CLARIFICATION B
TO: All Prospective Bidders and Plan Holders
FROM: Bryan McKinney, Public Works Director/City Engineer
DATE: September 30, 2022
SUBJECT: City Project No. 2011-05, Federal Project No. BRNBIL (537), Dune Palms
Road Bridge Improvements
The following is a clarification to the project bid documents.
ADDITIONAL INFORMATION
Q1. Are the existing flows in the sewer lines known?
A. The 18-inch peak flow is modeled at 165 gpm and the 12-inch peak
flow is modeled at 221 gpm.
The Contractor is hereby notified; Clarification B does NOT need to be
acknowledged and initialed.
APPROVED:
Bryan McKinney,
Public Works Director/City Engineer
END OF CLARIFICATION B