2020 12 01 Measure G AppropriationCity of La Quinta CITY COUNCIL MEETING: December 1, 2020 STAFF REPORT AGENDA TITLE: APPROPRIATE MEASURE G FUNDING FOR THE SILVERROCK PARK VENUE PROJECT NO. 2016-08 AND SILVERROCK RETENTION BASIN SOIL STABILIZATION PROJECT NO. 2020-07 RECOMMENDATION Appropriate Measure G funding in the amount of $290,000 for the SilverRock Park Venue Project No. 2016-08 for additional project improvements, and $10,000 for preliminary design of the SilverRock Retention Basin Soil Stabilization Project No. 2020-07. EXECUTIVE SUMMARY •On November 4, 2020, the Financial Advisory Commission (FAC) discussed the proposed SilverRock Venue Site Project (Project) (Attachment 1) Phase II improvements and prioritization. •A SilverRock Venue Site FAC Subcommittee (Subcommittee) was formed to perform review and analysis of the Phase II priorities with staff. •The Subcommittee identified priority improvements and recommended appropriation of Measure G Funds in the total amount of $300,000. •At their November 23 special meeting, the FAC recommended appropriation for the following priority improvements: o 50 additional shade trees; o Safety fence for the outlet structure; o Conversion of irrigation from well and potable water source to canal water; and o Preliminary design for the SilverRock Retention Basin Soil Stabilization Project (Soil Stabilization Project). •If preliminary design funding is approved, a budget for the entirety of the Stabilization Project will be established once a preferred design is recommended by Staff, reviewed by the FAC, and approved by City Council. BUSINESS SESSION ITEM NO. 1 41 •The remaining proposed Phase II enhancements would be evaluated in the future. FISCAL IMPACT Measure G funding is requested in the amount of $290,000 to complete priority improvements to the SilverRock Venue Site (Attachment 2). The following table shows the projects budgeted revenue sources and proposed requested funding: Current Budget Proposed Budget Arts in Public Spaces $ 300,000 $ 300,000 Measure G Funding $ 1,866,600 $ 2,156,600 Park & Rec DIF Fund $ 2,400,000 $ 2,400,000 Quimby Funding $ 2,000,000 $ 2,000,000 Total Budget: $ 6,566,600 $ 6,856,600 Measure G funding is also requested in the amount of $10,000 to complete the preliminary design options for the Soil Stabilization Project. The remaining budget for this project will be established once a preferred design option is approved. Soil Stabilization Project Budget Preliminary Design Options $ 10,000 The following is the breakdown of costs for the requested items: Cost Convert irrigation from well and potable water source to canal water $ 239,000 Adding 50 additional trees for shade in the park $ 36,425 Safety fencing for top of outlet structure $ 14,575 Preliminary design for retention basin stabilization project $ 10,000 Total: $ 300,000 A list of additional Phase II improvements to be addressed at a future time are included in Attachment 3. BACKGROUND/ANALYSIS On November 4, 2020, the Financial Advisory Commission (FAC) recommended approval of Measure G Funding ($404,700) to complete necessary project improvements for the SilverRock Venue Site and Alongi Building Projects. The FAC also discussed the proposed SilverRock Venue Site Project Phase II improvements and prioritization. 42 During this meeting, the FAC requested the formation of an FAC SilverRock Venue Site Subcommittee (Subcommittee) to further review and provide recommendations on any future Phase II improvements and appropriation of Measure G funds. The Subcommittee included Commissioners Dick Mills, Steven Rosen and Ellen Way. The Subcommittee conducted a site visit of SilverRock Park and held two review meetings to analyze and discuss the prioritization of proposed Phase II improvements. The Subcommittee identified priority improvements and the FAC recommended appropriation of Measure G funds in the amount of $300,000 at the November 23, 2020 special meeting to complete the following improvements: •50 additional shade trees • Safety fence for outlet structure •Conversion of irrigation from well and potable water source to canal water •Preliminary design for the Soil Stabilization Project If funding is approved for the preliminary design, a budget for the entirety of the Soil Stabilization Project will be established and funding appropriation will be requested once a preferred design is recommended by Staff, reviewed by the FAC, and approved by City Council. A temporary soil stabilization polymer will be applied in the interim, while a more permanent solution is identified and designed. Funding for the cost of the temporary polymer application was included in the previously approved SilverRock Venue Site Project budget at the November 17 City Council meeting. All of the remaining proposed Phase II items are identified as non-high priority improvements and are recommended to be addressed at a future time. ALTERNATIVES Council could elect to modify the improvements funded. Prepared by: Julie Mignogna, Management Analyst Approved by: Bryan McKinney, Public Works Director Attachments: 1.Project Vicinity Map 2.Cost breakdown of recommended improvements 3.Cost breakdown for future Phase II improvements 43 44 13145 46 Convert Irrigation from well and potable water source to canal water Cost Construction 164,000$ Design:16,400$ Professional:12,710$ Insp/Test/Survey:15,990$ Utility Allowance:8,200$ Contingency:21,700$ Total Soft Costs 75,000$ TOTAL COSTS 239,000$ Adding 50 additional trees for shade in park Cost Construction 25,000$ Design:2,500$ Professional:1,938$ Insp/Test/Survey:2,438$ Utility Allowance:1,250$ Contingency:3,300$ Total Soft Costs 11,425$ TOTAL COSTS 36,425$ Safety fencing for top of outlet structure Cost Construction 10,000$ Design:1,000$ Professional:775$ Insp/Test/Survey:975$ Utility Allowance:500$ Contingency:1,325$ Total Soft Costs 4,575$ TOTAL COSTS 14,575$ Total High Priority Construction:199,000$ Total High Priority Soft Costs 91,000$ TOTAL HIGH PRIORITY COST 290,000$ HIGH PRIORITY IMPROVEMENTS - COST BREAKDOWN ATTACHMENT 2 47 Shade Structures (3x500sf) Cost Additional Restroom Cost Construction 135,000$ Construction 234,138$ Design:13,500$ Design:23,414$ Professional:10,463$ Professional:18,146$ Insp/Test/Survey:13,163$ Insp/Test/Survey:22,828$ Utility Allowance:6,750$ Utility Allowance:11,707$ Contingency:17,888$ Contingency:31,023$ Total Soft Costs 61,763$ Total Soft Costs 107,118$ TOTAL COSTS 196,763$ TOTAL COSTS 341,256$ Storage Building Cost Adding concrete curb between the parking lot and overflow parking lot Cost Construction 140,062$ Construction 17,000$ Design:14,006$ Design:1,700$ Professional:10,855$ Professional:1,318$ Insp/Test/Survey:13,656$ Insp/Test/Survey:1,658$ Utility Allowance:7,003$ Utility Allowance:850$ Contingency:18,558$ Contingency:2,253$ Total Soft Costs 64,078$ Total Soft Costs 7,778$ TOTAL COSTS 204,140$ TOTAL COSTS 24,778$ Landscaping and Irrigation of surrounding slopes Cost Replacing DG Parking Lot with Permeable Pavers Cost Construction 275,000$ Construction 1,600,000$ Design:27,500$ Design:160,000$ Professional:21,313$ Professional:124,000$ Insp/Test/Survey:26,813$ Insp/Test/Survey:156,000$ Utility Allowance:13,750$ Utility Allowance:80,000$ Contingency:36,438$ Contingency:212,000$ Total Soft Costs 125,813$ Total Soft Costs 732,000$ TOTAL COSTS 400,813$ TOTAL COSTS 2,332,000$ Mitigation measures for retention basin bottom Cost Shade Cover over Stage Cost Construction 246,700$ Construction 350,000$ Design:24,670$ Design:35,000$ Professional:19,119$ Professional:27,125$ Insp/Test/Survey:24,053$ Insp/Test/Survey:34,125$ Utility Allowance:12,335$ Utility Allowance:17,500$ Contingency:32,688$ Contingency:46,375$ Total Soft Costs 112,865$ Total Soft Costs 160,125$ TOTAL COSTS 359,565$ TOTAL COSTS 510,125$ Total Construction:2,997,900$ Total Soft Costs 1,371,539$ TOTAL COST 4,369,439$ PHASE II FUTURE IMPROVEMENTS - COST BREAKDOWN ATTACHMENT 3 48