Loading...
2020 Urban Habitat Change Order 1 - Rancho Ocotillo Project 2016-03E TO: Jon McMillen, City Manager FROM: Ubaldo Ayon, Assistant Construction Manager Via: Bryan McKinney, P.E., Public Works Director/City Engineer DATE: January 13, 2021 RE: Contract Change Order No. 1 La Quinta Landscape Renovations – Ocotillo, 2016-03E Attached for your signatures is one (1) original Contract Change Order No. 1 between Urban Habitat and the City of La Quinta for the project referenced above. This Contract Change Order allows for additional 300 LF of mainline, 1120 LF of 1” gray PVC conduit, and painting and cleaning of 2 retention basin walls. Please sign and return the original to the City Clerk for final distribution. The following Budget Summary is provided: Project Budget $ 895,567 Original Contract Amount ($ 657,317) Contract Change Order No. 1 ($ 34,439) Balance Remaining $ 203,811 As indicated, adequate funding is available. REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE: _X_ Contract payments will be charged to the construction account number: 401-0000-60188-201603-CT Authority to execute this agreement is based upon: _X_ City Manager’s signature authority provided under Resolution No. 2018-014 for budgeted expenditures of $50,000 or less.