FYI – This weeks status report from Brad.
Let me know if you have questions.
Nick Nickerson, President
NAI Consulting, Inc.
68-955 Adelina Road
Cathedral City, CA 92234
Email: nnickerson@naiconsulting.com <mailto:nnickerson@naiconsulting.com>
Main: (760) 323-5344
Direct: (760 323-5026
Mobile: (760) 861-6401
From: Brad Donais <bdonais@hept7.com>
Sent: Tuesday, May 26, 2020 8:38 AM
To: Nick Nickerson <nnickerson@naiconsulting.com>
Cc: Scott Onishuk <Scott@BengalEngineering.com>
Subject: Dune Palms Bridge Update, Week Ending May 22
Nick:
The following is the current status, updates and Action Log for the bridge project:
Right of Way – Offers and Negotiations:
* Mobile home park – Action on agreement was approved at the last Council meeting. Update to be provided today at 1:00 by Dave C.
* Vacant Commercial – Update to be provided today at 1:00 by Dave C. I have already let Julie know that I have a conflict at 1:00 today for the video call, but can join in as soon as
my noon video call wraps up.
CVWD Channel Coordination:
* Outline of Tech Memo attached. We will be working on the document this week with an anticipated submittal by the end of the week.
CVWD Sewer & Water Relocation Plans:
* Watermain variances have been approval for the State Health Department (four locations where water main was below either storm drain (3) and sewer main (1)), per letter sent out last
week in an email.
* Per CVWD, plans have been approved and will be released with submittal of a number of requested items. Working on getting what we can at this point, but will work with CVWD staff
on releasing plans sooner than later. Sent over engineers estimate for water and sewer along with CAD files for both plans. Will need to provide Bill of Sale, executed copy of relocation
agreement, city insurance package and final plan check fees. A couple of prior will not be able to be sent until prior to construction (Insurance) since the start is still up in the
air.
IID Coordination:
* Per call last week, waiting on IID’s final decision for relocation which will also affect the shoo fly design. I will follow up with staff later this afternoon to see where they are
at in the process.
PS&E Submittal
* In City review.
* Working on additional CV Link elements per the most recent change order. Anticipate those to be wrapped up by next week.
* Will need to work out the final Bid Schedule with the additive alternates and other section breakouts.
CV Link Elements
* Per email on Friday, looking for City approval to insert the soffit panel element into the bridge package. If approved by the City, we will work with BestSigns and Alta on getting
the remaining information (specifications and estimate) to insert into final package.
* I will be reaching out to CVAG this week again on the final decision/direction for the interim connection.
Let me know if you have any questions on the above or will need additional information. Thanks.
Brad Donais, P.E.
Sr. Project Manager / Principal
Quality, Dedication & Experience
Civil Engineering & Construction Management
480.757.0997 Main
760.902.9367 Cell
bdonais@hept7.com <mailto:bdonais@hept7.com>
Check us out at: www.hept7.com <http://www.hept7.com/>