2025 Ortiz Enterprises - Project 2011-05 Dune Palms Bridge - Change Order No. 15ta Qai fra - — GEM ojtlx DESER"I — TO: Jon McMillen, City Manager FROM: Bryan McKinney, P.E., Public Works Director/City Engineer Via: Carley Escarrega, Administrative Technician DATE: April 30, 2025 RE: Contract Change Order No. 15 Dune Palms Road Bridge Project No. 2011-05 Attached for your signatures is one (1) electronic Contract Change Order No. 15 between Ortiz Enterprises, Inc. and the City of La Quinta for the project referenced above. DESCRIPTION OF CHANGE This Contract Change Order allows for additional time & materials Total $15,488.41 Please sign and return the original to the City Clerk for final distribution. REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE: X Contract payments will be charged to the construction account number: 401-0000-60188-111205-CT Authority to execute this agreement is based upon: City Manager's signature authority provided under Resolution No. 2019-021 for budgeted expenditures of $50,000 or less. _X— City Council approval on October 18, 2022 The following Budget Summary is provided: Project Budget $ 29,756,245 Contract Amount ($ 21,626,759.60) Change Order No. 1 - 14 ($ 756,059.80) This Contract Change Order No. 15 ($ 15,488.41) Balance Remaining $ 7,357,937.19 As indicated, adequate funding is available. 78-495 Calle Tampico La Quinta, CA 92253 760.777.7000 taQaiwra CALIFORNIA - Sheet 1 of 2 CONTRACT: Dune Palms Road Bridge Improvement Project PROJECT M 2011-05 CONTRACTOR: ORTIZ ENTERPRISES, INC. 6 Cushing Suite 200 Irvine, CA 92618-4221 CONTRACT CHANGE ORDER NO. 015 Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated all work shall conform to the terms, general conditions, and special provisions of the original Contract. DESCRIPTION OF CHANGE This change order provides payment for work to raise sewer drop manhole No. 1 Station 5+41.90 to finish grade. Plans called out to salvage and reinstall cone, frame and cover. However, because this was a sewer drop manhole, the 8" sewer lateral from the mobile home park required extra work. The lateral slurry encasement had to be broken out, a new 8" lateral installed with couplings, a new manhole shaft and eccentric cone installed and coring into the shaft for the lateral. This work was monitored as extra work at force account and price was based on the labor, equipment and materials used in this work. Payment shall be agreed lump sum price of $ 15,488.41 Current Contract Amount $ 22,382,819.40 Add This Change Order No. 015 $ 15,488.41 Revised Contract Total $ 22,398,307.81 By reason of this contract change order the time of completion is adjusted as follows: 3 days shall be granted for the work performed. The contract completion date is revised to: 03/20/2025 Submitted By Approved By: 14:27 PDT ta Quixta 4/18/25 Jon McMillen, City Manager / We, the undersigned Contractor ave given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, perform all labor except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses for any delays. Accepted By: Mac Delaney Title: Project Manager Contractor: Ortiz Enterprises, Inc. Date: 4/18/25