HomeMy WebLinkAboutClarification B Project 2011-05 1 of 1 CLARIFICATION B TO: All Prospective Bidders and Plan Holders FROM: Bryan McKinney, Public Works Director/City Engineer DATE: September 30, 2022 SUBJECT: City Project No. 2011-05, Federal Project No. BRNBIL (537), Dune Palms Road Bridge Improvements The following is a clarification to the project bid documents.  ADDITIONAL INFORMATION Q1. Are the existing flows in the sewer lines known? A. The 18-inch peak flow is modeled at 165 gpm and the 12-inch peak flow is modeled at 221 gpm. The Contractor is hereby notified; Clarification B does NOT need to be acknowledged and initialed. APPROVED: Bryan McKinney, Public Works Director/City Engineer END OF CLARIFICATION B