Guidelines on Preparing Engineer's Estimate, Bid Reviews and Evaluation
October 7, 2021
Notice
The U.S. Government does not endorse products or manufacturers. Trademarks or
manufacturer’s names appear in this document only because the Government
considers them essential to the objective of the document. The document includes them
for informational purposes only and the Government does not intend them to reflect a
preference, approval, or endorsement of any one product or entity.
Non-Binding Contents
Except for the statutes and regulations cited within, the contents of this document do not
have the force and effect of law and are not meant to bind the public in any way. This
document is intended only to provide clarity to the public regarding existing
requirements under the law or agency policies.
Quality Assurance Statement
The Federal Highway Administration (FHWA) provides high-quality information to serve
Government, industry, and the public in a manner that promotes public understanding.
The FHWA uses standards and policies to ensure and maximize the quality, objectivity,
utility, and integrity of its information. The FHWA periodically reviews quality issues and
adjusts its programs and processes to ensure continuous quality improvement.
Par.
1. Purpose
2. Background
3. Pre-Bid Considerations
4. Preparing Final Design Engineer’s Estimates
5. Bid Analysis and Contract Award
6. Post-Award Reviews
7. Suspension / Debarment
8. Special considerations for Design-Build (D-B) and Construction Manager / General
Contractor (CM/GC) Projects
Page 2 of 25
1. PURPOSE
a. To provide guidance for improving pre-bid, bid review and evaluation policies and
procedures.
b. To outline recommended procedures for preparing the engineer’s estimate for
reviewing bids prior to concurrence in award.
c. To improve competitive bidding procedures.
d. To ensure that the final Engineer’s Estimate supports the financial obligation in the
project authorization between FHWA and the STA [23 CFR 630.106]
2. BACKGROUND
A State Transportation Agency’s (STA) procedure for soliciting and awarding
construction contracts are an important part of the competitive bidding process. To
ensure a competitive contracting environment, the STA has the option to use either
prequalification or post-qualification procedures. In either case, the procedures must
support full and open competition by ensuring fairness in the pre-bid solicitation
process and post award review of construction bids [23 CFR 635.110(b)]. In addition,
the STA’s procedures for developing a reliable engineer’s estimate are critical to the
success of such programs. The engineer’s estimate should reflect a fair and
reasonable cost of the project in sufficient detail to provide an accurate estimate of
the financial obligations to be incurred by the State and FHWA and permit an effective
review and comparison of the bids received.
This guideline replaces Guidelines on Preparing Engineer’s Estimate, Bid Reviews
and Evaluation, dated January 20, 2004. This guideline is intended to serve as a
reference for STAs who are interested in improving their bid review and evaluation
procedures. Each STA may consider this guideline in developing its own procedures.
State contracting policies and procedures differ, and therefore, the topics in this
Guideline should be considered in light of each State’s unique policies and
procedures.
Except where specifically noted, this guideline applies to the traditional design-bid-
build project delivery system. It does not apply to Design-Build (D-B) contracting,
Construction Manager / General Contractor (CM/GC) contracting, or Indefinite
Delivery / Indefinite Quantity (ID/IQ) contracting. See Section 8 for a discussion of
specific estimating issues regarding D-B and CM/GC contracting.
3. PRE-BID CONSIDERATIONS
Page 3 of 25
a. Contractor Prequalification
In its 1981 Suggested Guidelines for Strengthening Bidding and Contract Procedures,
the American Association of State Highway and Transportation Officials (AASHTO)
defines prequalification as a means of predetermining job experience and work
capacity and to identify individuals from whom the agency may accept a bid. In
general, contractor prequalification is used to help determine the quantity and type of
work a firm is capable of undertaking. Normally the firm's resources, its financial
assets, work experience, and its staffing capability should be identified for it to
become prequalified. Some STAs that do not require prequalification find it
necessary to collect some information via a financial statement or some other
abbreviated process. These STAs do not specify the type of work or limit the size of
project a firm may bid upon because they feel prequalification may unduly restrict
competition. Other STAs do not prequalify but instead rely on the contractor’s ability
to provide a performance bond.
While the FHWA does not specify the STA’s procedures for qualifying and licensing
contractors, the Division Administrator must determine that any such procedures do
not restrict competition or operate to prevent the submission and consideration of a
bid submitted by any responsible contractor. [23 CFR 635.110(b)]
Prequalification has been identified by some STAs as a useful tool for gathering
pertinent information on the intricate management details of a contractor's firm. In the
event of a conviction for a crime such as bid rigging, such information proves useful
as an aid in determining the appropriate sanctions for the firm and the individuals
involved. Another possible use would be to determine the relationship of firms bidding
on a project.
Specific information that should be collected from a firm includes the following:
financial resources, principal individuals in the firm (anyone having a 10 percent or
more interest in the firm), all affiliates or subsidiary companies including material
sources, available equipment, work experience, individuals and organizations that
have control or influence over the firm's bidding procedures, and whether the firm has
ever been suspended or debarred from bidding and the related circumstances.
The instructions for completing the work experience section (of the pre-qualification
form) should require that the firm identify all projects for which it was the prime
contractor and those on which it worked as a subcontractor during at least the past
two years as well as the contracting agency for those projects. Also, the contracting
agency should describe the penalties for making false statements in the pre-
qualification process.
b. Non-collusion Statement
According to 23 CFR 635.112(f), STAs are required to include provisions in the
bidding proposals that require all bidders to include a non-collusion statement with
their bids. All non-collusion certifications shall be retained by the STA in accordance
Page 4 of 25
with the retention requirements of 2 CFR 200.334, which is three years after the
FHWA’s payment of the STA’s final project voucher.
c. Standard Specifications
All STAs should have standard specifications that address the issue of evidence of
collusion among bidders. STA specifications that currently address this item
generally specify that the STA may determine that the bidder is not responsible and
reject their proposal based on evidence of collusion. In addition to rejection of a firm's
proposal, the specification should advise that collusive bidding is a violation of the law
and could result in criminal prosecution, civil damage actions, and State and Federal
administrative sanctions.
d. Plan Holders Lists
Confidentiality of the plan holders list (those firms that have taken out plans and bid
proposal documents) has both advantages and disadvantages with the end goal of
maximizing competition.
Advantage - disclosing the plan holders list allows potential material suppliers and
subcontractors (including DBEs) to know which firms to contact about upcoming
projects. However, due to the nature of competitive bidding with suppliers and
subcontractors providing last-minute quotes to bidders, open communication is critical to
the completeness of bids. Further, because the bidder performs the contract work itself
or using subcontracts, the burden lies with the bidder to determine which other firms to
work with on a project. Unless the project has new or unusual material or construction
requirements, most bidders are likely aware of the available subcontractors and
potential material suppliers. Therefore, the bidder is generally the one seeking potential
subcontractors, especially if Disadvantaged Business Enterprise goals are included in
the proposal. Another advantage of not disclosing the plan holders list is that bidders
will submit what is believed to be a competitive bid based upon the company's own
individual circumstances. This is especially important for projects where there would be
limited competition.
Disadvantage - With the availability of bid tabulation information and plan holders lists
on the Internet, the potential for bid collusion is higher than in previous years when such
information was not readily available. To create the most competitive environment for
potential bidders, a firm should not be aware of the identity of the other potential
bidders.
A 2017 survey by the AASHTO Technical Committee on Cost Estimating found that
most states publish a plan holders list on their web site or make this information
available upon request. To discourage bid collusion, FHWA recommends that STAs not
publish or release information regarding plan holders. If STAs need to release this
information to be consistent with their own policies, consideration should be given to
waiting until there are at least three potential bidders for a project.
Page 5 of 25
e. Competition
Competition for projects by bidders is an integral part of a successful construction
program. An effort should be made by the contracting agency to maximize the
competition. An AASHTO 2009 survey by the Construction Subcommittee and the
AASHTO Practical Guide to Cost Estimating, 1st Edition (2013) provide several
strategies for improving bid competition:
• Advertise widely enough to advise those potential bidders interested in the type
of work and size of project involved.
• Based on the complexity of the project, consider using an extended
advertisement period.
• Consider the project's estimated cost and size to maximize the number of
bidders. The size normally varies in each State depending on the makeup of the
construction industry. In some situations, it may be desirable to divide the
project into several smaller contracts to foster competition. Alternatively, it may
be desirable to lump smaller contracts into a bigger project to increase
competition.
a. Jobs should be allowed to be bid individually or in combination.
b. Bundle projects in proposals to make them as attractive as possible.
Bundling strategies include matching contract size to contractor
capabilities, seeking to increase unit quantities of major cost items so that
contractors can reduce their fixed costs such as mobilization and traffic
control across more items, bundling projects by the type of work and
geographic location, and combining projects that only receive one bid with
other similar projects.
c. To accommodate both large and small contractors, allow contractors to tie
contracts for bidding purposes to encourage more competitive bid prices.
Contractors may limit the number of tied contracts they bid based on their
bidding capacity.
• Monitor contractor responsiveness to timing of letting to identify seasonal effects
on bids.
• Coordinate lettings based on availability and capacity of contractors. Contractors
may limit the number of projects they bid if an STA includes many similar
projects.
• Consider rejecting non-competitive bids and re-advertising.
• Evaluate using alternate materials (e.g., concrete paving, asphalt paving,
recycled materials, etc.).
• Balance work types in each letting.
• Consider including price adjustment clauses for certain materials to reduce
contractor's risk.
• Allow more time between advertisement and bid opening.
• Conduct more frequent lettings.
• Update construction cost estimate data.
• Consider using state aggregate sources where industry sources are not
competitive.
Page 6 of 25
f. Escrow of Bid Documents
FHWA recommends that STAs consider escrowing bid documents where it is
administratively feasible to do so. Section 103.08 – “Escrow of Bid Documentation” of
the AASHTO Guide Specifications for Highway Construction, 10th Edition (2020)
provides a sample specification if an STA wishes to make this a requirement.
g. Price Adjustment Clause
Commodity price escalation clauses, also referred to commodity price adjustment
clauses in a contract are intended to mitigate the risks related to price changes of
specific items or materials due to supply and demand. A STA may also use the term
‘price adjustment clause’ when referencing the impact of construction quality on the
price a STA pays for a final product. The use of material price indices in contract price
adjustment clauses can be an effective method of sharing the risks of material price
fluctuations for both the industry and contracting agencies. The AASHTO Committee on
Construction’s 2019 Survey on the Use of Price Adjustment Clauses for Inflation
provides the most recent summary of State practices regarding price adjustment
clauses.
FHWA does not participate in retroactive price adjustments. If price adjustment clauses
are not included in the bid proposal, FHWA cannot approve the use of Federal funds for
retroactive price adjustment clauses subsequently added by change order. See
FHWA’s letter to Maryland SHA dated April 8, 2004, for additional information. FHWA
Technical Advisory TA 5080.3 provides additional guidance on the use of price
adjustment clauses.
h. Inflation
For large projects lasting several years, STAs should consider the impacts of inflation.
Inflation affects the total contract cost, rather than specific items within it. Additional
information on inflation can be found in AASHTO Practical Guide to Cost Estimating,
Chapter 6 – Inflationary Considerations.
i. Contingencies
The AASHTO Practical Guide to Cost Estimating (2013) defines contingency as “An
estimate of costs associated with identified uncertainties and risks, the sum of which is
added to the base estimate to complete the project cost estimate.” The Practical Guide
provides detailed guidance on how agencies may incorporate contingencies in planning,
scoping, design and final design estimates (see Practical Guide Sections 1.2.2 and
3.3.7 for discussions on this topic).
Double-counting uncertainties and risks can lead to inaccurate estimates. Accepted
practice is to explicitly identify contingency as a line item in the estimate. Intentional,
Page 7 of 25
hidden contingencies, such as “padding” a line item based on experience, should be
avoided. Unintentional contingencies, such as estimator bias, are more difficult to
identify and may require independent estimate review.
The Practical Guide provides detailed information on how risk and contingency are
established for projects of varying complexity in Chapter 5 - Risk Based Cost Estimates.
Additional resources include Probabilistic Risk-based Estimating for Highway Project
Cost and Schedule, course No. 134205, which provides a detailed overview of the
concepts and recommended process to determine reliability-based estimates of
contingency.
4. PREPARING FINAL DESIGN ENGINEER’S ESTIMATE
The critical review of any bid depends on the reliability of the engineer’s estimate it is
being compared to. The engineer’s estimate is the contracting agency’s benchmark for
analyzing bids and is an essential element in the project approval process. STAs
should devote attention to preparation of engineer’s estimates using experienced staff
that apply the same level of detail as the contract bidders. STAs are encouraged to
provide sufficient resources and training opportunities for their staff. Available
resources include AASHTO’s Practical Guide to Cost Estimating (2013) and NCHRP
Report 574 “Guidance for Cost Estimation and Management for Highway Projects
During Planning, Programming, and Preconstruction” (2007). FHWA-NHI Course No.
134205; Probabilistic Risk-based Estimating (PRBE) for Highway Project Cost and
Schedule, provides additional guidance on how to develop reliability-based estimates
and emphasizes a scalable process.
The engineer’s estimate should reflect the amount the contracting agency considers fair
and reasonable and is willing to pay for performance of the contemplated work. Under-
estimating may cause project delays while additional funding is arranged to meet the
contract costs. On the other hand, over-estimating causes inefficient use of funds that
could be used for other projects. The contracting agency should anticipate changing
market conditions and factor the competitive bidding environment into the engineer’s
estimate.
a. Estimating Techniques
The AASHTO Practical Guide to Cost Estimating (2013) identifies four basic techniques
to develop estimates of project costs: Conceptual estimating, historical bid-based
estimates, cost-based estimates, and risk-based estimates. Conceptual estimating, or
parametric estimating, is used to support development of planning or early scoping
phase estimates when minimal information is known. This technique will not be
discussed in this guidance since it does not apply to the final design stage of project
development. The other estimating techniques are discussed below.
Historical bid-based estimating technique matches estimates of line-item quantities
from project plans to appropriate historical unit bid prices or average historical unit bid
Page 8 of 25
prices. Under this method, historical bid data are adjusted for project conditions (i.e.,
project location, size, quantities, etc.) and the general market conditions (i.e. competitive
bidding environment). The historical bid-based approach is a cost-effective method to
develop the engineer’s estimate. However, solely relying on historic data may not be
appropriate when the data is based on a non-competitive bidding environment. A file of
previous unit bid prices should be maintained according to type, size, and location of
project. Upcoming projects should be matched to the most recent projects to develop
base prices for estimating the value of the unit prices.
The historical bid-based method requires the least amount of time and personnel to
develop and produces an adequate estimate for use in budgeting/programming, if
competitive bid prices are used to build the estimate. Further adjustment of the base
prices should be considered based upon the ages of the similar projects, but past
inflation rates should not be projected into the future unless based on circumstances
which can be reasonably expected to occur, such as labor rate increases through labor
negotiations and known material price increases. Where the magnitude and timing of
future increases are uncertain and would present a significant risk, contractors tend to
bid additional cost to cover these risks, regardless of whether they occur or not. As
such, the inclusion of price adjustment clauses in project contracts may be a better
alternative.
Cost-based estimating technique takes into consideration factors related to actual
performance of the work (i.e. the current cost of labor, equipment, and materials;
sequence of operations; production rates; and a reasonable value of overhead and
profit). The estimator should have a good working knowledge of construction methods
and equipment to use this approach. The estimator should also have resources
available for determining production rates from actual work performed by the contracting
industry on similar type projects as well as resources for determining current
construction methods and equipment. While adjustments for current market conditions
are important, this approach typically produces an accurate estimate and is useful in the
bid review process in aiding the decision to award or reject the project. However, this
method may be more time consuming and may not be practical for all projects.
Combination Historical bid-based and Cost-based Techniques This approach
combines the use of historical bid and cost-based data. Most projects contain a small
number of items that together comprise a significant portion (e.g. 75 percent) of the total
cost. These major contract items may include Portland cement concrete pavement,
structural concrete, structural steel, asphalt concrete pavement, embankment, or other
major items of work within the contract. To the extent practical, STAs should collect
information on local market prices of materials, equipment manufacturers, dealers, and
rental companies, and material suppliers to obtain current cost information on a regular
basis. Davis-Bacon prevailing wage rates on Federal-aid contracts could be
incorporated to provide labor costs as determined by Department of Labor. Current
material costs are obtained from local approved sources. Equipment costs can be
obtained through rental companies or equipment dealers based on a reasonable
depreciation schedule. The remaining items can be estimated based on historical
prices and adjusted as appropriate for the specific project.
Page 9 of 25
Risk-based estimating (RBE) technique applies risk identification and uncertainty
analysis techniques to forecast project contingency. Estimators apply the RBE
technique most frequently in the planning, scoping, and early design phases where
uncertainty and project risks are greatest. However, it may also be used to develop the
final design engineer’s estimate and construction costs and validate project contingency
for remaining elements of risks (market, archeological, unsuitable soil, etc.). The
AASHTO Practical Guide to Cost Estimating (2013) provides the following
recommendations to apply the RBE technique based on project complexity.
Project Complexity Recommended Methods to Establish Risks and
Set Project Risk Contingency
1. Non-complex Develop list of risks and use a top-down
deterministic percentage of project cost to estimate
contingency
2. Moderate complex projects Include the use of more rigorous risk identification
methods and a top down deterministic percentage
estimation of contingency supplemented with a
bottom up deterministic estimate of specific
contingency line items.
3. Most complex i.e. major
projects
Include a facilitated determination of project risks
and a probabilistic determination of cost and
schedule completion.
Some STAs have implemented a scalable RBE process that matches the level of effort
to the cost of the project.
Probabilistic Risk-based Estimating for Highway Project Cost and Schedule, FHWA -
NHI Course No. 134205, provides additional guidance on how to develop reliability-
based estimates and emphasizes a scalable process.
b. Documentation of the Final Engineer’s Estimate
The STA’s request to obligate Federal-aid funds must be supported by a documented
cost estimate that is based on the State's best estimate of costs.(23 CFR 630.106(a)(3))
The STA is also required to maintain a process to adjust project costs estimates (23
CFR 630.106(a)(4)). Having a documented process is a critical factor to achieving
consistency in the estimation of project costs and review of bids received. A
documented process increases the STAs ability to provide accurate and timely updates
that reflect current estimates. The cost estimating method used by the contracting
agency should be documented, up to date, and readily available to staff.
Documentation of the estimating procedures enhances the consistent development and
application of the engineer’s estimate and provides a benchmark for process
improvements. The AASHTO Practical Guide to Cost Estimating (2013) is a valuable
resource for the development of cost estimating guidance.
Page 10 of 25
c. Confidentiality of the Engineer’s Estimate
For this guideline, the term “confidentiality of the Engineer’s Estimate” means the
Engineer’s Estimate is not released to the public. State laws, policies, procedures, and
practices regarding the term “confidentiality” vary.
Some STAs have a policy to keep the estimate confidential from public disclosure even
after the project has been constructed and opened to traffic. In general, public
procurement should be a transparent process; however, the engineer’s estimate should
not be disclosed prior to the award of the contract as there are few, if any, perceived
advantages to the contracting agency in doing so. This is especially important in cases
where the contracting agency anticipates minimal competition or a single bid for
construction.
If information regarding the engineer’s estimate were available, potential bidders would
know the price the contracting agency is willing to accept and in cases where
competition is limited, the STA may be receiving inflated bids. The industry already has
access to preliminary estimates for construction that are required by the State
Transportation Improvement Program or Transportation Improvement Program. See,
e.g., 23 CFR 450.218(i)(2). Some STAs also have policies requiring project
classification information regarding the relative size of the contract so that contractors
will know if their bonding capacity is adequate for bidding purposes. For example, a
range could be established as follows:
Project Classification Project Cost
A $ 0 - $100,000
B $100,000 - $250,000
C $250,000 - $500,000
D $500,000 - $1,000,000
E $1,000,000 - $2,500,000
F $2,500,000 - $5,000,000
G $5,000,000 - $10,000,000
H $10,000,000 - $15,000,000
I $15,000,000 - $25,000,000
J $25,000,000 or greater
A policy of providing a specified dollar amount for a bid bond could indicate the amount
of the estimate. This procedure should be revised to specify a percentage of the bid
submitted, thus maintaining the confidentiality of the estimate.
d. Consistency of the Engineer’s Estimate
FHWA recommends that STAs establish measures to monitor the consistency and
reliability of the estimating process and identify appropriate revisions when market
conditions change. Estimate consistency relies on the estimator using all the available
resources to create a fair and reasonable value for the proposed project. STAs should
Page 11 of 25
assess the performance of the engineer’s estimate to determine if opportunities exist to
increase the reliability of the engineer’s estimate for contract award.
Previous editions of this guidance recommended a performance measure based on the
engineer's estimate being within ±10 percent of the low bid for at least 50 percent of the
projects. If an STA elects to use a 10-percent threshold, FHWA recommends that the
engineer’s estimate be used as the base (or divisor) in any comparison (i.e. the
difference between the bid amount and the engineer’s estimate divided by the
engineer’s estimate).
Trend analysis is typically used to monitor the performance data for changes over time.
This allows the STA to determine when changes are necessary in the estimating
process (e.g. possibly due to inflationary pressures).
Attachment A provides a review guide for assessing a contracting agency’s procedures
for developing the engineer’s estimate.
Attachment B provides a list of performance data that could be used to monitor the
health and performance of an STA’s letting, award, and contract administration
processes. FHWA Division Offices and State DOTs performing risk analyses of their
programs are encouraged to consider the data listed in Attachment B.
5. BID ANALYSIS AND CONTRACT AWARD
The engineer’s estimate should be a fair and reasonable value for the work to be
performed. Specialized highway construction work should be evaluated on a case-by-
case basis. The following guideline discusses circumstances where an apparently
excessive bid may be justified as a basis for award:
a. Assessing Competition
The criteria used in an initial evaluation of the degree of competition for a given project
will depend on many factors. In evaluating the bids for a project, the following factors
should be considered in performing a preliminary assessment as to whether competition
was adequate:
• number of bids,
• difference between low bid and engineer’s estimate,
• difference between low bid and other bidders,
• spread or variation of all bids,
• type of project and the anticipated competition for this type of work,
• time of year,
• bidding opportunities for similar work with other nearby agencies or jurisdictions
(e.g. resurfacing work),
• bidding opportunities with neighboring agencies that may result in temporary
material shortages (e.g. large steel fabrication contracts);
Page 12 of 25
• relative availability of subcontractors and specialty subcontractors for the project,
and
• potential DBE or good faith effort issues with apparent low bid and other bidders
as appropriate.
If the preliminary assessment confirms that competition was adequate, the apparent low
bid should be further reviewed using the criteria in Section (c) below.
b. Considering Re-Advertisement
If the preliminary assessment indicates that competition was inadequate, then the
contracting agency could advance the project based on the determination that the
project is so critical that advancing it outweighs the potential benefit of reduced prices
through additional competition. Few projects are considered so essential that deferral
(even for 60 days to solicit re-advertised bids) would not be in the public interest.
However, projects that are considered essential may include the following:
1) Safety projects to correct extremely hazardous conditions where the traveling
public may be in danger.
2) Emergency repair or replacement of damaged facilities.
3) Projects to close gaps in otherwise completed facilities to allow opening to traffic.
4) Projects that are critical elements in a staged or phased construction schedule,
where a delay would mean substantial impact on the completion date of the
facility. Contracting agencies should evaluate additional costs against schedule
delays when re-advertising projects.
5) Projects in areas with limited construction windows such as: winter shutdowns,
non-work periods due to threatened or endangered species breeding periods, or
discretionary grant-funded projects with statutorily imposed completion deadlines.
It is unlikely that re-advertising would likely result in higher cost without concluding that
all practical anti-inflation measures have been employed to the maximum extent
possible.
Estimating errors should not be considered as the basis for readvertising unless the
magnitude of the error is significant, and procedures are modified to attempt to prevent
the occurrence of similar errors. Some errors are merely mistakes that can be
corrected easily once discovered, while others are “errors of judgment” which cannot be
as easily explained.
STAs are encouraged to track projects that are re-let and tabulate either savings or
higher cost for each calendar year. If higher costs are found in the re-let projects, a
thorough review of the current estimates and procedures should be performed. Also,
Page 13 of 25
current bid collusion detection techniques should be employed to identify potential bid
rigging or collusion.
The analysis and award process for a project should be thorough even when the low bid
is below or at a reasonable percentage above the engineer's estimate. It is reasonable,
however, to expect that larger projects will receive a more thorough review than very
small projects. The STA should have written procedures for justifying the award of
contract, or rejection of the bids, when the low bid appears excessive or rejection is
being considered for other reasons.
c. Bid Review Factors
1) Factors that should be considered in reviewing the bids received for a project
include the following (as appropriate):
(a) Comparison of the bids against the engineer's estimate.
(b) Number of bids submitted.
(c) Distribution or range of bids received.
(d) Identity and geographic location of the bidders.
(e) Potential for savings if the project is re-advertised.
(f) Bid prices for the project under review versus bid prices for similar
projects in the same letting.
(g) Urgency of the project
(h) Current market conditions/workload.
(i) Any unbalancing of bids.
(j) Whether unit bid prices differ significantly from the estimate or from
other bids.
(k) If there is a justification for the difference; and
(l) Any other factors the contracting agency has determined to be
important.
2) The influence of any one of the above factors may not be meaningful in isolation.
However, when considered in combination, the results could be significant. Although
the number of bids received is a measure of bidder interest, by itself the number does
not indicate the degree of competition. For example, one would not normally expect a
firm that is located near a project to be underbid by a firm located a distance from the
project and having extensive mobilization and materials transportation costs if both
Page 14 of 25
firms are bidding truly competitively. A number of other factors enter into a particular
firm's bid such as workload or the size of project, but a bidder's geographic location is a
significant factor.
d. Comparison of Bid Prices
A comparison of project unit bid prices should be made at each letting to determine if
contractors are submitting consistent prices on the different projects they bid. In
general, there will be an adequate number of projects in each letting to make a
comparison except for the large or very specialized jobs. Although the projects being
compared may not be in the same geographic area, the reviewers should be aware of
any geographic price differences, which normally remain constant between areas even
when the overall market conditions change.
e. Unbalancing of Unit Bid Prices
The unbalancing of unit bid prices by a contractor can be difficult to assess in that it is
quite normal for different contractors to place their costs such as overhead or their
expected profit for the project in the unit cost of different items. Normally these costs
will be in those items, which the individual contractor has determined will not be
eliminated or significantly underrun. The main concern of the contracting agency
should be to assure itself that the bids have not been materially unbalanced to take
advantage of errors in the plans or specifications. Unbalancing of bids may also occur
on those lump-sum and unit priced items that can be performed in the early stages of
the project. The contracting agency should assure itself that the schedule of payment
does not result in advance payment. The following FHWA memos provide additional
information on unbalanced bids:
• Bid Analysis and Unbalanced Bids (1988) -
https://www.fhwa.dot.gov/programadmin/contracts/051688.cfm
• Rejection of Unbalanced Bids (1987)
https://www.fhwa.dot.gov/construction/contracts/870729.cfm
It can be difficult to distinguish between a mathematically unbalanced bid and a
materially unbalanced bid. An example of a process for determining materially
unbalanced is the State of Wisconsin DOT’s (WisDOT), which utilizes a bid analysis
procedure. Using WisDOT’s process, an STA would examine significant items that are
mathematically unbalanced (as identified by a certain percentage over or under the
engineer’s estimated unit price for that item). If it appears that a quantity error may
have caused a contractor to unbalance, the STA would examine all significant bid items
for quantity errors. If quantity errors are found, the STA would examine the impact on
the bidder ranking if corrected quantities had been used. A change in the ranking is an
indicator of a materially unbalanced bid. See the following link for additional details:
http://wisconsindot.gov/rdwy/cmm/cm-02-10.pdf#cm2-10.2.1.
Page 15 of 25
f. Review Committee
A multidisciplinary review committee should be used to analyze the bids received so
that the various perspectives within the contracting agency are represented and are
provided with technical and managerial input. This approach can also be used to
readily identify the effects of awarding the contract or rejecting the bids. If a review
committee is not utilized for analyzing bids, as a minimum, the estimating section
should be involved. The estimating section is normally familiar with the project. Any
major differences in the unit bid prices and the estimate will be readily identifiable and
evaluated. Involving the estimating section also keeps it apprised of any trends in the
market conditions so the engineer's estimates can be kept current.
g. General Guidelines
It may be beneficial for a contracting agency to develop general guidelines to be used
in determining whether to award the contract or to reject all bids. However, each
project should be considered on its own merits, as some will normally have a higher
priority to begin construction than others. If guidelines are developed, consideration
should be given to the use of a "sliding scale" approach for low bids over the
estimate. A low bid 15 percent above the engineer’s estimate of $50,000 should not
necessarily be treated the same way as a low bid 15 percent above an engineer's
estimate of $5,000,000. Also, if guidelines are used, it is recommended that the
specifics be kept confidential from the general public so as not to influence
contractors who are preparing bids.
h. Submission of Bids
If a significant number of firms take out a set of plans and a bidding proposal, but only a
small percentage submit a bid, an effort should be made to determine the reasons for
the lack of interest. If the cause for lack of interest can be identified, appropriate steps
should be taken to improve the situation.
i. Bid Responsiveness
STAs have their own requirements for proposal responsiveness (typically identified in
the standard specifications and in the bid proposal package). For projects where a
DBE contract goal was established, contractors must submit, at the STA’s discretion,
DBE commitments or good faith efforts either with the initial bid proposal or within 5
days after the bid opening (49 CFR 26.53(b)(3)(i)).
6. POST-AWARD REVIEWS
a. Evaluation Period
Page 16 of 25
A conscientious effort should be made to determine if bid rigging is currently ongoing or
has occurred in the recent past. To make this determination, an adequate number of
projects awarded over a sufficient time period should be evaluated. A time period of
approximately 5 years should be selected for the initial evaluation to determine if any
abnormal competitive bid patterns exist, unless review of data supports shorter cycles.
b. Review Considerations
The following information should be considered in a post-award review for abnormal bid
patterns: (1) number of contract awards to a specific firm; (2) project bid tabulations; (3)
firms that submitted a bid and later became a subcontractor on that project; (4) rotation
of firms being the low bidder; (5) a consistent percentage differential between the
various firms' bids; (6) a specific percentage of the available work in a geographic area
to one firm or to several firms over a period of time; (7) a consistent percentage
differential between the low bid and the engineer's estimate; (8) location of the low
bidder's plant versus location of the second and third low bidders' plants; (9) variations
in unit bid prices submitted by a bidder on different projects in the same letting; (10)
type of work involved; (11) number of firms that took out a set of plans and a proposal
versus the number actually submitting a bid; and (12) any other items discovered in the
review that may indicate noncompetitive bidding. Re-advertised projects should be
checked to determine if the eventual low bidder was also low in the first letting.
c. Analysis
The information gathered in paragraph b provides the basis to determine if unusual
bid patterns exist. While many STAs have their own bid analysis system, the majority
of STAs responding to a 2017 AASHTO Technical Committee on Cost Estimating
survey said they use the Bid Analysis and Management System / Decision Support
System (BAMS/DSS)TM, a module within AASHTOWare Project Software. In
addition to the ability to analyze bids, BAMS/DSS provides collusion detection
capabilities. The use of a computer program is intended only to provide information to
indicate whether further investigation is warranted. If for any reason, a person feels
that bid rigging or fraud has occurred, they should contact the nearest U.S. DOT
Office of the Inspector General (OIG) Regional Office
http://www.oig.dot.gov/offices.php or the OIG Hotline https://www.oig.dot.gov/hotline.
This may be based on a suspicion or actual evidence of fraud, waste, and abuse in
any project funded by FHWA.
d. In-depth Post-Award Review
The extent to which an in-depth post-award review should be carried out by FHWA or
an STA will depend upon the circumstances surrounding each review. If an FHWA
Division office believes that irregular bid patterns may exist and further investigation is
warranted, any evidence should be furnished to the appropriate OIG office and the
State. Further, an STA should provide any evidence of wrongdoing to their State
Attorney General's Office, FHWA, and other appropriate officials. The frequency of the
Page 17 of 25
in-depth reviews should be adequate to verify that illegal activities are not ongoing or
have not occurred in the recent past.
7. SUSPENSION / DEBARMENT
Suspensions and debarments are discretionary administrative actions taken to protect
contracting agencies by preventing persons or companies from receiving additional
contracts or subcontracts. At the Federal Government level, a notice of suspension or
debarment ensures that the Federal Government does not conduct business with a
person or a company who has an unsatisfactory record of integrity and business ethics.
Suspension and debarment actions are administered Government-wide; consequently,
a person excluded by one Federal agency is excluded from doing business with any
Federal agency. Governmentwide suspension and debarment policies are in 2 CFR
Part 180 and FHWA supplemental policies are in 2 CFR Part 1200. The General
Services Administration’s System for Award Management (SAM) (https://www.sam.gov/)
is a website that is updated regularly for individuals and firms that are excluded from
participation in Federal programs. Contracting agencies may rely on this list to confirm
eligibility prior to awarding any Federally assisted contract or subcontract.
The Government-wide regulations implementing suspension/debarment policy require
participants involved in the contracting process to verify that that the person they are
doing business with is not presently excluded or disqualified (2 CFR 180.300). The
regulations allow verification to be accomplished by:
• Checking SAM Exclusions (recommended), or
• Collecting a certification from that person, or
• Adding a clause or condition to the covered transaction with that person.
While the certification regarding Debarment, Suspension, Ineligibility and Voluntary
Exclusion in Section X of form FHWA-1273 provides a level of verification for prime
contracts and subcontracts, it is not required to be included in purchase orders, rental
agreements, and other agreements for supplies or services. Therefore, FHWA
recommends that STAs and Local Public Agencies verify the eligibility of contractors,
subcontractors, suppliers, and service providers by checking SAM Exclusions prior to
awarding contracts or approving any subcontractor or agreement for services.
It is recommended that each contracting agency have a written policy addressing what
action will be taken in instances of contractor irregularities, such as bid rigging. A
written policy serves as a deterrent to the contracting industry by advising them, in
general terms, what activities the agency considers to be illegal or irresponsible and
how it intends to deal with those involved should any wrongdoing be detected. Further,
the policy may provide a basis for any action(s) that may be taken against the individual
or firm involved in the illegal wrongdoing by those responsible for enforcing the policy.
8. Special considerations for Design-Build and Construction Manager /
General Contractor Projects
Page 18 of 25
For Design-Build (D-B) and Construction Manager / General Contractor (CM/GC)
contracting, the procurement process and the terms used to describe solicitations and
proposals differ significantly from the traditional process. As a result, it is important to
consider different issues and criteria when describing the development of the engineer’s
estimate and its use in assessing price proposals or bids in the D-B and CM/GC
contracting method.
Design-Build
As it relates to the procurement process and the development of the engineer’s
estimate, the D-B procurement process differs from the bid-build process in several
key aspects:
• D-B contracts are typically lump sum contracts. Some contracting
agencies may require the design-builder to convert the lump sum price to
a schedule of values for administrative purposes.
• D-B contracts may be awarded to the lowest responsive proposer or the
best-value proposer as defined in the Request for Proposals (RFP)
document (23 CFR 636.201).
• When using two-phase selection procedures, contracting agencies
typically develop a short-list of 3 to 5 firms who are determined to be
most qualified (23 CFR 636.207).
• Contracting agencies may specify the relative importance of price in the
RFP. For best-value awards, both price and non-price criteria may be
used in the evaluation process. The contracting agency will determine
the relative importance of these evaluation criteria and provide this
information in the solicitation documents (23 CFR 636.301 and 636.302).
• The level of design presented in the RFP varies with each project.
Contracting agencies typically provide a level of design between 20% to
30% in the RFP document.
Because the level of design for a D-B project is relatively low in comparison with the
traditional design-bid-build process, it can be challenging for the contracting agency to
prepare an estimate of quantities for the engineer’s estimate. The contracting agency
may need to start with a preliminary design estimate or a semi-final design estimate and
apply various adjustments to the base estimate to reflect differences in the estimated
costs between the bid-build process and the design-build process. The estimate should
be prepared as the RFP is being finalized and updated as necessary throughout the
procurement process.
Adjustments:
• Design work performed by the design-builder. The adjustment for design
services may be estimated as a percentage of the construction cost. It
typically varies from a small markup for simple resurfacing contracts to a
larger percentage for complex projects where a higher level of effort is
necessary to apply standards, evaluate options and implement a design
in conjunction with the design-builder’s resources and experience. A
Page 19 of 25
typical adjustment factor used to estimate the design-builder’s costs for
design services ranges from 7% to 20% of the estimated construction
cost.
• Risk. The contracting agency should consider factors such as project
complexity, location, site conditions, contract schedules, permits,
construction calendar time restrictions, sensitive environmental/historic
areas, traffic maintenance and phasing issues, material availability and
other issues related to the design-builder’s risk in completing the contract
work. A typical adjustment factor used to account for risk ranges from
0% to 10%.
• Inflation. For contracts with durations longer than one-year, it is
recommended that an adjustment for inflation be applied based on the
time between the estimate date and the mid-point of construction.
• Coordination issues. Depending on the contracting agency’s risk
management plan, some agencies may require the design-builder to
perform services typically provided by the agency, in whole or in part,
such as: preliminary steps in the right-of-way acquisition process (e.g.
appraisals, preparation of correspondence, etc.), utility relocation
coordination or railroad coordination services, etc. Experience with the
delegation of responsibility for these services varies with agency
experience and the degree to which the design-builder is required to
perform these services may be determined on a project-by-project basis.
• Administrative costs. Some agencies may include an adjustment to
account for the design-builder’s costs associated with field offices
(additional office space to accommodate “co-location or over-the-
shoulder” design review requirements of the contracting agency),
additional project managers, communications staff, and other personnel
resources that are above what is typically required in a traditional
construction contract.
• Other miscellaneous costs. Agencies may include adjustments to
account for other miscellaneous costs specific to the project. Examples
of such costs include:
• Construction engineering and inspection as required by the quality
management plan,
• Public information / coordination costs as required by the project public
outreach management plan,
• Costs related to performance or warranty requirements, and
• Professional liability insurance requirements which are required by the
RFP.
For contracting agencies that allow the submission of alternative technical concepts
(ATCs), it may be appropriate to revise the engineer’s estimate after the apparent best-
value firm is determined to account for the ATCs being proposed by that firm. A
revised estimate will provide the agency with a better comparison with the design-
builder’s price proposal and serve to supplement the agency’s determination regarding
the selection of the successful firm.
Page 20 of 25
In summary, the engineer’s estimate prepared for a design-build project differs from the
engineer’s estimate prepared for a traditional project. It is the contracting agency’s
estimate of a competitive price for all services provided under the design-build contract.
If the contracting agency awards the contract on a best-value basis, the engineer’s
estimate is used to evaluate the reasonableness of price as it relates to other award
criteria.
CM/GC
The CM/GC procurement process differs from the bid-build process in several key
aspects:
• The contracting agency may select the CM/GC firm based on qualifications,
experience, best value, or any other combination of factors considered
appropriate by the contracting agency and the Division Administrator (23 CFR
635.504(b)(5);
• The engineer’s estimate for construction is not used in the selection of the
CM/GC firm for preconstruction services, but it is used in determining price
reasonableness by comparing it with the price proposal or bid submitted for
construction services (23 CFR 635.506(d)(3) and (d)(4));
• Many contracting agencies also use an independent cost estimate (ICE) as a
supplemental basis for determining price reasonableness prior to awarding early
work packages or the primary construction contract (23 CFR 635.506(d)(3)); and
• Contracting agencies prepare cost estimates for early work packages and the
entire project (23 CFR 635.506(d)).
Adjustments:
In contrast to the design-build project development process, adjustments in the
contracting agency’s cost estimate are made as the design develops based on the input
received from the CM/GC contractor and the firm preparing the ICE.
• During the design-development process, the contracting agency, the firm
preparing the ICE, and the CM/GC contractor meet regularly to discuss risk,
preliminary design issues, cost, schedule, and administrative issues. The
contracting agency may review the CM/GC contractor’s cost model in
comparison with the ICE and discuss factors that lead to differences in prices.
The contracting agency typically does not release information regarding its
engineer’s estimate. All three parties develop a shared understanding of risk
issues that affect the project cost. This enables the contracting agency and the
firm preparing the ICE to prepare realistic cost estimates.
• Typically, the discussions allow the contracting agency and the contractor to
discuss requirements and issues that may have an impact on cost. As a result,
the contracting agency can identify, manage, and possibly share risk in a manner
that produces the lowest possible price for the contracting agency.
Page 21 of 25
Attachment A –
POTENTIAL QUESTIONS AND STEPS FOR REVIEWING ENGINEER’S
ESTIMATE PREPARATION
1. Are any State laws or administrative regulations in effect regarding
release or protection of the engineer’s estimate?
2. Are any State laws or administrative regulations in effect for
determination of whether a contract award is proper, based on
engineer’s estimate overrun, competition, or other factors?
3. Review and attach any copies of any procedures or instructions the STA
may have pertaining to preparation, revision, checking, and use of the
engineer’s estimate.
4. Briefly describe the intended process for preparation of estimates. Verify
the actual method used in comparison with intended process and note
any differences.
5. Does the STA have an estimating section? Which other portions of the
agency become involved in preparing, checking, or approving the
estimate?
6. Briefly describe the personnel resources available for preparing
estimates and note any workload changes vs. personnel available over
the past 3 years.
7. What is the primary basis for establishing estimated unit prices?
8. What methods are used to identify and incorporate anticipated changes
in cost of labor, equipment, and material?
9. Are upcoming labor negotiations considered in the process?
10. Are material suppliers contacted for anticipated material costs?
11. Are adjustments made for individual project conditions? In what way?
12. What other factors are used to adjust the primary basis to determine the
estimated prices for the project?
13. How is contingency determined? Is contingency based on historical data
or specific risks to cost and schedule completion?
14. Does the State have a method to adjust the engineer’s estimate to
account for locally changed market conditions?
Page 22 of 25
15. In typical cases, how far in advance of the letting date is the estimate
prepared? How often is the estimate revised during the advertising
period? Discounting addenda and quantity changes, what are the usual
reasons for revising estimated prices?
16. Is every estimate routinely evaluated by anyone other than preparer? If
so, when?
17. If possible, determine how often further study and/or revision is believed
desirable but not accomplished due to workload restriction.
18. Is any information released publicly, which may indicate the actual or
approximate value of the estimate prior to opening bids? Is the estimate
released after opening bids?
a. When?
b. Is it published and where?
c. Who receives copies, if published?
d. In detail or only giving total cost?
19. Is any other information regarding the estimate available to contractors
upon request?
20. Review the STA’s experience during the past calendar year for Federal-
aid contract.
a. Determine the percentage of projects sampled where the low bid
fell within +/-10 percent of the estimate and plot the distribution of
low bids above and below the estimate.
b. Determine the percentage of projects with zero, one, two, three,
four, etc., bids. Are there any project size trends noted?
c. Prepare graphs with percent above or below estimate for each
project vs. cumulative percent of number of low bids for three
separate groups of projects, single bids, two or three, and four or
more bids. (Each group should be arranged in ascending order to
facilitate preparing these graphs.) Are any trends noted?
21. Review the Contracting agency’s procedure for evaluating bids received
prior to recommending award or rejection.
Page 23 of 25
a. Is there an established policy on, or apparent pattern of, awards or
rejections of bids at a set level above the engineer’s estimate?
b. In the case of poor competition or excessive difference between the
estimate and the low bid, does the Contracting agency contact the
bidders and non-bidders who requested proposal forms?
c. Are there any “ground rules” for adjusting estimates after receipt of bids?
Is such action taken on its own merits or may it be prompted by pressure
to award an apparently excessive bid?
Page 24 of 25
Attachment B
The following information may be useful in monitoring the estimating, letting,
award, and contract administration processes under FHWA’s Risk-based
Stewardship and Oversight program.
Letting and Award Data (project basis)
• Engineer’s estimate
• Low bid
• Number of bidders
• Percentage difference between low bid and the engineer’s
estimate
• Range of other bids and variation from the engineer’s estimate
Letting and Award Program Data
• Average number of bidders
• Average number of bidders by contract size
• Average number of bidders per project per month
• Average number of bidders by work type (e.g. resurfacing
contracts, bridge replacement, etc.)
• Number of projects with one bid, two bids or more than two bids
• Number of projects bid per month
• Value of projects bid per month
• Number of projects bid per year
• Value of projects bid per year
• Percentage of projects with low bid within +/–10 percent of the
engineer’s estimate
• Number or percent of projects let on schedule
• Annual number of projects re-let
• Average bid prices (and trends) of key work items susceptible to
inflationary pressures (paving, grading, structural steel, etc.).
Construction Contract Administration Monitoring
• Percent difference between award amount and final contract
amount on a project basis
• Percent difference between award amount and final contract
amount on a monthly or annual basis
• Percent difference between engineer’s estimate and final amount
on a monthly, quarterly, annual, or other basis.
• Annual percent of construction projects completed on schedule
(per current contract schedule)
• Reasons for change orders - This information is related to a
State’s administration of the construction program. Relatively high
percentages of change orders initiated for a certain reason may
reveal underlying issues.
STA directed changes
Page 25 of 25
Plan quantity changes
Unforeseen conditions
Plan errors and omissions
Other