HomeMy WebLinkAbout2026-27 Desert Concepts Constr - Parks Landscape Maint Project 2023-30 - Change Order No. 2MEMORANDUM
CALIFORNIA -
DATE: 6/18/26------------
TO: Jon McMillen, City Manager
FROM: Dianne Hansen, M&O Superintendent
RE: Desert Concepts Construction, Inc., Parks Landscape Maintenance & On -Call Services; Project No 2023-30; CCO#2
Please list the Contracting Party/ Vendor Name, any change orders or amendments, and the type of services to be provided. Make
sure to list any related Project No. and Project Name.
Authority to execute this agreement is based upon:
❑✓ Approved by City Council on June 16, 2026 C12
❑ City Manager's signing authority provided under the City's Purchasing & Contracting Policy
[Resolution No. 2023-008] for budget expenditures of $50,000 or less.
❑ City Manager's signing authority provided under the City's Personnel Policy Section 3.2 for
temporary employment positions.
❑ Department Director's or Manager's signing authority provided under the City's Purchasing Policy
[Resolution No. 2023-008] for budget expenditures of $15,000 and $5,000, respectively, or less.
Procurement Method (one must apply):
❑ Bid RFP 17 RFQ ❑ 3 written informal bids
❑ Sole Source ❑ Select Source Cooperative Procurement
Requesting department shall check and attach the items below as appropriate:
Agreement payment will be charged to Account No.: 101-3005; 215-7004; 202-3006; 202-3004-60112
Agreement term: Start Date July 1, 2026 End Date June 30, 2027
Amount of Agreement, Amendment, Change Order, etc.: $ 1 ,245,785; $300,000 On -Call
REMINDER: Signing authorities listed above are applicable on the apprepate Agreement amount, not individual
Amendments or Change Orders!
Insurance certificates as required by the Agreement for Risk Manager approval
Approved by: Oscar Mojica (MyCOI) Date: 6/22/2026
.❑
NOTE:
Bonds (originals) as required by the Agreement (Performance, Payment, etc.)
Conflict of Interest Form 700 Statement of Economic Interests from Consultant(s)
Review the "Form 700 Disclosure for Consultants" guidance to determine if a Form 700 is required pursuant
FPPC regulation 18701(2)
Business License No. 0006902 Expires: 1 /31 /2027
Requisition for a Purchase Order has been prepared (Agreements over $5,000)
ta Qa�fra
GEM of the DESERT —
Sheet 1 of 2
AGREEMENT: CITYWIDE PARK LANDSCAPE MAINTENANCE SERVICE
PROJECT NO. 2023-30
CONTRACTOR: DESERT CONCEPTS CONSTRUCTION, INC.
CHANGE ORDER NO. 2
*******************************************************************************************************************
Pursuant to the terms of the original Contract, you are hereby directed to make the herein described
changes or do the following described work not included in the plans and specifications for this Contract.
Unless otherwise stated all work shall conform to the terms, general conditions, and special provisions
of the original Contract.
DESCRIPTION OF CHANGE
1. As provided in Section 1240(C) - the Contract sum is amended as follows: the total agreement
amount of $1,209,500 is increased to $1,245,785 which includes a 3% increase of $36,285
2. As provided in Section 1240(B) — the City and Contractor agree to extend the term of the contract
for the second one-year extension, commencing on July 1, 2026, through June 30, 2027.
3. As provided in Section 3000, B. General Facility Operations is revised to include maintenance
and repair of drinking fountains.
8. All drinking fountains including dog parks and trails shall be kept clean and operational at
all times.
a. Minor repairs to include but not limited to unclogging drains, labor for replacing damaged
or broken parts, and miscellaneous parts shall be included in the contract price. City to provide
replacement parts such as valves, and tubing,
b. All miscellaneous repairs such as leaking fountains shall be completed within twelve (12)
hours of notification received.
C. Every instance of damage shall be reported to the City representative. Repairs due to
damage shall be completed within twenty-four (24) hours after damage occurs.
d. Should damage be repetitive, the City representative will evaluate replacement with a
more damage resistant model through extra work or separate action.
*******************************************************************************************************************
Contract for FY 2024/25
$ 1,180,000
Change Order No. 1 for FY 2025/26
(includes compounded 2.5% CPI annual increase)
$ 1,209,500
Change Order No. 2 for FY 2026/27
includes compounded 3% CPI annual increase)$
1,245,785
Revised Agreement Total
$ 3,635,285
******************************************************************************************************************************
ON -CALL SERVICES SPENDING AUTHORITY
On -call services is not guaranteed and must be requested
and approved by the Contract Officer in advance. Work may
include but is not limited to landscape restoration with
modification to the irrigation system, replacement of trees,
shrubs, ground cover, accident damage, vandalism repair,
weed abatement storm debris cleanup irrigation repair and
FY 2024/25 $ 300,000
(approved 6118124)
FY 2025/26 $ 300,000
(approved 4115125)
FYs 2026/27 — 2030/31 $ 300,000
(approved 6116126)
1 ,
assessments, etc. for services outside the scope of the contract.
By reason of this change order the time of completion is adjusted as follows: -365- days added/deleted
to contract time. The start date for these services shall be: July 1, 2026
Submitted By: Date:
Approved By:
Jon McMillen, City Manager
06/18/26
Z
We," the undersigned Contractor, have given careful consideration to the change proposed and
hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials,
perform all labor, except as may be noted above, and perform all services necessary to complete the
above specified work, and hereby accept as full payment the amount shown above, which includes all
direct and indirect overhead expenses for any delays.
Accepted By:
Title: President
Print Name."- io Castro Print Company: DESERT CONCEPTS CONSTRUCTION, INC
CONSENT CALENDAR ITEM NO. 12
City of La Quinta
CITY COUNCIL MEETING: June 16, 2026
STAFF REPORT
AGENDA TITLE: APPROVE CONTRACT WITH DESERT CONCEPTS
CONSTRUCTION, INC FOR PARK LANDSCAPE MAINTENANCE SERVICES,
PROJECT NO. 2023-30, THROUGH FISCAL YEAR 2030/31; AND AUTHORIZE THE
PUBLIC WORKS DEPARTMENT TO UTILIZE THIS VENDOR AS SELECT SOURCE
FOR ON -CALL LANDSCAPE MAINTENANCE SERVICES
RECOMMENDATION
Approve contract with Desert Concepts Construction, Inc. for Park Landscape
Maintenance Services, Project No. 2023-30, through fiscal year 2030/31, and authorize the
City Manager to execute the contract / change orders; and authorize the Public Works
Department to utilize this vendor as a select source for on -call landscape maintenance
services for up to $300,000 effective fiscal year 2026/27 through 2030/31.
EXECUTIVE SUMMARY
• The City contracts landscape maintenance services (LMS) for its parks, civic
facilities, and retention areas. Section 1240 of the contract allows for extra work for
landscape renovation and improvements on an on -call, as needed basis.
• On June 18, 2024, following a Request for Qualifications (RFQ) competitive
selection process, Council awarded a 3-year contract to Desert Concepts
Construction, Inc. (Desert Concepts) for citywide parks LMS based on their
qualifications and experience, effective fiscal year (FY) 2024/25, to be executed as
1-year terms based on satisfactory performance by Desert Concepts; the contract
can be extended for up to 6 additional years, through FY 2030/31.
• Staff seeks Council approval for the remainder of the available contract term, from
FY 2027/28 through FY 2030/31.
• Staff utilizes Desert Concepts, as a select source throughout the duration of the
contract, for additional LMS that are not included in the scope of the contracted
parks LMS on an on -call, as -needed basis, in accordance with Council -approved
additional spending authority.
FISCAL IMPACT
On June 18, 2024, Council approved a 3-year contract with Desert Concepts, effective FY
2024/25, to be executed as 1-year terms based on satisfactory performance by the
contractor, and a 5% contingency, compounded year -over -year, to be used towards
241
negotiating future annual compensation increases, not to exceed the lesser of 5% or the
annual Consumer Price Index (CPI) for Riverside, San Bernardino, and Ontario. Staff
seeks Council approval for the remainder of the available contract term, from FY 2027/28
through FY 2030/31, and a not to exceed 5% contingency for the additional terms,
compounded year -over -year, as detailed in the table below.
Fiscal Year
Landscape Maintenance Services
Estimated
Costs
Actual
Costs
FY 2024/25
$1,180,000
$1,180,000
FY 2025/26 (Change Order 1 — included compounded 2.5% CPI = $29,500)
$1,180,000
$1,209,500
FY 2026/27 (Change Order 2 - includes compounded 3% CPI = $36,285)
$1,180,000
$1,245,785
Contingency at 5% (compounded year -over -year for CPI per Section 1240)
$ 179,950
-
(Approved 6/18/2024) Total:
$3,719,950
$3,635,285
Proposed Extended Term
FY 2027/28
$1,245,785
TBD
FY 2028/29
$1,245,785
TBD
FY 2029/30
$1,245,785
TBD
FY 2030/31
$1,245,785
TBD
Contingency at 5% (compounded year -over -year for CPI per Section 1240)
$ 249,157
-
Total:
$5,232,297
TBD
Grand Total:
$8,952,247
TBD
Costs for each FY will be budgeted pursuant to the contract and are allocated between the
following 4 fund accounts:
Fund Account
FY 2026/27
Park Fund 101-3005-60112
$
1,004,659
L&L Fund 215-7004-60112
$
184,144
Museum Fund 202-3006-60112
$
21,917
Library Fund 202-3004-60112
$
35,065
Change Order No. 2 Total:
$
1,245,785
On -call services are not guaranteed work, however, utilizing the same contractor as a
select source for extra work would ensure continuity and consistency of landscape
maintenance and improvements in areas with aged and deferred landscaping. Work may
generally include modification to the irrigation system, replacement of trees, shrubs, ground
cover, accident damage, vandalism repair, weed abatement, storm debris cleanup,
irrigation repair and assessments, landscape of field improvements, etc.
Council approved additional spending authority for Desert Concepts for FYs 2024/25 (June
18, 2024) and 2025/26 (April 15, 2025) for on -call LMS, beyond the contract's scope of
work, at city -owned properties, on as needed basis. Staff requests Council approval for
additional spending authority up to $300,000 for on -call LMS effective FY 2026/27 through
FY 2030/31, which is the remaining term of the contract, should it remain in effect, as
detailed in the table below. Any unused spending authority would remain available and
carryover each FY until expended or until the agreement expires, whichever occurs first.
242
Fiscal Year
On -Call Services
Approved
Spending Authority
Actual
Expenditures
FY 2024/25
$300,000
$194,289
FY 2025/26 (was of 6/11/2026)
$300,000
$222,160*
FY 2026/27 through FY 2030/31
$300,000
-
Funds will be budgeted each FY for the remaining on -call spending authority pursuant to
Council's approval, and will be expended against various accounts based on the type of
work being performed ((L&L 215-7004-60691; Fire Stations 101-2002-60112; Museum
202-3006-60112; Library 202-3004-60112; Parks 101-3005-60691) for landscape
maintenance, renovation, weed abatement, tree removal, and storm damage clean-up of
city -owned properties.
BACKGROUND/ANALYSIS
The City contracts LMS for its parks, trails, natural areas, retention basins, and landscaped
areas around civic facilities (YMCA, Library, Museum, etc.), retention areas for daily
cleaning and weekly maintenance. Section 1240 of the contract allows for extra work for
landscape renovation and improvements on an on -call, as needed basis.
On April 2, 2024, an RFQ was posted for LMS and on -call LMS; 4 proposals were received;
and the selection committee recommended contracting with Desert Concepts based on
their qualifications and experience.
On June 18, 2024, Council awarded a 3-year contract to Desert Concepts for LMS, starting
FY 2024/25 through FY 2026/27, to be executed as 1-year terms based on satisfactory
performance by Desert Concepts. Staff seeks Council approval for the remainder of the
available contract term, from FY 2027/28 through FY 2030/31. In accordance with the
contract terms, per section 1240, subsection (C), the City may authorize a maximum
increase per FY, to be negotiated not to exceed the lesser of 5% or the annual CPI for
Riverside, San Bernardino, and Ontario.
In May 2025, staff executed Change Order No. 1 extending the initial term for 1 additional
year, through FY 2025/26, and increased compensation by 2.5%. Staff will execute Change
Order No. 2, included as Attachment 1, before the end of this FY to extend the term for 1
additional year, through FY 2026/27, and increase compensation by 3%.
Section 1240 of the contract specifically allows for extra work for landscape renovation and
improvements on an on -call, as needed basis.
Staff utilizes Desert Concepts, as a select source throughout the duration of the contract,
for additional LMS that are not included in the scope of the contracted LMS on an on -call,
as -needed basis, in accordance with Council -approved additional spending authority.
Council approved additional spending authority for Desert Concepts for FYs 2024/25 and
2025/26 for on -call LMS, beyond the contract's scope of work, at city -owned properties, on
as needed basis, which are detailed in the table above under the Fiscal Impact section of
this report. Staff requests Council approval for additional spending authority of up to
243
$300,000 for on -call LMS effective FY 2026/27 through FY 2030/31, which is the remaining
term of the contract, should it remain in effect. Any unused spending authority would remain
available and carryover each FY until expended or until the agreement expires, whichever
occurs first.
To date, on -call LMS has included landscape restoration of the perimeter landscape
around La Quinta Park, sports field improvements at La Quinta Park and the Sports
Complex, and plant and tree replacement at various city parks, Civic Center Campus, and
Pioneer Park.
ALTERNATIVES
Council may elect not to approval extending the contract and related compensation.
Prepared by: Dianne Hansen, Maintenance & Operations Superintendent
Approved by: Bryan McKinney, Public Works Director/City Engineer
Attachment: 1. Change Order No. 2 with Desert Concepts
244