2025 Granite Construction Company - Ch Ord 1 - Hwy 111 Pavement Rehab Project 2022-254c2uaa - CALIFORNIA CONTRACT: HIGHWAY 111 PAVEMENT REHABILITATION PROJECT #: 2022-25 CONTRACTOR: Granite Construction Company 3800 Monroe St Indio, CA 92203 CONTRACT CHANGE ORDER NO. 1 Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated all work shall conform to the terms, general conditions, and special provisions of the original Contract. DESCRIPTION OF CHANGE 1. SWPPP Credit- This Contract Change Order allows for the reimbursement of the cost of preparing a SWPPP which was not needed for this project. Portion of bid Item #3. TOTAL-$2,438.00 2. Additional Survey- The plans did not include an elevation grid for the intersection of Washington Street and HWY 111. This cost will provide the survey Granite requests to perform the work within the intersection of Washington Rd. and HWY 111. TOTAL $6,043.05 3. Restoration of landscaping at the new ramp on Washington and HWY 111- The plans were revised after the bid was awarded. The new ramp had a smaller footprint, so additional restoration was required in areas where landscaping was increased. This cost will provide the complete restoration of the landscaping around the ramp. TOTAL $4,094.31 Original Contract Amount $ 7,032,777.00 Add This Change Order No. 1 $7,699.36 Revised Contract Total $7,040,476.36 By reason of this contract change order the time of completion is adjusted as follows: - 2 days added to contract time. 78495 Calle Tampico I La Uinta, California 92253 1760.711.1000 I www.laquintaca.gov 401thira The revised contract completion date shall be: 10/30/2025 Submitted By: !don uI3 2025 15:13:22 PDT) Date: Approved By. a,$� ah MclC5 5: 658 or Date: We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses for any delays. Accepted B ", �4 % p Y Contractor: ‘otepai ` ' &'" s Date: 7 J Ay es" Title: efv,.r f -z 18495 Calle Tampico Ica Uinta, Cantorma 92253 1169 in IN) I www.anuotaca.go, GRAflITE Change Order Request-2 Project: Highway 111 Resurfacing Project Project No: 2022-25 Federal Project No. HIPL-5433(021) Granite Job No: 1643605 1- SWPPP Credit 7/8/2025 1 LS $ (2,438.00) This credit represents the value of the work associated with SWPPP preparation that will no longer be performed by the Contractor due to a change in project requirements initiated by the Owner. The Contractor remains responsible for on -site project -specific Best Management Practices (BMPs) implementation and maintenance per Section 3-12.6 of the Standard Specifications and the City of La Quinta requirements. GRANITE CONSTRUCTION COMPANY PROJECT NAME: Highway 111 Resurfacing Project Project No: 2022-25 Federal Project No. HIPL 5433(021) Contract No. GCCO PROJECT NO: DESCRIPTION OF WORK: DATE PERFORMED: REPORT NO: Storm Water Pollution Control Plan- Credit TBD TBD Granite Job No: 1643605 LABOR REGULAR HOURS OVERTIME EQUIPMENT NO. CLASS MAKE CODE HRS RATE TOTAL NAME EA SUBSISTENCE HRS RATE TOTAL HRS RATE TOTAL $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - TOTAL SUBS. $ - TOTAL REG TIME $ - TOTAL O.T. $ - LABOR DOUBLE HOURS NAME CRAFT ID HRS RATE TOTAL SUBTOTAL $ - TOTAL DBL TIME $ - MARKUP@5% $ EQUIPMENT TOTAL $ MATERIALS/RENTAL EQUIPMENT DESCRIPTION QTY UNITS COST TOTAL Zila Stormwater Management SWPP 1 LS $ (2,120.00) $ (2,120.00) $ - $ - $ - $ - $ - $ - MATERIAL SUBTOTAL $ (2,120.00) MATERIAL/RENTAL EQUIPMENT MARKUP @25% $ (318.00) TOTAL MATERIAL $ (2,438.00) DESCRIPTION SUBCONTRACTOR QTY UNITS COST TOTAL HR $ HR $ - SUBCONTRACTOR SUBTOTAL $ SUBCONTRACTOR MARKUP @ 5% $ TOTAL MATERIAL $ LABOR SUBTOTAL $ LABOR SURCHARGE @ 0 % LABOR WI SURCHARGE $ LABOR MARKUP @ 25% $ TOTAL COST OF LABOR $ TOTAL COST OF LABOR $ - TOTAL COST OF EQUIPMENT $ - TOTAL COST OF MATERIAL $ (2,438.00) TOTAL COST OF SUBCONTRACTOR $ - TOTAL THIS REPORT $ (2,438.00) ZILA Stormwater Management & Civil Engineering DIR Registration #: 1000062414 SLB/SBE Certificate #: 4166 Phone: 323.455.5012 Fax: 323.455.5013 www.zilaco.coln Main: 10880 Wilshire Blvd, Ste 1101 Los Angeles, CA 90024 North CA: 1700 Van Ness Ave San Francisco, CA 94109 SWPPP Proposal Proposal No. S039548-1 To (Client): Granite Construction - Indio (Desert Cities) Date: 3/26/2025 Project: Highway 111 Pavement Rehabilitation Project No: 2022-25, HIPL-5433(021) City of La Quinta CA-111, La Quinta, CA 92253 Task U/M Price Qty Total Initial 1 Prepare Stormwater Pollution Prevention Plan (SWPPP) by Certified QSD Including Revisions LS $1 295.00 1 $1,295.00 2 Prepare Application to Obtain NOI (Notice of Intent) and WDID / SWPPP Upload to SMARTS LS $275.00 1 $275.00 3 Prepare Application to Obtain NOT (Notice of Termination) LS $275.00 1 $275.00 4 Prepare Stormwater Annual Report in SMARTS (due Sept 1st) EA $275.00 (b) See (b) 5 Site Visit/Report Based CGP 2022 EA $950.00 See QSD on requirements (d) (d) 6 Prepare Erosion Control Plan Dust Control Plan LS 0 $0.00 or Total: TBD (a) Proposal is valid for 90 days (b) 1 NOI and 1 NOT for the whole project and 1 Annual Report per number of project years are required per CGP (c) Number of inspections depends on actual project duration and rain events (d) Mostly 2 visits are required each year (unless a condition is triggered based on CGP 2022) (e) Excludes SWPPP implementation and hard copies (f) Limitations may apply in providing visits and inspections and they may not be available at certain area/time. Please check for availability prior selecting these services. If this proposal is satisfactory please initial applicable items, sign and email to Alex Ardani (alex@zilaco.com) Authorized Client Rep: Signature: Date: For any question please contact: Alex Ardani Email: alex@zilaco.com Office: 323.455.5012 ext. 71 Direct: 323.455.5014 Fax: 323.455.5013 GRAflITE Change Order Request-1 Project: Highway 111 Resurfacing Project Project No: 2022-25 Federal Project No. HIPL-5433(021) Granite Job No: 1643605 6/30/2025 1- Intersection Survey Topo 1 LS $ 6,043.05 Survey/ Topo all intersections in the project limits The work to be performed includes providing a 3-person crew to conduct surveys and traffic control at seven intersections of varying sizes. The crew will work for approx 16 hours to capture as much topographic data as possible in order to determine existing conditions. GRANITE CONSTRUCTION COMPANY PROJECT NAME: Highway 111 Resurfacing Project Contract No. 2022-25 Federal No. HIPL-5433(021) DESCRIPTION OF WORK: DATE PERFORMED: REPORT NO: Topo Intersections TBD TBD GCCO PROJECT NO: 1643605 LABOR REGULAR HOURS OVERTIME EQUIPMENT NO. EQUIPMENT DESC. CLASS MAKE CODE HRS RATE TOTAL NAME EA SUBSISTENCE HRS RATE TOTAL HRS RATE TOTAL Pickup Truck 4 $ 52.44 $ 209.76 Grade Setter 1 16.00 $ 108.07 $ 1,729.12 $ - $ - Traffic Control Truck 4 $ 52.44 $ 209.76 Traffic Control Foreman 1 16.00 $ 88.94 $ 1,423.04 $ - $ - $ - $ - Labor 1 16.00 $ 81.02 $ 1,296.32 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - TOTAL SUBS. $ - TOTAL REG TIME $ 4,448.48 TOTAL O.T. $ - $ - $ - LABOR DOUBLE HOURS $ - $ - NAME CRAFT ID HRS RATE TOTAL $ - $ - $ - $ - $ - $ - SUBTOTAL $ 419.52 TOTAL DBL TIME $ - MARKUP @ 15% $ EQUIPMENT TOTAL $ 62.93 482.45 MATERIALS/RENTAL EQUIPMENT DESCRIPTION QTY UNITS COST TOTAL $ $ - $ - $ - $ - $ - $ - $ - $ - $ - MATERIAL SUBTOTAL $ MATERIAL/RENTAL EQUIPMENT MARKUP @ 15% $ TOTAL MATERIAL $ DESCRIPTION SUBCONTRACTOR QTY UNITS COST TOTAL $ $ SUBCONTRACTOR SUBTOTAL $ SUBCONTRACTOR MARKUP @ 5% $ TOTAL MATERIAL $ LABOR SUBTOTAL $ 4,448.48 LABOR SURCHARGE @0% $ - LABOR W/ SURCHARGE $ 4,448.48 LABOR MARKUP @ 25% $ 1,112.12 TOTAL COST OF LABOR $ 5,560.60 TOTAL COST OF LABOR $ 5,560.60 TOTAL COST OF EQUIPMENT $ 482.45 TOTAL COST OF MATERIAL $ - TOTALCOSTOFSUBCONTRACTOR $ - TOTAL THIS REPORT $ 6,043.05 GRAflITE Change Order Request-5 Project: Highway 111 Resurfacing Project Project No: 2022-25 Federal Project No. HIPL-5433(021) Granite Job No: 1643605 1- Ramp Backfill Restoration -Washington 7/8/2025 QTY Unit Unit Cost Total 2 ea $ 4,150.59 $ 8,301.18 Restore landscaping to existing per satisfaction to City at SE Washinton and HWY 111. GRANITE CONSTRUCTION COMPANY PROJECT NAME: Highway 111 Resurfacing Project Project No: 2022-25 Federal Project No. HIPL 5433(021) Contract No. GCCO PROJECT NO: DESCRIPTION OF WORK: DATE PERFORMED: REPORT NO: Restore Landscape for Ramps at Washington St TBD TBD Granite Job No: 1643605 LABOR REGULAR HOURS OVERTIME EQUIPMENT NO. CLASS MAKE CODE HRS RATE TOTAL NAME EA SUBSISTENCE HRS RATE TOTAL HRS RATE TOTAL Traffic Control truck 20-28 9 $ 57.26 $ 515.34 Tc Foreman 1 8.00 $ 88.94 $ 711.52 1.00 $ 116.340 $ 116.34 Foreman Truck 06-12 9 $ 41.96 $ 377.64 TC Laborer 1 8.00 $ 81.02 $ 648.16 1.00 $ 104.810 $ 104.81 TC Laborer 1 8.00 $ 81.02 $ 646.16 1.00 $ 104.910 $ 104.91 $ - $ - $ - $ - $ - $ - TOTAL SUBS. $ - TOTAL REG TIME $ 2,007.84 TOTAL O.T. $ 326.06 LABOR DOUBLE HOURS NAME CRAFT ID HRS RATE TOTAL SUBTOTAL $ 892.98 TOTAL DBL TIME $ - MARKUP @15% $ 133.95 EQUIPMENT TOTAL $ 1,026.93 MATERIALS/RENTAL EQUIPMENT DESCRIPTION QTY UNITS COST TOTAL Arrow Boards 1 EA $ - Traffic Control Devices 1 LS $ - $ - $ - $ - $ - $ - $ - MATERIAL SUBTOTAL $ MATERIAL/RENTAL EQUIPMENT MARKUP @15% $ TOTAL MATERIAL $ DESCRIPTION SUBCONTRACTOR QTY UNITS COST TOTAL Landscape restoration Sub Universal Concrete 2 EA $ 1,861.05 $ 3,722.10 HR $ SUBCONTRACTOR SUBTOTAL $ 3,722.10 SUBCONTRACTOR MARKUP @ 10% $ 372.21 TOTAL MATERIAL $ 4,094.31 LABOR SUBTOTAL LABOR SURCHARGE @ 9% LABOR WI SURCHARGE LABOR MARKUP @ 25% TOTAL COST OF LABOR $ 2,333.90 $ 210.05 $ 2,543.95 $ 635.99 $ 3,179.94 TOTAL COST OF LABOR $ 3,179.94 TOTAL COST OF EQUIPMENT $ 1,026.93 TOTAL COST OF MATERIAL $ - TOTAL COST OF SUBCONTRACTOR $ 4,094.31 TOTAL THIS REPORT $ 8,301.18 Replace landscape at Wahsington Street to the satisfaction of the city per existing. TO: Universal Construction And Engineering Address: 77725 Enfield Lane Ste. 210 Palm Desert, CA 92211 Project Name: Project Location: Highway 111- COR #3 Highway 111, La Quinta, CA Item # Item Description Estimated Quantity Contact: Alfonso Montes Phone: 760-200-3100 Bid Number: Bid Date: 2025-046 Unit Unit Price Total Price 1 Grade Parkway (Backfill) 2 EA $1,861.05 $3,722.10 Bid Price Subtotal: $3,722.10 Total Bid Price: $3,722.10 Notes: • Universal Construction and Engineering License #1019619 A, C-8; DIR#1000534892; DBE #44250. • Pnces on labor and material good through 08/31/2025. • General Exclusions: Traffic control (maintaining access, trench plates, signage, etc.), engineering, surveying, lay out, inspection cost, soil testing, concrete testing, utility relocation or protection, permits and bonds, sanitation facilities, concrete pump, concrete washout, night work, weekend work, contact with hazardous or toxic materials, vapor barrier, PM10 & SWPPP, slot patching, backhll, excavation, rebar, fill sand, protection of finished work following installation, replacement or repairing of work damaged by others. ACCEPTED: The above prices, specifications and conditions are satisfactory and hereby accepted. Buyer: Signature: Date of Acceptance: CONFIRMED: Your Company Name Authorized Signature: Estimator: Joanna Montes /60-397-5406 joanna@universalconstructioneng.com 7/7/2025 Page 1 of 1 7/7/25, 3:06 PM Mail - Freddy Benito - Outlook Outlook RFQ Landscape for Ramps From Bartikofsky, Jake <Jake.Bartikofsky@gcinc.com> Date Thu 7/3/2025 11:21 AM To Freddy Benito <freddy@universalconstructioneng.com>; Joanna Montes <joanna@universalconstructioneng.com>; Alfonso Montes <alfonso@universalconstructioneng.com> Cc Alfaro Castaneda, Mario <Mario.Alfaro@gcinc.com>; Salazar, Sibel <Sibel.Salazar@gcinc.com>; Joseph, Joel <Joel.Joseph@gcinc.com> 2 attachments (3 MB) Universal Concrete.pdf; Ramp Washington.jpg; Can Universal please furnish a quote to replace landscape to the satisfaction of the city per existing. These were the only 2 that did not have construction note 15 directing the original quote provided by Universal. Thanks for the catch Freddy, you're the man. https://outlook.office.com/mail/inbox/id/AQQkAGM4YzkwMAItMWQyNi1jMjIkLTAwAi0wMAoAEADKI2oKnP9ERr1 vpVx94JRH?nativeVersion=1.2025.6... 1/3 7/7/25, 3:06 PM Mail - Freddy Benito - Outlook oo Tak0111* tal II I I tort / 1 / `.c/ /G/ N o O 44* Om CA -SE A N„,se DETAIL "A" 6 z • 2 CA JOIN Fx' 2 EA HWY 111 DETAIL "B" CASF A TRAFFIC SGNAL TRAFFIC SIGNA- https://outlook.office.com/mail/inbox/id/AQQkAGM4YzkwMAItMWQyNi 1jMjIkLTAwAi0wMAoAEADKI2oKnP9ERr1 vpVx94JRH?nativeVersion=1.2025.6... 2/3 7/7/25, 3:06 PM Mail - Freddy Benito - Outlook 11 Thanks, GRADE PARKWAY MAX 1:3 SLOPE TO JOIN CURB RAMP, MODIFY/ADJUST IRRIGATION AND REPLACE LANDSCAPE TO SATISFACTION OF CITY EST. 1922 GRAIlITE JAKE BARTIKOFSKY Project Manager I ® 760-296-7967 0 38000 Monroe Street, Indio, CA 92203 graniteconstruction.com https://outlook.office.com/mail/inbox/id/AQQkAGM4YzkwMAItMWQyNi 1jMjIkLTAwAi0wMAoAEADKI2oKnP9ERr1 vpVx94JRH?nativeVersion=1.2025.6... 3/3 2024-18 CCO 1 Final Audit Report 2025-07-31 Created: 2025-07-31 By: Mirta Lerma (mlerma@laquintaca.gov) Status: Signed Transaction ID: CBJCHBCAABAAvy8PC06r7KedehL2kpuIJHYIZC-1V0pD "2024-18 CCO 1" History Document created by Mirta Lerma (mlerma@laquintaca.gov) 2025-07-31 - 10:11:33 PM GMT Document emailed to uayon@laquintaca.gov for signature 2025-07-31 - 10:11:41 PM GMT Email viewed by uayon@laquintaca.gov 2025-07-31 - 10:11:51 PM GMT Signer uayon@laquintaca.gov entered name at signing as Ubaldo Ayon 2025-07-31 - 10:13:20 PM GMT Document e-signed by Ubaldo Ayon (uayon@laquintaca.gov) Signature Date: 2025-07-31 - 10:13:22 PM GMT - Time Source: server Document emailed to bmckinney@laquintaca.gov for signature 2025-07-31 - 10:13:24 PM GMT Email viewed by bmckinney@laquintaca.gov 2025-07-31 - 10:13:34 PM GMT Signer bmckinney@laquintaca.gov entered name at signing as Bryan McKinney 2025-07-31 - 10:16:56 PM GMT Document e-signed by Bryan McKinney (bmckinney@laquintaca.gov) Signature Date: 2025-07-31 - 10:16:58 PM GMT - Time Source: server Agreement completed. 2025-07-31 - 10:16:58 PM GMT 0 Adobe Acrobat Sign