Qvadrant Consulting, Inc. TRANSMITTAL LETTER SEALED BID – HIGHWAY 111 REHABILITATION PROJECT – PROJECT NO. 2022-25 - CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES – DO NOT OPEN WITH REGULAR MAIL Date: November 18. 2024 TO: Carley Escarrega AdministraƟve Technician, Public Works Department City of La Quinta 78-495 Calle Tampico La Quinta, CA 92253 FROM: Vishal Jakkaraju Qvadrant ConsulƟng Inc. 73639 Okeeffe Way Palm Desert CA 92211 Page | 1 TABLE OF CONTENTS 1.0 Cover LeƩer…………………………………………………………………………………………….. 2 2.0 References of California government agencies…………………………………………. 3 3.0 Scope of Services……………………………………………………………………………………… 6 4.0 List of Complementary Services……………………………………………………………….. 25 5.0 Disclosures………………………………………………………………………………………………. 27 6.0 Acknowledgement of Insurance Requirements………………………………………… 27 7.0 Non-Collusion Affidavit…………………………………………………………………………….. 27 8.0 Acknowledgement of Addenda………………………………………………………………… 27 Appendix A- Resumes Appendix B-SupporƟng DocumentaƟon Page | 2 Page | 3 2.0 References of California government agencies: REFERENCE 1 Project Name: La Quinta Village Complete Streets- City Project No. 2015-03 Project Owner: City of La Quinta, 78495 Calle Tampico La Quinta, CA 92253 Project Owner RepresentaƟve: Bryan McKinney, 760-777-7045, bmckinney@laquintaca.gov Project CompleƟon Date: 08/17/2020 Project description: The project includes the construcƟon of five new roundabouts in the La Quinta Village where pedestrian, bicycle, golf cart, and automobile traffic exists. These roundabouts will help to accommodate non-vehicular traffic. The La Quinta Village Complete Streets project is focused on making roadways safer and more accessible to pedestrians and bicycles in the La Quinta Village. The Project will reduce four traffic lanes to two lanes along Calle Tampico and Calle Sinaloa from Eisenhower to Desert Club Drive, and along Eisenhower from Calle Tampico to Calle Sinaloa. This area will be used as space for designated bike and golf cart lanes. Roundabouts will be installed at five key intersecƟons, Calle Tampico and Desert Club Drive, Calle Tampico and Avenida Bermudas, Calle Tampico and Eisenhower Drive, Eisenhower Drive and Avenida Montezuma, and Calle Sinaloa/Avenue 52 and Avenida Bermudas, to provide beƩer traffic flows. The reduced lanes and crosswalks added midblock crossing will provide pedestrians with safer access to Civic Center Park, Old Town La Quinta, and the Benjamin Franklin Elementary School. Staff from Qvadrant who worked on this project: Vishal Jakkaraju, during employment with Granite Construction (Indio Office). Project Outcome: The project owner inspected and reviewed all the performance data and test results to verify that the project is of exemplary quality. This project was recognized by NAPA (National Asphalt Pavement Association) for Quality in Construction Award. REFERENCE 2 Project Name: Madison Street Improvement Project Owner: City of Indio, 83101 Ave 45 Indio CA 92201 Project Owner RepresentaƟve: Tom Rafferty, 760- 391-4017, trafferty@indio.org Project CompleƟon Date: 03/28/2019 Page | 4 Project description: The work includes asphalt paving, concrete construcƟon, drainage installaƟons, traffic signal installaƟons, landscaping and irrigaƟon, water relocaƟons and upgrades, traffic control, surveying, conduit installaƟon, pot- holing, and related work to widen a four-lane road. We partnered with City of Indio, City of La Quinta, Golden Voice, Empire Polo, El Dorado Polo, IID, FronƟer, AT&T, SCG, CVWD, Indio Water Authority, Spectrum, Valley Sanitary District. Staff from Qvadrant who worked on this project: Vishal Jakkaraju, during employment with Granite Construction (Indio Office). Project Outcome: The project owner inspected and reviewed all the performance data and test results to verify that the project is of exemplary quality. This project was recognized by NAPA (National Asphalt Pavement Association) for Quality in Construction Award. REFERENCE 3 Project Name: Lincoln Street Pavement RestoraƟon and Sidewalk Project Project Owner: County of Riverside, 2950 Washington Street Riverside CA 92504 Project Owner RepresentaƟve: David Hylkema, 951-955-688, dhylkema@rivco.org Project CompleƟon Date: 09/03/2021 Project description: The Lincoln Street is one of roads that connects the community of Mecca with the Coachella Valley located on the East. the street was in desperate need of repair. This project consisted of resurfacing approximately 2 miles of exisƟng asphalt concrete (AC) pavement of Lincoln Street from 5th Street to 62nd Avenue; The project included full removal and replacement of AC in certain areas as well as pulverizaƟon and re- pavement of the exisƟng road. Staff from Qvadrant who worked on this project: Vishal Jakkaraju, during employment with Granite Construction (Indio Office). Project Outcome: The project owner inspected and reviewed all the performance data and test results to verify that the project is of exemplary quality. This project was recognized by NAPA (National Asphalt Pavement Association) for Quality in Construction Award. REFERENCE 4 Project Name: Agua Caliente Band of Cahuilla Indians-SecƟon 24 Roadway Improvements Phase 1A Project Owner: City of Rancho Mirage, 69825 Hwy 111 Rancho Mirage CA 92270 Project Owner RepresentaƟve: Glenn Deal, 760- 835-4810, glennd@ranchomirageca.gov Project CompleƟon Date: 10/22/2021 Page | 5 Project description: The purpose of the project is to provide enƟre underground services and street widening for the Tribe’s upcoming development across the Agua Caliente Casino. The Project includes but is not limited to, construcƟon of street improvements involving demoliƟon, earthwork, clear and grub, asphalt concrete and PCC pavement, PCC curbs, curb and guƩers, valley guƩers, spandrel, and cross guƩers; storm drain systems, bike paths, traffic signals, pavement striping and markings, roadside signs, and retenƟon basins; construcƟon of waterline and sewer lines, uƟlity relocaƟons and improvements; and adjacent site earthwork. Staff from Qvadrant who worked on this project: Vishal Jakkaraju, during employment with Granite Construction (Indio Office). Project Outcome: The project owner inspected and reviewed all the performance data and test results to verify that the project is of exemplary quality. This project was recognized by NAPA (National Asphalt Pavement Association) for Quality in Construction Award. REFERENCE 5 Project Name: I-10 Pavement RehabilitaƟon (Caltrans #08-1E8604) Project Owner: Caltrans, 73800 Dinah Shore Suite 104 Palm Desert CA 92211. Project Owner RepresentaƟve: Essi Mohammadi, 951-453-8943, essi.mohammadi@dot.ca.gov Project CompleƟon Date: FY 2017. Project description: The Interstate-10 Pavement Rehab Project is one of the largest Pavement RehabilitaƟon Projects in the long history of the California Department of TransportaƟon (Caltrans) The Project was located on one of the busiest Interstate Highways in the USA: State Highway (Interstate-10) in Riverside County near Desert Centre from 1.9 miles East of Cactus Rest Area to 0.4 mile East of Route 177. This Interstate-10 corridor is a major trucking thoroughfare between Los Angeles and rest of the country. The traffic on the East Bound was approximately 13,200 vehicles per day with about 36% being truck traffic and West Bound was approximately 13,700 vehicles per day with about 36% being truck traffic. The unique construcƟon features of the project were: 1.6 Million square yards of asphalt pavement cold planning; placement of 521,000 Tons of Hot Mix Asphalt and 177,000 Tons of Rubberized Hot Mixed Asphalt; placement of 75,000 linear feet of asphalt dike; applying 765 tons of Tack Coat; removal of 258,000 lbs. of treated wood waste; installing 29,000 linear feet of Midwest Guardrail System; 3.8 Million linear feet of temporary pavement striping and 1.1 Million linear feet of final pavement striping. Staff from Qvadrant who worked on this project: Vishal Jakkaraju, during employment with Granite Construction (Indio Office). Project Outcome: Caltrans Partnering Award and the project owner inspected and reviewed all the performance data and test results to verify that the project is of exemplary quality. This project was recognized by NAPA (National Asphalt Pavement Association) for Quality in Construction Award. Page | 6 3.0 SCOPE OF SERVICES INTRODUCTION Qvadrant’s Vision Statement Our vision is to deliver World Class Quality results to the City of La Quinta in all phases of this project by leveraging our ConstrucƟon Management and InspecƟon services. Why Choose Qvadrant? Qvadrant has customer saƟsfacƟon at the forefront of everything needed for the planning and execuƟon of this project. Our team members are highly engaged, high performing and innovaƟve individuals. We will implement state-of-the-art processes on this project and are commiƩed to providing an excellent experience to the City of La Quinta. We have used a “HolisƟc System” approach to deliver world class quality outcomes in ConstrucƟon Management and InspecƟons services to the city. Qvadrant’s Value ProposiƟon to the City of La Quinta  A local firm with staff that has supported the successful compleƟon of construcƟon projects with the City of La Quinta and other local agencies.  Successful partnering experience with local General Contractors and material suppliers resulƟng in award winning projects in Coachella Valley.  Roadways/Highways RehabilitaƟon projects experience.  Subject MaƩer Experts in delivering ConstrucƟon Management and InspecƟons services uƟlizing streamlined, cost-effecƟve and project first approach to make decisions in the best interest of the project.  Commitment to safety of all stakeholders, meeƟng budgets and schedules, geƫng it right the first Ɵme (Quality), protecƟng environment and using resources responsibly and implemenƟng a ConƟnuous InnovaƟon mindset. Qvadrant’s HolisƟc System: Qvadrant has developed a simple, yet robust HolisƟc system for the City of La Quinta. The philosophy of this system is to set up all stakeholders of this project for success. We strongly believe that, when team members on this project take pride in their work and strive to implement their roles and responsibiliƟes with a mindset to “Get it Right the First Time” the results will speak for themselves. Overall, our goal is to meet and exceed the expectaƟons of the City of La Quinta on this project and build relaƟonships and value for City so that we can become trusted partners and win future work. Page | 7 SchemaƟc of Qvadrant’s HolisƟc System Qvadrant’s OrganizaƟon Chart Phase 1 Pre-Construction Preparation Phase 2 Construction Management Implementation Phase 3 Compliance Monitoring and Measurment Phase 4 Documentation and Reporting Phase 5 Closeout Vishal Jakkaraju Construction Manager Suseela Jakkaraju Outreach Coordinator Juan Vasquez Inspector Sushruth Project Engineer Page | 8 3.1 CONSTRUCTION MANAGEMENT SERVICES: Qvadrant has a robust construcƟon management system built on a system of planning, implemenƟng, checking and innovaƟng. This system is designed to drive consistent results using unique processes and tools to verify conformance to the City of La Quinta’s goals and expectaƟons for this project. This system is designed to deliver repeatable performance and innovaƟve construcƟon management outputs in every stage of the project. The system is also a method to measure performance to maintain accountability of the contractor and subcontractors. This system will be administered by ConstrucƟon Manager Vishal Jakkaraju with the program's top prioriƟes being customer saƟsfacƟon and delivering products to the city that meet or exceed project requirements. Our holisƟc system will facilitate clear communicaƟon and coordinaƟon among the city, construcƟon manager, design engineer, survey team, and construcƟon contractor. To ensure a comprehensive and professional construcƟon management system aligned with Caltrans standards, the approach can be summarized into five key phases: Pre-ConstrucƟon PreparaƟon, ConstrucƟon Management ImplementaƟon, Compliance Monitoring and Measurement, DocumentaƟon & ReporƟng, and Closeout. Below is the systemaƟc approach: PHASE 1 PRE-CONSTRUCTION PREPARATION A. CONSTRUCTABILITY REVIEW Qvadrant will conduct a detailed review of plans, specificaƟons, and addenda to idenƟfy potenƟal design or constructability issues. We will review construcƟon drawings and specificaƟons for clarity, accuracy, and consistency, minimizing potenƟal misunderstandings. Our evaluaƟon shall ensure details are provided for complex areas, such as corners, intersecƟons, or non- standard construcƟon methods. We will verify that roadway, drainage, electrical, signage and marking drawings are well-coordinated and avoid conflicts. Based on our review, a report highlighƟng risks, discrepancies, or opportuniƟes for opƟmizaƟon will be presented to the city. B. FIELD WALKS (QVADRANT’S INNOVATIVE APPROACH) Living and supporƟng the building of numerous construcƟon projects in the Coachella Valley for over a decade and frequently driving on HWY 111 in La Quinta, we have firsthand experience of understanding the impact and strategizing with CiƟes to execute a successful construcƟon project especially with numerous busy businesses being impacted with the construcƟon operaƟons of this project. We believe that the field walk(s) is a very criƟcal step in the planning process of this project and therefore we will ensure a deliberate and focused approach is implemented during our field walks. Page | 9 Qvadrant’s field walk findings will be documented in a detailed report with photos, diagrams, and annotated maps, forming a strong foundaƟon for planning construcƟon acƟviƟes and miƟgaƟon strategies. Our evaluaƟng factors that may impact construcƟon, traffic flow, public safety, and business operaƟons and a comprehensive list of items that we will assess are presented below: ExisƟng Site CondiƟons Roadway CondiƟons: Pavement type, condiƟon, and exisƟng damage. Road markings, lane configuraƟons, and traffic flow paƩerns. Sidewalks and Pedestrian Pathways: CondiƟon and accessibility of sidewalks and crosswalks. Areas with ADA compliance needs. UƟliƟes: LocaƟon and condiƟon of visible uƟliƟes (water, sewer, gas, electrical, communicaƟon lines). Presence of manholes, hydrants, valves, and uƟlity poles. Drainage: ExisƟng drainage systems, catch basins, and potenƟal flood-prone areas. Traffic and Access ConsideraƟons Traffic Volumes and PaƩerns: Peak and off-peak traffic flows. IntersecƟon performance and potenƟal congesƟon points. Access to Businesses: Driveway locaƟons and configuraƟons for each business. Delivery/loading zones and service entrances. Public Transit: Presence of bus stops, transit shelters, and routes along the roadway. Parking: On-street parking availability and uƟlizaƟon. Proximity of off-street parking lots to businesses. Business Impacts IdenƟfy high-traffic businesses, such as restaurants, retail stores, or medical faciliƟes. Consider operaƟng hours and peak customer Ɵmes. Signage and Visibility: Placement of exisƟng business signs and potenƟal visibility impacts during construcƟon. Customer and Delivery Access: Observe how customers and suppliers currently access each business. Safety ConsideraƟons Pedestrian Safety: Areas of high pedestrian acƟvity, such as crosswalks, intersecƟons, and sidewalk zones. PotenƟal conflict points between vehicles and pedestrians. Traffic Control Needs: LocaƟons requiring temporary signals, signage, or barriers to ensure safe operaƟons Emergency Access: Routes used by fire, police, and medical services that must remain accessible. Environmental and AestheƟc ConsideraƟons Landscaping: ExisƟng trees, plants, and green spaces that may be impacted or require protecƟon. Noise and Air Quality: Areas likely to be affected by construcƟon noise or dust. Adjacent ProperƟes: SensiƟve areas, such as schools, hospitals, or residenƟal properƟes, requiring addiƟonal miƟgaƟon. UƟlity CoordinaƟon Underground UƟliƟes: Evaluate plans for potenƟal conflicts with underground uƟliƟes. Check for exisƟng uƟlity markers and potholing requirements. Page | 10 Overhead UƟliƟes Presence of powerlines or communicaƟon cables that may require relocaƟon or protecƟon. Future ConstrucƟon Planning Staging and Storage Areas: IdenƟfy possible locaƟons for contractor staging areas, material storage, and equipment parking. Detours and AlternaƟve Routes Evaluate potenƟal detour routes for vehicular and pedestrian traffic. Temporary Signage LocaƟons Assess ideal spots for “Business Open” or “Detour” signs to minimize customer confusion. Regulatory and Permiƫng Requirements Environmental Permits: Check for requirements such as stormwater management (SWPPP) and dust control (PM-10). Right-of-Way IdenƟfy any areas requiring temporary or permanent right-of-way acquisiƟons. Special Permits Evaluate requirements for noise variances, lane closures, or sidewalk use. Visual DocumentaƟon Photographic Records: Take photos to document exisƟng condiƟons, including driveways, sidewalks, and traffic control devices. Highlight sensiƟve or problemaƟc areas requiring special aƩenƟon. Stakeholder Engagement CoordinaƟon with Businesses: Meet with business owners or managers to discuss operaƟonal concerns. Understand delivery schedules, customer access needs, and peak business hours. Community Concerns: IdenƟfy any community expectaƟons or potenƟal objecƟons related to the project. C. KICK-OFF MEETING AŌer conducƟng the field walk(s), the following items will be presented to the city. These items will be uƟlized to assist the city in developing project goals, expectaƟon of contractors and project performance measurements to ensure successful overall project execuƟon. Findings from the Field Walk  Summary of exisƟng site condiƟons, including roadway, sidewalks, uƟliƟes, and drainage.  Key access points to businesses, parking lots, and pedestrian pathways.  ObservaƟons about traffic flow, peak hours, and congesƟon points.  Specific constraints or challenges idenƟfied during the field walk, such as uƟlity conflicts, space limitaƟons for staging, or sensiƟve areas. Page | 11 Project Scope and ObjecƟves  Detailed scope of work and construcƟon acƟviƟes planned.  Expected project Ɵmelines and phases, including start date, major milestones, and compleƟon date.  Specific deliverables, such as ADA-compliant upgrades, uƟlity improvements, or landscaping restoraƟon. Traffic Control and Access  Proposed Traffic Control Plan (TCP), including lane closures, detours, and rerouƟng of vehicles and pedestrians.  Strategies to minimize impacts to business access, such as alternaƟve access routes, temporary driveways, or off-peak construcƟon hours.  CoordinaƟon of public transit, bus stop relocaƟons, or changes to transit schedules.  Emergency access plans to ensure unimpeded routes for first responders. Business and Community Impacts  CommunicaƟon plan for keeping businesses and the community informed, including:  NoƟficaƟons of construcƟon phases and potenƟal disrupƟons.  Use of signage like “Business Open During ConstrucƟon.”  Dedicated hotline, email, or website for project updates.  Plans to coordinate with businesses, such as:  Maintaining delivery/loading zones.  ProtecƟng high-traffic Ɵmes for businesses. UƟliƟes and Permits  Review of potenƟal uƟlity conflicts (underground and overhead) and required relocaƟons or protecƟons.  Status of permits (e.g., encroachment, environmental, noise variances) and any pending approvals.  CoordinaƟon with uƟlity providers for adjustments or planned outages. ConstrucƟon Staging and LogisƟcs  Proposed locaƟons for staging areas, material storage, and equipment parking.  Delivery schedules and haul routes to minimize disrupƟon to traffic and businesses.  Plans for dust control and cleanliness, including regular street sweeping or washing.  Site safety measures, including barriers and signage. Public and Business Outreach  Strategies for community engagement, such as: o Scheduling regular progress meeƟngs with stakeholders. o Sending mailers or flyers to nearby businesses and residents. Page | 12 o UpdaƟng project informaƟon on the City’s website and social media channels. o Assigning responsibiliƟes for public inquiries, such as hotline calls or emails. Environmental and Regulatory Compliance  Plan for monitoring and enforcing SWPPP (stormwater polluƟon prevenƟon) requirements.  Strategies for controlling dust, noise, and vibraƟon, especially in sensiƟve areas.  Compliance with Caltrans and local agency standards. Scheduling and CoordinaƟon  Review of the contractor’s preliminary schedule, including phasing and sequencing of work.  CoordinaƟon with other ongoing projects in the area to minimize cumulaƟve impacts.  Agreement on look-ahead schedules to provide regular updates to stakeholders. Special Concerns and PotenƟal Risks  IdenƟficaƟon of high-priority concerns, such as: o Complex uƟlity relocaƟons. o Maintaining business access during key operaƟonal hours. o Handling peak traffic volumes without causing significant delays. o PotenƟal risks or conflicts that need immediate resoluƟon. DocumentaƟon and ReporƟng  Process for maintaining and sharing daily logs, progress reports, and photographic records.  Protocol for documenƟng and addressing RFIs, change orders, and claims.  Recordkeeping requirements, including as-built drawings and field diaries. Next Steps  Assign acƟon items and responsible parƟes for unresolved issues.  Schedule follow-up meeƟngs or inspecƟons as needed.  Confirm key milestones and dates for project progression. D. INITIAL DOCUMENTATION SETUP AŌer compleƟng a field walk and determining key project milestones for this project from Kick-off meeƟng with City, the following iniƟal documentaƟon setup items will be created to ensure efficient project management and compliance. Seƫng up these documents and systems will provide a strong foundaƟon for successful project execuƟon, minimizing risks and ensuring clear communicaƟon with all stakeholders: Page | 13 Project Management DocumentaƟon  Project Charter or Scope Statement: Summarize the project’s objecƟves, scope, key milestones, stakeholders, and constraints.  Work Breakdown Structure (WBS): Outline tasks, responsibiliƟes, and Ɵmelines to organize the project.  Roles and ResponsibiliƟes Matrix: Define roles for the project team, contractors, inspectors, and stakeholders.  CommunicaƟon Plan: Establish protocols for communicaƟon between the project team, businesses, and public stakeholders.  Include key contact lists for city staff, contractors, business owners, and emergency responders. Scheduling and Planning Documents  Project Schedule: Include major milestones, phases, deadlines, and dependencies.  Milestone Chart: A high-level summary of key dates and deliverables.  Look-Ahead Schedules: Prepare for 2-week or monthly planning to provide short-term progress updates. Traffic and Public Access DocumentaƟon  Traffic Control Plan (TCP): Document Road closures, detours, and alternaƟve routes, ensuring access to businesses and emergency vehicles.  Business Access Plan: Detail measures to maintain customer access to businesses during construcƟon, including signage, temporary driveways, and communicaƟon.  Pedestrian Access Plan: Ensure safe and ADA- compliant pedestrian pathways. Environmental and Regulatory Compliance  Stormwater PolluƟon PrevenƟon Plan (SWPPP): Ensure measures for erosion and sediment control.  Dust Control Plan: Include procedures for miƟgaƟng dust during construcƟon.  Noise MiƟgaƟon Plan: Document strategies for minimizing noise impacts, especially during business hours.  Permits Log: Maintain a record of all required permits (e.g., encroachment permits, environmental approvals). Recordkeeping and Field DocumentaƟon  Daily and Weekly Report Templates: Create forms for recording work acƟviƟes, weather condiƟons, and inspecƟons.  Field Diary Setup: Prepare bound workbooks or digital plaƞorms for tracking construcƟon progress, issues, and changes.  Photo DocumentaƟon Protocol: Define methods for taking and archiving photographs, including pre-construcƟon condiƟons and ongoing progress.  RFI and SubmiƩal Logs: Create systems to track and manage contractor Requests for InformaƟon (RFIs), submiƩals, and responses. Page | 14 Stakeholder CommunicaƟon Materials  Public NoƟficaƟon LeƩers: Prepare templates for noƟfying businesses and residents of construcƟon impacts.  Signage Plan: Document plans for project signage, such as “Business Open” and detour signs, along with placement details.  Project Webpage Content: DraŌ iniƟal content for the city’s project webpage, including hotline numbers, FAQs, maps, and schedules.  ConstrucƟon Hotline and Email Protocols: Establish procedures for maintaining and responding to public inquiries within defined Ɵmelines. Contract and Budget Management  Contract DocumentaƟon: Ensure copies of contracts, specificaƟons, and addenda are available and organized.  Change Order Log: Create a tracking system for managing change orders and approvals.  Cost Tracking Spreadsheet: Establish a budget tracking tool for monitoring expenditures against the project budget. InspecƟon and Quality Assurance  InspecƟon Checklists: Develop standard checklists for tracking compliance with ADA, SWPPP, and contract specificaƟons.  Quality Control/Quality Assurance Plan: Document procedures for ensuring all work meets design and material standards. Risk Management  Risk Register: IdenƟfy potenƟal risks (e.g., traffic delays, business disrupƟons) and miƟgaƟon strategies.  ConƟngency Plans: Document alternaƟve plans for unforeseen issues, such as uƟlity conflicts or extreme weather events. CoordinaƟon and MeeƟng Setup  Kickoff MeeƟng Agenda: Prepare an agenda to discuss field walk findings, milestones, and stakeholder concerns.  Stakeholder CoordinaƟon Calendar: Schedule regular progress meeƟngs with city staff, contractors, businesses, and uƟlity companies.  Create an organized system to maintain contracts, plans, RFIs, change orders, shop drawings, and other relevant documents for easy access and review. PHASE 2 CONSTRUCTION MANAGEMENT IMPLEMENTATION A structured implementaƟon plan is essenƟal to facilitate clear communicaƟon and coordinaƟon among the design engineer, survey team, and construcƟon contractor. The following plan outlines roles, responsibiliƟes, and communicaƟon protocols to ensure alignment at every stage of the project. Page | 15 Pre-ConstrucƟon MeeƟng  AƩendees: City staff, ConstrucƟon Manager, CM- Project Engineer, CM- Project Inspector, Design Engineer, Survey Team, Outreach Co-Ordinator, ConstrucƟon Contractor Project Manager, Site Supervisor, and any key subcontractors.  ObjecƟve: Establish iniƟal communicaƟon channels, review design intent, understand site- specific challenges, and clarify roles and responsibiliƟes.  Agenda: o Review project goals, Ɵmelines, and milestones. o Clarify the scope of work for each party. o Discuss criƟcal project control points, benchmarks, and any preliminary survey data. o Set expectaƟons for deliverables, inspecƟon schedules, and change order procedures. o Determine points of contact and preferred communicaƟon methods (e.g., weekly meeƟngs, email updates, digital project management tools). Pre-Survey CoordinaƟon MeeƟng  AƩendees: ConstrucƟon Manager, CM-Project Engineer, CM-Project Inspector, Survey Team, Design Engineer, and ConstrucƟon Contractor’s Site Supervisor.  ObjecƟve: Finalize survey requirements, review design plans, and confirm control points before site work begins.  Agenda: o Confirm control points, benchmarks, and verƟcal/horizontal reference data. o Review the site layout, grading requirements, and uƟlity alignment. o Discuss any potenƟal discrepancies in design plans or specificaƟons. o Address site access, safety protocols, and staging areas for the survey team. o Deliverables: Survey team confirms control points and submits an iniƟal site layout plan for contractor verificaƟon. Weekly CoordinaƟon MeeƟngs  AƩendees: ConstrucƟon Manager, CM-Project Engineer, Outreach Co-Ordinator, ConstrucƟon Contractor (Project Manager/Site Supervisor), Survey Team Lead, and Design Engineer (as needed).  ObjecƟve: Review weekly progress, address immediate needs, and discuss any design adjustments, layout modificaƟons, or survey updates.  Agenda: o Review the current week’s progress and work plan. o Address layout needs or addiƟonal survey requests from the construcƟon team. Page | 16 o Discuss any changes in construcƟon sequences or issues impacƟng layout. o Share updates on any design modificaƟons or clarificaƟons needed. o Deliverables: MeeƟng minutes documenƟng key decisions, pending issues, and survey requests for the following week. Milestone Review MeeƟngs  Timing: Scheduled at key project milestones (e.g., pulverizaƟon, grind and overlay, grading, uƟliƟes, signing and striping).  AƩendees: ConstrucƟon Manager, CM-Project Engineer, Outreach Co-Ordinator, Design Engineer, Survey Team, ConstrucƟon Contractor, and City/Third-Party Inspectors (if applicable).  ObjecƟve: Verify that milestone work is in line with design specificaƟons, confirm layout accuracy, and ensure as-built data collecƟon.  Agenda: o Survey team presents verificaƟon of completed layouts (e.g., foundaƟon, structural grids). o ConstrucƟon contractors provide updates on compleƟon of specific work elements. o Review and address any discrepancies or adjustments required. o Deliverables: VerificaƟon reports, milestone sign-offs, and any correcƟve acƟons or adjustments documented. Daily Field Check-Ins  Timing: Daily or as needed when criƟcal layout work is in progress.  AƩendees: CM-Project Engineer, CM-Project Inspector, Survey Team and ConstrucƟon Contractor’s Site Supervisor.  ObjecƟve: Ensure ongoing layout tasks meet design specificaƟons and quickly resolve layout issues.  Agenda: o Survey team performs field verificaƟon of criƟcal layout tasks. o Contractor provides feedback on layout and alignment needs. o Address immediate issues, such as any discrepancies or adjustments due to field condiƟons. o Deliverables: Daily field notes documenƟng any deviaƟons or adjustments made. Design Change and RFI (Request for InformaƟon) Protocol  ObjecƟve: Establish a streamlined process to address design changes and resolve layout issues in real Ɵme.  Protocol: o RFI Submission: ConstrucƟon Contractor submits RFIs to the Design Engineer for any layout conflicts or clarificaƟon needed. Page | 17 o Response Time: Design Engineer provides Ɵmely responses, typically within 24-48 hours, to avoid delays. o DocumentaƟon: All changes or clarificaƟons are documented and shared with the Survey Team to adjust layout data as necessary. o Deliverables: RFI log maintained with resoluƟons, and updated drawings if design changes are approved. Monthly Progress and Risk Review  AƩendees: ConstrucƟon Manager, CM-Project Engineer, Outreach Co-Ordinator, ConstrucƟon Contractor, Design Engineer, and Survey Team.  ObjecƟve: Review cumulaƟve project progress, address unresolved issues, and assess potenƟal risks to the schedule or budget.  Agenda: o Review cumulaƟve progress against the project schedule. o IdenƟfy any recurring layout issues or discrepancies. o Assess risks related to layout or design that could impact future work. o Deliverables: Monthly progress report with acƟon items and risk miƟgaƟon plans. CommunicaƟon Protocols  Regular Email Updates: Weekly or biweekly email updates summarizing meeƟng outcomes, acƟon items, and schedule changes.  Document Control: Centralized access for up-to- date plans, specificaƟons, and approved changes to ensure that all parƟes work from the latest documents.  Emergency Contacts: Provide a list of emergency contacts to quickly resolve any criƟcal layout or design issues that arise on-site. PHASE 3 COMPLIANCE MONITORING AND MEASURMENT Goal: To monitor and measure tracking, documenƟng, and reporƟng on the project’s progress to ensure it stays on schedule, within budget, and meets quality standards. AddiƟonally, to implement an effecƟve progress monitoring and measurement program that ensures projects are completed on Ɵme, within budget, and to the desired quality standards. This structured approach helps miƟgate risks, improve decision- making, and enhance stakeholder communicaƟon throughout the project’s lifecycle Define Program ObjecƟves and Metrics  Set Clear ObjecƟves: Establish the main goals of the program, such as tracking the project’s progress, idenƟfying potenƟal delays, ensuring quality, and maintaining budget compliance.  IdenƟfy Key Performance Indicators (KPIs): Determine the specific metrics that will be used to assess progress, such as:  Schedule adherence (milestone compleƟon dates)  Work completed vs. work planned  Cost performance (actual costs vs. budgeted costs) Page | 18  Quality of work  Resource uƟlizaƟon  Establish a Baseline: Ensure a clear project baseline is set for schedule, cost, and scope before monitoring begins. Develop a Monitoring and Measurement Plan  Create a Monitoring Framework: Develop a detailed plan for monitoring the construcƟon progress, including how and when progress will be tracked, who will track it, and how data will be reported.  Establish ReporƟng Requirements: Define the format, frequency, and recipients for progress reports. Determine if daily, weekly, or monthly reporƟng is necessary.  Assign ResponsibiliƟes: Designate personnel to track and measure progress, including project managers, site supervisors, and inspectors. Implement a Regular Data CollecƟon Process  Track Work Progress: Regularly update the progress of the work, including: o Percentage of work completed on various tasks o Milestone achievements o Completed deliverables  Update the Schedule: Ensure the project schedule is updated to reflect actual work completed, including rescheduling any delayed or completed tasks.  Monitor Material and Resource Usage: Track the delivery and usage of materials, labor, and equipment to ensure they align with the planned schedule and budget.  Site InspecƟons: Conduct regular site inspecƟons to validate progress against plans and ensure quality standards are being met. Measure Cost Performance  Track Actual Costs: Record and compare actual costs against the project budget, including labor, materials, and overheads.  Use Earned Value Management (EVM): Apply EVM to assess: o Planned Value (PV): What was planned to be spent at a given Ɵme. o Earned Value (EV): What has actually been earned (based on completed work). o Actual Cost (AC): What has been actually spent. o Cost Variance (CV) and Cost Performance Index (CPI) to evaluate financial performance.  IdenƟfy Variance and Forecast Future Costs: Compare the project’s financial status to the baseline, idenƟfy cost overruns or savings, and forecast future spending to avoid budget issues. Track Schedule Performance  Monitor Task CompleƟon: Regularly update the schedule to track completed tasks and milestones. Page | 19  Use the CriƟcal Path Method (CPM): IdenƟfy the criƟcal path and ensure that any delays in criƟcal tasks are quickly addressed to avoid affecƟng the project compleƟon date.  Track Delays and MiƟgate Risks: Log any delays or setbacks, idenƟfy their causes, and implement correcƟve acƟons to keep the project on track.  Analyze Float Time: Regularly analyze float (slack) Ɵme to assess flexibility in the schedule and proacƟvely address potenƟal delays. Quality Control and Assurance Monitoring  Conduct Regular Quality InspecƟons: Implement regular inspecƟons of completed work to ensure compliance with the quality standards outlined in the project specificaƟons.  Track Non-Conformance: Maintain a log of any quality issues, non-conformance reports (NCRs), or deficiencies, and ensure correcƟve acƟons are promptly taken.  Document Issues and ResoluƟons: Track issues in a centralized database and monitor their resoluƟon to ensure quality assurance throughout the project.  Measure Rework and Waste: Measure any instances of rework or material waste as a result of poor quality and idenƟfy strategies to reduce them. Conduct Stakeholder MeeƟngs and Updates  Regular Progress MeeƟngs: Organize weekly or bi- weekly meeƟngs with the project team, contractors, and stakeholders to review progress, challenges, and upcoming tasks.  Distribute Progress Reports: Provide stakeholders with regular, detailed progress reports highlighƟng the current status of schedule, budget, and quality metrics, including any risks or issues that require aƩenƟon.  Review Milestones and Adjust Plans: At regular intervals, review project milestones, adjust schedules if necessary, and ensure resources are allocated efficiently. Track Change Orders and VariaƟons  Document Change Requests: Ensure that any changes to the scope of work, schedule, or cost are properly documented and approved via change orders or variaƟons.  Assess Impact: Evaluate how changes affect the project’s Ɵmeline, budget, and resource allocaƟon.  Update Schedules and Budgets: Ensure that the project schedule and budget are updated to reflect any approved changes, and communicate the impact of changes to all relevant stakeholders. IdenƟfy and MiƟgate Risks  Risk Monitoring: ConƟnuously monitor risks idenƟfied during project planning and look for new risks as the project progresses.  Update Risk Register: Regularly update the project’s risk register to reflect new, emerging, or miƟgated risks.  Implement MiƟgaƟon Plans: Ensure that miƟgaƟon acƟons are being executed for high- Page | 20 priority risks, such as those related to delays, cost overruns, or safety. Conduct Regular Performance Reviews  Review Progress Against the Baseline: Periodically compare the actual performance (schedule, budget, quality) against the iniƟal project baseline to assess project health.  Adjust Plans if Necessary: If progress is behind or costs are over budget, adjust strategies, resources, or Ɵmelines to get the project back on track.  Assess Subcontractor Performance: Monitor subcontractor progress to ensure they meet their contractual obligaƟons, including work quality, schedule, and safety compliance. Evaluate and Report on Project Trends  Track Trends Over Time: Use historical data to idenƟfy performance trends, such as recurring issues, delays, or cost overruns.  Analyze Root Causes of Variances: InvesƟgate paƩerns of poor performance and idenƟfy root causes (e.g., resource shortages, scheduling issues, or inefficiencies).  Forecast Future Performance: Use trend analysis to predict future project performance and address any potenƟal issues before they impact the project. Final Review and Closeout  Conduct a Final Progress Review: As the project nears compleƟon, assess the final state of the schedule, cost, and quality to ensure all project goals have been met.  Ensure CompleƟon of Punch List Items: Track and manage any remaining work or deficiencies (punch list) to ensure final quality standards are achieved.  Provide a Final Progress Report: Summarize the project’s progress, noƟng any key deviaƟons, lessons learned, and the final status of the schedule and budget. PHASE 4 -DOCUMENTATION & REPORTING Qvadrant will provide Daily, Weekly and Monthly ReporƟng to summarize work performed, condiƟons, statement of working days and criƟcal conversaƟons. We will maintain an up-to-date repository of all project- related documentaƟon, including marked-up plans, RFIs, change orders, and test results and assist in claims management by tracking and documenƟng potenƟal claims and assist the city in resolving disputes with contractors. PHASE 5 -CLOSEOUT Qvadrant will partner with the City and all stakeholders in Final InspecƟon & Punch List by conducƟng and documenƟng final walkthroughs, ensuring all issues on the punch list are addressed. We will confirm the operability of systems like lighƟng, signals, and irrigaƟon. Also, we will manage Final Payments & CerƟficaƟons including verifying lien releases, guarantees, and as-built drawings before recommending release of retenƟon or final payments Page | 21 and calculate final payments and assist with the preparaƟon of federal aid compleƟon reports. Finally, we will coordinate the handover of the completed project to the City’s maintenance teams, ensuring all documentaƟon and training materials are provided. 3.2 INSPECTIONS SERVICES Goal: To ensure that all work meets quality standards, complies with regulaƟons, and adheres to project specificaƟons. AddiƟonally, ensure that all construcƟon acƟviƟes align with quality, safety, and compliance standards by providing thorough oversight, improve project outcomes, and maintain a high standard of workmanship throughout each phase of construcƟon. Develop an InspecƟon Plan  Outline InspecƟon Requirements: IdenƟfy all required inspecƟons, including those for safety, quality, environmental compliance, and regulatory standards.  Define InspecƟon Types and Frequency: Specify when inspecƟons will occur (e.g., daily, weekly, at each milestone) and types of inspecƟons (e.g., roadway, civil and electrical).  Establish InspecƟon Standards: Use relevant codes, standards, and project specificaƟons to define acceptable quality criteria for each inspecƟon. Assign Qualified Inspectors  IdenƟfy and Appoint Qualified Personnel: Select inspectors with the appropriate experience and cerƟficaƟons relevant to the project (e.g., roadway inspectors, civil inspectors, or quality assurance specialists).  Provide Training on InspecƟon Protocols: Train inspectors on the project’s specific inspecƟon requirements, documentaƟon standards, and safety protocols.  Ensure Third-Party CerƟficaƟon as Needed: For specialized inspecƟons, ensure third-party inspectors are cerƟfied and meet industry standards. Establish InspecƟon Procedures and Protocols  Standardize InspecƟon Checklists: Develop checklists to guide each inspecƟon, covering key aspects of quality, safety, and compliance.  Implement DocumentaƟon Protocols: Create a system for logging inspecƟon results, non- compliance issues, and correcƟve acƟons, including digital forms or soŌware.  Establish a ReporƟng Process: Define how and when inspectors report their findings, including both scheduled and unscheduled inspecƟons. Conduct Pre-ConstrucƟon InspecƟons  Verify IniƟal Site CondiƟons: Inspect site setup, access, and safety measures to ensure the project can start safely and efficiently.  Inspect and Approve IniƟal Materials: Review and approve construcƟon materials before they are used to ensure they meet specificaƟons. Page | 22  Document Baseline CondiƟons: Record the iniƟal condiƟon of structures, site features, and materials as a reference for ongoing inspecƟons. Schedule Regular and Milestone InspecƟons  Plan InspecƟons at Key Milestones: Conduct inspecƟons at criƟcal stages, such as foundaƟon, structural framing, electrical, plumbing, and final compleƟon.  Conduct Daily or Weekly InspecƟons: Perform rouƟne inspecƟons to monitor ongoing work, idenƟfy issues early, and ensure adherence to standards.  Adjust Frequency Based on Risk: Increase inspecƟon frequency in high-risk areas or aŌer issues are idenƟfied, as necessary. Inspect Work in Progress and Verify Compliance  Monitor Contractor Work Quality: Conduct inspecƟons to verify that the contractor’s work meets design specificaƟons and quality standards.  Check Compliance with Codes and Standards: Inspect for adherence to local building codes, safety standards, environmental regulaƟons, and project-specific requirements.  Ensure CorrecƟve AcƟons Are Taken Promptly: When issues arise, require the contractor to correct them immediately and reinspect as needed. Document Findings and Track Non-Compliance Issues  Maintain Detailed InspecƟon Records: Document each inspecƟon with records, photos, and checklists, ensuring all findings and correcƟve acƟons are logged.  Track Non-Compliance Issues: Record issues in a tracking system, categorize them by severity, and follow up to ensure they are resolved.  Establish a CorrecƟve AcƟon Log: Keep a log of correcƟve acƟons taken, tracking compleƟon and verifying compliance through follow-up inspecƟons. Implement a Quality Assurance Review Process  Conduct Quality Assurance (QA) Audits: Periodically audit inspecƟon processes and results to ensure consistency, accuracy, and compliance with quality standards.  Verify Inspector Performance: Review the performance of inspectors to ensure they are thorough, accurate, and unbiased in their assessments.  Update Procedures Based on QA Findings: Adjust inspecƟon procedures as needed based on QA audit results and lessons learned. Engage in Regular CommunicaƟon and Feedback with Contractors  Hold Weekly CoordinaƟon MeeƟngs: Meet with contractors to review inspecƟon findings, discuss issues, and plan correcƟve acƟons as needed.  Provide Feedback on Performance: Offer construcƟve feedback to contractors on workmanship quality, safety pracƟces, and adherence to standards. Page | 23  Establish an Issue EscalaƟon Process: Define a process for escalaƟng unresolved issues to higher management or third-party evaluators if necessary. Verify Compliance with Safety and Environmental Standards  Conduct Safety InspecƟons and Audits: Regularly inspect the site for compliance with OSHA and other safety regulaƟons, focusing on high-risk acƟviƟes.  Monitor Environmental Compliance: Ensure inspecƟons include environmental compliance checks, such as waste disposal, erosion control, and air quality.  Require Immediate CorrecƟon of Safety and Environmental ViolaƟons: Address any safety or environmental concerns immediately to prevent risk escalaƟon. Review and Approve Final InspecƟons  Conduct a Comprehensive Final InspecƟon: Before project closeout, inspect all aspects of the work to verify that the project meets all specificaƟons and standards.  Document CompleƟon and Compliance: Ensure that final inspecƟon records are complete, showing that the project meets all regulatory and quality standards.  Approve Work for Final Payment: Only authorize final payments once all inspecƟons have confirmed compliance with project requirements. Facilitate Project Closeout and Handover  Complete Punch List InspecƟons: Finalize all outstanding items, ensuring all minor fixes are completed and approved before handover.  Ensure As-Built DocumentaƟon is Accurate: Verify that all changes made during construcƟon are accurately reflected in the as-built documentaƟon.  Coordinate with Client for Handover: Meet with the client to review inspecƟon findings, provide final reports, and answer any quesƟons before project closeout. Page | 24 3.3 QUALITY CONTROL PLAN Qvadrant will develop and implement a Quality Control Plan (QCP) that includes structured, actionable steps to ensure all work meets professional standards and contractual requirements. These steps ensure that the QCP is both proactive and robust, fostering high-quality outcomes and compliance throughout the contract term. Below is a breakdown of key steps for our QCP: Establish Quality Control Roles and Responsibilities  The Construction Manager will oversee the implementation and enforcement of the QCP.  Identify roles for independent reviewers, back-checkers, and coordinators.  Conduct training sessions on quality control processes, documentation standards, and regulatory requirements. Develop Documentation and Review Procedures  Create templates and checklists for calculations, drawings, and related documents.  We will Implement Independent Reviews that require an independent qualified reviewer to check, correct, and back-check all work.  We will track reviews and corrections to ensure all design elements (e.g., plans, specifications) are aligned and free from conflicts. Perform Continuous Coordination and Validation  Schedule routine reviews to identify and resolve conflicts between drawings, specifications, and other documents.  Confirm that all design and construction meet contractual, regulatory, and engineering standards. Maintain and Archive Documentation  Store all original drawings, calculations, and related documents in an organized, secure system.  Maintain detailed logs of changes, reviews, and corrections throughout the project lifecycle.  Make records available for periodic audits or inspections by the city. Page | 25 4.0 LIST OF COMPLEMENTARY SERVICES INTEGRATED TEAM MORALE Goal: To build and maintain an integrated team morale to ensure smooth project execuƟon, collaboraƟon, and producƟvity. AddiƟonally, build a cohesive, moƟvated, and resilient team by emphasizing clear communicaƟon, respect, recogniƟon, and ongoing development. Establish Clear CommunicaƟon Channels  Set Up CommunicaƟon Plaƞorms: Use centralized communicaƟon tools (e.g., project management soŌware, messaging apps) to keep all team members informed and connected.  Hold Regular MeeƟngs: Schedule regular team meeƟngs to review project goals, progress, challenges, and feedback, ensuring everyone stays aligned.  Encourage Open Dialogue: Foster an environment where team members feel comfortable sharing ideas, raising concerns, and giving feedback. Define Roles, ResponsibiliƟes, and Goals  Clarify Roles and ResponsibiliƟes: Clearly outline each team member’s role, ensuring everyone understands their duƟes and expectaƟons.  Set CollaboraƟve Project Goals: Define project milestones and objecƟves collaboraƟvely, so each team member feels involved in the overall mission.  Align Individual Goals with Team ObjecƟves: Connect each team member’s tasks to the broader goals, reinforcing the value of their contribuƟon. Foster a Culture of Respect and Inclusivity  Encourage Respect and Inclusivity: Promote respect for diverse ideas, backgrounds, and experiences, creaƟng a posiƟve environment for all team members.  Celebrate Diversity: Organize events or team-building acƟviƟes that celebrate different cultures and backgrounds to enhance team understanding and cohesion.  PracƟce AcƟve Listening: Ensure all voices are heard by acƟvely listening to ideas and concerns, validaƟng each team member’s input. Page | 26 Provide OpportuniƟes for Team Building  Organize Team-Building AcƟviƟes: Plan regular team-building events (e.g., site-based ac ƟviƟes, workshops, ouƟngs) to build rapport and strengthen relaƟonships.  Promote Informal Team InteracƟons: Encourage break Ɵmes or group lunches where team members can connect informally and build friendships.  Hold Project Milestone CelebraƟons: Celebrate achievements at key milestones to recognize team effort and maintain a posiƟve atmosphere. Recognize and Reward Efforts  Acknowledge Individual ContribuƟons: Regularly recognize and reward team members for their hard work, whether through verbal praise, small incenƟves, or public acknowledgments.  Celebrate Team Successes: Highlight team achievements to reinforce the value of working together and recognize collecƟve accomplishments.  Provide Feedback and RecogniƟon: Give Ɵmely feedback and express appreciaƟon for both small wins and major contribuƟons. Encourage ConƟnuous Learning and Professional Development  Offer Training and Development Programs: Provide opportuniƟes for team members to enhance their skills through workshops, cerƟficaƟons, or on-site training.  Promote Knowledge Sharing: Encourage team members to share knowledge, best prac Ɵces, and insights from their own experiences.  Support Mentorship Programs: Pair junior team members with experienced professionals to foster growth, build relaƟonships, and promote knowledge transfer. Empower Team Members with Autonomy  Delegate Responsibility: Give team members ownership of specific tasks or components of the project to promote accountability and boost confidence.  Encourage IniƟaƟve: Support team members in taking the iniƟaƟve, allowing them to propose and implement soluƟons within their areas of experƟse.  Allow Flexibility in Problem-Solving: Trust team members to approach problems creaƟvely, giving them freedom to develop effecƟve soluƟons. Page | 27 Resolve Conflicts and Address Issues Promptly  Establish a Conflict ResoluƟon Process: Develop a clear, fair process for addressing conflicts, ensuring team members feel their issues are taken seriously.  Mediate Conflicts Quickly: Address disputes or concerns promptly and diplomaƟcally to prevent escalaƟon and maintain posiƟve relaƟonships.  Encourage Empathy and Understanding: Help team members approach conflicts with empathy, aiming for soluƟons that benefit both the individuals and the team. Solicit Feedback and Make Improvements  Conduct Regular Team Morale Surveys: Use surveys or informal check-ins to assess morale and idenƟfy areas for improvement.  Hold One-on-One MeeƟngs: Give team members the opportunity to discuss any concerns, ideas, or feedback with management in private meeƟngs.  Act on Feedback: Take acƟon on feedback, demonstraƟng that team members’ input is valued and that management is commiƩed to a posiƟve work environment. 5.0 DISCLOSURES There are no alleged significant prior or ongoing agreement failures, any civil or criminal liƟgaƟon or invesƟgaƟon pending, which involved Qvadrant or in which Qvadrant has been judged guilty or liable within the last five (5) years. 6.0 ACKNOWLEDGEMENT OF INSURANCE REQUIREMENTS If selected, Qvadrant will provide the minimum insurance coverage and indemnificaƟon noted in Exhibits E and F, respecƟvely, of the City’s Agreement for Contract Services. See AƩached. 7.0 NON-COLLUSION AFFIDAVIT SEE ATTACHED 8.0 ACKNOWLEDGEMENT OF ADDENDA SEE ATTACHED Page | 28 Page | 29 Page | 30 Page | 31 APPENDIX A Page | 32 Page | 33 Page | 34 Page | 35 Page | 36 Page | 37 Page | 38 Page | 39 Page | 40 Page | 41 Page | 42 Page | 43 Page | 44 Page | 45 Page | 46 APPENDIX B Page | 47 Page | 48 Page | 49 Page | 50 Page | 51 Page | 52 Page | 53 Page | 54