HomeMy WebLinkAbout2026 LNL Property Services Project 2025-09 Dune Palms Mobile Estates Pool Abandonment - Change Ord 1ta QaLfra
GEM ofthe DESERT —
TO: Jon McMillen, City Manager
FROM: Bryan McKinney, P.E., Public Works Director/City Engineer
Via: Carley Escarrega, Public Works Specialist
DATE: July 15, 2026
RE: Contract Change Order No. 1
Dune Palms Mobile Estates Pool Abandonment
Project No. 2025-09
Attached for your signatures is one (1) electronic Contract Change Order No. 1 between LNL
Property Services and the City of La Quinta for the project referenced above.
DESCRIPTION OF CHANGE
This Contract Change Order allows for demo fencing, wall, cobble, AQMD permit, rentals, sawcut AC and footings
Total $9,315.00
This Contract Change Order allows for furnishing and install of fencing Total $7,440.00
Please sign and return the original to the City Clerk for final distribution.
REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE:
X Contract payments will be charged to the construction account number: 401-0000-60188-202509-CT
Authority to execute this agreement is based upon:
City Manager's signature authority provided under Resolution No. 2023-008 for budgeted expenditures
of $50,000 or less.
_X_ Housing Authority approval on January 20, 2026
The following Budget Summary is provided:
Project Budget
$ 105,000
Contract Amount
($ 60,490.50)
This Change Order No. 1
($ 16,755.00)
Balance Remaining
$ 27,754.50
As indicated, adequate funding is available.
78-495 Calle Tampico La Quinta, CA 92253 760.777.7000
CONTRACT: DUNE PALMS MOBILE ESTATES POOL ABANDONMENT
PROJECT #: 2025-09
CONTRACTOR: LNL PROPERTY SERVICES
PO BOX 9183
PAHRUMP, NV 89060
CONTRACT CHANGE ORDER NO. 1
Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the
herein described changes or do the following described work not included in the plans and
specifications for this Contract. Unless otherwise stated all work shall conform to the terms,
general conditions, and special provisions of the original Contract.
DESCRIPTION OF CHANGE
This Contract Change Order allows for Demo fencing, wall, cobble; AQMD Permit; Rentals;
Sawcut AC and Footings Total $9,315.00
This Contract Change Order allows for furnishing and install of fencing Total $7,440.00
Original Contract Amount
$ 60,490.50
Add This Change Order No. 1
$ 16,755.00
Revised Contract Total
$ 77,245.50
By reason of this contract change order the time of completion is adjusted as follows: - 0-
days added to contract time. The contract completion date shall be: July 7, 2026
-2"f& 51-1 Mcklniley
Submitted By: Ja a�,�y n (Jul 15, 2026 09 57 10 PDT) g,ya cKinney (Ju115, 20261 0313 PDT) Date:
Approved By: Jon McMillen, City ManaaerDate:
We, the undersigned Contractor, have given careful consideration to the change proposed
and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all
materials, perform all labor, except as may be noted above, and perform all services necessary
to complete the above specified work, and hereby accept as full payment the amount shown
above, which includes all direct and indirect overhead expenses for any delays.
Accepted By:
Q�
Title: OWNER
Contractor: LNL PROPERTY SERVICES Date: 7/14/2026
LNL PROPERTY SERVICES
951-712-8544
CHANGE ORDER 001
PROJECT NO.2025-09 DUNE PALMS MOBILE ESTATES
POOLABANDONMENT
DATE
1. DEMO AND DISPOSE OF 50 LN.FT OF METAL FENCING
2. DEMO AND DISPOSE OF 36 X 50' LN. FT.OF BLOCK PONY WALL
3. DEMO AND DISPOSE OF 4'6X74' X8" OF RUBBLE. 6.66 CU. YDS.
4. SAW CUT 74' OF AC
5 SAW CUT 12 HOLES IN AC FOR FENCE POST.
Note* The pony wall was resting on AC extending about 2' in from the
fence line. We will need to saw cut and remove AC to be able to drill
our post holes.
6 EQUIPMENT RENTAL
7 AQMD PERMIT
SUBTOTAL
P&O
TOTAL
6/22/2026
1250.00
2500.00
1300.00
500.00
500.00
.11 11
250.00
6900.00
2415.00
9315.00
LNL PROPERTY SERVICES
951-712-8544
CHANGE ORDER 002
PROJECT NO.2025-09 DUNE PALMS MOBILE ESTATES
POOLABANDONMENT
DATE 7/8/2026
Furnish and install50' of steel fence 6200
P&0 1240
Total $7,440.00