HomeMy WebLinkAbout2022_11_2011-05_Backup List2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
La Quinta BRIDGE NO. 00L0070, Dune Palms Road OVER the Coachella Valley Stormwater Channel (Whitewater River). Replace 3-Lane Low-Water
Crossing with 4-Lane Bridge. (This project must appear in the RTP.)
Fund Source Summary:
PE
R/W
Total
545,000
2,295,000
CON
Total
17,966,000 17,966,000
1,750,000
773,000 1,318,000
773,000 17,966,000 21,034,000
1,750,000
Phase Summary:
Fed $
Local AC
Local Match
Total
263,237
2,295,000
LSSRP Bond
Total
684,337 10,000,000 5,905,300 18,621,400
88,663 2,060,700 -0 2,412,600
15,905,300 -10,000,000 -5,905,300
773,000 17,966,000 21,034,000
2,031,764
BRLKS-5433(014)Fed Proj:
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
PE Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
200,725
1,750,000
LSSRP Bond
Total
1,549,275
200,725
1,750,000
1,549,275
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 HBP 1,549,275PE1,549,275
Local Match 200,725200,725
Total:1,750,000Fed. Reimb. Rate:88.53%10/9/2012 Linda Newton: New eligible project.
Caltrans, Division of Local Assistance Page 1510/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
R/W Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
62,512
545,000
LSSRP Bond
Total
684,337 1,166,825
88,663 151,175
773,000 1,318,000
482,489
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 HBP 684,337R/W -684,337
Local Match 88,663-88,663
Total:Fed. Reimb. Rate:88.53%8/24/2020 Bobby Zezoff: LAPG 6-D approved and funds moved to 20/21 due to out of funds at approval date.
4024 HBP 684,337R/W 684,337
Local Match 88,66388,663
Total:773,000Fed. Reimb. Rate:88.53%10/9/2019 Eduardo Moreno-Castaneda: Not ready to ad within 6 months. Additional R/W funding in FFY 19/20 as submitted in
September 2019 HBP Survey.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate: 88.53%10/10/2018 Eileen Crawford: Not ready to ad within 6 months. RW funds moved from FFY 17/18 to 18/19. Funds not obligated, moved
to next fiscal year. 7/27/2021 DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2018/19-23/24 to 2020/21-25/26. This does
not impact funds in the current FTIP cycle.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%12/5/2019 Linda Newton: Fund line has not failed to deliver.
10/19/2018 DLA-Admin: Fund line failed to deliver.
9/15/2017 Vu Ngo: Not ready to ad within 6 months. RW funds moved from FFY 19/20 to 17/18. As requested in September 2017
Survey. 7/27/2021 DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2018/19-23/24 to 2020/21-25/26. This does not impact
funds in the current FTIP cycle.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%10/9/2016 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 17/18 to 19/20. NEPA not yet clear. 7/27/2021
DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2018/19-23/24 to 2020/21-25/26. This does not impact funds in the
current FTIP cycle.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%10/21/2015 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 16/17 to 17/18. NEPA not yet clear. 8/25/2019
DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2016/17-21/22 to 2018/19-23/24. This does not impact funds in the
current FTIP cycle.
Caltrans, Division of Local Assistance Page 1610/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%10/1/2015 Albert Vergel de Dios: Not ready to ad within 6 months. RW funds moved from FFY 17/18 to 16/17. As requested in
September 2015 Survey. 8/25/2019 DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2016/17-21/22 to 2018/19-23/24.
This does not impact funds in the current FTIP cycle.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%3/18/2015 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 15/16 to 17/18. NEPA not yet clear. 8/25/2019
DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2016/17-21/22 to 2018/19-23/24. This does not impact funds in the
current FTIP cycle.
4024 HBP 482,489R/W 482,489
Local Match 62,51262,512
Total:545,000Fed. Reimb. Rate:88.53%10/9/2012 Linda Newton: New eligible project.
CON Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
10,000,000 5,905,300 15,905,300
2,060,700 -0 2,060,700
15,905,300 -10,000,000 -5,905,300
17,966,000 17,966,000
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 Local AC (HBP)5,905,300CON -5,905,300
Local Match 765,094 -765,094
Total:Fed. Reimb. Rate:88.53%
New!
10/24/2022 DLA-Admin: CON funds split between FFY 22/23 and 23/24 to reflect LAPG Chapter 6 policy for Mid-Level projects.
4024 HBP -5,905,300CON 5,905,300
Local Match -765,094 765,094
Total:Fed. Reimb. Rate:88.53%
New!
10/24/2022 DLA-Admin: CON funds split between FFY 22/23 and 23/24 to reflect LAPG Chapter 6 policy for Mid-Level projects.
4024 HBP 7,952,650CON -7,952,650
Local Match 1,030,350 -1,030,350
Total:Fed. Reimb. Rate:88.53%
New!
10/20/2022 DLA-Admin: CON AC conversion moved from FFY 23/24 to FFY 22/23.
4024 Local AC (HBP)-7,952,650CON 7,952,650
Local Match -1,030,350 1,030,350
Total:Fed. Reimb. Rate:88.53%
New!
10/20/2022 DLA-Admin: CON AC conversion moved from FFY 23/24 to FFY 22/23.
4024 Local AC (HBP)-7,952,650CON -7,952,650 15,905,300
Local Match -1,030,350 0-1,030,350 2,060,700
Total:0Fed. Reimb. Rate:88.53%
New!
10/13/2022 DLA-Admin: Revise CON AC Conversion as requested in 2022 HBP Annual Status.
Caltrans, Division of Local Assistance Page 1710/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 HBP 7,952,650CON 7,952,650 -15,905,300
Local Match 1,030,350 -01,030,350 -2,060,700
Total:-0Fed. Reimb. Rate:88.53%
New!
8/18/2022 Matt Sapp: CON funds moved from FFY 25/26 to FFY 22/23 and 23/24. Action taken by request of City through Annual Status
update. City advertised 8/12/2022.
4024 Local AC (HBP)15,905,300CON -15,905,300
Local Match 2,060,700 -2,060,700
Total:Fed. Reimb. Rate:88.53%11/9/2021 Linda Newton: Add AC to CON in FFY 21/22 project as requested by local agency.
4024 HBP CON -15,905,300 15,905,300
Local Match -2,060,700 2,060,700
Total:Fed. Reimb. Rate:88.53%10/28/2021 DLA-Admin: Ready to Advertise. CON funds moved from FFY 24/25 to 25/26. Action taken to financially constrain the FTIP
(PUSH). Attempt will be made to program this project in year shown.
4024 HBP CON -15,905,300 15,905,300
Local Match -2,060,700 2,060,700
Total:Fed. Reimb. Rate:88.53%10/28/2021 DLA-Admin: Ready to Advertise. CON funds moved from FFY 23/24 to 24/25. Action taken to financially constrain the FTIP
(PUSH). Attempt will be made to program this project in year shown.
4024 HBP -7,952,650CON 7,952,650
Local Match -1,030,350 1,030,350
Total:Fed. Reimb. Rate:88.53%10/28/2021 DLA-Admin: Ready to Advertise. CON funds moved from FFY 22/23 to 23/24. Action taken to financially constrain the FTIP
(PUSH). Attempt will be made to program this project in year shown.
4024 HBP -7,952,650 7,952,650CON
Local Match -1,030,350 1,030,350
Total:Fed. Reimb. Rate:88.53%10/27/2021 DLA-Admin: Ready to Advertise. CON funds moved from FFY 21/22 to 22/23. Action taken to financially constrain the FTIP
(PUSH). Attempt will be made to program this project in year shown.
4024 HBP 7,952,650CON 7,952,650
Local Match 1,030,350 -01,030,350
Total:-0Fed. Reimb. Rate:88.53%10/15/2021 DLA-Admin: Ready to Advertise. CON funds moved from FFY Beyond to 21/22. As requested in September 2021 Status.
-15,905,300
-2,060,700
4024 Local AC (HBP)-15,905,300CON
Local Match -2,060,700
Total:Fed. Reimb. Rate:88.53%8/23/2021 DLA-Admin: Remove AC from CON phase.
15,905,300
2,060,700
4024 Local AC (HBP)15,905,300 -15,905,300CON
Local Match 2,060,700 -2,060,700
Total:Fed. Reimb. Rate:88.53%9/23/2020 Eduardo Moreno-Castaneda: Moved AC CON funds from FFY 21/22 to 20/21 as requested in 2020 September Survey.
4024 HBP 2,435,460CON
Local Match 315,540
Total:2,751,000Fed. Reimb. Rate:88.53%10/9/2019 Linda Newton: Add CON cost increase as submitted in September 2019 HBP Survey.
2,435,460
315,540
Caltrans, Division of Local Assistance Page 1810/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 Local AC (HBP)15,905,300CON
Local Match 2,060,700
Total:Fed. Reimb. Rate:88.53%10/9/2019 Linda Newton: Add AC to CON in FFY 21/22.
-15,905,300
-2,060,700
4024 HBP -13,469,840CON
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2018 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 21/22 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP -13,469,840 13,469,840CON
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2018 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 20/21 to 21/22. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP 13,469,840CON-13,469,840
Local Match 1,745,161-1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2018 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to 20/21. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/25/2018 Matt Sapp: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 19/20. As requested in September 2018
Survey.
-13,469,840
-1,745,161
4024 HBP -13,469,840CON
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2017 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 21/22 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP -13,469,840 13,469,840CON
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2017 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 20/21 to 21/22. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP 13,469,840CON-13,469,840
Local Match 1,745,161-1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2017 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to 20/21. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/15/2017 Vu Ngo: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 19/20. As requested in September 2017
Survey.
-13,469,840
-1,745,161
4024 HBP CON -13,469,840
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2016 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
Caltrans, Division of Local Assistance Page 1910/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/20/2016 Albert Vergel de Dios: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 19/20. As requested in
September 2016 Survey.
-13,469,840
-1,745,161
4024 HBP CON -13,469,840
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/29/2015 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP CON
Local Match
Total:Fed. Reimb. Rate:88.53%10/29/2015 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 18/19 to 19/20. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown. 7/27/2021 DLA-Admin: Fundline zeroed out due
to FTIP cycle migration: 2018/19-23/24 to 2020/21-25/26. This does not impact funds in the current FTIP cycle.
4024 HBP CON
Local Match
Total:Fed. Reimb. Rate:88.53%10/29/2015 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 17/18 to 18/19. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown. 7/27/2021 DLA-Admin: Fundline zeroed out due
to FTIP cycle migration: 2018/19-23/24 to 2020/21-25/26. This does not impact funds in the current FTIP cycle.
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%10/1/2015 Albert Vergel de Dios: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 17/18. As requested in
September 2015 Survey.
-13,469,840
-1,745,161
4024 HBP CON -13,469,840
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/28/2014 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 17/18 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/3/2014 Albert Vergel de Dios: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 17/18 per September Survey.
-13,469,840
-1,745,161
4024 HBP 13,469,840CON
Local Match 1,745,161
Total:15,215,000Fed. Reimb. Rate:88.53%10/9/2012 Linda Newton: New eligible project.
13,469,840
1,745,161
Caltrans, Division of Local Assistance Page 2010/25/2022, 8:37 AM Det2 FL4 SmlTxt