2021 07 20 Urban Habitat Change Order 15City of La Quinta CITY COUNCIL MEETING: July 20, 2021 STAFF REPORT AGENDA TITLE: APPROVE CHANGE ORDER NO. 15 TO CONTRACT WITH URBAN HABITAT FOR THE SILVERROCK PARK VENUE PROJECT AND ACCEPT SILVERROCK PARK VENUE PROJECT NO. 2016-08 RECOMMENDATION Approve Change Order No. 15 in the amount of $145,493; accept the SilverRock Park Venue Project as complete; authorize the City Clerk to file a Notice of Completion with the Office of the County Recorder; and authorize staff to release retention in the amount of $281,878, thirty-five days after the Notice of Completion is recorded. EXECUTIVE SUMMARY •The SilverRock Park Venue project included a parking lot, approximately eight acres of walking paths, turf, landscaping and a meandering stream with lake and stage area. In addition, one restroom building, one storage building, and a 3,050 square foot building with utility hook -up. The project also included pads for future art installations. (Attachment 1) •Change Order No. 15 (Attachment 2) includes final quantity adjustments and additional costs for the initial utility delays, labor agreement delays, and building shipping delays. •The work is complete and Council acceptance will close the contract and allow final payment. FISCAL IMPACT The following is the financial accounting for Project No. 2016-08 with funding in the amount of $6,566,600 from account number 401-0000-20600 and $432,903 from the Alongi Project account number 101 -1007-71050: Original Contract Amount $ 4,218,880 Change Order No. 1 - 14 $ 1,273,188 Pending Change Order No. 15 $ 145,493 Final Contract Amount $ 5,637,561 Project Budget $ 6,999,503 CONSENT CALENDAR ITEM NO. 9 75 Final Contract Amount ($ 5,637,561) Design & Professional Costs ($ 623,935) Inspection, Survey, Plans, & Other Construction Costs ($ 737,069) Anticipated Funds Remaining* $ 938 * All costs to date have been accounted for and no further costs are anticipated . There are adequate funds to close this project; the final retention amount of $281,878 will be paid from account number 401-0000-20600. BACKGROUND/ANALYSIS On August 6, 2019, Council awarded a $4,218,880 contract to Urban Habitat. On October 8, 2019, a Notice to Proceed was issued with a 120-working day completion time starting on October 14, 2019 and ending on April 9, 2020. The project was deemed substantially complete on March 30, 2021. No liquidated damages or early completion incentives are recommended. Contract Change Order No. 1 through 14 allow for miscellaneous repairs and additions; also extending the contract completion date to April 1, 2021. Contract Change Order No. 15 will be issued for final quantity adjustments and for the initial utility delays, labor agreement delays, and building shipping delays. The additional funding budget for delay was recommended by the FAC on November 4, 2020 and approved by Council on November 17, 2020. The project construction effort is complete and in compliance with the plans and specifications. Staff recommends acceptance and release of the retention thirty-five days after the Notice of Completion is recorded. ALTERNATIVES Staff does not recommend an alternative. Prepared by: Carley Escarrega, Management Assistant Approved by: Bryan McKinney, P.E., Public Works Director/City Engineer Attachments: 1. Vicinity Map 2. Change Order No. 15 76 78 Sheet 1 of 5 CONTRACT: SilverRock Park Venue PROJECT NO. 2016-08 CONTRACTOR: Urban Habitat PO Box 1177 La Quinta, CA 92247 CONTRACT CHANGE ORDER NO. 15 Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated all work shall conform to the terms, general conditions, and special provisions of the original Contract. DESCRIPTION OF CHANGE This Contract Change Order allows for final quantity adjustments and additional costs for the initial utility delays, labor agreement delays, and building shipping delays. Total $143,493.00 By reason of this contract change order the time of completion is adjusted as follows: - 0 - days added to contract time. The contract completion date shall be: Monday, April 1, 2021. Submitted By: Date: Approved By: Date: We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree , if this proposal is approved, that we will provide all equipment, furnish all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown above, which includes all direct and indirect overhead expenses for any delays. Accepted By: Title: Contractor: Date: Previous Contract Amount Through CCO #14 $ 5,492,068.01 Add This Change Order No. 15 $ 145,493.00 Revised Contract Total $ 5,637,561.01 ATTACHMENT 2 79 80