2025 Ortiz Enterprises - Project 2011-05 Dune Palms Bridge - Change Order No. 13ta Qai fra - — GEM ojtlx DESER"I — TO: Jon McMillen, City Manager FROM: Bryan McKinney, P.E., Public Works Director/City Engineer Via: Carley Escarrega, Administrative Technician DATE: April 30, 2025 RE: Contract Change Order No. 13 Dune Palms Road Bridge Project No. 2011-05 Attached for your signatures is one (1) electronic Contract Change Order No. 13 between Ortiz Enterprises, Inc. and the City of La Quinta for the project referenced above. DESCRIPTION OF CHANGE This Contract Change Order allows for additional time & materials Total $51,300.00 Please sign and return the original to the City Clerk for final distribution. REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE: X Contract payments will be charged to the construction account number: 401-0000-60188-111205-CT Authority to execute this agreement is based upon: City Manager's signature authority provided under Resolution No. 2019-021 for budgeted expenditures of $50,000 or less. _X— City Council approval on October 18, 2022 The following Budget Summary is provided: Project Budget $ 29,756,245 Contract Amount ($ 21,626,759.60) Change Order No. 1 - 12 ($ 701,239.80) This Contract Change Order No. 13 ($ 51,300.00) Balance Remaining $ 7,376,945.60 As indicated, adequate funding is available. 78-495 Calle Tampico La Quinta, CA 92253 760.777.7000 taQaiwra CALIFORNIA - Sheet 1 of 2 CONTRACT: Dune Palms Road Bridge Improvement Project PROJECT #: 2011-05 CONTRACTOR: ORTIZ ENTERPRISES, INC. 6 Cushing Suite 200 Irvine, CA 92618-4221 CONTRACT CHANGE ORDER NO. 013 Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated all work shall conform to the terms, general conditions, and special provisions of the original Contract. DESCRIPTION OF CHANGE This change order provides payment for work required by CVWD to remove the concrete encasement of their 36" water line during construction of the bottom of the NW channel slope protection and also to rewrap their pipe and slurry backfill. This change order includes removal of a portion of the CVWD access ramp that interfered with the channel slope protection. Finally, this change order provided for the sawcutting and remove of a concrete blob at the SE end of the project conflicting with the upper channel slope. This work was monitored as extra work at force account and price was based on the labor, equipment and materials used in this work. Payment shall be agreed lump sum price of $ 51,300.00 Current Contract Amount $ 22,327,999.40 Add This Change Order No. 013 $ 51,300.00 Revised Contract Total $ 22,379,299.40 By reason of this contract change order the time of completion is adjusted as follows: 11 days shall be granted for the work performed. The contract completion date is revised to: 03/17/2025 Submitted By: 20251424 PDT] W t�NNW 4/18/25 Approved By: $ MG�Js7h2It Date: S Z Z Jon McMillen, City Manager We, the undersigned Contractor, given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expe es for any delays. Accepted By: Mac Delaney Title: Project Manager arm Contractor: Ortiz Enterprises, Inc. Date: 4/18/25