CC Resolution 2026-002 Hampton Inn Hotel, SDP 2026-0001 (SDP 2022-0007 Ext 1)RESOLUTION NO. 2026 – 002
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
LA QUINTA, CALIFORNIA, APPROVING A FIRST TIME
EXTENSION FOR A SITE DEVELOPMENT PERMIT FOR
CONSTRUCTION OF A HAMPTON INN HOTEL LOCATED
AT THE SOUTHWEST CORNER OF AUTO CENTRE DRIVE
AND LA QUINTA DRIVE WITHIN THE CENTRE AT LA
QUINTA SPECIFIC PLAN AREA
CASE NUMBERS:
SITE DEVELOPMENT PERMIT 2026-0001
(SDP 2022-0007, EXTENSION NO. 1)
PROJECT: HAMPTON INN HOTEL
APPLICANT: VERDANT LAQUINTA LLC
WHEREAS, the City Council of the City of La Quinta, California, did on January
16, 2024, hold a duly noticed public hearing and adopt Resolution No. 2024-004
approving Specific Plan 2022-0003 (SP 1997-029, Amendment No. 6) and Site
Development Permit 2022-0007 for a 3-story, 125-room Hampton Inn hotel project on a
2.78 acre parcel located at the southwest corner of Auto Centre Drive and La Quinta
Drive, more commonly described as:
Assessor Parcel Number: 600-340-060
WHEREAS, the applicant, on January 6, 2026, applied for a two-year time
extension for Site Development Permit 2022-0007, citing difficulty in receiving assurance
that electrical service through Imperial Irrigation District would be available for the project;
and
WHEREAS, the City Council of the City of La Quinta, California, did, on March 3,
2026, consider a request by the applicant for approval of a two-year first time extension
for the project, Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1);
and
WHEREAS, the Design and Development Department has determined that the
request has been assessed in conjunction with and is consistent with Environmental
Assessment 2022-0011 (Addendum to EA 2017-0009) prepared for the project, adopted
via Resolution No. 2024-003 on January 16, 2024; and
WHEREAS, upon hearing and considering all testimony and arguments of all
interested persons, if any, desiring to be heard, the City Council did make the following
mandatory findings to justify approval of the Site Development Permit time extension:
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 2 of 4
1. Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1) is
consistent with the La Quinta General Plan, in that the project is designated as
Regional Commercial. The City’s General Plan policies relating to Regional
Commercial encourage a broad range of commercial land uses within the City in
order to accommodate development ranging from supermarkets and drugstores,
major national retailers, professional offices, services businesses, restaurants,
research and development, in addition to hotels and motels.
2. Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1) is
consistent with the La Quinta Zoning Code in terms of architectural style, building
height, building mass, and landscaping. The Site Development Permit conforms to
the development standards set forth in the project Specific Plan and has been
conditioned to ensure compliance with the Specific Plan and zoning standards of
the Regional Commercial zoning district and other supplemental nonresidential
development standards as established in Title 9 of the La Quinta Municipal Code.
3. Processing and approval of Site Development Permit 2026-0001 (SDP 2022-0007,
Extension No. 1) is in compliance with the requirements of the California
Environmental Quality Act. The Design and Development Department has
determined that the time extension request is consistent with Environmental
Assessment 2022-0011 (Addendum to EA 2017-0009) for the Centre at La Quinta
Specific Plan. No changed circumstances or conditions are proposed which would
trigger the preparation of subsequent environmental analysis pursuant to Public
Resources Code Section 21166.
4. The architectural design of Site Development Permit 2026-0001 (SDP 2022-0007,
Extension No. 1) including, but not limited to, the architectural style, scale, building
mass, materials, colors, architectural details, and other architectural elements, are
compatible with surrounding developments and the quality of design prevalent in
the City. The contemporary design elements of the hotel structure are appropriate
in context with surrounding developments.
5. The site design of Site Development Permit 2026-0001 (SDP 2022-0007,
Extension No. 1) including but not limited to project entries, interior circulation,
proposed amenities, screening of mechanical equipment, exterior lighting, parking,
pedestrian accessibility and other site design elements are compatible with the
surrounding developments and with the prevalent quality of design in the City.
6. The proposed landscaping for Site Development Permit 2026-0001 (SDP 2022-
0007, Extension No. 1) complies with the landscaping standards and plant palette
outlined in the project’s Specific Plan and aligns with the aesthetic and landscaping
goals of the General Plan and Zoning Code. No turf will be installed on the site.
�RV�
LINDA EVANS, Mayor
City of La Quinta, California
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 3 of 4
Synthetic turf will be used only within the enclosed patio and dog park areas. The
overall landscape design emphasizes decomposed granite and a drought-tolerant
plant palette.
7. As required by Section 9.200.080 of the La Quinta Zoning Code, the Applicant has
demonstrated that circumstances of the project, including difficulty in receiving
electrical service through Imperial Irrigation District, has caused difficulty in
exercising the SDP entitlement.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of La
Quinta, California, as follows:
SECTION 1. That the above recitations are true and constitute the Findings of the City
Council in this case.
SECTION 2. That the proposed time extension is consistent with the above project and
the City Council hereby finds it to be consistent with Environmental Assessment 2022-
0011 (Addendum to EA 2017-0009) for the Centre at La Quinta Specific Plan.
SECTION 3. That the City Council hereby does approve a first time extension to January
16, 2028, for Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1), for
the reasons set forth in this Resolution and subject to the attached Conditions of Approval,
incorporated herewith as Exhibit A to this Resolution.
PASSED, APPROVED, and ADOPTED at a regular meeting of the City of La
Quinta City Council, held on March 3, 2026, by the following vote:
AYES:
NOES:
Councilmembers Fitzpatrick, McGarrey, Peña, Sanchez, and Mayor Evans
None
ABSENT: None
ABSTAIN: None
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 4 of4
ATTEST:
MO ity Clerk
City of La Quinta, California
APPROVED AS TO FORM:
l,J .. �yt/� WILLIAM H. IHRKE, City Attorney
City of La Quinta, California
Resolution No. 2026-002 EXHIBIT A
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 1 of 16
GENERAL
1. The applicant agrees to defend, indemnify, and hold harmless the City of La Quinta
(“City”), its agents, officers, and employees from any claim, action, or proceeding
to attack, set aside, void, or annul the approval of this Site Development Permit.
The City shall have sole discretion in selecting its defense counsel.
The City shall promptly notify the applicant of any claim, action, or proceeding and
shall cooperate fully in the defense.
2. Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1) shall
comply with all applicable conditions and/or mitigation measures for the following
related approvals:
Tentative Parcel Map 37359
In the event of any conflict(s) between approval conditions and/or provisions of
these approvals, the Planning Manager shall adjudicate the conflict by determining
the precedence.
3. The Site Development Permit shall expire two years from January 6, 2026, and
shall become null and void in accordance with La Quinta Municipal Code Section
9.200.080, unless a building permit has been issued. A time extension may be
requested per LQMC Section 9.200.080.
4. Prior to the issuance of any grading, construction, or building permit by the City,
the applicant shall obtain any necessary clearances and/or permits from the
following agencies, if required:
Riverside County Fire Marshal
La Quinta Development Services Division: Grading Permit and Green Sheet
(Public Works Clearance) for Building Permits, Water Quality Management
Plan (WQMP) Exemption Form – Whitewater River Region, Improvement
Permit
La Quinta Design and Development Department
Riverside Co. Environmental Health Department
Desert Sands Unified School District (DSUSD)
Coachella Valley Water District (CVWD)
Imperial Irrigation District (IID)
California Regional Water Quality Control Board (CRWQCB)
State Water Resources Control Board
SunLine Transit Agency (SunLine)
South Coast Air Quality Management District Coachella Valley (SCAQMD)
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 2 of 16
The applicant is responsible for all requirements of the permits and/or clearances
from the above-listed agencies. When these requirements include approval of
improvement plans, the applicant shall furnish proof of such approvals when
submitting those improvement plans for City approval.
5. Coverage under the State of California General Construction Permit must be
obtained by the applicant, who then shall submit a copy of the Regional Water
Quality Control Board’s (“RWQCB”) acknowledgment of the applicant’s Notice of
Intent (“NOI”) and Waste Discharger Identification (WDID) number to the City prior
to the issuance of a grading or building permit.
6. The applicant shall comply with applicable provisions of the City’s NPDES
stormwater discharge permit, LQMC Sections 8.70.010 et seq. (Stormwater
Management and Discharge Controls), and 13.24.170 (Clean Air/Clean Water);
Riverside County Ordinance No. 457; the California Regional Water Quality
Control Board – Colorado River Basin Region Board Order No. R7-2013-0011 and
the State Water Resources Control Board’s Order No. 2012-0006-DWQ.
A. For construction activities including clearing, grading or excavation of land
that disturbs one (1) acre or more of land, or that disturbs less than one (1)
acre of land, but which is a part of a construction project that encompasses
more than one (1) acre of land, the Permitee shall be required to submit a
Storm Water Pollution Protection Plan (“SWPPP”) to the State Water
Resources Control Board.
The applicant or design professional can obtain the California Stormwater
Quality Association SWPPP template at www.cabmphandbooks.com for
use in their SWPPP preparation.
B. The applicant shall ensure that the required SWPPP is available for
inspection at the project site at all times through and including acceptance
of all improvements by the City.
C. The applicant’s SWPPP shall include provisions for all of the following Best
Management Practices (“BMPs”) (LQMC Section 8.70.020 (Definitions)):
1) Temporary Soil Stabilization (erosion control).
2) Temporary Sediment Control.
3) Wind Erosion Control.
4) Tracking Control.
5) Non-Storm Water Management.
6) Waste Management and Materials Pollution Control.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 3 of 16
D. The SWPPP and BMPs shall remain in effect for the entire duration of
project construction until all improvements are completed and accepted by
the City Council.
E. The inclusion in the Conditions, Covenants, and Restrictions (CC&Rs), a
requirement for the perpetual maintenance and operation of all post-
construction BMPs as required.
7. Permits issued under this approval shall be subject to the provisions of the
Development Impact Fee and Transportation Uniform Mitigation Fee programs in
effect at the time of issuance of building permit(s).
8. Approval of this Site Development Permit shall not be construed as approval for
any horizontal dimensions implied by any site plans or exhibits unless specifically
identified in the following conditions of approval.
9. Developer shall reimburse the City, within thirty (30) days of presentment of the
invoice, all costs and actual attorney’s fees incurred by the City Attorney to review,
negotiate, and/or modify any documents or instruments required by these
conditions, if Developer requests that the City modify or revise any documents or
instruments prepared initially by the City to effect these conditions. This obligation
shall be paid in the time noted above without deduction or offset and Developer’s
failure to make such payment shall be a material breach of the Conditions of Approval.
10. Developer shall reimburse the City, within thirty (30) days of presentment of the
invoice, all costs and actual consultant’s fees incurred by the City for engineering
and/or surveying consultants to review and/or modify any documents or
instruments required by this project. This obligation shall be paid in the time noted
above without deduction or offset, and Developer’s failure to make such payment
shall be a material breach of the Conditions of Approval.
PROPERTY RIGHTS
11. Prior to issuance of any permit(s), the applicant shall acquire or confer easements
and other property rights necessary for the construction or proper functioning of
the proposed development. Conferred rights shall include irrevocable offers to
dedicate or grant access easements to the City for emergency services and for
maintenance, construction, and reconstruction of essential improvements.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 4 of 16
12. Pursuant to the aforementioned condition, conferred rights shall include approvals
from the master developer over easements and other property rights necessary
for construction and proper functioning of the proposed development not limited to
access rights over proposed and/or existing private streets that access public
streets and open space/drainage facilities of the master development.
13. The applicant shall offer for dedication all public street rights-of-way in
conformance with the City's General Plan, Municipal Code, applicable specific
plans, and/or as required by the City Engineer.
14. The public street right-of-way offers for dedication required for this project include:
A. PUBLIC STREETS
1) Auto Centre Drive South – No additional right-of-way dedication is
required.
2) La Quinta Drive – No additional right-of-way dedication is required.
3) Auto Centre Way – No additional right-of-way dedication is required.
15. Dedications shall include additional widths as necessary for dedicated right and
left turn lanes, bus turnouts, and other features contained in the approved
construction plans.
16. When the City Engineer determines that access rights to the proposed street
rights-of-way shown on the approved Site Development Permit are necessary prior
to approval of the improvements dedicating such rights-of-way, the applicant shall
grant the necessary rights-of-way within 60 days of a written request by the City.
17. Where public facilities (e.g., sidewalks) are placed on privately-owned setbacks,
the applicant shall offer for dedication blanket easements for those purposes.
18. The applicant shall offer for dedication those easements necessary for the
placement of, and access to, utility lines and structures, drainage basins, mailbox
clusters, park lands, and common areas.
19. Direct vehicular access to Auto Centre Dr South, La Quinta Drive, and Auto Centre
Way is restricted, except for those access points identified on the Site
Development Permit, or as otherwise conditioned in these conditions of approval.
20. The applicant shall furnish proof of easements, or written permission, as
appropriate, from those owners of all abutting properties on which grading,
retaining wall construction, permanent slopes, or other encroachments will occur.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 5 of 16
STREET AND TRAFFIC IMPROVEMENTS
21. The applicant shall comply with the provisions of LQMC Sections 13.24.060 (Street
Improvements), 13.24.070 (Street Design - Generally) & 13.24.100 (Access for
Individual Properties and Development) for public streets; and Section 13.24.080
(Street Design - Private Streets), where private streets are proposed.
22. Streets shall have vertical curbs or other approved curb configurations that will
convey water without ponding and provide lateral containment of dust and residue
during street sweeping operations. If a wedge or rolled curb design is approved,
the lip at the flowline shall be near vertical with a 1/8" batter and a minimum height
of 0.1'. Unused curb cuts on any lot shall be restored to standard curb height prior
to final inspection of permanent building(s) on the lot.
23. The applicant shall construct the following street improvements to conform with the
General Plan (street type noted in parentheses.)
A. OFF-SITE STREETS
1) La Quinta Drive
a. The applicant shall construct 6-foot wide sidewalk on the west
side.
Other required improvements in the right-of-way and/or adjacent landscape
setback area include:
a) All appurtenant components, such as, but not limited to, curb,
gutter, traffic control striping, legends, and signs.
The applicant is responsible for construction of all improvements mentioned above.
The applicant shall extend improvements beyond the project boundaries to ensure
they safely integrate with existing improvements (e.g., grading; traffic control
devices and transitions in alignment, elevation or dimensions of streets and
sidewalks).
24. The applicant shall design street pavement sections using CalTrans' design
procedure for 20-year life pavement, and the site-specific data for soil strength and
anticipated traffic loading (including construction traffic). Minimum structural
sections shall be as follows:
Parking Lot & Aisles (Low Traffic) 3.0" a.c./4.5" c.a.b.
Parking Lot & Aisles (High Traffic) 4.5" a.c /5.5" c.a.b.
or the approved equivalents of alternate materials per the City Engineer.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 6 of 16
25. The applicant shall submit current mix designs (less than two years old at the time
of construction) for base, asphalt concrete and Portland cement concrete. The
submittal shall include test results for all specimens used in the mix design
procedure. For mix designs over six months old, the submittal shall include recent
(less than six months old at the time of construction) aggregate gradation test
results confirming that design gradations can be achieved in current production.
The applicant shall not schedule construction operations until mix designs are
approved.
26. General access points and turning movements of traffic are limited to the following:
Auto Centre Way South and Auto Centre Drive: Full turn movements in and out
are allowed.
27. Improvements shall include appurtenances such as traffic control signs, markings,
and other devices, raised medians if required, street name signs, and sidewalks.
Mid-block street lighting is not required.
28. Improvements shall be designed and constructed in accordance with City adopted
standards, supplemental drawings and specifications, or as approved by the City
Engineer. Improvement plans for streets, access gates, and parking areas shall be
stamped and signed by qualified engineers.
29. Standard knuckles and corner cut-backs shall conform to Riverside County
Standard Drawings #801 and #805, respectively, unless otherwise approved by
the City Engineer.
PARKING LOT and ACCESS POINTS
30. The design of parking facilities shall conform to LQMC Chapter 9.150 and in
particular, the following:
A. The parking space and aisle widths and the double hairpin stripe parking
space design shall conform to LQMC Chapter 9.150.
B. Cross slopes should be a maximum of 2% where ADA accessibility is
required, including accessibility routes between buildings.
C. Building access points shall be shown on the Precise Grading Plans to
evaluate ADA accessibility issues.
D. Accessibility routes to public streets and adjacent development shall be
shown on the Precise Grading Plan.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 7 of 16
E. Parking space lengths shall be according to LQMC Chapter 9.150 and be a
minimum of 17 feet in length with a 2-foot overhang for standard parking
spaces and 18 feet with a 2-foot overhang for handicapped parking space
or as approved by the City Engineer. One (1) van accessible parking space
is required per eight (8) accessible parking spaces.
F. Drive aisles between parking spaces shall be a minimum of 26 feet, with
access drive aisles to Public Streets a minimum of 30 feet or as approved
by the City Engineer.
Entry drives, main interior circulation routes, corner cutbacks, bus turnouts,
dedicated turn lanes, ADA accessibility route to public streets and other features
shown on the approved construction plans, may require additional street widths
and other improvements as may be determined by the City Engineer.
IMPROVEMENT PLANS
As used throughout these Conditions of Approval, professional titles such as “engineer,”
“surveyor,” and “architect,” refer to persons currently certified or licensed to practice their
respective professions in the State of California.
31. Improvement plans shall be prepared by or under the direct supervision of qualified
engineers and/or architects, as appropriate, and shall comply with the provisions
of LQMC Section 13.24.040 (Improvement Plans).
32. The following improvement plans shall be prepared and submitted for review and
approval by the Development Services Division. A separate set of plans for each
line item specified below shall be prepared. The plans shall utilize the minimum
scale specified, unless otherwise authorized by the City Engineer in writing. Plans
may be prepared at a larger scale if additional detail or plan clarity is desired. Note,
the applicant may be required to prepare other improvement plans not listed here
pursuant to improvements required by other agencies and utility purveyors.
A. PM10 Plan 1” = 40’ Horizontal
B. Erosion Control Plan 1” = 40’ Horizontal
C. WQMP (Plan submitted in Report Form)
D. Precise Grading Plan 1” = 30’ Horizontal
NOTE: A through D to be submitted concurrently.
(Separate Storm Drain Plans if applicable)
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 8 of 16
Other engineered improvement plans prepared for City approval that are not listed
above shall be prepared in formats approved by the City Engineer prior to
commencing plan preparation.
All Off-Site Plan & Profile Street Plans and Signing & Striping Plans shall show all
existing improvements for a distance of at least 200-feet beyond the project limits,
or a distance sufficient to show any required design transitions.
All On-Site Signing & Striping Plans shall show, at a minimum; Stop Signs, Limit
Lines and Legends, No Parking Signs, Raised Pavement Markers (including Blue
RPMs at fire hydrants) and Street Name Signs per Public Works Standard Plans
and/or as approved by the Engineering Department.
Precise Grading plans shall normally include all on-site surface improvements,
including but not limited to finish grades for curbs & gutters, building pad and floor
elevations, wall elevations, parking lot improvements, and accessibility
requirements.
33. The City maintains standard plans, detail sheets, and/or construction notes for
elements of construction which can be accessed via the “Plans, Notes and Design
Guidance” section of the Public Works Department at the City website
(www.laquintaca.gov). Please navigate to the Public Works Department home
page and look for the Standard Drawings hyperlink.
34. The applicant shall furnish a complete set of all approved improvement plans on a
storage media acceptable to the City Engineer.
35. Upon completion of construction, and prior to final acceptance of the improvements
by the City, the applicant shall furnish the City with reproducible record drawings
of all improvement plans which were approved by the City. Each sheet shall be
clearly marked "Record Drawing" and shall be stamped and signed by the engineer
or surveyor certifying to the accuracy and completeness of the drawings. The
applicant shall have all approved mylars previously submitted to the City, revised
to reflect the as-built conditions. The applicant shall employ or retain the Engineer
of Record (EOR) during the construction phase of the project so that the EOR can
make site visits in support of preparing "Record Drawing". However, if subsequent
approved revisions have been approved by the City Engineer and reflect said
"Record Drawing" conditions, the EOR may submit a letter attesting to said fact to
the City Engineer in lieu of a mylar submittal.
IMPROVEMENT SECURITY AGREEMENTS
36. Prior to constructing any off-site improvements, the applicant shall deposit
securities equivalent to both a Performance and Labor & Material Bonds, each
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 9 of 16
valued at 100% of the cost of the off-site improvements, or as approved by the City
Engineer.
37. Improvements to be made, or agreed to be made, shall include the removal of any
existing structures or other obstructions which are not a part of the proposed
improvements; and shall provide for the setting of the final survey monumentation.
38. When improvements are phased through a “Phasing Plan,” or an administrative
approval (e.g., Site Development Permits), all off-site improvements and common
on-site improvements (e.g., backbone utilities, retention basins, perimeter walls,
landscaping and gates) shall be constructed, or secured, prior to the issuance of
any permits in the first phase of the development, or as otherwise approved by the
City Engineer.
Improvements and obligations required of each subsequent phase shall either be
completed or secured prior to the completion of homes or the occupancy of
permanent buildings within such latter phase, or as otherwise approved by the City
Engineer.
In the event the applicant fails to construct the improvements for the development,
or fails to satisfy its obligations for the development in a timely manner, pursuant
to the approved phasing plan, the City shall have the right to halt issuance of all
permits, and/or final inspections, withhold other approvals related to the
development of the project, or call upon the surety to complete the improvements.
39. Depending on the timing of the development of this Site Development Permit, and
the status of the off-site improvements at the time, the applicant may be required to:
A. Construct certain off-site improvements.
B. Construct additional off-site improvements, subject to the reimbursement of
its costs by others.
C. Reimburse others for those improvements previously constructed that are
considered to be an obligation of this Site Development Permit.
D. Secure the costs for future improvements that are to be made by others.
E. To agree to any combination of these actions, as the City may require.
Off-Site Improvements should be completed on a first priority basis. The applicant
shall complete Off-Site Improvements in the first phase of construction.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 10 of 16
In the event that any of the improvements required for this development are
constructed by the City, the applicant shall, prior to the approval of the Site
Development Permit, or the issuance of any permit related thereto, reimburse the
City for the costs of such improvements.
40. The applicant shall submit detailed construction cost estimates for all proposed on-
site and off-site improvements for checking and approval by the City Engineer.
Such estimates shall conform to the unit cost schedule as approved by the City
Engineer.
Estimates for improvements under the jurisdiction of other agencies shall be
approved by those agencies and submitted to the City along with the applicant’s
detailed cost estimates. Security will not be required for telephone, natural gas, or
Cable television improvements.
GRADING
41. The applicant shall comply with the provisions of LQMC Section 13.24.050
(Grading Improvements).
42. Prior to occupancy of the project site for any construction or other purposes, the
applicant shall obtain a grading permit approved by the City Engineer.
43. To obtain an approved grading permit, the applicant shall submit and obtain
approval of all of the following:
A. A grading plan prepared by a civil engineer registered in the State of
California,
B. A preliminary geotechnical (“soils”) report prepared by an engineer
registered in the State of California,
C. A Fugitive Dust Control Plan prepared in accordance with LQMC Chapter
6.16, (Fugitive Dust Control), and
D. An Erosion Control Plan showing Best Management Practices prepared in
accordance with LQMC Sections 8.70.010 and 13.24.170 (NPDES
Stormwater Discharge Permit and Storm Management and Discharge
Controls).
E. A final WQMP prepared by an appropriate professional registered in the
State of California.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 11 of 16
F. A grading bond in a form acceptable to the City, and in an amount sufficient
to guarantee compliance with the grading bond requirements.
All grading shall conform with the recommendations contained in the Preliminary
Soils Report and shall be certified as being adequate by soils engineer, or
engineering geologist registered in the State of California.
The applicant shall furnish security, in a form acceptable to the City, and in an
amount sufficient to guarantee compliance with the approved Fugitive Dust Control
Plan provisions as submitted with its application for a grading permit. Additionally,
the applicant shall replenish said security if expended by the City of La Quinta to
comply with the Plan as required by the City Engineer.
44. The applicant shall maintain all open graded, undeveloped land in order to prevent
wind and/or water erosion of such land. All open graded, undeveloped land shall
either be planted with interim landscaping, or stabilized with such other erosion
control measures, as were approved in the Fugitive Dust Control Plan.
45. Grading within the perimeter setback and parkway areas shall have undulating
terrain and shall conform with the requirements of LQMC Section 9.60.240(F)
except as otherwise modified by this condition. The maximum slope shall not
exceed 3:1 anywhere in the landscape setback area, except for the backslope (i.e.,
the slope at the back of the landscape lot), which shall not exceed 2:1 if fully
planted with ground cover. The maximum slope in the first six (6) feet adjacent to
the curb shall not exceed 4:1 when the nearest edge of sidewalk is within six feet
(6’) of the curb, otherwise the maximum slope within the right of way shall not
exceed 3:1. All unpaved parkway areas adjacent to the curb shall be depressed
one and one-half inches (1.5") in the first eighteen inches (18") behind the curb.
46. Building pad elevation on the precise grading plan submitted for City Engineer’s
approval shall conform with pad elevations shown on the preliminary grading plan,
unless the pad elevations have other requirements imposed elsewhere in these
Conditions of Approval, or as approved by the City Engineer.
47. Prior to any site grading or regrading that will raise or lower any portion of the site
by more than plus or minus half of a foot (0.5’) from the elevations shown on the
approved Site Development Permit, the applicant shall submit the proposed
grading changes to the City Engineer for a substantial conformance review.
48. Prior to the issuance of a building permit for any building lot, the applicant shall
provide a lot pad certification stamped and signed by a qualified engineer or
surveyor with applicable compaction tests and over excavation documentation.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 12 of 16
Each pad certification shall list the pad elevation as shown on the approved
grading plan, the actual pad elevation, and the difference between the two, if any.
Such pad certification shall also list the relative compaction of the pad soil. The
data shall be organized by lot number and listed cumulatively if submitted at
different times.
DRAINAGE
49. Stormwater handling shall conform with the approved hydrology and drainage
report for the Hampton Inn Hotel project (SDP2022-0007), or as approved by the
City Engineer. Nuisance water shall be disposed of in an approved manner.
Nuisance water shall be retained onsite and disposed of via an underground
percolation improvement approved by the City Engineer.
50. The applicant shall comply with the provisions of LQMC Section 13.24.120
(Drainage), Retention Basin Design Criteria, Engineering Bulletin No. 06-16 –
Hydrology Report with Preliminary Hydraulic Report Criteria for Storm Drain
Systems and Engineering Bulletin No. 06-015 - Underground Retention Basin
Design Requirements. More specifically, stormwater falling on site during the 100-
year storm shall be retained within the development, unless otherwise approved
by the City Engineer. The design storm shall be the 1 hour, 3 hour, 6 hour or 24
hour event producing the greatest total run off.
51. Nuisance water shall be retained on site. Nuisance water shall be disposed of per
approved methods contained in Engineering Bulletin No. 06-16 – Hydrology Report
with Preliminary Hydraulic Report Criteria for Storm Drain Systems and
Engineering Bulletin No. 06-015 - Underground Retention Basin Design
Requirements.
52. In the design of retention facilities, the maximum percolation rate shall be two
inches per hour. The percolation rate will be considered to be zero unless the
applicant provides site specific data indicating otherwise, and as approved by the
City Engineer.
53. The project shall be designed to accommodate purging and blowoff water (through
underground piping and/or retention facilities) from any on-site or adjacent well
sites granted or dedicated to the local water utility authority as a requirement for
development of this property.
54. No fence or wall shall be constructed around any retention basin unless approved
by the Planning Manager and the City Engineer.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 13 of 16
55. For on-site above ground common retention basins, retention depth shall be
according to Engineering Bulletin No. 06-16 – Hydrology Report with Preliminary
Hydraulic Report Criteria for Storm Drain Systems. Side slopes shall not exceed
3:1 and shall be planted with maintenance free ground cover. Additionally,
retention basin widths shall be not less than 20 feet at the bottom of the basin.
56. Stormwater may not be retained in landscaped parkways or landscaped setback
lots. Only incidental storm water (precipitation which directly falls onto the setback)
will be permitted to be retained in the landscape setback areas. The perimeter
setback and parkway areas in the street right-of-way shall be shaped with berms
and mounds, pursuant to LQMC Section 9.100.040(B)(7).
57. The design of the development shall not cause any increase in flood boundaries
and levels in any area outside the development.
58. The development shall be graded to permit storm flow in excess of retention
capacity to flow out of the development through a designated overflow and into the
historic drainage relief route.
59. Storm drainage historically received from adjoining property shall be received and
retained or passed through into the historic downstream drainage relief route.
60. The applicant shall comply with applicable provisions for post construction runoff
per the City’s NPDES stormwater discharge permit, LQMC Sections 8.70.010 et
seq. (Stormwater Management and Discharge Controls), and 13.24.170 (Clean
Air/Clean Water); Riverside County Ordinance No. 457; and the California
Regional Water Quality Control Board – Colorado River Basin (CRWQCB-CRB)
Region Board Order No. R7-2013-0011.
A. For post-construction urban runoff from New Development and
Redevelopment Projects, the applicant shall implement requirements of the
NPDES permit for the design, construction, and perpetual operation and
maintenance of BMPs per the approved Water Quality Management Plan
(WQMP) for the project as required by the California Regional Water Quality
Control Board – Colorado River Basin (CRWQCB-CRB) Region Board
Order No. R7-2013-0011.
B. The applicant shall implement the WQMP Design Standards per
(CRWQCB-CRB) Region Board Order No. R7-2013-0011 utilizing BMPs
approved by the City Engineer. A project specific WQMP shall be provided,
which incorporates Site Design and Treatment BMPs utilizing first flush
infiltration as a preferred method of NPDES Permit Compliance for
Whitewater River receiving water, as applicable.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 14 of 16
C. The developer shall execute and record a Stormwater Management/BMP
Facilities Agreement that provides for the perpetual maintenance and
operation of stormwater BMPs.
UTILITIES
61. The applicant shall comply with the provisions of LQMC Section 13.24.110
(Utilities).
62. The applicant shall obtain the approval of the City Engineer for the location of all
utility lines within any right-of-way, and all above-ground utility structures including,
but not limited to, traffic signal cabinets, electric vaults, water valves, and
telephone stands, to ensure optimum placement for practical and aesthetic
purposes.
63. Existing overhead utility lines within, or adjacent to, the proposed development,
and all proposed utilities shall be installed underground.
The 92 KV transmission power poles and all existing utility lines attached to joint
use 92 KV transmission power poles are exempt from the requirement to be placed
underground.
64. Underground utilities shall be installed prior to overlying hardscape. For installation
of utilities in existing improved streets, the applicant shall comply with trench
restoration requirements maintained or required by the City Engineer.
The applicant shall provide certified reports of all utility trench compaction for
approval by the City Engineer. Additionally, grease traps and the maintenance
thereof shall be located as to not conflict with access aisles/entrances.
CONSTRUCTION
65. The City will conduct final inspections of habitable buildings only when the
buildings have improved street and (if required) sidewalk access to publicly
maintained streets. The improvements shall include required traffic control
devices, pavement markings, and street name signs. If on-site streets in residential
developments are initially constructed with partial pavement thickness, the
applicant shall complete the pavement prior to final inspections of the last ten
percent of homes within the development or when directed by the City, whichever
comes first.
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 15 of 16
LANDSCAPE AND IRRIGATION
66. The applicant shall comply with LQMC Sections 13.24.130 (Landscaping
Setbacks) & 13.24.140 (Landscaping Plans).
67. Landscape and irrigation plans for landscaped lots and setbacks, medians,
retention basins, and parks shall be signed and stamped by a licensed landscape
architect.
68. All new and modified landscape areas shall have landscaping and permanent
irrigation improvements in compliance with the City’s Water Efficient Landscape
regulations contained in LQMC Section 8.13 (Water Efficient Landscape).
69. Lighting plans shall be submitted with the final landscaping plans for a
recommendation to the Planning Manager for his approval. Exterior lighting shall
be consistent with LQMC Section 9.100.150 (Outdoor Lighting). All freestanding
lighting shall not exceed 18 feet in height and shall be fitted with a visor if deemed
necessary by staff to minimize trespass of light off the property. The illuminated
carports shall be included in the photometric study as part of the final lighting plan
submittal.
70. All water features shall be designed to minimize “splash” and use high efficiency
pumps and lighting to the satisfaction of the Design and Development Director.
They shall be included in the landscape plan water efficiency calculations per
Municipal Code Chapter 8.13.
71. All rooftop mechanical equipment shall be completely screened from view. Utility
transformers or other ground mounted mechanical equipment shall be fully
screened with a screening wall or landscaping and painted to match the adjacent
buildings.
72. The applicant shall submit the final landscape plans for review, processing, and
approval to the Community Development Department, in accordance with the Final
Landscape Plan application process. Planning Manager approval of the final
landscape plans is required prior to issuance of the first building permit unless the
Planning Manager determines extenuating circumstances exist that justify an
alternative processing schedule.
NOTE: Plans are not approved for construction until signed by the appropriate City
official, including the Planning Manager and/or City Engineer.
73. The applicant or his agent has the responsibility for proper sight distance
requirements per guidelines in the AASHTO “A Policy on Geometric Design of
Highways and Streets, 5th Edition” or latest, in the design and/or installation of all
Resolution No. 2026-002
Site Development Permit 2026-0001 (SDP 2022-0007, Extension No. 1)
Project: Hampton Inn Hotel
Location: Southwest Corner of Auto Centre Drive and La Quinta Drive
Applicant: Verdant LaQuinta LLC
Adopted: March 3, 2026
Page 16 of 16
landscaping and appurtenances abutting and within the private and public street
right-of-way.
74. The final design of the perimeter landscaping, particularly the perimeter wall, shall
be included with the Final Landscape Plan submittal.
PUBLIC SERVICES
75. The applicant shall provide public transit improvements if required by SunLine
Transit Agency and approved by the City Engineer.
MAINTENANCE
76. The applicant shall comply with the provisions of LQMC Section 13.24.160
(Maintenance).
77. The applicant shall make provisions for the continuous and perpetual maintenance
of perimeter landscaping up to the curb, common areas, access drives, sidewalks,
and stormwater BMPs.
FEES AND DEPOSITS
78. The applicant shall comply with the provisions of LQMC Section 13.24.180 (Fees
and Deposits). These fees include all deposits and fees required by the City for
plan checking and construction inspection. Deposits and fee amounts shall be
those in effect when the applicant makes an application for plan check and permits.
PLANNING
79. The parking light poles along the south project border shall not exceed more than
12 feet in height.
80. The parapet architectural features shall have a minimum depth of 10 feet.
81. No building-mounted signage shall be placed on the south elevation. Signage on
the porte-cochere (west or east facing) or ground-mounted signage is acceptable
at the south side of the site.