
The airflow rate measurement apparatus used to perform the airflow rate measurement identified on this Certificate of Installation was
calibrated in accordance with the apparatus manufacturer's specifications and conforms to the instrumentation specifications given in
RA3.3.1.
03
A visual inspection shall confirm that bypass ducts that deliver conditioned supply air directly to the space conditioning system return
duct airflow are not used on newly constructed zonally controlled systems unless the Performance Certificate of Compliance indicates an
allowance for use of a bypass duct. When a bypass duct is accounted for on the Performance Certificate of Compliance, the airflow rate
shall conform to the specifications listed on the Certificate of Compliance.
04
All registers were fully open during the diagnostic test.
05
System fan was set at maximum speed during the diagnostic test.
06
If fresh air duct is part of the HVAC system it was not closed during the diagnostic test.
07
Airflow rate and fan watt draw shall be simultaneous measurements when used to calculate the Fan Efficacy tested value.
08
Multi -speed compressor space cooling systems or variable speed compressor systems shall verify air flow (cfm/ton) and fan efficacy
(Watt/cfm) with system operating in cooling mode at the maximum compressor speed and the maximum air handler fan speed.
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met.
Registration Number:
423-A020204948A-000-001-M 23005A-0000
Registration Date/Time: 2023-12-04 08:31:29
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:11:52
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF2R-MCH-23-H
(Page 3 of 3)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 23005A-0000
Registration Date/Time: 2023-12-04 08:31:29 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-25-H
(Page 1 of 5)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
Each system requiring refrigerant charge verification will be documented on a separate certificate.
01
Space Conditioning System Identification or Name
System 2
02
Space Conditioning System Location or Area Served
Master
03
Condenser (or package unit) Make or Brand
AMANA
04
Condenser (or package unit) Model Number
ASZ160361LB
05
Nominal Cooling Capacity (tons) of Condenser
3
06
Condenser (or package unit) Serial Number
2205076869
07
Refrigerant Type
R-410A
08
Other Refrigerant Type (if applicable)
n/a
09
Liquid Line Filter Drier Installed According to Manufacturers
Specifications (if applicable)
Yes
10
System Installation Type
New
11
Fault Indicator Display (FID) Status (Note: Even systems with a FID
must have refrigerant charge verified by installer).
This system does not have a FID device installed
12
Is the system of a type that the minimum airflow can be verified for
all indoor units using an approved measurement procedure (RA3.3
or RA3.3.3)?
Yes
13
Is the system of a type that approved refrigerant charge verification
procedures can be used to verify compliance with the refrigerant
charge verification requirements when temperatures are >= 55 °F
(RA3.2.2, or RA1)?
Yes, one of the Refrigerant charge verification procedures from
RA3.2.2 or RA1 is applicable to this system and can be used to
verify compliance
14
Date of Refrigerant Charge Verification for this system
2023-12-04
15
Refrigerant charge verification method used.
Subcooling (outdoor temperature must be equal to or greater than
55 degF)
16
Person who performed the Refrigerant Charge Verification
reported on this Certificate of Installation
HERS rater
17
HERS Verification Compliance Requirement Status
System does not qualify for group sampling
Registration Number:
423-A020204948A-000-001-M 25009A-0000
Registration Date/Time: 2023-12-04 08:39:30
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:11:56
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-25-H
(Page 2 of 5)
MCH-25b - Refrigerant Charge Verification - Subcooling Method
B. Metering Device Verification
Subcooling Method can only be used on systems that have a variable metering device.
01
Refrigerant metering device
Thermostatic Expansion Valve (TXV)
02
Subcooling Method applicability status
Subcooling Method is applicable to this system.
C. Instrument Calibration
Procedures for instrument calibration are given in Reference Residential Appendix RA3.2.2 and RA3.2.2.2
01
Date of Digital Refrigerant Gauge Calibration
2023-11-30
02
Date of Digital Thermocouple Calibration
2023-11-30
03
Digital Refrigerant Gauge Calibration Status
Calibration is current
04
Digital Thermocouple Calibration Status
Calibration is current
D. Measurement Access Hole (MAH) Verification
Procedures for installing MAH are specified in Reference Residential Appendix RA3.2.2.3
01
Method Used to Demonstrate Compliance with the Measurement
Access Hole (MAH) Requirement
MAH installed and labeled consistent with Figure 3.2-1
E. Minimum System Airflow Rate Verification
Procedures for verifying minimum system airflow are specified in Reference Residential Appendix RA3.3.3.
01
02
03
Indoor Unit Name or Description of Area
Served
Minimum Required System Airflow Rate (cfm)
System Airflow Rate Verification Status
Master
1400
System complies with minimum airflow rate
requirements
04
SC System complies with Minimum System Airflow Rate Verification
Notes:
Registration Number:
423-A020204948A-000-001-M 25009A-0000
Registration Date/Time: 2023-12-04 08:39:30 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 3 of 5)
F. Data Collection and Calculations
Procedures for determining Refrigerant Charge using the Standard Charge Verification Procedure are given in Reference Residential Appendix
RA3.2.2.
01
Lowest Return Air Dry Bulb Temperature that Occurred During the
Refrigerant Charge Verification Procedure (°F)
85
02
Measured Condenser Air Entering Dry -Bulb Temperature
(Tcondenser,db)
71
03
Outdoor Temperature Qualification Status
Outdoor temperature is within range for using Subcooling
refrigerant charge verification method
04
Measured Liquid Line Temperature (Tiiquid) ( °F)
75.1
05
Measured Liquid Line Pressure (Piiquid) (psig)
283.0
06
Condenser Saturation Temperature (Tcondenser, sat) from Digital
Gauge or P-T Table using Line F05 (°F)
80.5
07
Measured Subcooling (Line F06 - Lilne F04 (°F)
5.4
08
Target Subcooling from Manufacturer (°F)
8
09
Compliance Statement:
System complies with Subcooling Method - Must also pass
metering device verification, next section
G. Metering Device Verification
Procedures for the verification of proper metering device operation are specified in RA3.2.2.6.2
01
Measured Suction Line Temperature (Tsuction) (°F)
55.4
02
Measured Suction Line Pressure (Psuction) (psig)
133.0
03
Evaporator Saturation Temperature (Tevaporator, sat) from Digital
Gauge or P-T Table using Line G02 (°F)
46.2
04
Measured Superheat (Line G01- Line G03) (°F)
9.2
05
Measured Superheat (Line G04) is between 4 °F and 25 °F
(inclusive)
Passes CEC requirement
06
Measured Superheat (Line G04) is within Manufacturer's
Specifications ( if known)
Yes, documentation to be provided upon request
07
Compliance Statement
Metering device verification passes
MCH-25d - Refrigeration Charge Verification - Fault Indicator Display (FID)
H. Fault Indicator Display
This section does not apply to this project.
Registration Number:
423-A020204948A-000-001-M 25009A-0000
Registration Date/Time: 2023-12-04 08:39:30
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 4 of 5)
I. Fault Indicator Display Additional Requirements
This section does not apply to this project.
Registration Number:
423-A020204948A-000-001-M 25009A-0000
Registration Date/Time: 2023-12-04 08:39:30 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 5 of 5)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 25009A-0000
Registration Date/Time: 2023-12-04 08:39:30 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-20-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
01
Space Conditioning System Identification or Name
System 3
02
Space Conditioning System Location
or Area Served
Casita
03
Indoor Unit Name or Description
of Area Served
Casita
04
Building Type from from parent CC
Single family
05
Verified Low Leakage Ducts in Conditioned
from parent CC?
Space (VLLDCS) Credit
No, credit is not taken
06
Verified Low Leakage Air Handling
Unit Credit from parent CC?
No, credit is not taken
07
Duct System Compliance Category
New
08
Portions of Duct Located in Garage?
No
09
Is the system type Small Duct High Velocity (SDHV) ?
No
MCH-20a - Completely New Duct System
Registration Number:
423-A020204948A-000-001-M 20006A-0000
Registration Date/Time: 2023-12-04 08:31:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 2 of 4)
B. Duct Leakage Diagnostic Test
01
Air Handling Unit Airflow (AHU Airflow) Determination Method
Cooling system method
02
Condenser Nominal Cooling Capacity (ton)
2
03
Indoor Unit Nominal Cooling Capacity
2
04
Heating Capacity (kBtu/h)
n/a
05
Conditioned Floor Area Served by this HVAC System (ft2)
772
06
Measured AHU Airflow (cfm)
n/a
07
Duct Leakage Test Conditions
Test final
08
Duct Leakage Test Method
Total leakage
09
Leakage Factor
0.05
10
Calculated Target Allowable Duct
Leakage (cfm)
40
11
Actual Duct Leakage Rate from Leakage Test Measurement (cfm)
40
12
Compliance Statement
System passes leakage test
Registration Number:
423-A020204948A-000-001-M 20006A-0000
Registration Date/Time: 2023-12-04 08:31:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 3 of 4)
C. Additional Requirements for Compliance
01
System was tested in its normal operation condition. No temporary taping allowed.
02
Outside air (OA) duct connections to the central forced air duct system shall not be sealed/taped off during duct leakage testing. OA
ducts used for Central Fan Integrated (CFI) Indoor Air Quality ventilation systems, or Central Fan Ventilation Cooling Systems, that utilize
dampers that open only when OA is required and automatically close when OA is not required, may configure the OA damper to the
closed position during duct leakage testing.
03
All supply and return register boots were sealed to the drywall.
04
Building cavities were not used as plenums or platform returns in lieu of ducts.
05
If cloth backed tape was used it was covered with Mastic and draw bands.
06
All connection points between the
air handler and the supply and return plenums are completely
sealed.
Visual Inspection at Final Construction
After installing the interior finishing wall
Stage (applicable if system was tested at rough -in).
and verifying that the above rough -in tests was completed, the following procedure must be performed
07
For all supply and return registers,
verify that the spaces between the register boot and the interior
finishing wall are properly sealed.
08
If the house rough -in duct leakage
handler and the supply and return
test was conducted without an air handler installed, inspect the
plenums to verify that the connection points are properly sealed.
connection points between the air
09
Inspect all joints to ensure that no
cloth backed rubber adhesive duct tape is used.
The responsible person's signature on this
compliance document affirms that all applicable requirements
in this table have been met.
Registration Number:
423-A020204948A-000-001-M 20006A-0000
Registration Date/Time: 2023-12-04 08:31:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
DUCT LEAKAGE DIAGNOSTIC TEST
CF2R-MCH-20-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 20006A-0000
Registration Date/Time: 2023-12-04 08:31:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:52
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CERTIFICATE OF INSTALLATION
CF2R-MCH-23-H
(Page 1 of 3)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. Ducted Cooling System Information
01
Space Conditioning System Identification or Name
System 3
02
Space Conditioning System Description of Area Served
Casita
03
Indoor Unit Name
Casita
04
System Installation Type
New
05
Nominal Cooling Capacity (tons)
2
06
Condenser Speed Type
n/a
07
Cooling System Zonal Control Type
n/a
08
Central Fan Integrated (CFI) Ventilation System Status
Not a CFI system
09
System Bypass Duct Status
n/a
10
Date of System Airflow Rate Measurement
2023-12-04
11
Airflow Rate Protocol Utilized
RA3.3 procedures for airflow rate measurement
12
Central Fan Ventilation Cooling System Status
Not a CFVCS
B. Hole for the placement of a Static Pressure Probe (HSPP), and Permanently Installed Static Pressure Probe (PSPP) in the Supply Plenum.
Procedures for installing HSPP or PSPP are specified in RA3.3.1.1.
01
Method Used to Demonstrate Compliance with the HSPP/PSPP
Requirement
HSPP installed and labeled consistent with Figure RA3.3-1
Registration Number:
423-A020204948A-000-001-M 23007A-0000
Registration Date/Time: 2023-12-04 08:32:35 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:55
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF2R-MCH-23-H
(Page 2 of 3)
C. Airflow Rate Measurement Apparatus and Procedure Information
Instrument Specifications are given in RA3.3.1.1, and system airflow rate measurement apparatus information is given in RA3.3.2.
01
Airflow Rate Measurement Type used for this airflow rate
verification.
Traditional Flow Capture Hood according to procedure in
RA3.3.3.1.4
02
Manufacturer of Airflow Measurement Apparatus
TESTO
03
Model number of Airflow Measurement Apparatus
420
04
Certification Status of the Airflow Measurement Apparatus
Accuracy
Certified by Manufacturer and listed on CEC Website at
http://www.energy.ca.gov/title24/equipment_cert/ama_fas/index.
html
MCH-23a Forced Air System Airflow Rate Measurement - Newly Installed Non -Zoned Systems or Zoned Multi -Speed Compressor
D. Forced Air System Airflow Rate Measurement
The procedures for System Airflow Rate Verification are specified in Reference Residential Appendix RA3.3.
01
Required Minimum System Airflow Rate (cfm/ton)
350
02
Required Minimum System Airflow Target (cfm)
700
03
Actual System Airflow Rate Measurement (cfm)
749
04
Compliance Statement:
System airflow rate complies
E. Additional Requirements
01
Air filters that meet the applicable requirements of Standards Section 150.0(m)12 or 150.0(m)13 were properly installed in the system
during system air flow rate measurement identified on this Certificate of Installation.
02
The airflow rate measurement apparatus used to perform the airflow rate measurement identified on this Certificate of Installation was
calibrated in accordance with the apparatus manufacturer's specifications and conforms to the instrumentation specifications given in
RA3.3.1.
03
A visual inspection shall confirm that bypass ducts that deliver conditioned supply air directly to the space conditioning system return
duct airflow are not used on newly constructed zonally controlled systems unless the Performance Certificate of Compliance indicates an
allowance for use of a bypass duct. When a bypass duct is accounted for on the Performance Certificate of Compliance, the airflow rate
shall conform to the specifications listed on the Certificate of Compliance.
04
All registers were fully open during the diagnostic test.
05
System fan was set at maximum speed during the diagnostic test.
06
If fresh air duct is part of the HVAC system it was not closed during the diagnostic test.
07
Airflow rate and fan watt draw shall be simultaneous measurements when used to calculate the Fan Efficacy tested value.
08
Multi -speed compressor space cooling systems or variable speed compressor systems shall verify air flow (cfm/ton) and fan efficacy
(Watt/cfm) with system operating in cooling mode at the maximum compressor speed and the maximum air handler fan speed.
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met.
Registration Number:
423-A020204948A-000-001-M 23007A-0000
Registration Date/Time: 2023-12-04 08:32:35
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:11:55
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF2R-MCH-23-H
(Page 3 of 3)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 23007A-0000
Registration Date/Time: 2023-12-04 08:32:35 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:55
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF INSTALLATION
CF2R-MCH-25-H
(Page 1 of 5)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
Each system requiring refrigerant charge verification will be documented on a separate certificate.
01
Space Conditioning System Identification or Name
System 3
02
Space Conditioning System Location or Area Served
Casita
03
Condenser (or package unit) Make or Brand
GOODMAN
04
Condenser (or package unit) Model Number
GSZH502410AA
05
Nominal Cooling Capacity (tons) of Condenser
2
06
Condenser (or package unit) Serial Number
2309240920
07
Refrigerant Type
R-410A
08
Other Refrigerant Type (if applicable)
n/a
09
Liquid Line Filter Drier Installed According to Manufacturers
Specifications (if applicable)
Yes
10
System Installation Type
New
11
Fault Indicator Display (FID) Status (Note: Even systems with a FID
must have refrigerant charge verified by installer).
This system does not have a FID device installed
12
Is the system of a type that the minimum airflow can be verified for
all indoor units using an approved measurement procedure (RA3.3
or RA3.3.3)?
Yes
13
Is the system of a type that approved refrigerant charge verification
procedures can be used to verify compliance with the refrigerant
charge verification requirements when temperatures are >= 55 °F
(RA3.2.2, or RA1)?
Yes, one of the Refrigerant charge verification procedures from
RA3.2.2 or RA1 is applicable to this system and can be used to
verify compliance
14
Date of Refrigerant Charge Verification for this system
2023-12-04
15
Refrigerant charge verification method used.
Subcooling (outdoor temperature must be equal to or greater than
55 degF)
16
Person who performed the Refrigerant Charge Verification
reported on this Certificate of Installation
HERS rater
17
HERS Verification Compliance Requirement Status
System does not qualify for group sampling
Registration Number:
423-A020204948A-000-001-M 25010A-0000
Registration Date/Time: 2023-12-04 08:40:43
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:11:56
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CF2R-MCH-25-H
(Page 2 of 5)
MCH-25b - Refrigerant Charge Verification - Subcooling Method
B. Metering Device Verification
Subcooling Method can only be used on systems that have a variable metering device.
01
Refrigerant metering device
Thermostatic Expansion Valve (TXV)
02
Subcooling Method applicability status
Subcooling Method is applicable to this system.
C. Instrument Calibration
Procedures for instrument calibration are given in Reference Residential Appendix RA3.2.2 and RA3.2.2.2
01
Date of Digital Refrigerant Gauge Calibration
2023-11-30
02
Date of Digital Thermocouple Calibration
2023-11-30
03
Digital Refrigerant Gauge Calibration Status
Calibration is current
04
Digital Thermocouple Calibration Status
Calibration is current
D. Measurement Access Hole (MAH) Verification
Procedures for installing MAH are specified in Reference Residential Appendix RA3.2.2.3
01
Method Used to Demonstrate Compliance with the Measurement
Access Hole (MAH) Requirement
MAH installed and labeled consistent with Figure 3.2-1
E. Minimum System Airflow Rate Verification
Procedures for verifying minimum system airflow are specified in Reference Residential Appendix RA3.3.3.
01
02
03
Indoor Unit Name or Description of Area
Served
Minimum Required System Airflow Rate (cfm)
System Airflow Rate Verification Status
Casita
1400
System complies with minimum airflow rate
requirements
04
SC System complies with Minimum System Airflow Rate Verification
Notes:
Registration Number:
423-A020204948A-000-001-M 25010A-0000
Registration Date/Time: 2023-12-04 08:40:43 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 3 of 5)
F. Data Collection and Calculations
Procedures for determining Refrigerant Charge using the Standard Charge Verification Procedure are given in Reference Residential Appendix
RA3.2.2.
01
Lowest Return Air Dry Bulb Temperature that Occurred During the
Refrigerant Charge Verification Procedure (°F)
85
02
Measured Condenser Air Entering Dry -Bulb Temperature
(Tcondenser,db)
75
03
Outdoor Temperature Qualification Status
Outdoor temperature is within range for using Subcooling
refrigerant charge verification method
04
Measured Liquid Line Temperature (Tiiquid) (°F)
79.5
05
Measured Liquid Line Pressure (Piiquid) (psig)
252.6
06
Condenser Saturation Temperature (Tcondenser, sat) from Digital
Gauge or P-T Table using Line F05 (°F)
85.7
07
Measured Subcooling (Line F06 - Lilne F04 (°F)
6.2
08
Target Subcooling from Manufacturer (°F)
8
09
Compliance Statement:
System complies with Subcooling Method - Must also pass
metering device verification, next section
G. Metering Device Verification
Procedures for the verification of proper metering device operation are specified in RA3.2.2.6.2
01
Measured Suction Line Temperature (Tsuction) (°F)
55.9
02
Measured Suction Line Pressure (Psuction) (psig)
134.5
03
Evaporator Saturation Temperature (Tevaporator, sat) from Digital
Gauge or P-T Table using Line G02 (°F)
46.8
04
Measured Superheat (Line G01- Line G03) (°F)
9.1
05
Measured Superheat (Line G04) is between 4 °F and 25 °F
(inclusive)
Passes CEC requirement
06
Measured Superheat (Line G04) is within Manufacturer's
Specifications ( if known)
Yes, documentation to be provided upon request
07
Compliance Statement
Metering device verification passes
MCH-25d - Refrigeration Charge Verification - Fault Indicator Display (FID)
H. Fault Indicator Display
This section does not apply to this project.
Registration Number:
423-A020204948A-000-001-M 25010A-0000
Registration Date/Time: 2023-12-04 08:40:43
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 4 of 5)
I. Fault Indicator Display Additional Requirements
This section does not apply to this project.
Registration Number:
423-A020204948A-000-001-M 25010A-0000
Registration Date/Time: 2023-12-04 08:40:43 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF2R-MCH-25-H
(Page 5 of 5)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Installation documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:
A vl, 9P) A re.C311/60,Cti
Company:
iPermit
Signatur ate:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this certificate of installation is true and correct.
2. I am either: a) a responsible person eligible under division 3 of the business and professions code in the applicable
classification to accept responsibility for the system design, construction, or installation of features, materials,
components, or manufactured devices for the scope of work identified on this certificate of installation, and attest to the
declarations in this statement, or b) i am an authorized representative of the responsible person and attest to the
declarations in this statement on the responsible person's behalf.
3. The constructed or installed features, materials, components or manufactured devices (the installation) identified on
this certificate of installation conforms to all applicable codes and regulations and the installation conforms to the
requirements given on the certificate of compliance, plans, and specifications approved by the enforcement agency.
4. I understand that a HERS rater will check the installation to verify compliance and if such checking determines the
installation fails to comply, I am required to offer any necessary corrective action at no charge to the building owner.
5. I understand that a registered copy of this certificate of installation shall be posted or made available with the building
permit(s) issued for the building and made available to the enforcement agency for all applicable inspections, and I will
take the necessary steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this certificate of installation is required to be included with the documentation
the builder provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is
accomplished.
Responsible Builder/Installer Name:
Tom Powers (authorized Angel Arechiga)
Responsible Builder/Installer Signature:
A r 0 A Vec114i3O,a/
Company Name: (Installing Subcontractor or General Contractor or
Builder/Owner)
DEH Mechanical Company Inc
Position With Company (Title):
Contractor/Installer
Address:
PO Box 12374
CSLB License:
752819
City/State/Zip:
Palm Desert CA 92255
Phone:
(760) 346-5354
Date Signed:
2023-12-04
Third Party Quality Control Program (TPQCP) Status:
Name of TPQCP (if applicable):
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 25010A-0000
Registration Date/Time: 2023-12-04 08:40:43 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF VERIFICATION
CF3R-MCH-20-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
01
Space Conditioning System Identification or Name
System 1
02
Space Conditioning System Location
or Area Served
Kitchen living room
03
Indoor Unit Name or Description
of Area Served
Kitchen living room
04
Building Type from from parent CC
Single family
05
Verified Low Leakage Ducts in Conditioned
from parent CC?
Space (VLLDCS) Credit
No, credit is not taken
06
Verified Low Leakage Air Handling
Unit Credit from parent CC?
No, credit is not taken
07
Duct System Compliance Category
New
08
Portions of Duct Located in Garage?
No
09
Is the system type Small Duct High
Velocity (SDHV) ?
No
MCH-20a - Completely New Duct System
Registration Number:
423-A020204948A-000-001-M 20002A-M 20A
Registration Date/Time: 2023-12-04 08:40:51 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 2 of 4)
B. Duct Leakage Diagnostic Test
01
Air Handling Unit Airflow (AHU Airflow) Determination Method
Cooling system method
02
Condenser Nominal Cooling Capacity (ton)
4
03
Indoor Unit Nominal Cooling Capacity
4
04
Heating Capacity (kBtu/h)
n/a
05
Conditioned Floor Area Served by this HVAC System (ft2)
771
06
Measured AHU Airflow (cfm)
n/a
07
Duct Leakage Test Conditions
Test final
08
Duct Leakage Test Method
Total leakage
09
Leakage Factor
0.05
10
Calculated Target Allowable Duct Leakage (cfm)
80
11
Actual Duct Leakage Rate from Leakage Test Measurement (cfm)
80
12
Compliance Statement
System passes leakage test
13
Notes:
C. Additional Requirements for Compliance
01
System was tested in its normal operation condition. No temporary taping allowed.
02
Outside air (OA) duct connections to the central forced air duct system shall not be sealed/taped off during duct leakage testing. OA ducts
used for Central Fan Integrated (CFI) Indoor Air Quality ventilation systems, or Central Fan Ventilation Cooling Systems, that utilize
dampers that open only when OA is required and automatically close when OA is not required, may configure the OA damper to the
closed position during duct leakage testing.
03
All supply and return register boots were sealed to the drywall.
04
Building cavities were not used as plenums or platform returns in lieu of ducts.
05
If cloth backed tape was used it was covered with Mastic and draw bands.
06
All connection points between the air handler and the supply and return plenums are completely sealed.
Visual Inspection at Final Construction Stage (applicable if system was tested at rough -in).
After installing the interior finishing wall and verifying that the above rough -in tests was completed, the following procedure must be performed
07
For all supply and return registers, verify that the spaces between the register boot and the interior finishing wall are properly sealed.
08
If the house rough -in duct leakage test was conducted without an air handler installed, inspect the connection points between the air
handler and the supply and return plenums to verify that the connection points are properly sealed.
Registration Number:
423-A020204948A-000-001-M 20002A-M 20A
Registration Date/Time: 2023-12-04 08:40:51
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 3 of 4)
09
Inspect all joints to ensure that no cloth backed rubber adhesive duct tape is used.
10
Verification Status:
Pass - all applicable requirements are met.
11
Correction Notes:
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met unless
otherwise noted in the Verification Status and the Corrections Notes in this table.
D. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 20002A-M 20A
Registration Date/Time: 2023-12-04 08:40:51 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 20002A-M 20A
Registration Date/Time: 2023-12-04 08:40:51 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CERTIFICATE OF VERIFICATION
CF3R-MCH-23-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. Ducted Cooling System Information
01
Space Conditioning System Identification or Name
System 1
02
Space Conditioning System Description of Area Served
Kitchen living room
03
Indoor Unit Name
Kitchen living room
04
System Installation Type
New
05
Nominal Cooling Capacity (tons)
4
06
Condenser Speed Type
n/a
07
Cooling System Zonal Control Type
n/a
08
Central Fan Integrated (CFI) Ventilation System Status
Not a CFI system
09
System Bypass Duct Status
n/a
10
Date of System Airflow Rate Measurement
2023-12-04
11
Airflow Rate Protocol Utilized
RA3.3 procedures for airflow rate measurement
12
Central Fan Ventilation Cooling System Status
Not a CFVCS
B. Hole for the placement of a Static Pressure Probe (HSPP), and Permanently Installed Static Pressure Probe (PSPP) in the Supply Plenum.
Procedures for installing HSPP or PSPP are specified in RA3.3.1.1.
01
Method Used to Demonstrate Compliance with the HSPP/PSPP
Requirement
HSPP installed and labeled consistent with Figure RA3.3-1
Registration Number:
423-A020204948A-000-001-M 23003A-M 23A
Registration Date/Time: 2023-12-04 08:40:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 2 of 4)
C. Airflow Rate Measurement Apparatus and Procedure Information
Instrument Specifications are given in RA3.3.1.1, and system airflow rate measurement apparatus information is given in RA3.3.2.
01
Airflow Rate Measurement Type used for this airflow rate
verification.
Traditional Flow Capture Hood according to procedure in
RA3.3.3.1.4
02
Manufacturer of Airflow Measurement Apparatus
TESTO
03
Model number of Airflow Measurement Apparatus
420
04
Certification Status of the Airflow Measurement Apparatus
Accuracy
Certified by Manufacturer and listed on CEC Website at
http://www.energy.ca.gov/title24/equipment_cert/ama_fas/index.
html
MCH-23a Forced Air System Airflow Rate Measurement - Newly Installed Non -Zoned Systems or Zoned Multi -Speed Compressor
D. Forced Air System Airflow Rate Measurement
The procedures for System Airflow Rate Verification are specified in Reference Residential Appendix RA3.3.
01
Required Minimum System Airflow Rate (cfm/ton)
350
02
Required Minimum System Airflow Target (cfm)
1400
03
Actual System Airflow Rate Measurement (cfm)
1449
04
Compliance Statement:
System airflow rate complies
E. Additional Requirements
01
Air filters that meet the applicable requirements of Standards Section 150.0(m)12 or 150.0(m)13 were properly installed in the system
during system air flow rate measurement identified on this Certificate of Verification.
02
The airflow rate measurement apparatus used to perform the airflow rate measurement identified on this Certificate of Verification was
calibrated in accordance with the apparatus manufacturer's specifications and conforms to the instrumentation specifications given in
RA3.3.1.
03
A visual inspection shall confirm that bypass ducts that deliver conditioned supply air directly to the space conditioning system return
duct airflow are not used on newly constructed zonally controlled systems unless the Performance Certificate of Compliance indicates an
allowance for use of a bypass duct. When a bypass duct is accounted for on the Performance Certificate of Compliance, the airflow rate
shall conform to the specifications listed on the Certificate of Compliance.
04
All registers were fully open during the diagnostic test.
05
System fan was set at maximum speed during the diagnostic test.
06
If fresh air duct is part of the HVAC system it was not closed during the diagnostic test.
07
Airflow rate and fan watt draw shall be simultaneous measurements when used to calculate the Fan Efficacy tested value.
Registration Number:
423-A020204948A-000-001-M 23003A-M 23A
Registration Date/Time: 2023-12-04 08:40:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 3 of 4)
E. Additional Requirements
08
Multi -speed compressor space cooling systems or variable speed compressor systems shall verify air flow (cfm/ton) and fan efficacy
(Watt/cfm) with system operating in cooling mode at the maximum compressor speed and the maximum air handler fan speed.
09
Verification Status:
Pass - all applicable requirements are met.
10
Correction Notes:
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met unless
otherwise noted in the Verification Status and the Corrections Notes in this table
F. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 23003A-M 23A
Registration Date/Time: 2023-12-04 08:40:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 23003A-M 23A
Registration Date/Time: 2023-12-04 08:40:53 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:56
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF VERIFICATION
CF3R-MCH-25-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
HERS Rater to field -verify all system information, discrepancies to be noted by overwriting entry.
01
Space Conditioning System Identification or Name
System 1
02
Space Conditioning System Location or Area Served
Kitchen living room
03
Condenser (or package unit) make or brand
AMANA
04
Condenser (or package unit) model number
ASZ160481LB
05
Nominal Cooling Capacity (tons) of Condenser
4
06
Condenser (or package unit) serial number
2206430160
07
Refrigerant Type
R-410A
08
Other Refrigerant Type (if applicable)
n/a
09
Liquid Line Filter Drier Installed According to Manufacturers
Specifications (if applicable)
Yes
10
System Installation Type
New
11
Fault Indicator Display (FID) Status (Note: Even systems with a FID
must have refrigerant charge verified by installer)
This system does not have a FID device installed
12
Is the system of a type that the minimum airflow can be verified for
all indoor units using an approved measurement procedure (RA3.3
or RA3.3.3)?
Yes
13
Is the system of a type that approved refrigerant charge verification
procedures can be used to verify compliance with the refrigerant
charge verification requirements when temperatures are >= 55 °F
(RA3.2.2, or RA1)?
Yes, one of the Refrigerant charge verification procedures from
RA3.2.2 or RA1 is applicable to this system and can be used to
verify compliance
14
Date of Refrigerant Charge Verification for this system
2023-12-04
15
Refrigerant charge verification method used.
Subcooling (outdoor temperature must be equal to or greater than
55 degF)
16
Person who performed the Refrigerant Charge Verification
reported on this Certificate of Installation
HERS rater
17
HERS Verification Compliance Requirement Status
System does not qualify for group sampling
Registration Number:
423-A020204948A-000-001-M 25008A-M 25A
Registration Date/Time: 2023-12-04 08:41:03
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:12:00
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 2 of 4)
A. System Information
HERS Rater to field -verify all system information, discrepancies to be noted by overwriting entry.
18
Refrigerant charge verification method used by HERS Rater.
Subcooling
MCH-25b - Refrigerant Charge Verification - Subcooling Method
B. Metering Device Verification
HERS Rater is required to visually field verify all information from CF2R. Subcooling Method can only be used on systems that have a variable
metering device.
01
Refrigerant metering device
Thermostatic Expansion Valve (TXV)
02
Subcooling Method applicability status
Subcooling Method is applicable to this system.
C. Instrument Calibration
HERS Raters are required to calibrate their diagnostic tools. Procedures for instrument calibration are given in Reference Residential Appendix
RA3.2.2 and RA3.2.2.2
01
Date of Digital Refrigerant Gauge Calibration
2023-11-30
02
Date of Digital Thermocouple Calibration
2023-11-30
03
Digital Refrigerant Gauge Calibration Status
Calibration is current
04
Digital Thermocouple Calibration Status
Calibration is current
D. Measurement Access Hole (MAH) Verification
HERS Raters are required to visually field verify MAH. Procedures for installing MAH are specified in Reference Residential Appendix RA3.2.2.3
01
Method Used to Demonstrate Compliance with the Measurement
Access Hole (MAH) Requirement
MAH installed and labeled consistent with Figure 3.2-1
E. Minimum System Airflow Rate Verification
Procedures for verifying minimum system airflow are specified in Reference Residential Appendix RA3.3.3.
01
02
03
Indoor Unit Name or Description of Area
Served
Minimum Required System Airflow Rate (cfm)
System Airflow Rate Verification Status
Kitchen living room
1400
System complies with minimum airflow rate
requirements
04
SC System complies with Minimum System Airflow Rate Verification
Notes:
Registration Number:
423-A020204948A-000-001-M 25008A-M 25A
Registration Date/Time: 2023-12-04 08:41:03 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 3 of 4)
F. Data Collection and Calculations
HERS Rater must independently collect all data in this section. Procedures for determining Refrigerant Charge using the Standard Charge
Verification Procedure are given in Reference Residential Appendix RA3.2.2 and RA3.2.2.2
01
Lowest Return Air Dry Bulb Temperature that Occurred During the
Refrigerant Charge Verification Procedure (°F)
85
02
Measured Condenser Air Entering Dry -Bulb Temperature
(Tcondenser,db)
70
03
Outdoor Temperature Qualification Status
Outdoor temperature is within range for using Subcooling
refrigerant charge verification method
04
Measured Liquid Line Temperature (Tiiquid) (°F)
75.0
05
Measured Liquid Line Pressure (Piiquid) (psig)
283.0
06
Condenser Saturation Temperature (Tcondenser, sat) from Digital
Gauge or P-T Table using Line F05 (°F)
80.1
07
Measured Subcooling (Line F06 - Lilne F04 (°F)
5.1
08
Target Subcooling from Manufacturer (°F)
8
09
Compliance Statement:
System complies with Subcooling Method - Must also pass
metering device verification, next section
G. Metering Device Verification
HERS Rater must independently collect all data in this section. Procedures for the verification of proper metering device operation are specified
in RA3.2.2.6.2
01
Measured Suction Line Temperature (Tsuction) (°F)
53.0
02
Measured Suction Line Pressure (Psuction) (psig)
135.9
03
Evaporator Saturation Temperature (Tevaporator, sat) from Digital
Gauge or P-T Table using Line G02 (°F)
43.6
04
Measured Superheat (Line G01- Line G03) (°F)
9.4
05
Measured Superheat (Line G04) is between 3 °F and 26 °F
(inclusive)
Passes CEC requirement
06
Measured Superheat (Line G04) is within Manufacturer's
Specifications ( if known)
Yes, documentation to be provided upon request
07
Compliance Statement:
Metering device verification passes
H. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 25008A-M 25A
Registration Date/Time: 2023-12-04 08:41:03
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:12:00
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 25008A-M 25A
Registration Date/Time: 2023-12-04 08:41:03 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF VERIFICATION
CF3R-MCH-20-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
01
Space Conditioning System Identification or Name
System 2
02
Space Conditioning System Location
or Area Served
Master
03
Indoor Unit Name or Description
of Area Served
Master
04
Building Type from from parent CC
Single family
05
Verified Low Leakage Ducts in Conditioned
from parent CC?
Space (VLLDCS) Credit
No, credit is not taken
06
Verified Low Leakage Air Handling
Unit Credit from parent CC?
No, credit is not taken
07
Duct System Compliance Category
New
08
Portions of Duct Located in Garage?
No
09
Is the system type Small Duct High
Velocity (SDHV) ?
No
MCH-20a - Completely New Duct System
Registration Number:
423-A020204948A-000-001-M 20004A-M 20A
Registration Date/Time: 2023-12-04 08:40:55 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:58
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 2 of 4)
B. Duct Leakage Diagnostic Test
01
Air Handling Unit Airflow (AHU Airflow) Determination Method
Cooling system method
02
Condenser Nominal Cooling Capacity (ton)
3
03
Indoor Unit Nominal Cooling Capacity
3
04
Heating Capacity (kBtu/h)
n/a
05
Conditioned Floor Area Served by this HVAC System (ft2)
772
06
Measured AHU Airflow (cfm)
n/a
07
Duct Leakage Test Conditions
Test final
08
Duct Leakage Test Method
Total leakage
09
Leakage Factor
0.05
10
Calculated Target Allowable Duct Leakage (cfm)
60
11
Actual Duct Leakage Rate from Leakage Test Measurement (cfm)
57
12
Compliance Statement
System passes leakage test
13
Notes:
C. Additional Requirements for Compliance
01
System was tested in its normal operation condition. No temporary taping allowed.
02
Outside air (OA) duct connections to the central forced air duct system shall not be sealed/taped off during duct leakage testing. OA ducts
used for Central Fan Integrated (CFI) Indoor Air Quality ventilation systems, or Central Fan Ventilation Cooling Systems, that utilize
dampers that open only when OA is required and automatically close when OA is not required, may configure the OA damper to the
closed position during duct leakage testing.
03
All supply and return register boots were sealed to the drywall.
04
Building cavities were not used as plenums or platform returns in lieu of ducts.
05
If cloth backed tape was used it was covered with Mastic and draw bands.
06
All connection points between the air handler and the supply and return plenums are completely sealed.
Visual Inspection at Final Construction Stage (applicable if system was tested at rough -in).
After installing the interior finishing wall and verifying that the above rough -in tests was completed, the following procedure must be performed
07
For all supply and return registers, verify that the spaces between the register boot and the interior finishing wall are properly sealed.
08
If the house rough -in duct leakage test was conducted without an air handler installed, inspect the connection points between the air
handler and the supply and return plenums to verify that the connection points are properly sealed.
Registration Number:
423-A020204948A-000-001-M 20004A-M 20A
Registration Date/Time: 2023-12-04 08:40:55
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:58
Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 3 of 4)
09
Inspect all joints to ensure that no cloth backed rubber adhesive duct tape is used.
10
Verification Status:
Pass - all applicable requirements are met.
11
Correction Notes:
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met unless
otherwise noted in the Verification Status and the Corrections Notes in this table.
D. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 20004A-M 20A
Registration Date/Time: 2023-12-04 08:40:55 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:58
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 20004A-M 20A
Registration Date/Time: 2023-12-04 08:40:55 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:11:58
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CERTIFICATE OF VERIFICATION
CF3R-MCH-23-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. Ducted Cooling System Information
01
Space Conditioning System Identification or Name
System 2
02
Space Conditioning System Description of Area Served
Master
03
Indoor Unit Name
Master
04
System Installation Type
New
05
Nominal Cooling Capacity (tons)
3
06
Condenser Speed Type
n/a
07
Cooling System Zonal Control Type
n/a
08
Central Fan Integrated (CFI) Ventilation System Status
Not a CFI system
09
System Bypass Duct Status
n/a
10
Date of System Airflow Rate Measurement
2023-12-04
11
Airflow Rate Protocol Utilized
RA3.3 procedures for airflow rate measurement
12
Central Fan Ventilation Cooling System Status
Not a CFVCS
B. Hole for the placement of a Static Pressure Probe (HSPP), and Permanently Installed Static Pressure Probe (PSPP) in the Supply Plenum.
Procedures for installing HSPP or PSPP are specified in RA3.3.1.1.
01
Method Used to Demonstrate Compliance with the HSPP/PSPP
Requirement
HSPP installed and labeled consistent with Figure RA3.3-1
Registration Number:
423-A020204948A-000-001-M 23005A-M 23A
Registration Date/Time: 2023-12-04 08:40:57 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 2 of 4)
C. Airflow Rate Measurement Apparatus and Procedure Information
Instrument Specifications are given in RA3.3.1.1, and system airflow rate measurement apparatus information is given in RA3.3.2.
01
Airflow Rate Measurement Type used for this airflow rate
verification.
Traditional Flow Capture Hood according to procedure in
RA3.3.3.1.4
02
Manufacturer of Airflow Measurement Apparatus
TESTO
03
Model number of Airflow Measurement Apparatus
420
04
Certification Status of the Airflow Measurement Apparatus
Accuracy
Certified by Manufacturer and listed on CEC Website at
http://www.energy.ca.gov/title24/equipment_cert/ama_fas/index.
html
MCH-23a Forced Air System Airflow Rate Measurement - Newly Installed Non -Zoned Systems or Zoned Multi -Speed Compressor
D. Forced Air System Airflow Rate Measurement
The procedures for System Airflow Rate Verification are specified in Reference Residential Appendix RA3.3.
01
Required Minimum System Airflow Rate (cfm/ton)
350
02
Required Minimum System Airflow Target (cfm)
1050
03
Actual System Airflow Rate Measurement (cfm)
1063
04
Compliance Statement:
System airflow rate complies
E. Additional Requirements
01
Air filters that meet the applicable requirements of Standards Section 150.0(m)12 or 150.0(m)13 were properly installed in the system
during system air flow rate measurement identified on this Certificate of Verification.
02
The airflow rate measurement apparatus used to perform the airflow rate measurement identified on this Certificate of Verification was
calibrated in accordance with the apparatus manufacturer's specifications and conforms to the instrumentation specifications given in
RA3.3.1.
03
A visual inspection shall confirm that bypass ducts that deliver conditioned supply air directly to the space conditioning system return
duct airflow are not used on newly constructed zonally controlled systems unless the Performance Certificate of Compliance indicates an
allowance for use of a bypass duct. When a bypass duct is accounted for on the Performance Certificate of Compliance, the airflow rate
shall conform to the specifications listed on the Certificate of Compliance.
04
All registers were fully open during the diagnostic test.
05
System fan was set at maximum speed during the diagnostic test.
06
If fresh air duct is part of the HVAC system it was not closed during the diagnostic test.
07
Airflow rate and fan watt draw shall be simultaneous measurements when used to calculate the Fan Efficacy tested value.
Registration Number:
423-A020204948A-000-001-M 23005A-M 23A
Registration Date/Time: 2023-12-04 08:40:57 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 3 of 4)
E. Additional Requirements
08
Multi -speed compressor space cooling systems or variable speed compressor systems shall verify air flow (cfm/ton) and fan efficacy
(Watt/cfm) with system operating in cooling mode at the maximum compressor speed and the maximum air handler fan speed.
09
Verification Status:
Pass - all applicable requirements are met.
10
Correction Notes:
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met unless
otherwise noted in the Verification Status and the Corrections Notes in this table
F. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 23005A-M 23A
Registration Date/Time: 2023-12-04 08:40:57 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 23005A-M 23A
Registration Date/Time: 2023-12-04 08:40:57 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF VERIFICATION
CF3R-MCH-25-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
HERS Rater to field -verify all system information, discrepancies to be noted by overwriting entry.
01
Space Conditioning System Identification or Name
System 2
02
Space Conditioning System Location or Area Served
Master
03
Condenser (or package unit) make or brand
AMANA
04
Condenser (or package unit) model number
ASZ160361LB
05
Nominal Cooling Capacity (tons) of Condenser
3
06
Condenser (or package unit) serial number
2205076869
07
Refrigerant Type
R-410A
08
Other Refrigerant Type (if applicable)
n/a
09
Liquid Line Filter Drier Installed According to Manufacturers
Specifications (if applicable)
Yes
10
System Installation Type
New
11
Fault Indicator Display (FID) Status (Note: Even systems with a FID
must have refrigerant charge verified by installer)
This system does not have a FID device installed
12
Is the system of a type that the minimum airflow can be verified for
all indoor units using an approved measurement procedure (RA3.3
or RA3.3.3)?
Yes
13
Is the system of a type that approved refrigerant charge verification
procedures can be used to verify compliance with the refrigerant
charge verification requirements when temperatures are >= 55 °F
(RA3.2.2, or RA1)?
Yes, one of the Refrigerant charge verification procedures from
RA3.2.2 or RA1 is applicable to this system and can be used to
verify compliance
14
Date of Refrigerant Charge Verification for this system
2023-12-04
15
Refrigerant charge verification method used.
Subcooling (outdoor temperature must be equal to or greater than
55 degF)
16
Person who performed the Refrigerant Charge Verification
reported on this Certificate of Installation
HERS rater
17
HERS Verification Compliance Requirement Status
System does not qualify for group sampling
Registration Number:
423-A020204948A-000-001-M 25009A-M 25A
Registration Date/Time: 2023-12-04 08:41:06
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:12:06
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 2 of 4)
A. System Information
HERS Rater to field -verify all system information, discrepancies to be noted by overwriting entry.
18
Refrigerant charge verification method used by HERS Rater.
Subcooling
MCH-25b - Refrigerant Charge Verification - Subcooling Method
B. Metering Device Verification
HERS Rater is required to visually field verify all information from CF2R. Subcooling Method can only be used on systems that have a variable
metering device.
01
Refrigerant metering device
Thermostatic Expansion Valve (TXV)
02
Subcooling Method applicability status
Subcooling Method is applicable to this system.
C. Instrument Calibration
HERS Raters are required to calibrate their diagnostic tools. Procedures for instrument calibration are given in Reference Residential Appendix
RA3.2.2 and RA3.2.2.2
01
Date of Digital Refrigerant Gauge Calibration
2023-11-30
02
Date of Digital Thermocouple Calibration
2023-11-30
03
Digital Refrigerant Gauge Calibration Status
Calibration is current
04
Digital Thermocouple Calibration Status
Calibration is current
D. Measurement Access Hole (MAH) Verification
HERS Raters are required to visually field verify MAH. Procedures for installing MAH are specified in Reference Residential Appendix RA3.2.2.3
01
Method Used to Demonstrate Compliance with the Measurement
Access Hole (MAH) Requirement
MAH installed and labeled consistent with Figure 3.2-1
E. Minimum System Airflow Rate Verification
Procedures for verifying minimum system airflow are specified in Reference Residential Appendix RA3.3.3.
01
02
03
Indoor Unit Name or Description of Area
Served
Minimum Required System Airflow Rate (cfm)
System Airflow Rate Verification Status
Master
1400
System complies with minimum airflow rate
requirements
04
SC System complies with Minimum System Airflow Rate Verification
Notes:
Registration Number:
423-A020204948A-000-001-M 25009A-M 25A
Registration Date/Time: 2023-12-04 08:41:06 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:06
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 3 of 4)
F. Data Collection and Calculations
HERS Rater must independently collect all data in this section. Procedures for determining Refrigerant Charge using the Standard Charge
Verification Procedure are given in Reference Residential Appendix RA3.2.2 and RA3.2.2.2
01
Lowest Return Air Dry Bulb Temperature that Occurred During the
Refrigerant Charge Verification Procedure (°F)
85
02
Measured Condenser Air Entering Dry -Bulb Temperature
(Tcondenser,db)
71
03
Outdoor Temperature Qualification Status
Outdoor temperature is within range for using Subcooling
refrigerant charge verification method
04
Measured Liquid Line Temperature (Tiiquid) ( °F)
75.1
05
Measured Liquid Line Pressure (Piiquid) (psig)
283.0
06
Condenser Saturation Temperature (Tcondenser, sat) from Digital
Gauge or P-T Table using Line F05 (°F)
80.5
07
Measured Subcooling (Line F06 - Lilne F04 (°F)
5.4
08
Target Subcooling from Manufacturer (°F)
8
09
Compliance Statement:
System complies with Subcooling Method - Must also pass
metering device verification, next section
G. Metering Device Verification
HERS Rater must independently collect all data in this section. Procedures for the verification of proper metering device operation are specified
in RA3.2.2.6.2
01
Measured Suction Line Temperature (Tsuction) (°F)
55.4
02
Measured Suction Line Pressure (Psuction) (psig)
133.0
03
Evaporator Saturation Temperature (Tevaporator, sat) from Digital
Gauge or P-T Table using Line G02 (°F)
46.2
04
Measured Superheat (Line G01- Line G03) (°F)
9.2
05
Measured Superheat (Line G04) is between 3 °F and 26 °F
(inclusive)
Passes CEC requirement
06
Measured Superheat (Line G04) is within Manufacturer's
Specifications ( if known)
Yes, documentation to be provided upon request
07
Compliance Statement:
Metering device verification passes
H. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 25009A-M 25A
Registration Date/Time: 2023-12-04 08:41:06
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:12:06
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 25009A-M 25A
Registration Date/Time: 2023-12-04 08:41:06 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:06
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF VERIFICATION
CF3R-MCH-20-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
01
Space Conditioning System Identification or Name
System 3
02
Space Conditioning System Location
or Area Served
Casita
03
Indoor Unit Name or Description
of Area Served
Casita
04
Building Type from from parent CC
Single family
05
Verified Low Leakage Ducts in Conditioned
from parent CC?
Space (VLLDCS) Credit
No, credit is not taken
06
Verified Low Leakage Air Handling
Unit Credit from parent CC?
No, credit is not taken
07
Duct System Compliance Category
New
08
Portions of Duct Located in Garage?
No
09
Is the system type Small Duct High
Velocity (SDHV) ?
No
MCH-20a - Completely New Duct System
Registration Number:
423-A020204948A-000-001-M 20006A-M 20A
Registration Date/Time: 2023-12-04 08:40:59 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 2 of 4)
B. Duct Leakage Diagnostic Test
01
Air Handling Unit Airflow (AHU Airflow) Determination Method
Cooling system method
02
Condenser Nominal Cooling Capacity (ton)
2
03
Indoor Unit Nominal Cooling Capacity
2
04
Heating Capacity (kBtu/h)
n/a
05
Conditioned Floor Area Served by this HVAC System (ft2)
772
06
Measured AHU Airflow (cfm)
n/a
07
Duct Leakage Test Conditions
Test final
08
Duct Leakage Test Method
Total leakage
09
Leakage Factor
0.05
10
Calculated Target Allowable Duct Leakage (cfm)
40
11
Actual Duct Leakage Rate from Leakage Test Measurement (cfm)
40
12
Compliance Statement
System passes leakage test
13
Notes:
C. Additional Requirements for Compliance
01
System was tested in its normal operation condition. No temporary taping allowed.
02
Outside air (OA) duct connections to the central forced air duct system shall not be sealed/taped off during duct leakage testing. OA ducts
used for Central Fan Integrated (CFI) Indoor Air Quality ventilation systems, or Central Fan Ventilation Cooling Systems, that utilize
dampers that open only when OA is required and automatically close when OA is not required, may configure the OA damper to the
closed position during duct leakage testing.
03
All supply and return register boots were sealed to the drywall.
04
Building cavities were not used as plenums or platform returns in lieu of ducts.
05
If cloth backed tape was used it was covered with Mastic and draw bands.
06
All connection points between the air handler and the supply and return plenums are completely sealed.
Visual Inspection at Final Construction Stage (applicable if system was tested at rough -in).
After installing the interior finishing wall and verifying that the above rough -in tests was completed, the following procedure must be performed
07
For all supply and return registers, verify that the spaces between the register boot and the interior finishing wall are properly sealed.
08
If the house rough -in duct leakage test was conducted without an air handler installed, inspect the connection points between the air
handler and the supply and return plenums to verify that the connection points are properly sealed.
Registration Number:
423-A020204948A-000-001-M 20006A-M 20A
Registration Date/Time: 2023-12-04 08:40:59
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 3 of 4)
09
Inspect all joints to ensure that no cloth backed rubber adhesive duct tape is used.
10
Verification Status:
Pass - all applicable requirements are met.
11
Correction Notes:
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met unless
otherwise noted in the Verification Status and the Corrections Notes in this table.
D. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 20006A-M 20A
Registration Date/Time: 2023-12-04 08:40:59 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
DUCT LEAKAGE DIAGNOSTIC TEST
CALIFORNIA ENERGY COMMISSION
CF3R-MCH-20-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 20006A-M 20A
Registration Date/Time: 2023-12-04 08:40:59 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CERTIFICATE OF VERIFICATION
CF3R-MCH-23-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. Ducted Cooling System Information
01
Space Conditioning System Identification or Name
System 3
02
Space Conditioning System Description of Area Served
Casita
03
Indoor Unit Name
Casita
04
System Installation Type
New
05
Nominal Cooling Capacity (tons)
2
06
Condenser Speed Type
n/a
07
Cooling System Zonal Control Type
n/a
08
Central Fan Integrated (CFI) Ventilation System Status
Not a CFI system
09
System Bypass Duct Status
n/a
10
Date of System Airflow Rate Measurement
2023-12-04
11
Airflow Rate Protocol Utilized
RA3.3 procedures for airflow rate measurement
12
Central Fan Ventilation Cooling System Status
Not a CFVCS
B. Hole for the placement of a Static Pressure Probe (HSPP), and Permanently Installed Static Pressure Probe (PSPP) in the Supply Plenum.
Procedures for installing HSPP or PSPP are specified in RA3.3.1.1.
01
Method Used to Demonstrate Compliance with the HSPP/PSPP
Requirement
HSPP installed and labeled consistent with Figure RA3.3-1
Registration Number:
423-A020204948A-000-001-M 23007A-M 23A
Registration Date/Time: 2023-12-04 08:41:01 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 2 of 4)
C. Airflow Rate Measurement Apparatus and Procedure Information
Instrument Specifications are given in RA3.3.1.1, and system airflow rate measurement apparatus information is given in RA3.3.2.
01
Airflow Rate Measurement Type used for this airflow rate
verification.
Traditional Flow Capture Hood according to procedure in
RA3.3.3.1.4
02
Manufacturer of Airflow Measurement Apparatus
TESTO
03
Model number of Airflow Measurement Apparatus
420
04
Certification Status of the Airflow Measurement Apparatus
Accuracy
Certified by Manufacturer and listed on CEC Website at
http://www.energy.ca.gov/title24/equipment_cert/ama_fas/index.
html
MCH-23a Forced Air System Airflow Rate Measurement - Newly Installed Non -Zoned Systems or Zoned Multi -Speed Compressor
D. Forced Air System Airflow Rate Measurement
The procedures for System Airflow Rate Verification are specified in Reference Residential Appendix RA3.3.
01
Required Minimum System Airflow Rate (cfm/ton)
350
02
Required Minimum System Airflow Target (cfm)
700
03
Actual System Airflow Rate Measurement (cfm)
749
04
Compliance Statement:
System airflow rate complies
E. Additional Requirements
01
Air filters that meet the applicable requirements of Standards Section 150.0(m)12 or 150.0(m)13 were properly installed in the system
during system air flow rate measurement identified on this Certificate of Verification.
02
The airflow rate measurement apparatus used to perform the airflow rate measurement identified on this Certificate of Verification was
calibrated in accordance with the apparatus manufacturer's specifications and conforms to the instrumentation specifications given in
RA3.3.1.
03
A visual inspection shall confirm that bypass ducts that deliver conditioned supply air directly to the space conditioning system return
duct airflow are not used on newly constructed zonally controlled systems unless the Performance Certificate of Compliance indicates an
allowance for use of a bypass duct. When a bypass duct is accounted for on the Performance Certificate of Compliance, the airflow rate
shall conform to the specifications listed on the Certificate of Compliance.
04
All registers were fully open during the diagnostic test.
05
System fan was set at maximum speed during the diagnostic test.
06
If fresh air duct is part of the HVAC system it was not closed during the diagnostic test.
07
Airflow rate and fan watt draw shall be simultaneous measurements when used to calculate the Fan Efficacy tested value.
Registration Number:
423-A020204948A-000-001-M 23007A-M 23A
Registration Date/Time: 2023-12-04 08:41:01 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 3 of 4)
E. Additional Requirements
08
Multi -speed compressor space cooling systems or variable speed compressor systems shall verify air flow (cfm/ton) and fan efficacy
(Watt/cfm) with system operating in cooling mode at the maximum compressor speed and the maximum air handler fan speed.
09
Verification Status:
Pass - all applicable requirements are met.
10
Correction Notes:
The responsible person's signature on this compliance document affirms that all applicable requirements in this table have been met unless
otherwise noted in the Verification Status and the Corrections Notes in this table
F. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 23007A-M 23A
Registration Date/Time: 2023-12-04 08:41:01 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
SPACE CONDITIONING SYSTEM AIRFLOW
RATE
CF3R-MCH-23-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 23007A-M 23A
Registration Date/Time: 2023-12-04 08:41:01 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:00
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
REFRIGERANT CHARGE VERIFICATION
CALIFORNIA ENERGY COMMISSION
CERTIFICATE OF VERIFICATION
CF3R-MCH-25-H
(Page 1 of 4)
Project Name:
2061543
Enforcement Agency:
La Quinta, City of
Dwelling Address:
58-864 Marbella LOT 62
Permit Number:
PENDING
City and Zip Code
LA QUINTA, 92253
Permit Application Date:
2023-05-01
A. System Information
HERS Rater to field -verify all system information, discrepancies to be noted by overwriting entry.
01
Space Conditioning System Identification or Name
System 3
02
Space Conditioning System Location or Area Served
Casita
03
Condenser (or package unit) make or brand
GOODMAN
04
Condenser (or package unit) model number
GSZH502410AA
05
Nominal Cooling Capacity (tons) of Condenser
2
06
Condenser (or package unit) serial number
2309240920
07
Refrigerant Type
R-410A
08
Other Refrigerant Type (if applicable)
n/a
09
Liquid Line Filter Drier Installed According to Manufacturers
Specifications (if applicable)
Yes
10
System Installation Type
New
11
Fault Indicator Display (FID) Status (Note: Even systems with a FID
must have refrigerant charge verified by installer)
This system does not have a FID device installed
12
Is the system of a type that the minimum airflow can be verified for
all indoor units using an approved measurement procedure (RA3.3
or RA3.3.3)?
Yes
13
Is the system of a type that approved refrigerant charge verification
procedures can be used to verify compliance with the refrigerant
charge verification requirements when temperatures are >= 55 °F
(RA3.2.2, or RA1)?
Yes, one of the Refrigerant charge verification procedures from
RA3.2.2 or RA1 is applicable to this system and can be used to
verify compliance
14
Date of Refrigerant Charge Verification for this system
2023-12-04
15
Refrigerant charge verification method used.
Subcooling (outdoor temperature must be equal to or greater than
55 degF)
16
Person who performed the Refrigerant Charge Verification
reported on this Certificate of Installation
HERS rater
17
HERS Verification Compliance Requirement Status
System does not qualify for group sampling
Registration Number:
423-A020204948A-000-001-M 25010A-M 25A
Registration Date/Time: 2023-12-04 08:41:09
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:12:06
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 2 of 4)
A. System Information
HERS Rater to field -verify all system information, discrepancies to be noted by overwriting entry.
18
Refrigerant charge verification method used by HERS Rater.
Subcooling
MCH-25b - Refrigerant Charge Verification - Subcooling Method
B. Metering Device Verification
HERS Rater is required to visually field verify all information from CF2R. Subcooling Method can only be used on systems that have a variable
metering device.
01
Refrigerant metering device
Thermostatic Expansion Valve (TXV)
02
Subcooling Method applicability status
Subcooling Method is applicable to this system.
C. Instrument Calibration
HERS Raters are required to calibrate their diagnostic tools. Procedures for instrument calibration are given in Reference Residential Appendix
RA3.2.2 and RA3.2.2.2
01
Date of Digital Refrigerant Gauge Calibration
2023-11-30
02
Date of Digital Thermocouple Calibration
2023-11-30
03
Digital Refrigerant Gauge Calibration Status
Calibration is current
04
Digital Thermocouple Calibration Status
Calibration is current
D. Measurement Access Hole (MAH) Verification
HERS Raters are required to visually field verify MAH. Procedures for installing MAH are specified in Reference Residential Appendix RA3.2.2.3
01
Method Used to Demonstrate Compliance with the Measurement
Access Hole (MAH) Requirement
MAH installed and labeled consistent with Figure 3.2-1
E. Minimum System Airflow Rate Verification
Procedures for verifying minimum system airflow are specified in Reference Residential Appendix RA3.3.3.
01
02
03
Indoor Unit Name or Description of Area
Served
Minimum Required System Airflow Rate (cfm)
System Airflow Rate Verification Status
Casita
1400
System complies with minimum airflow rate
requirements
04
SC System complies with Minimum System Airflow Rate Verification
Notes:
Registration Number:
423-A020204948A-000-001-M 25010A-M 25A
Registration Date/Time: 2023-12-04 08:41:09 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:06
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 3 of 4)
F. Data Collection and Calculations
HERS Rater must independently collect all data in this section. Procedures for determining Refrigerant Charge using the Standard Charge
Verification Procedure are given in Reference Residential Appendix RA3.2.2 and RA3.2.2.2
01
Lowest Return Air Dry Bulb Temperature that Occurred During the
Refrigerant Charge Verification Procedure (°F)
85
02
Measured Condenser Air Entering Dry -Bulb Temperature
(Tcondenser,db)
75
03
Outdoor Temperature Qualification Status
Outdoor temperature is within range for using Subcooling
refrigerant charge verification method
04
Measured Liquid Line Temperature (Tiiquid) (°F)
79.5
05
Measured Liquid Line Pressure (Piiquid) (psig)
252.6
06
Condenser Saturation Temperature (Tcondenser, sat) from Digital
Gauge or P-T Table using Line F05 (°F)
85.7
07
Measured Subcooling (Line F06 - Lilne F04 (°F)
6.2
08
Target Subcooling from Manufacturer (°F)
8
09
Compliance Statement:
System complies with Subcooling Method - Must also pass
metering device verification, next section
G. Metering Device Verification
HERS Rater must independently collect all data in this section. Procedures for the verification of proper metering device operation are specified
in RA3.2.2.6.2
01
Measured Suction Line Temperature (Tsuction) (°F)
55.9
02
Measured Suction Line Pressure (Psuction) (psig)
134.5
03
Evaporator Saturation Temperature (Tevaporator, sat) from Digital
Gauge or P-T Table using Line G02 (°F)
46.8
04
Measured Superheat (Line G01- Line G03) (°F)
9.1
05
Measured Superheat (Line G04) is between 3 °F and 26 °F
(inclusive)
Passes CEC requirement
06
Measured Superheat (Line G04) is within Manufacturer's
Specifications ( if known)
Yes, documentation to be provided upon request
07
Compliance Statement:
Metering device verification passes
H. Determination of HERS Verification Compliance
All applicable sections of this document shall indicate compliance with the specified verification protocol requirements in order
for this Certificate of Verification as a whole to be determined to be in compliance.
01
Complies: All specified verification protocol requirements on this document are met.
Registration Number:
423-A020204948A-000-001-M 25010A-M 25A
Registration Date/Time: 2023-12-04 08:41:09
HERS Provider: CHEERS
CA Building Energy Efficiency Standards
2022 Residential Compliance
Report Version: 2022.0.000
Schema Version: rev 20220101
Report Generated: 2023-12-04 13:12:06
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.
4g, CALIFORNIA ENERGY COMMISSION
REFRIGERANT CHARGE VERIFICATION
CF3R-MCH-25-H
(Page 4 of 4)
DOCUMENTATION AUTHOR'S DECLARATION STATEMENT
1. I certify that this Certificate of Verification documentation is accurate and complete.
Documentation Author Name:
Angel Arechiga
Documentation Author Signature:u
Angel e Areclut "_
Company:
iPermit
Date Signed:
2023-12-04
Address:
31225 La Baya Drive
CEA/ HERS Certification Identification (if applicable):
RCN13516
City/State/Zip:
Westlake Village CA 91362
Phone:
818-735-7876
RESPONSIBLE PERSON'S DECLARATION STATEMENT
I certify the following under penalty of perjury, under the laws of the State of California:
1. The information provided on this Certificate of Verification is true and correct.
2. I am the certified HERS Rater who performed the verification identified and reported on this Certificate of Verification (responsible
rater).
3. The installed features, materials, components, manufactured devices, or system performance diagnostic results that require HERS
verification identified on this Certificate of Verification comply with the applicable requirements in Reference Appendices RA2, RA3,
and the requirements specified on the Certificate of Compliance for the building approved by the enforcement agency.
4. The information reported on applicable sections of the Certificate(s) of Installation (CF2R) signed and submitted by the person(s)
responsible for the construction or installation conforms to the requirements specified on the Certificate(s) of Compliance (CF1R)
approved by the enforcement agency.
5. I understand that a registered copy of this Certificate of Verification shall be posted, or made available with the building permit(s)
issued for the building, and made available to the enforcement agency for all applicable inspections, and I will take the necessary
steps to ensure this requirement is accomplished.
6. I understand that a registered copy of this Certificate of Verification is required to be included with the documentation the builder
provides to the building owner at occupancy, and I will take the necessary steps to ensure this requirement is accomplished.
BUILDER OR INSTALLER INFORMATION AS SHOWN ON THE CERTIFICATE OF INSTALLATION
Company Name (Installing Subcontractor, General Contractor, or Builder/Owner):
DEH Mechanical Company Inc
Responsible Builder or Installer Name:
Tom Powers (authorized Angel Arechiga)
CSLB License:
752819
HERS PROVIDER DATA REGISTRY INFORMATION
Sample Group Number (if applicable):
Dwelling Test Status in Sample Group (if applicable)
N/A
HERS RATER INFORMATION
HERS Rater Company Name:
iPermit
Responsible Rater Name:
Angel Arechiga
Responsiblele1 Rater,�Signature: ��
A v"O eArec�7_ v"O,"�.
Responsible Rater Certification Number w/ this HERS Provider:
RCN13516
Date Signed:
2023-12-04
Digitally signed by California Home Energy Efficiency Rating Services (CHEERS). This digital signature is provided in order to secure the content of
this registered document, and in no way implies Registration Provider responsibility for the accuracy of the information.
Registration Number:
423-A020204948A-000-001-M 25010A-M 25A
Registration Date/Time: 2023-12-04 08:41:09 HERS Provider: CHEERS
CA Building Energy Efficiency Standards
Report Version: 2022.0.000 Report Generated: 2023-12-04 13:12:06
2022 Residential Compliance Schema Version: rev 20220101
NOTICE: This document has been generated by California Home Energy Efficiency Rating Services (CHEERS) using information uploaded by third parties not affiliated with or
related to CHEERS. Therefore, CHEERS is not responsible for, and cannot guarantee, the accuracy or completeness of the information contained in this document.