HomeMy WebLinkAboutLa Quinta_Ave 502020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
La Quinta BRIDGE NO. 00L0091, AVENUE 50 OVER LA QUINTA EVACUATION CHANNEL. Replace 3-lane low water crossing with 4-lane bridge.
Fund Source Summary:
PE
R/W
Total
CON
Total
10,800,000
600,000 1,300,000 1,900,000
1,320,000
600,000 1,300,000 14,020,000
10,800,000
1,320,000
12,120,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
480,000 1,040,000 11,216,000
120,000 260,000 2,804,000
600,000 1,300,000 14,020,000
9,696,000
2,424,000
12,120,000
Fed Proj:
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
PE Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
480,000 1,040,000 1,520,000
120,000 260,000 380,000
600,000 1,300,000 1,900,000
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4370 HBP PE -1,040,000 1,040,000
Local Match -260,000 260,000
Total:Fed. Reimb. Rate:80.00%
New!
10/8/2022 DLA-Admin: Not ready to ad within 6 months. PE funds moved from FFY 24/25 to 25/26. Project has not received
authorization to proceed. Move funding out.
4370 HBP PE -1,040,000 1,040,000
Local Match -260,000 260,000
Total:Fed. Reimb. Rate:80.00%10/28/2021 DLA-Admin: Not ready to ad within 6 months. PE funds moved from FFY 23/24 to 24/25. Action taken to financially constrain
the FTIP (PUSH). Attempt will be made to program this project in year shown.
4370 HBP -1,040,000PE 1,040,000
Local Match -260,000 260,000
Total:Fed. Reimb. Rate:80.00%10/25/2021 DLA-Admin: Revised PE funds to provide what is needed to clear NEPA.
4370 HBP 1,520,000 1,520,000PE
Local Match 380,000 380,000
Total:1,900,000Fed. Reimb. Rate:80.00%8/15/2021 DLA-Admin: Revise PE reimbursement rate from 88.53% to 80.00% for on system project, local agency wants to keep
programmed for PE not yet authorized
Caltrans, Division of Local Assistance Page 2110/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4370 HBP -1,682,070 -1,682,070PE
Local Match -217,930 -217,930
Total:-1,900,000Fed. Reimb. Rate:88.53%8/15/2021 DLA-Admin: Revise PE reimbursement rate from 88.53% to 80.00% for on system project, local agency wants to keep
programmed for PE not yet authorized
4370 HBP -1,682,070 1,682,070PE
Local Match -217,930 217,930
Total:Fed. Reimb. Rate:88.53%10/27/2020 DLA-Admin: Not ready to ad within 6 months. PE funds moved from FFY 20/21 to 22/23. Funding pushed due to project
prioritization.
4370 HBP 1,682,070PE-442,650
Local Match 217,930-57,350
Total:Fed. Reimb. Rate:88.53%10/18/2020 DLA Admin: Remove AC from PE.
9/22/2020 Eduardo Moreno-Castaneda: Moved PE funds from FFY 19/20 to 20/21 as requested in 2020 September Survey.
-1,239,420
-160,580
4370 Local AC (HBP)PE -1,239,420
Local Match -160,580
Total:Fed. Reimb. Rate:88.53%9/22/2020 Eduardo Moreno-Castaneda: Moved PE AC funds from FFY 19/20 to 20/21 as requested in 2020 September Survey.
1,239,420
160,580
4370 Local AC (HBP)PE 1,239,420
Local Match 160,580
Total:Fed. Reimb. Rate:88.53%10/31/2019 DLA-Admin: PE Funding moved from 21/22 to Beyond, AC PE Funding. Action taken to financially constrain the FTIP
(PUSH).
-1,239,420
-160,580
4370 HBP PE -1,239,420
Local Match -160,580
Total:Fed. Reimb. Rate:88.53%10/30/2019 DLA-Admin: PE funds moved from 19/20 to 21/22. Action taken to financially constrain the FTIP(PUSH).
1,239,420
160,580
4370 HBP -1,682,070PE1,682,070
Local Match -217,930217,930
Total:Fed. Reimb. Rate:88.53%9/25/2018 Matt Sapp: Not ready to ad within 6 months. PE funds moved from FFY 20/21 to 19/20.
4370 HBP 1,682,070 1,682,070PE
Local Match 217,930 217,930
Total:1,900,000Fed. Reimb. Rate:88.53%2/12/2018 Eileen Crawford: New Project per 6A dated 6/10/2015
Caltrans, Division of Local Assistance Page 2210/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
R/W Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
1,056,000
264,000
1,320,000
1,056,000
264,000
1,320,000
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4370 HBP 1,056,000R/W
Local Match 264,000
Total:1,320,000Fed. Reimb. Rate:80.00%8/15/2021 DLA-Admin: Revise RW reimbursement rate from 88.53% to 80.00% for on system project, local agency wants to keep
programmed for PE not yet authorized
1,056,000
264,000
4370 HBP -1,168,596R/W
Local Match -151,404
Total:-1,320,000Fed. Reimb. Rate:88.53%8/15/2021 DLA-Admin: Revise RW reimbursement rate from 88.53% to 80.00% for on system project, local agency wants to keep
programmed for PE not yet authorized
-1,168,596
-151,404
4370 HBP R/W -1,168,596
Local Match -151,404
Total:Fed. Reimb. Rate:88.53%10/27/2020 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 23/24 to Beyond. Funding pushed due to project
prioritization.
1,168,596
151,404
4370 HBP -1,168,596R/W 1,168,596
Local Match -151,404 151,404
Total:Fed. Reimb. Rate:88.53%10/18/2020 DLA-Admin: Not ready to ad within 6 months. funds moved from FFY 22/23 to 23/24. Project has not received authorization
to proceed. Move funding out.
4370 HBP 1,168,596R/W
Local Match 151,404
Total:Fed. Reimb. Rate:88.53%9/22/2020 Eduardo Moreno-Castaneda: Moved RW funds from Beyond to FFY 22/23 as requested in 2020 September Survey.
-1,168,596
-151,404
4370 HBP 1,168,596R/W
Local Match 151,404
Total:1,320,000Fed. Reimb. Rate:88.53%2/13/2018 Eileen Crawford: New Project per 6A dated 6/10/2015
1,168,596
151,404
Caltrans, Division of Local Assistance Page 2310/25/2022, 8:37 AM Det2 FL4 SmlTxt
2020/21-2025/26 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
CAUTION -- This is NOT the FTIP/FSTIP. See the appropriate FTIP/FSTIP for current funding commitments. This report includes projects that should be line
item projects in the FTIP/FSTIP.
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
CON Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
8,640,000
2,160,000
10,800,000
8,640,000
2,160,000
10,800,000
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
Prior 20/21 21/22 22/23 23/24 24/25 25/26 Beyond
4370 HBP 8,640,000CON
Local Match 2,160,000
Total:10,800,000Fed. Reimb. Rate:80.00%8/15/2021 DLA-Admin: Revise Con reimbursement rate from 88.53% to 80.00% for on system project, local agency wants to keep
programmed for PE not yet authorized
8,640,000
2,160,000
4370 HBP -9,561,240CON
Local Match -1,238,760
Total:-10,800,000Fed. Reimb. Rate: 88.53%8/15/2021 DLA-Admin: Revise Con reimbursement rate from 88.53% to 80.00% for on system project, local agency wants to keep
programmed for PE not yet authorized
-9,561,240
-1,238,760
4370 HBP 9,561,240CON
Local Match 1,238,760
Total:10,800,000Fed. Reimb. Rate:88.53%2/13/2018 Eileen Crawford: New Project per 6A dated 6/10/2015
9,561,240
1,238,760
Caltrans, Division of Local Assistance Page 2410/25/2022, 8:37 AM Det2 FL4 SmlTxt