2022 Urban Habitat - Change Order 2 - X-Park Lands & Irrigation Project 2016-03G4 aide
CAL IFORNIA
Sheet 1 of 3
CONTRACT: X-Park Landscaping and Irrigation Improvements
PROJECT NO. 2016-03G
CONTRACTOR: Urban Habitat
PO Box 1177
La Quinta, CA 92247
CONTRACT CHANGE ORDER NO. 2
**********************************************************************
Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the herein described
changes or do the following described work not included in the plans and specifications for this Contract. Unless
otherwise stated all work shall conform to the terms, general conditions, and special provisions of the original
Contract.
**********************************************************************
DESCRIPTION OF CHANGE
This Contract Change Order allows for preparation of pedestrian gate for panic bar
Total $1,326.94
**********************************************************************
Original Contract Amount
$ 529,819.52
Change Order No. 1
$ 4,361.27
Add This Change Order No. 2
$ 1,326.94
Revised Contract Total
$ 535,507.73
By reason of this contract
change order the time of
completion is adjusted as follows: - 0 - days added to contract time.
The contract completion date shall be: 9/26/2022
**********************************************************************
Digitally signed by Carley Escarrega
Digitally signed L rssa GrueM DN: cn=Carley Escarrega. o=City or La
Gnu g y g y ° Carley Escarrega 9/26/2022
canna Date: zozz.os.zs t z:z7:4s -07 00 email=cescarrega@lagulnraca goy, c=us
Submitted By: Date: 2042.0926„ ns z Date:
Approved By:
Digitally signed by Bryan McKinney
DN: cn=Bryan McKinney, o, ou,
email=bmckinney@laquintaca.goy, c=US
Date: 9/26/22
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this
proposal is approved, that we will provide all equipment, furnish all materials, perform all labor, except as may be noted
above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the
amount shown above, which includes all direct and indirect overhead expenses for any delays.
Digitally signed by Brett Brennan
Brett Brennan Date: 2022.09.22 15:50:14
Accepted By:-07r00r President
Title:
Urban Habitat
Contractor: Date: 9/22/22
78495 Cally Tampico I La Quirlta, California 92253 I T61).1117000 I www.laquintaca.gov
URBAN
Change Order Request * 0 HABITAT
LANDSCAPE CONTRACTORS
PROJECT: X Park Project
TO CONTRACTOR: City of La Quinta
CHANGE ORDER NUMBER:
DATE:
PROJECT NUMBER:
CONTRACT DATE:
3
9/21/2022
22-25
The Contract is changed as follows:
See below cost to prep the gate for the panic hardware/Von Duprin per RFI No. 03 - Pedestrian Gate and Trash Enclosure.
1) See attached subcotractor cost.
2) O&P
1) Bond
$ 1,139.00
$ 170.85
$ 17.09
Total $ 1,326.94
The original Contract Sum was
Net change by previously authorized Change orders
The Contract Sum prior to this Change order was
The Contract Sum will be amended by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be amended by
The date of Substantial Completion as of the date of this Change Order therefore is
Urban Habitat
SUBCONTRACTOR
PO Box 1177, La Quinta, CA 92247
Address
BY6�L
DATE 9/21/22
$ 529,819.52
$ 4,361.27
$ 534,180.79
$ 1,326.94
$ 535,507.73
OWNER
Address
BY
DATE
AIA Form G701
1440 BEAUMONT AVE. STE. A2 #324 BEAUMONT, CA 92223
OFFICE: (844)707-0007 FAX: (909)453 -3254
LIC # 995035 C-13
Change Order #oi REVISED PREP GATE
Project Name:
X PARK- LA QUINTA
Change Order #
01 REVISED
Owner:
CITY OF LA QUINTA
Contract Amt.
$26,680.00
Contractor:
AB Fence Company, Inc.
This Changes:
$1,139.00
New Contract Amount:
$27,819.00
Requested By:
Alberto Bedolla
Date & Time:
09/20/2022
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and
materials, and perform all work as necessary or required to complete the Change Order items for a lump sum price agreed upon
between the Contractor, and URBAN HABITAT LANDSCAPE CONTRACTOR otherwise referred to as General Contractor.
DESCRIPTION
TOTAL
Additive:
-
-
-
Prep gate for future installation of panic hardware
Install (2) 10"x3' 14ga steel plate on each side of gate (color to match existing) $600.00
Plate is needed on both sides of gate for coverage of bolts & mechanism of panic hardware & pull
handle.
Install (1) 10"x3' 14ga steel kick plate on (1) side of gate only $300.00
Weld (1) door stop 1-1/2"x2" steel flat bar $239.00
$1,139.00
TOTAL
$1,139.00
This Contract Change Order consists of 2 pages and any exhibits attached to this Contract Change Order shall not be part of the Contract Change Order unless specifically initialed by or on
behalf of both the Contractor and Horizons Construction.
The undersigned Contractor approves the foregoing Change Order #01- as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other
miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order #01-. The Contractor
agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change
Order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the
Owner. Contractor accepts the terms and conditions stated above as full and final settlement of any and all claims arising out of or related to the subject of this Change Order and acknowledges
that the compensation (time and cost) set forth herein comprises the total compensation due for the work or
Change defined in the Change Order, including all impact on any unchanged work. By signing this Change Order, the Contractor acknowledges and agrees that the stipulated compensation
includes payment for all work contained in the Change Order, plus all payment for any acceleration or interruption of schedules, extended overhead costs, delay, and all impact or cumulative
impact on all Work under this Contract. The signing of this Change Order acknowledges full mutual accord and satisfaction for the change and that the stated time and/or cost constitute the
total equitable adjustment owed the Contractor as a result of the change. The Contractor hereby releases and agrees to waive all rights, without exception or reservation of any kind whatsoever,
to file any further claim or request for equitable adjustment of any type, for any reasonably foreseeable cause that shall arise out of, or as a result of, this Change Order and/or its impact on the
remainder of the work under the Contract.