HomeMy WebLinkAbout03_NBIL(537)_2011-05_15-B_RE Checklist
□
□
□
□
□
□
□
□
□
□
□
□ □
Local Assistance Procedures Manual Exhibit 15-B
Resident Engineer’s Construction Contract Administration Checklist
Exhibit 15-B: Resident Engineer’s Construction Contract Administration Checklist
This form is to be completed and signed by the local agency’s Resident Engineer and submitted with Local Agency’s Award Package
This form was created to help local agency Resident Engineers with the administration of the federal-aid projects. This list does not contain all the federal-aid requirements for administration of federal-aid projects. Resident Engineers are advised to review the Local Assistance Procedures Manual to be familiar with all the federal-aid requirements.
This form shall be used as reference if the local agency’s federal-aid project is subject to a Process Review.
Local Agency Name ________________________________________________________________
Federal-aid Project No. _______________________________________________________
1.Contract Staffing:
Names and titles of all staff assigned to the contract shall be in the contract files and shall be adequate (see LAPM Chapter 16, Section 16.2: Project Supervision and Inspection).
Date of Pre-construction Conference (Attendees list in contract file) _____________________
2.Authorization:
Date of the “Authorization to Proceed with Construction” _______________________________ (Shall be prior to date project was advertised)
Date the project was advertised ____________________________________________________
3.Contract Files:
Files shall be in an established order and separate from other contracts (see LAPM Chapter 16, Section 16.3: Maintaining Project Records). Check one of the following:
Index used on this project is Local agency’s standard for all jobs, or
For federal-aid jobs only.
4.Resident Engineer’s/Construction Inspectors Daily Diaries:
Shall be current, thorough and neat with detailed information on all work performed (see LAPMChapter 16, Section 16.8: Engineer’s Daily Reports).
5.Construction Records and Accounting Procedures:
Detail Estimate(s) and Finance Letter(s) are in the project files.
Amount of federal-aid funds encumbered for the project ________________________________
Program Supplemental Agreement is in the project files.
There shall be source documents supporting progress payments made to Contractor.
There shall be separate item sheets for each contract item paid.
Page 1 of 4
January 2021
□
□
□
□
□
□
□
□
□
□
□
□
□
□
□ □
I
Local Assistance Procedures Manual Exhibit 15-B
Resident Engineer’s Construction Contract Administration Checklist
There shall be a procedure for Administrative or Labor Compliance deductions.
Invoices to the State shall match progress payments made to the Contractor.
6.Contract Time:
A method shall be established to determine contract time (see LAPM Chapter 16, Section 16.6:
Tracking Contract Time).
7.Labor Compliance:
Certified payrolls shall be spot-checked against daily diaries and prevailing wages (see LAPM
Chapter 16, Section 16.9: Labor Compliance).
Local agency’s Labor Compliance Officer: ___________________________________________
8.EEO:
Maintain records to ensure EEO requirements are performed and documented in contract
record (see LAPM Chapter 16, Section 16.9: Equal Employment Opportunity).
Local agency’s EEO Compliance Officer: _______________________________________
9.EEO/Wage Rate/False Statements Posters:
Federal posters shall be posted for every worker to see at, or near, the contractor’s office at the
construction site or at the workers central gathering point.
10.Employee Interviews:
There shall be employee interviews conducted (see Exhibit 16-N).
11.OJT: (Refer to Chapter 12, Section 12.8: Federal Contract Requirements)
Is the job less than 100 working days? Yes No
If yes, proceed to Item #12. If No, answer the questions below.
What is the total dollar amount of the items listed in Table 12-2: __________
What is the required number of trainees for this contract? _________
Documentation will be retained in project files to account for the apprentices on the job.
12.DBE:
DBE Contract Goal Percentage Exhibit 9-D: ____________________
Local Agency’s DBE Liaison Officer: __________________________
Verified that a copy of the completed Local Agency Bidder DBE Commitment (Construction
Contracts) (Exhibit 15-G) has been submitted to the DLAE within 30 days of contract award.
Contractor has been provided “Monthly DBE Trucking Verification” Form (see LAPM Chapter
16, Exhibit 16-Z1)
Contractor has been provided the monthly Exhibit 9-F: DBE Running Tally of Payments
Page 2 of 4
January 2021
□
□
□
□
□
□
□
□
□
□
□
□
□
□
□ □
Local Assistance Procedures Manual Exhibit 15-B
Resident Engineer’s Construction Contract Administration Checklist
13. CCOs/CLAIMs:
A CCO approval process shall be established. For NHS projects, major change orders will be approved by DLAE prior to performance of work (see LAPM Chapter 16, Section 16.10: Change Orders).
There shall be a list of the approved CCOs.
All CCOs shall note federal-aid eligibility or not.
Pending claims to be identified and documentation in contract file.
14. Traffic Safety in Highway and Street Work Zones:
Traffic Control Plan (TCP)/Traffic Management Plan (TMP) in the PS&E? Yes No
(see LAPM Chapter 16, Section 16.15: Traffic Safety in Highway and Street Work Zones)
Comments:
Responsible Person _________________________________ (if not the RE)
Local Agency shall field review the project to see that the TCP agrees with the actual conditions.
Local Agency shall be analyzing construction work site accidents for the purpose of correcting deficiencies which might be found to exist on these projects and to improve the content of futureTCPs.
15. Materials Files:
The Quality Assurance Program (QAP) is in the project files (see LAPM Chapter 16, Section 16.11: Quality Assurance Program).
There shall be procedures for and filing of: (if appropriate)
Notice of Materials to be used
Certifications of Compliance
“Buy America” Requirements
Acceptance Sampling and Testing Reports shall be in the files.
There shall be a “Summary Log” of tests.
Frequency tables shall be used.
Failed tests shall be documented in the files with cross references to re-tests.
Resident Engineer shall review all test reports.
Page 3 of 4
January 2021
□
□
□
□
□
□
____________________________________
Local Assistance Procedures Manual Exhibit 15-B
Resident Engineer’s Construction Contract Administration Checklist
16.Environmental
The approved NEPA document is in the project files.
The construction project shall adhere to the mitigation requirements in the approved NEPAdocument.
17.For Projects on the State Highway System
A Caltrans Encroachment Permit has been issued.
Local Agency shall comply with State’s Representative's oversight requirements.
Local Agency’s Resident Engineer
Check Appropriate Box:
Agency Employee
Consultant
Date: ________________________
If a Consultant, please sign below
Local Agency’s person in “Responsible (Local)Charge” if Resident Engineer is a Consultant.
Signature Date
Distribution: 1) Local Agency Project File
2)DLAE (please put on first page only)
Page 4 of 4