January 6, 2021
To: Jon McMillen, City Manager
From: Bryan McKinney, Public Works Director/City Engineer
Reference: Dune Palms Road Bridge, Project No. 2011-05
Avenue 50 Bridge, Project No. 2019-02
Subject: Highway Bridge Program (HBP) Funding Constraints
In November 2020, Caltrans advised that the HBP Funding Program had been
oversubscribed for Federal Fiscal Years (FFY) 20/21 and 21/22 and there is no
additional programming capacity for projects already in construction or ready to
advertise. As a result, Caltrans HBP Managers issued the attached (ATT 1) HBP
Financial Constraint Order of Priorities.
Caltrans receives $300 million of new programming capacity each FFY for the HBP
Funding Program. The programming capacity is split $100 million for Off System
Bridges and $200 million for On System Bridges. The City of La Quinta receives its
HBP Funding from the On-System account.
The HBP Financial Constraint Order of Priorities directly affects and likely will result
in the delay of the two new bridge projects in the City of La Quinta. These projects
include: Dune Palms Road Bridge, Project No. 2011-05 and Avenue 50 Bridge
Project, Project No. 2019-02. Each of these bridges are at a different point in the
project development process and are discussed separately.
Avenue 50 Bridge Spanning the Evacuation Channel, Project No. 2019-02
The Avenue 50 Bridge Improvement was originally programmed to receive HBP
funding for the Preliminary Engineering (Environmental/Design) Phase during FFY
19/20. Following review of the City’s HBP funding request submittal, Caltrans
advised the City that the HBP Obligation Authority for FFY 19/20 had been exceeded
and that the Avenue 50 Bridge would be reprioritized in accordance with the HBP
Financial Constraint Order of Priorities following the September 2020 Update.
Following the September 2020 HBP Program Update, Caltrans issued the Attached
(ATT 2) new FTIP Programming Sheet for the project. As illustrated, the
Environmental/Design Phase of the Avenue 50 Bridge Project has been delayed
until FFY 22/23. The Right-of-Way and Construction Phases are not programmed
within the current FTIP and the estimated costs are shown in the “Beyond” column.
Currently, the estimated cost of the Avenue 50 Bridge is $14,020,000. These costs
are separated into the following phases:
Preliminary Engineering
(Environmental/Design):
$1,900,000
Right-of-Way Acquisition: $1,320,000
Construction: $10,800,000
Total: $14,020,000
The HBP Funding is expected to contribute 88.53% or $12,411,906 toward eligible
project costs. The remaining 11.47% or $1,608,094 is considered the “Local Match”
and is the responsibility of the City. The project is listed as an eligible improvement
within the Coachella Valley Regional Arterial Program. As such, CVAG typically
agrees to fund up to 75% of the “Local Match”. Once the project is initiated, staff
will submit the appropriate funding request for CVAG’s consideration.
In order to accelerate the PE Phase of the Avenue 50 Bridge Improvement before
FFY 22/23, the City would be required to provide “at risk” advance funding either
through Section 1440 of the Fixing America’s Surface Transportation Act (FAST Act)
or through the Advance Construction Procedure outlined in Section 3.7 of the
Caltrans Local Procedures Manual. The use of either of these programs/procedures
to advance the PE Phase of the project come with the risk that Federal Funds may
never become available.
The Avenue 50 Bridge Improvement has not yet started, and the City’s investment
has been minimal to this point. Staff recommends the City delay the project until
Federal Funds become available in FFY 22/23.
Dune Palms Road Bridge Spanning the Whitewater River, Project No. 2011-
05
The Dune Palms Road Bridge received HBP Funding for the Environmental/Design
Phase on September 3, 2013. The project development process has been actively
underway since the City Council approved the Agreement for Contract Services
between the City and Bengal Engineering, Inc. for services related to the Dune Palms
Road Low Water Crossing Replacement at the Coachella Valley Storm Water Channel
on June 17, 2014.
The project is anticipated to be shovel (construction) ready by March 2021. The
City has worked out most of the right of way and utility relocation issues. The Mobile
Home Park resident (Property Manager) living in the single-family home still needs
to be relocated and we still need to resolve the relocation of IID’s conflicting
facilities. Unless we experience additional delays, it is expected that these
remaining issues will be resolved before the end of February 2021. The project
schedule currently assumes the project will be advertised for construction in June
or July 2021.
As previously discussed, the HBP Funding Program does not have or expect to have
new programming capacity until after FFY 21/22. Following the September 2020
HBP Program Update, Caltrans issued the Attached (ATT 3) new FTIP Programming
Sheet for the project. During FFY 20/21 the project is programmed to receive the
remaining Right-of-Way Funds that were previously delayed during FFY 19/20 and
the Construction Phase has been programmed as Local Advance Construction (AC)
Funds. The conversion of the Local AC Funds to Federal Funds are not programmed
within the current 5 Year FTIP and are shown in the “Beyond” column.
By programming Local AC funding for the Construction Phase during FFY 20/21,
Caltrans is acknowledging the project is “shovel ready” and has provided an
opportunity for the City to begin construction during the current 5-year FTIP.
Currently, the estimated cost of the Dune Palms Road Bridge is $21,034,000 of
eligible participating costs. These costs are separated into the following phases:
Preliminary Engineering
(Environmental/Design):
$1,750,000
Right-of-Way Acquisition: $1,318,000
Construction: $17,996,000
Total: $21,034,000
The HBP Funding will ultimately contribute 88.53% or “up to” $18,621,400 toward
eligible project costs. The remaining 11.47% or $2,412,600 is considered the “Local
Match” and is the responsibility of the City. The project is listed as an eligible
improvement within the Coachella Valley Regional Arterial Program. CVAG has
agreed to fund up to 75% of the “Local Match” and for 100% of the non-participating
costs associated with the CV Link Enhancements. CVAG is currently considering
Amendment 2 which, if approved, will increase the Regional Share of the project to
$5,395,230.
The project schedule assumes we will be advertising the project for construction in
June or July 2021. In order for this to happen the City will need to agree to provide
“at risk” advance funding using the Advance Construction Procedure outlined in
Section 3.7 of the Caltrans Local Procedures Manual.
Considerations for Local Advance Construction:
Caltrans has only programmed other AC conversion projects during FFY 20/21. This
trend is expected to continue well into the future, leaving no programming capacity
for other new projects ready to advertise.
Caltrans has typically programmed AC conversion to Federal Funding within 2
Federal Fiscal Years for other local agencies.
HBP Programming Capacity for new projects ready to advertise will not likely be
available during the remaining FTIP Process.
The City has invested a considerable amount of time and money obtaining
Environmental Clearance, Permits, Right of Way and Preparing the Plans and
Specifications getting the project ready for construction.
Delaying the project until Federal Funds become available will likely require the City
to reapply and/or renew the Environmental Permits required to construct the project
if and when Federal Funding becomes available.
Delaying the project may also delay the CV Link within La Quinta. The CV Link
cannot demonstrate “logical termini” or “independent utility” without the CV Link
components included as part of the Dune Palms Road Bridge Improvement.
Considerations against Local Advance Construction:
The City must consider the risk that Federal Funds may never become available.
The City cannot advance the Construction Funding without outside help. CVAG or
RCTC may be available funding partners for advancing funds.
The City will likely be required to obligate its future Measure A Funding toward any
funding advanced by either CVAG or RCTC until the AC is converted to real HBP
Funding in the future.
Construction is expected to be complete within 18 months following award. The
Construction Phase is estimated to cost nearly $18 million. The City will be
committed to monthly cash flow needs of approximately $1,000,000 per month for
18 months.
Attachments: 1. HBP Financial Constraints Order of Priorities
2. Avenue 50 Bridge FTIP Sheet
3. Dune Palms Road Bridge FTIP Sheet
Division of Local Assistance Page 1 of 2 10/29/2020
HBP Financial Constraint Order of Priorities
In order to achieve a constrained program for Federal Fiscal Years (FFY) 20/21 and 21/22, the
HBP managers have made the following priorities. The demand for funding in the current fiscal
year has resulted in inadequate programming capacity. Off System demand is slightly less than
On System.
The normal review of projects for NEPA clearance, approved PE time extensions, RW
certification, and 100% PS&E was performed. HBP managers requested additional information
on some projects and the answers have been taken into consideration for the funding on
projects. The situation before constraining FFY 20/21 is shown below and the reason for this
order of priorities.
Off System - $74,910,000 programming capacity
20/21 PE & RW - $16,655,564
20/21 AC conversion for CON - $43,069,272
20/21 CON increases - $6,081,888
Leaving $9,103,277 for projects ready to advertise.
On System - $197,337,000 programming capacity
20/21 PE & RW - $71,712,190
20/21 AC conversion for CON - $189,028,506
20/21 CON increases - $31,305,403
Leaving no programming capacity for projects already in construction or ready to advertise.
The above analysis shows that additional steps are required to best meet current policy of a
financially constrained program. The below are HBP managers’ order of priorities for the
October 2020 financial constraint process. This order of priorities is applicable to the current
financial constraint process only. HBP manager’s goal is to not have these additional priorities.
Until programming capacity is not an issue, future years’ order of priorities is subject to change.
1. All projects without an initial PE authorization have been moved to FFY 23/24. If a local
agency wants to begin one of these projects, they may utilize AC. The conversion will
be programmed in FFY 23/24. The AC conversion advancement into an earlier year
may occur, based upon future programming capacity. There is no guarantee on
conversions prior to 23/24.
2. Bridge Inspections
3. High cost bridge projects with signed agreements will continue to have the conversion
programmed in FFY 20/21 and 21/22. This is due to having signed agreements and the
need to get them converted and closed. This accounts for $98,222,890 of the 20/21 On
System AC conversion value above.
4. Prop 1B seismic projects are the top priority for projects with construction cost increases.
5. Prop 1B seismic projects that are ready to advertise for construction and have a signed
Project Delivery Agreement.
6. Cost increases for projects in construction based upon Rank order.
7. HBP will not add AC to projects for construction in FFY 20/21, with a conversion in
21/22.
ATTACHMENT 1
Division of Local Assistance Page 2 of 2 10/29/2020
8. HBP will not enter into new high cost agreements with local agencies with construction
funding in FFY 20/21 or 21/22 for on system projects. HBP will consider entering into
new high cost agreements for off system projects with funding in 21/22.
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
La Quinta BRIDGE NO. 00L0091, AVENUE 50 OVER LA QUINTA EVACUATION CHANNEL. Replace 3-lane low water crossing with 4-lane bridge.
Fund Source Summary:
PE
R/W
Total
CON
Total
10,800,000
1,900,000 1,900,000
1,320,000
1,900,000 14,020,000
10,800,000
1,320,000
12,120,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
1,682,070 12,411,906
217,930 1,608,094
1,900,000 14,020,000
10,729,836
1,390,164
12,120,000
Fed Proj:
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
PE Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
1,682,070 1,682,070
217,930 217,930
1,900,000 1,900,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4370 HBP -1,682,070PE 1,682,070
Local Match -217,930 217,930
Total:Fed. Reimb. Rate:88.53%
New!
10/27/2020 DLA-Admin: Not ready to ad within 6 months. PE funds moved from FFY 20/21 to 22/23. Funding pushed due to project
prioritization.
4370 HBP -442,650 1,682,070PE
Local Match -57,350 217,930
Total:Fed. Reimb. Rate:88.53%
New!
10/18/2020 DLA Admin: Remove AC from PE.
9/22/2020 Eduardo Moreno-Castaneda: Moved PE funds from FFY 19/20 to 20/21 as requested in 2020 September Survey.
-1,239,420
-160,580
4370 Local AC (HBP)-1,239,420PE
Local Match -160,580
Total:Fed. Reimb. Rate:88.53%
New!
9/22/2020 Eduardo Moreno-Castaneda: Moved PE AC funds from FFY 19/20 to 20/21 as requested in 2020 September Survey.
1,239,420
160,580
Caltrans, Division of Local Assistance Page 1711/6/2020, 7:48 AM Det2 FL4 SmlTxt
ATTACHMENT 2
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4370 Local AC (HBP) 1,239,420PE
Local Match 160,580
Total:Fed. Reimb. Rate:88.53%10/31/2019 DLA-Admin: PE Funding moved from 21/22 to Beyond, AC PE Funding. Action taken to financially constrain the FTIP
(PUSH).
-1,239,420
-160,580
4370 HBP -1,239,420PE
Local Match -160,580
Total:Fed. Reimb. Rate:88.53%10/30/2019 DLA-Admin: PE funds moved from 19/20 to 21/22. Action taken to financially constrain the FTIP(PUSH).
1,239,420
160,580
4370 HBP 1,682,070 -1,682,070PE
Local Match 217,930 -217,930
Total:Fed. Reimb. Rate:88.53%9/25/2018 Matt Sapp: Not ready to ad within 6 months. PE funds moved from FFY 20/21 to 19/20.
4370 HBP 1,682,070 1,682,070PE
Local Match 217,930 217,930
Total:1,900,000Fed. Reimb. Rate:88.53%2/12/2018 Eileen Crawford: New Project per 6A dated 6/10/2015
R/W Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
1,168,596
151,404
1,320,000
1,168,596
151,404
1,320,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4370 HBP R/W -1,168,596
Local Match -151,404
Total:Fed. Reimb. Rate:88.53%
New!
10/27/2020 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 23/24 to Beyond. Funding pushed due to project
prioritization.
1,168,596
151,404
4370 HBP R/W -1,168,596 1,168,596
Local Match -151,404 151,404
Total:Fed. Reimb. Rate:88.53%
New!
10/18/2020 DLA-Admin: Not ready to ad within 6 months. funds moved from FFY 22/23 to 23/24. Project has not received authorization
to proceed. Move funding out.
4370 HBP R/W 1,168,596
Local Match 151,404
Total:Fed. Reimb. Rate:88.53%
New!
9/22/2020 Eduardo Moreno-Castaneda: Moved RW funds from Beyond to FFY 22/23 as requested in 2020 September Survey.
-1,168,596
-151,404
Caltrans, Division of Local Assistance Page 1811/6/2020, 7:48 AM Det2 FL4 SmlTxt
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4370 HBP 1,168,596R/W
Local Match 151,404
Total:1,320,000Fed. Reimb. Rate:88.53%2/13/2018 Eileen Crawford: New Project per 6A dated 6/10/2015
1,168,596
151,404
CON Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
9,561,240
1,238,760
10,800,000
9,561,240
1,238,760
10,800,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4370 HBP 9,561,240CON
Local Match 1,238,760
Total:10,800,000Fed. Reimb. Rate:88.53%2/13/2018 Eileen Crawford: New Project per 6A dated 6/10/2015
9,561,240
1,238,760
Caltrans, Division of Local Assistance Page 1911/6/2020, 7:48 AM Det2 FL4 SmlTxt
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
La Quinta BRIDGE NO. 00L0070, Dune Palms Road OVER the Coachella Valley Stormwater Channel (Whitewater River). Replace 3-Lane Low-Water
Crossing with 4-Lane Bridge. (This project must appear in the RTP.)
Fund Source Summary:
PE
R/W
Total 1,750,000
CON
Total
17,966,000 17,966,000
1,750,000
545,000 773,000 1,318,000
545,000 18,739,000 21,034,000
1,750,000
Phase Summary:
Fed $
Local AC
Local Match
Total
200,725
1,750,000
LSSRP Bond
Total
482,489 684,337 18,621,400
62,512 2,149,363 2,412,600
15,905,300
545,000 18,739,000 21,034,000
1,549,275 15,905,300
-15,905,300
BRLKS-5433(014)Fed Proj:
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
PE Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
200,725
1,750,000
LSSRP Bond
Total
1,549,275
200,725
1,750,000
1,549,275
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4024 HBP 1,549,275PE1,549,275
Local Match 200,725200,725
Total:1,750,000Fed. Reimb. Rate:88.53%10/9/2012 Linda Newton: New eligible project.
Caltrans, Division of Local Assistance Page 1211/6/2020, 7:48 AM Det2 FL4 SmlTxt
ATTACHMENT 3
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
482,489 684,337 1,166,825
62,512 88,663 151,175
545,000 773,000 1,318,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4024 HBP -684,337 684,337R/W
Local Match -88,663 88,663
Total:Fed. Reimb. Rate:88.53%
New!
8/24/2020 Bobby Zezoff: LAPG 6-D approved and funds moved to 20/21 due to out of funds at approval date.
4024 HBP 684,337 684,337R/W
Local Match 88,663 88,663
Total:773,000Fed. Reimb. Rate:88.53%10/9/2019 Eduardo Moreno-Castaneda: Not ready to ad within 6 months. Additional R/W funding in FFY 19/20 as submitted in
September 2019 HBP Survey.
4024 HBP 482,489R/W -482,489
Local Match 62,512-62,512
Total:Fed. Reimb. Rate:88.53%10/10/2018 Eileen Crawford: Not ready to ad within 6 months. RW funds moved from FFY 17/18 to 18/19. Funds not obligated, moved
to next fiscal year.
4024 HBP -482,489R/W 482,489
Local Match -62,51262,512
Total:Fed. Reimb. Rate:88.53%12/5/2019 Linda Newton: Fund line has not failed to deliver.
10/19/2018 DLA-Admin: Fund line failed to deliver.
9/15/2017 Vu Ngo: Not ready to ad within 6 months. RW funds moved from FFY 19/20 to 17/18. As requested in September 2017
Survey.
4024 HBP 482,489R/W -482,489
Local Match 62,512-62,512
Total:Fed. Reimb. Rate:88.53%10/9/2016 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 17/18 to 19/20. NEPA not yet clear.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%10/21/2015 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 16/17 to 17/18. NEPA not yet clear. 8/25/2019
DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2016/17-21/22 to 2018/19-23/24. This does not impact funds in the
current FTIP cycle.
Caltrans, Division of Local Assistance Page 1311/6/2020, 7:48 AM Det2 FL4 SmlTxt
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%10/1/2015 Albert Vergel de Dios: Not ready to ad within 6 months. RW funds moved from FFY 17/18 to 16/17. As requested in
September 2015 Survey. 8/25/2019 DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2016/17-21/22 to 2018/19-23/24.
This does not impact funds in the current FTIP cycle.
4024 HBP R/W
Local Match
Total:Fed. Reimb. Rate:88.53%3/18/2015 DLA-Admin: Not ready to ad within 6 months. RW funds moved from FFY 15/16 to 17/18. NEPA not yet clear. 8/25/2019
DLA-Admin: Fundline zeroed out due to FTIP cycle migration: 2016/17-21/22 to 2018/19-23/24. This does not impact funds in the
current FTIP cycle.
4024 HBP 482,489R/W 482,489
Local Match 62,51262,512
Total:545,000Fed. Reimb. Rate:88.53%10/9/2012 Linda Newton: New eligible project.
CON Summary:
Proj id Funds Src TotalPhase
Phase Funding Details:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
15,905,300
2,060,700 2,060,700
15,905,300
17,966,000 17,966,000
15,905,300
-15,905,300
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4024 Local AC (HBP)15,905,300CON -15,905,300
Local Match 2,060,700 -2,060,700
Total:Fed. Reimb. Rate:88.53%
New!
9/23/2020 Eduardo Moreno-Castaneda: Moved AC CON funds from FFY 21/22 to 20/21 as requested in 2020 September Survey.
4024 HBP 2,435,460CON
Local Match 315,540
Total:2,751,000Fed. Reimb. Rate:88.53%10/9/2019 Linda Newton: Add CON cost increase as submitted in September 2019 HBP Survey.
2,435,460
315,540
4024 Local AC (HBP)CON 15,905,300
Local Match 2,060,700
Total:Fed. Reimb. Rate:88.53%10/9/2019 Linda Newton: Add AC to CON in FFY 21/22.
-15,905,300
-2,060,700
4024 HBP CON -13,469,840
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2018 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 21/22 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
Caltrans, Division of Local Assistance Page 1411/6/2020, 7:48 AM Det2 FL4 SmlTxt
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4024 HBP -13,469,840CON 13,469,840
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2018 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 20/21 to 21/22. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP -13,469,840 13,469,840CON
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2018 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to 20/21. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP 13,469,840CON
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/25/2018 Matt Sapp: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 19/20. As requested in September 2018
Survey.
-13,469,840
-1,745,161
4024 HBP CON -13,469,840
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2017 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 21/22 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP -13,469,840CON 13,469,840
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2017 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 20/21 to 21/22. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP -13,469,840 13,469,840CON
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2017 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to 20/21. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP 13,469,840CON
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/15/2017 Vu Ngo: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 19/20. As requested in September 2017
Survey.
-13,469,840
-1,745,161
4024 HBP -13,469,840CON
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/25/2016 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP 13,469,840CON
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/20/2016 Albert Vergel de Dios: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 19/20. As requested in
September 2016 Survey.
-13,469,840
-1,745,161
Caltrans, Division of Local Assistance Page 1511/6/2020, 7:48 AM Det2 FL4 SmlTxt
2018/19-2023/24 Highway Bridge Program
District:County:
Responsible Agency
08 Riverside
Total
See the appropriate FTIP/FSTIP for current funding commitments. This listing includes projects that should be individually listed in the FTIP/FSTIP. (Line item
projects only)
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4024 HBP -13,469,840CON
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/29/2015 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 19/20 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP -13,469,840 13,469,840CON
Local Match -1,745,161 1,745,161
Total:Fed. Reimb. Rate:88.53%10/29/2015 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 18/19 to 19/20. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP 13,469,840CON-13,469,840
Local Match 1,745,161-1,745,161
Total:Fed. Reimb. Rate:88.53%10/29/2015 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 17/18 to 18/19. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%10/1/2015 Albert Vergel de Dios: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 17/18. As requested in
September 2015 Survey.
-13,469,840
-1,745,161
4024 HBP CON -13,469,840
Local Match -1,745,161
Total:Fed. Reimb. Rate:88.53%10/28/2014 DLA-Admin: Not ready to ad within 6 months. CON funds moved from FFY 17/18 to Beyond. Action taken to financially
constrain the FTIP (PUSH). Attempt will be made to program this project in year shown.
13,469,840
1,745,161
4024 HBP CON 13,469,840
Local Match 1,745,161
Total:Fed. Reimb. Rate:88.53%9/3/2014 Albert Vergel de Dios: Not ready to ad within 6 months. CON funds moved from FFY Beyond to 17/18 per September Survey.
-13,469,840
-1,745,161
4024 HBP 13,469,840CON
Local Match 1,745,161
Total:15,215,000Fed. Reimb. Rate:88.53%10/9/2012 Linda Newton: New eligible project.
13,469,840
1,745,161
Caltrans, Division of Local Assistance Page 1611/6/2020, 7:48 AM Det2 FL4 SmlTxt